Servants of Knowledge
Extraordinary Gazette of India · Government of India

The Central Electricity Regulatory Commission(Terms and Conditions of Tariff) (Amendment) Regulations, 2007

Published 14 March 2007

Ministry
Central Electricity Regulatory Commission
Department
NOT available
Office
NOT available
Gazetteid
NOT available ( 9455 )
Identifier
in.gazette.central.e.2007-03-14.9455
Languages
English, Hindi
Published at
Original source ↗

REGD. NO . D. L -33004/99 रजिस्ट्री सं० डी० एल०-33004/99

भारत का राजपन The Gazette of India

असाधारण

EXTRAORDINARY

भाग III-खण्ड 4

PART III Section 4

प्राधिकार से प्रकाशितः

PUBLISHED BY AUTHORITY

सं. 60]

नई दिल्ली, बुधवार , मार्च 14 , 2007 /फाल्गुन 23 , 1928

No. 60]

NEW DELHI, WEDNESDAY, MARCH 14, 2007/PHALGUNA 23 , 1928

केन्द्रीय विद्युत विनियामक आयोग

अधिसूधना

नई दिल्ली, 13 मार्च , 2007

सं. एल-7/25( 5 )/2003 - सीईआरसी केन्द्रीय विद्युत विनियामक आयोग , विद्युत अधिनियम , 2003 ( 2003 का 36 ) की धारा 178 के अधीन प्रदत्त शक्तियों का और इस निमित्त सामर्थ्यकारी सभी अन्य शक्तियों का प्रयोग करते हुए, और पूर्व प्रकाशन के परचार, केन्द्रीय विद्युत विनियामक आयोग (टैरिफ के निबंधन और शर्तें ) विनियम , 2004 , जिसे इसमें इसके पश्चात्, " मूल विनियम " कहा गया है , का और संशोधन करने के लिए निम्नलिखित विनियम बनाता है , अर्थात्:-

1. संक्षिप्त नाम तथा प्रारंभ. ( 1 ) इन विनियमों का संक्षिप्त नाम केन्द्रीय विद्युत विनियामक आयोग (टैरिफ के निबंधन और सते ) (संशोधन) विनियम , 2007 है।

(2) ये विनियम 1-4-2007 से प्रवृत्त होंगे ।

2. विनियम 16 का संशोधन, मूल विनियम के विनियम 16 के स्थान पर, निम्नलिखित विनियम रखा जाएगा, अर्थात् "16. प्रचालन के संनियम. -प्रचालन के संनियम जो नीचे दिए गए हैं, निम्नलिखित को लागू होंगे-

( i ) पूर्ण क्षमता ( नियत ) प्रभारों की वसूली के लिए लक्ष्य उपलब्धता-

80 %

( क ) नीचे खण्ड ( ख ) के अधीन आने वाले स्टेशनों के सिवाय सभी ताप ऊर्जा

उत्पादन केन्द्र

(ख) नवेली लिग्नाइट कारपोरेशन लि. के ताप ऊर्जा

-75 %

उत्पादन केन्द्र ( टी पी एस- I , टी पी एस- II , प्रक्रम 1 और 2 और टी पी एस -1

विस्तारण ) और एन टी पी सी लि, के तलचर ताप ऊर्जा केन्द्र

टिश्यपण:

लक्ष्य उपलब्धता के स्तर के नीचे की क्षमता ( नियत ) प्रभारों की वसूली आनुपातिक आधार पर की जाएगी । शून्य उपलब्धका पर कोई भी क्षमता प्रभार संदेय नहीं होगा ।

(ii ) प्रोत्साहन के लिए लक्ष्य संयंत्र भार कारक-

(क) नीचे खण्ड ( ख) के अधीन आने वाले केन्द्रों के सिवाय सभी ताप उत्पादन केन्द्र

80 % 877 GI/2007

(1) 2

THE GAZETTE OF INDIA : EXTRAORDINARY

[PART III-SEC. 4]

