Registered No. HSE-49/2016
GOVERNMENT OF ANDHRA PRADESH
ABSTRACT
Planning Department - Pulivendula Area Development Agency ( PADA) - Administrative sanction of Rs.265.78 crores instead of Rs.251.16 crores for certain project components in Pulivendula for development of Pulivendula as Model Town - Modified Orders - Issued .
===
PLANNING ( IX) DEPARTMENT
G.O.Rt.No.176 .
Dated.29.11.2022 . Read the following:
1. G.O.Rt.No.261 , Planning ( IX) Department , dated.21.12.2020 .
2. G.O.Rt.No.62 , Planning ( IX) Department , dated.22.04.2021 .
3. G.O.Rt.No.68 , Planning ( IX) Department , dated.30.04.2021.
G.2167 W.No.48 5.
4. G.O.Rt.No.140, Planning (IX) Department, dated.27.09.2021. From IAMARIAVAIT & THURSDAY , AREGEMBERA2022
Pulivendula , Letter Rc . No :A1/ 202/ 2020, dated.24.11.2022.
ORDER:
PART I - NOTIFICATIONS BY GOVERNMENT , HEADS OF DEPARTMENTS AND OTHER OFFICERS
In the GOGO 4th read above , the Government have accorded amount of RsNOTIFI NOTIFICATIO Pulivendula as Model Town . ministrative sanction for an development of S BY GOVERNM Nation for 2. TheDistrict Collector, YSR District and Chairman , PADA in the reference 5th read above , has Informed that the works are in brisk progress and during the execution of works , it was found that there was need for change in some components of the Model Town Projects to meet architectural requirements which necessitates re - appropriation of Budget . The proposed changes have been discussed and finalized during the weekly review meetings . Accordingly, the proposals have been worked out for Re -Appropriation of Budget within the overall budget of Rs.651.19 crores.
3. The District Collector , YSR District has requested the Government that the following re- allocation of the administrative sanction for an amount of Rs.265.78 crores for certain project components in Pulivendula for development of Pulivendula as Model Town instead of earlier administrative sanction of Rs.251.16 crores as stated below:
SI .
Remarks ProjectComponent
No
Nameof the Department
Proposed Budget (Rs. in Cr)
Approved
Project cost
(Rs.inCr)
Addition/ Deletion (Rs. in Cr )
1
28.65
24.00
HousingWater Supply Works
-4.65 Revised Housing Layout-Sewerage
49.19
42.94
-6.25
2
Revised 3
69.86
Housing Layout - Roads & Drains
69.86
0.00 No change MA& UD
4
0.00
28.12
28.12
Housing Layout- Roads & Drains( Package - II )
New Component Markets
5
3.47
3.47
0.00 No change
Revised Markets( Package - 2)
6
0.59
0.96
0.37 Citizen Service Center 7
8
Citizen Service Center (Package-2)
9
Slaughter house
Shopping Complex
10
11
Shopping Complex (Package-2)
Central Boulevard
12
13
Central Boulevard (Package-2)
SWM
MA& UD
14
15
Internal Roads - MAUD 16
Burial Grounds
17
Vending zones
Total 7.50
7.50
0.00 No change 0.00
1.60
1.60
New Component 8.70
9.38
0.68 Revised 11.29
11.29
0.00 No change 0.00
5.74
5.74
New Component
Revised 4.57
5.04
0.47
4.70
0.00
-4.70
Revised
Revised 24.43
25.43
1.00
Revised 26.49
18.30
-8.19
Revised 9.80
10.23
0.43
1.92
1.92
0.00
No change 251.16
265.78 (+)14.62
4. After careful examination of the proposal of the District Collector and Chairman PADA, YSR District, the Government hereby accord revised administrative sanction for an amount of Rs.265.78 Crore ( Rupees Two hundred and sixty five Crores and seventy eight Lakhs only) for the project component as detailed below: -
ProjectComponent
SI No
1.
Housing Water Supply Works
2.
Housing Layout-Sewerage 3. Housing Layout - Roads & Drains
4.
Project Cost (Rs. in Cr)
24.00
42.94
69.86
28.12
Housing Layout - Roads & Drains ( Package-
II)
5. Markets
6. Markets ( Package - 2) 7.
Citizen Service Center 8. CitizenService Center ( Package - 2 )
9. Slaughter house
10.
Shopping Complex 11 .
Shopping Complex ( Package - 2)
12.
Central Boulevard 13. SWM
3.47
0.96
7.50
1.60
9.38
11.29
5.74
5.04
25.43 14. Internal Roads - MAUD
18.30
15. Burial Grounds
10.23
16.
Vending zones
1.92
Total
265.78
5. All the terms and conditions mentioned in the G.O. 4th read above continued to be in force .
6. The District Collector and Chairman , PADA shall take necessary action for speedy implementation of the Project without compromising on the quality and responsible for overall project management with the assistance of APUIAML .
( BY ORDER AND IN THE NAME OF THE GOVERNER OF ANDHRA PRADESH )
VIJAY KUMAR G.SRKR SECRETARY TO GOVERNMENT To
The Special Chief Secretary to Government, Municipal Administration & Urban Development Department
TheDistrict Collector and Chairman Pulivendula Area Development Agency ( PADA) , Pulivendula , YSR Kadapa District
TheEngineer - in- Chief, ( PH ) Public Health & Municipal Engineering Department , Guntur
TheDirector of Works & Accounts , Anjaneya Towers , Ibrahimpatnam , Vijayawada
TheDirector of Treasuries & Accounts , Anjaneya Towers , Ibrahimpatnam , Vijayawada
TheAccountant General , AP, Vijayawada
The PAO , YSR District
TheChief Executive Officer, APUIAML, Vijayawada
Copy to:
TheSpecial Chief Secretary to Government , Industries & Commerce
TheSpecial Chief Secretary to Government , Infrastructure & Investment
TheSpecial Chief Secretary to Government , Housing Department
TheSpecial Chief Secretary to Government, School Education Department
TheSpecial Chief Secretary to Government , Finance Department
TheSpecial Chief Secretary to Government , Environment , Forest , Science & Technology Department ThePrincipal Secretary to Government , Transport , Roads & Buildings Department
ThePrincipal Secretary to Government , Water Resources ( MI ) Department
ThePrincipal Secretary to Government , Skills Development and Training Department
TheCommissioner and Director of Municipal Administration , Guntur
The Prl . Chief Conservator of Forests & Head of Forest Force , A.P. , Guntur
TheManaging Director, APIIC , Mangalagiri
TheMD, Andhra Pradesh Greening and Beautification Corporation , Vijayawada
TheDirector , APSHCL , Vijayawada
TheDirector, APSSDC, Tadepalli , Guntur
TheOfficer on Special Duty, Pulivendula Area Development Agency ( PADA) ,
Pulivendula , YSR Kadapa District
TheDivisional Head - Smart Cities , APUIAML, Vijayawada
TheOSD to Secretary to C.M
ThePS to Secretary to Government, Planning Department
SF/SC .
// FORWARDED :: BY ORDER //
V. Paman Ban SECTION OFFICER
AP