GOVERNMENT OF ANDHRA PRADESH
ABSTRACI
WATER RESOURCES DEPARTMENT- "Permanent restoration with NOF Concrete dam and providing additional spillway for Annamayya Project near Badanagadda (V), Rajampet Mandal of Annamayya District for an amount of Rs.787.77 Crores
(Rupees seven hundred and eighty seven Crores and Seventy seven lakhs only)
Administrative sanction Orders - Issued.
- - - - - -
WATER RESOURCES (PROJECTS.1I) DEPARTMENT
G.0.Rt.No.2076 Dated:02.11.2022. Read the following:
G.O.Rt.No.15 Water Resources (Projects.III) Department, dated 10- 1-
1) 2022.
From the Chief Engineer (P), Kadapa Letter No.CE(P)/ WRD/
4 KDP/TS2/AE1/ ANP-Dam Road/AA/21, Dt:05.02.2022.
From the Engineer-in-Chief (1), Vijayawada Letter No.ENC(I)/ DCE
(GDS)/OT2/ AEES/ANNAMAYYA Dt: 22.06.2022 and 22-8-2022.
&&&&
ORDER:
In the G 1s read above, Government have issued orders for administrative sanction for an amount of Rs.411.50 Lakhs (Rupees Four Crores Eleven Lakhs Fifty Thousand only) for the work "Permanent restoration of Gate No.5, installation of Stop-log elements and other damaged items during NIVAR Cyclone flood at Annamayya Project Dam across Cheyyeru River near Badanagadda (V), Rajampet (M) of Kadapa District" in relaxation of FRBM norms subject to certain conditions.
3. After careful examination of the matter, Government hereby accorded administrative approval for the work "Permanent restoration with NOF Concrete dam and providing additional spillway for Annamayya Project near Badanagadda (V), Rajampet Mandal of Annamayya District" for an amount of Rs.787.77 Crores (Rupees seven hundred and eighty seven Crores and Seventy seven lakhs only) in relaxation of FRBM norms, duly cancelling the GO Rt.No.15, dt.10.01.2022 to avoid duplication subject to the following conditions:-
1. The correctness of the provisions, quantities, leads & rages proposed in the estimate 2. The design/drawings for the proposed NOF dam and Additional spillway (for Civil & mechanical components) may be got approved by the CE/CDO) 3. The sand rates may be adopted as per the latest sand policy of the Govt. 4. Detailed estimates/competitive quotations may be supported for the LS
provisionns
{{^{{FOOTNOTE 4 }}}} The above expenditure is debitable to the HOA: 4701 COL on Medium Irrigation -03-Commercial-MH 137 Cheyyeru River-GH (11) State development schemes - SH (26) D&A - 530 Major works-531 Major works & 532 Lands. 5. The Chief Engineer (P), Kadapa/ Engineer-in-Chief (I), Vijayawada are therefore requested to take necessary further action accordingly.
5. This order issues with the concurrence of Finance (VFMU.WR.II, Department vide their U.O.Note.No. FIN01-FMUOMRAS(WR2)/111/2022- FMU-WR-II , Computer
No.1826937 dated:31-10-2022.
7. Copy of this order is available in the apegazette.cgg.gov.in website.
(BY ORDER AND IN THE NAME OF THE GOVERNOR OF ANDHRA PRADESH)
SHASHI BHUSHAN KUMAR
PRINCIPAL SECRETARY TO GOVERNMENT
To
The ENC (I), Vijayawada. The Chief Engineer (P), Kadapa.
opy to:
Finance (FMU. WR.II) Department.
The PS to Hon'ble Minister for WRD
The PS to Principal Secretary (WRD);
File No.ICD01/290/2022-PROJ-III(1644620) SF/SC
/FORWARDED:: BY ORDER//
SECTION OFFICER