75 % ( ख ) नवेली लिग्नाइट कारपोरेशन लि. के ताप ऊर्जा उत्पादन केन्द्र ( टी पी एस -1 , टी पी एस- II , प्रक्रम 1 और 2 विस्तारण ) तथा एन टी पी सी लि. के तलचर ताप ऊर्जा केन्द्र

( iii ) सकल केन्द्र हीट दर-

( क ) नीचे खण्ड ( ख ) और ( ग ) में दिए गए केन्द्रों के सिवाय कोयला आधारित ताप ऊर्जा उत्पादन केन्द्र

200/210/250 मेगावाट सैट

500 मेगावाट और उससे ऊपर के सैट

स्थिरीकरण अवधि के दौरान

2600 कि. कैलोरी/किलोवाट घंटा

2550 कि. कैलोरी/किलोवाट घंटा

पश्चात्वर्ती अवधि

2500 कि. कैलोरी/किलोवाट घंटा

2450 कि. कैलोरी/ किलोवाट घंटा

टिप्पण 1 :

500 मैगावाट और उससे ऊपर के यूनिटों के संबंध में , जहां बायलर फीड पम्प विद्युत से प्रचालित किए जाते हैं वहां कुल उत्पादन ताप दर उपरोक्त उपदर्शित उत्पादन ताप दर , से 40 कि. कैलोरी/किलोवाट घंटा कम होगी।

टिप्पण 2 :

ऐसे उत्पादन केन्द्रों के लिए , जिनके पास 200/210/250 मेगावाट सैट और 500 मेगावाट और उससे ऊपर ,के सैट का संयोजन है , मानकीय सकल उत्पादन केन्द्र ताप दर , भारित औसत उत्पादन केन्द्र ताप दर होगी ।

J

(ख ) तलचर ताप ऊर्जा केन्द्र

3100 कि. कैलोरी/किलोवाट घंटा

(ग ) टांडा ताप ऊर्जा केन्द्र

2850 कि. कैलोरी/किलोवाट घंटा

( घ ) लिग्नाइट से चलने वाले तापीय ऊर्जा उत्पादन केन्द्र

( । ) कोयला आधारित ताप ऊर्जा उत्पादन केन्द्रों के लिए ऊपर खंड ( क ) के अधीन विनिर्दिष्ट सकल उत्पादन केन्द्र ताप की दरें नवेली लिग्नाइट कारपोरेशन लिमिटेड के टीपीएस 1 और टीपीएस -11 ( प्रक्रम 1 और 2 ) के सिवाय नीचे दिए गए गुणककारकों का उपयोग करते हुए , संशोधित की जाएंगी :-

( i ) 50 प्रतिशत आर्द्रता वाली लिग्नाइट के लिए 1.10 का गुणनकारक;

( ii ) 40 प्रतिशत आर्द्रता वाली लिग्नाइट के लिए 1.07 का गुणनकारक;

(iii ) 30 प्रतिशत आर्द्रता वाली लिग्नाइट के लिए 1.04 का गुणनकारक ;

( iv ) आर्द्रता अंतर्वस्तु के अन्य मूल्यों के लिए गुणककारक उपरोक्त उप - खंड ( i ) से खंड ( iii ) में दी गई अपनी-अपनी रेंज के लिए गुणककारक के रेटेड मूल्यों पर निर्भर रहते हुए , 30-40 और 40-50 की बीच की आर्द्रता अंतर्वस्तु हेतु अनुपात में निर्धारित की जाएगी ।

(2 ) नवेली लिग्नाइट कारपोरेशन लिमिटेड के टीपीएस 1 और टीपीएस- II :

टीपीएस- 1

3900 कि. कैलोरी/किलोवाट घंटा

2850 कि. कैलोरी/किलोवाट घंटा

टोपीएस- II

( ङ ) गैस टर्बाइन/ संयुक्त आवर्तन ऊर्जा उत्पादन केन्द्र-

( i ) एनटीपीसी लि. के स्वामित्वाधीन विद्यमान उत्पादन केन्द्र

उत्पादन केन्द्र का नाम

संयुक्त आवर्तन ( साइकिल )

खुला आवर्तन

(कि. कैलोरी/किलोवाट )

(कि. कैलोरी/किलोवाट )

गंधार जी पी एस

2000

2900

कवास जी पी एस

3010

2075

2075

अन्ता जी पी एस

3010

दादरी जी पी एस

2075

3010

2100

औरेयाजी पी एस

3045

2000

फरीदाबाद जी पी एस

2900

2000

2900

कायमकुलम जी पी एस भारत का राजपत्र असाधारण

[भाग III- खण्ड 4 ]

(ii) 1-4-2004 को या उसके पश्चात् वाणिज्यिक प्रचालन के अधीन घोषित उत्पादन केन्द्र

ई/ईए/ईसी/ई2 श्रेणी मशीन

उन्नत श्रेणी मशीन

2830 कि. कैलोरी/किलोवाट घंटा

2685कि. कैलोरी/किलोवाट घंटा

खुला आवर्तन

1950कि. कैलोरी/ किलोवाट घंटा

1850 कि. कैलोरी/ किलोवाट घंटा

संयुक्त आवर्तन

(iii ) लघु गैस टर्बाइन ऊर्जा उत्पादन केन्द्र :

(क) असम गैस आधारित ऊर्जा केन्द्र, कैथलगुड़ी:

3225 कि. कैलोरी/किलोवाट घंटा

खुला आवर्तन

2250 कि. कैलोरी/किलोवाट, घंटा

संयुक्त आवर्तनं

(ख) अगरतला गैस आधारित ऊर्जा केन्द्र, रामचन्द्रनगर

- 3580 कि. कैलोरी /किलोवाट घंटा

खुला आवर्तन

(ग) उपरोक्त (क ) और ( ख ) को छोड़कर

द्रवं इंधन सहित

प्राकृतिक गैस सहित

1.02 × 3125 कि. कैलोरी/किलोवाढ घंटा

- 3125 कि. कैलोरी/किलोवाट घंटा

खुला आवर्तन

1.02 × 2030 कि. कैलोरी/किलोबाट घंटा

2030 कि. कैलोरी/किलोवाट घंटा

संयुक्त आंवर्तन

(iv ) गौण ईंधन तेल खपत

(क) कोयला आधारित उत्पादन केन्द्र:

(i ) नीचे खण्ड ( ii ) के अधीन आने वाले केन्द्रों के सिवाय सभी कोयला आधारित ताप ऊर्जा उत्पादन केन्द्र

स्थिरीकरण अवधि के दौरान

4.5 मि.ली./किलोवाट घंटा

( ii ) तलघर ताप ऊर्जा केन्द्र

(ख) लिग्नाइट आधारित ताप ऊर्जा उत्पादन केन्द्र

स्थिरीकरण अवधि के दौरान

3.0 मि.ली./किलोवाटं घंटा

( v ) अतिरिक्त ऊर्जा खपत

(क) कोयला आधारित उत्पादन केन्द्र:

पश्चात्वर्ती अवधि

-2.0 मि. ली./किलोवाट घंटा

3.5 मि.ली./किलोवाट घंटा

पश्चात्वर्ती अवधि

3.0 मि. ली./किलोवाट घंय

शीतलन ( कूलिंग) शीतलन (कूलिंग)

                                                   टावर सहित                             टावर कें बिना
                                                   9.0%                                  8.5%
          (1) 200 मेगावाट श्रृंखला
          (ii) 500 मेगावाट श्रृंखला
               भाप चालित बायलर फीड पम्प             7.5%                                 7.0%
                                                   9.0%                                  8.5%
               विद्युत चालित बायलर फीड पम्प
          (iii) तलचर ताप ऊर्जा केन्द्र              11.0%
         (iv ) टांडा ताप ऊर्जा केन्द्र              12.0%
(ख) गैस टर्बाइन/संयुक्त आवर्तन उत्पादन केन्द्र :
          (i ) संयुक्त आवर्तन                       3.0%
          (ii) खुला आवर्तन                          1.0%
 (ग) लिग्नाइट आधारित ताप ऊर्जा उत्पादन केन्द्र

(i ) नवेली लिग्नाइट कारपोरेशन लिमिटेड के टीपीएस 1 और टीपीएस- II ( प्रक्रम I और II ) के सिवाय सभी उत्पादन केन्द्र:

4

THE GAZETTE OF INDIA : EXTRAORDINARY

[PART III-SHC . 4]

.. उपरोक्त ( v ) ( क) ( i ) और ( ii ) पर कोयला आधारित उत्पादन केन्द्र के सहायक ऊर्जा खपत संनियम का प्रतिशतता बिन्दु अतिरिक्त ऊर्जा खपत संनियम से अधिक 0.5 होगा।

( ii ) नवेली लिग्नाइट कारपोरेशन लिमिटेड के टीपीएस 1 और टीपीएस- II प्रक्रम 1 और II :

पी टी एस-1

12.0%

टी पी एस -11

10.%

टिप्पण :

स्थिरीकरण अत्रधि के दौरान , मानकीय अतिरिक्त खपत ऊपर खंड ( क ) , ( ख ) और ( ग ) में उपदर्शित संनियमों से अधिक 0.5% तक मानी जाएगी।

( vi ) स्थिरीकरण अवधि

यूनिट के संबंध में उस यूनिट के वाणिज्यिक प्रचालन की तारीख से प्रारंभ होने वाली स्थिरीकरण अवधि निम्नानुसार मानी जाएगी , अर्थात्:-

(क) कोयला आधारित और लिग्नाइट चालित उत्पादन केन्द्र

180दिन (ख ) गैस टर्बाइन/संयुक्त आवर्तन उत्पादन केन्द्र

90दिन टिप्पण :

स्थिरीकरण अर्वाध और स्थिरीकरण अवधि के दौरान लागू शिथिल संनियम 1-4-2006 से लागू न होंगे। "

के. एस. ढींगरा , प्रमुख ( विधि)

[विज्ञापन III/IV/150/2006/असा. ] पाद टिप्पण :

मूल विनियम भारत के राजपत्र ( असाधारण ) भाग III , खंड 4 में तारीख 29-3-2004 को अधिसूचित किए गए थे और समय समय पर निम्नानुसार संशोधित किए गए थे :

(i ) भारत के राजपत्र ( असाधारण ) , भाग III , खंड 4 , तारीख 9-9-2004 को अधिसूचित केन्द्रीय विद्युत विनियामक आयोज (टैरिफ के निबंधन और शर्तें ) ( पहला संशोधन ) विनियम, 2004 ।

(ii ) भारत के राजपत्र ( असाधारण ) , भाग III , खंड 4 , तारीख 25-8-2005 को अधिसूचित केन्द्रीय विद्युत विनियामक आयोज (टैरिफ के निबंधन और शर्तें ) ( पहला संशोधन) विनियम, 2005 ।

( iii ) भारत के राजपत्र ( असाधारण ) , भाग III , खंड 4, तारीख 8-6-2006 को अधिसूचित केन्द्रीय विद्युत बिनियामक आयोज (टैरिफ के निबंधन और शर्तें ) ( पहला संशोधन ) विनियम, 2006 ।

CENTRAL ELECTRICITY REGULATORY COMMISSION

NOTIFICATION

New Delhi , the 13th March, 2007

No. L- 7 / 25 ( 5 )/2003-CERC.-In exercise of powers conferred under Section 178 of the Electricity Act, 2003 (36 of 2003), and all other powers enabling it in this behalf, and after previous publication, the Central Electricity Regulatory Commission hereby makes the following regulations to further amend the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations , 2004 , hereinafter referred to as "the principal regulations " , namely:-

1. Short title and commencement. ( 1 ) These regulations may be called the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) (Amendment) Regulations, 2007.

(2) These regulations shall come into force on 1-4-2007.

2. Amendment of Regulation 16. Regulation 16 of the principal regulations shall be substituted as under:

"16. Norms of Operation: The norms of operation as given hereunder shall apply :

भारत का राजपत्र असाधारण

[ भाग III- खण्ड 4 ]

(i) Target availability for recovery offull capacity (fixed) charges

-80% (a).All thermal power generating stations , except those covered under clause (b) below

-75% (b) Thermal power generating stations of Neyveli Lignite Corporation Ltd. (TPS -I , TPS- II, Stage I & II and TPS I Expansion ) and Talchar Thermal Power Station ofNational Thermal Power Corporation Ltd.

Note: Recovery of capacity (fixed) charges below the level of target availability shall be on pro rata basis. At zero availability, no capacity charges shall be payable .

(ii)Target Plant Load Factor for Incentive

-80% (a) All thermal power generating stations , except those covered under clause (b ) below

-75% (b) Thermal power generating stations of Neyveli Lignite Corporation Ltd. (TPS-I, TPS- II , Stage I & II and TPS - I Expansion) and Talcher Thermal Power Station of National Thermal Power Corporation Ltd.

(iii)Gross Station Heat Rate

(a) Coal -based thermal power generating stations , other than those covered under clauses (b) and (c)below

500 MW and above sets

200/210/250 MW sets

2550 Kcal/kWh

2600Kcal/kWh

During stabilization period

2450 Kcal/kWh

2500 Kcal/kWh

Subsequent period

Note 1

Inrespect of 500 MW and above units where the boiler feed pumps are electrically operated , the gross station heat rate shall be 40 kCal/kWh lower than the station heat rate indicated above .

Note 2

For generating stations having combination of 200/210/250 MW sets and 500 MW and above sets, the normative gross station heat rate shall be the weighted average station heat rate.

(b) Talcher Thermal Power Station

(c) Tanda Thermal Power Station.

3100 kCal /kWh

2850 kcal/kWh

(d) Lignite - fired Thermal Power generating Stations

(1) For lignite- fired generating stations except for TPS - I and TPS - II (Stage I & II) of Neyveli Lignite Corporation Ltd. , the gross station heat rates specified under clause ( a) above for coal -based thermal power generating stations shall be corrected, using multiplying factors as given below:

(1) For lignite having 50 % moisture : Multiplying factor of1.10

(ii) For lignite having 40% moisture : Multiplying factor of1.07

(iii) For lignite having 30 % moisture : Multiplying factor of1.04

(iv) For other values of moisture content , multiplying factor shall be pro -rated for moisture content between 30-40 and 40-50 depending upon the rated values of multiplying factor for the respective range given under sub-clauses ( i) to (iii) above ..

(2) TPS - I,and TPS- II (Stage I & II) ofNeyveli Lignite Corporation Ltd,

TPS-I

TPS- II

3900 kcal/kWh

2850 kcal/kWh

(e) Gas Turbine/Combined Cycle generating stations

(1) Existing generating stations owned by National Thermal Power Corporation Ltd.

Opencycle

Combined cycle....

Name ofGenerating

station.

(kCal/kWh)

(kCal/kWh)

                                 2000                                 2900
GandharGPS
KawasGPS                         2075                                 3040
                                 2075                                 3010
AntaGPS
DadriGPS                         2075                                 3010
                                 2100                                 3045
AuraiyaGPS
                                 2000                                 2900
 FaridabadGPS
                                 2000                                 2900
Kayamkulam GPS

6

THE GAZETTE OF INDIA : EXTRAORDINARY

[PART III-SEC. 4]

( ii) Generating stations declared under commercial operation on or after 1-4-2004

Advanced Class Machines

F /EA /EC/E2 Class Machines

2685 kCal/kWh

2830 kCal/kWh Open cycle

1850 kCal/kWh

Combined cycle

1950 kCal/kWh

(iii) Small Gas Turbine Power Generating Stations:

( a) Assam Gas Based Power Station , Kathalguri:

3225 kcal/kWh

Open Cycle

2250 kCal/kWh

CombinedCycle

3580 kCal/kWh

(b ) Agartala Gas Based Power Station, Ramachandranagar : Open Cycle

( c ) Other than (a) and (b) above :

With Natural Gas

With Liquid Fucl

3125 kcal/kWh

Open Cycle

1.02 x3125 kCal/kWh CombinedCycle

2030 kCal/kWh

1.02 x2030 kCal/kWh

(iv) Secondary Fuel Oil Consumption

(a) Coal -based generating stations :

( i ) All coal -based thermal power generating stations except those covered under sub - clause ( ii) below :

Subsequent period

During Stabilization period

4.5 ml/kWh

2.0 ml/kWh

( ii) Talcher Thermal Power Station

3.5 ml/kWh

(b) Lignite- fired generating stations:

Subsequent period

During Stabilization period

5.0 ml/ kWh

3.0 ml/kWh

(v) Auxiliary Energy Consumption

(a) Coal-based generating stations :

With cooling tower

Without cooling tower (1) 200 MW series

9.0%

8.5%

7.5%

7.0%

( i ) 500 MW series Steam driven boiler feed pumps

9.0%

8.5%

Electricallydriven boiler feed pumps

(iii) Talcher Thermal Power Station

11.0%

( iv) Tanda Thermal Power Station

12.0%

(b ) Gas Turbine / Combined Cycle generating stations :

3.0%

( i) Combined cycle

1.0%

( ii) Open cycle

(c) Lignite- fired thermal power generating stations :

(1) All generating stations , except TPS - I and TPS - II ( Stage 1 & II ) of Neyveli Lignite Corporation Ltd.: The auxiliary energy consumption norms shall be 0.5 percentage point more than the above auxiliary energy consumption norms of coal - based generating stations at ( v) ( a ) ( i ) & (ii ) above .

( ii ) TPS - I & TPS - II Stage - I & II of Neyveli Lignite Corporation Ltd.:

TPS - I

12.0%

TPS- 11

10.0%

i भारत का राजपत्र असाधारण

[ भाग III- खण्ड 4 ]

Note:

During stabilization period, normative auxiliary consumption shall be reckoned at 0.5 percentage point more than the norms indicated at (a), (b) and (c) above .

(vi) Stabilization period

In relation to a unit, stabilization period shall be reckoned commencing from the date ofcommercial operation of that unit as follows, namely:

180 days

(a) Coal-based and lignite- fired generating stations

90days

(b) Gas turbine/combined cycle generating stations

Note:

The stabilization period and relaxed norms applicable during the stabilization period shall cease to apply from 1-4-2006.

K. S. DHINGRA, Chief(Law)

[ADVT III/IV/150/2006/Exty.]

Note:

Theprincipal regulations were notified in the Gazette of India (Extraordinary) Part - III, Section 4 on 29-3-2004 and were amended from time to time as under :

(i) Central Electricity Regulatory Commission (Terms and Conditions ofTariff) (First Amendment) Regulations, 2004, notified in the Gazette of India (Extraordinary), Part III, Section 4 dated 9-9-2004.

(ii) Central Electricity Regulatory Commission (Terms and Conditions of Tariff) (First Amendment) Regulations, 2005,notified in the Gazette of India (Extraordinary) , Part III, Section 4dated25-8-2005.

(iii) Central Electricity Regulatory Commission (Terms and Conditions ofTariff) (First Amendment ) Regulations, 2006, notified in the Gazette of India (Extraordinary) , Part III , Section 4 dated 8-6-2006.

Printed by the Manager , Govt . of India Press, Ring Road, Mayapuri , New Delhi - 110064. and Published by the Controller of Publications, Delhi - 110054.

Cite this issue. Extraordinary Gazette of India, Government of India, 14 March 2007. Indian Gazettes, https://egazette.servantsofknowledge.in/details/in.gazette.central.e.2007-03-14.9455/. Archive identifier in.gazette.central.e.2007-03-14.9455.