Servants of Knowledge
Extraordinary Gazette of India · Government of India

The Central Electricity Regulatory Commission (Terms and Conditions of Tariff)(Third Amendment) Regulation, 2007.

Published 01 October 2007

Ministry
Central Electricity Authority
Department
NOT available
Office
NOT available
Gazetteid
NOT available ( 11921 )
Identifier
in.gazette.central.e.2007-10-01.11921
Languages
English, Hindi
Published at
Original source ↗

17

REGD . NO . D. L -33004/99 रजिस्ट्री सं ० डी० एल०-33004/99

भारतको राजपत्र The Gazette of India

असाधारण

EXTRAORDINARY

भाग III - खण्ड 4

PART III-Section 4

प्राधिकार से प्रकाशित

PUBLISHED BY AUTHORITY

सं. 196]

No. 196]

नई दिल्ली, सोमवार , अक्तूबर 1 , 2007/आश्विन 9 , 1929 NEW DELHI , MONDAY, OCTOBER 1, 2007/ASVINA 9 , 1929

केंद्रीय विद्युत विनियामक आयोग

टिप्पण: लक्ष्य उपलब्धता के स्तर के नीचे की क्षमता ( नियत )

अधिसूचना

नई दिल्ली, 27 सितम्बर , 2007

प्रभारों की वसूली आनुपातिक आधार पर की जाएगी । शून्य उपलब्धता पर , कोई भी क्षमता प्रभार संदेय नहीं होगा ।

( ii ) प्रोत्साहन के लिए लक्ष्य संयंत्र भार कारक

(क) नीचे खंड ( ख ) के अधीन आने वाले केंद्रों के सिवाय सभी ताप उत्पादन केंद्र -80%

(ख) नेवेली लिग्नाइट कारपोरेशन लि. के ताप ऊर्जा उत्पादन केंद्र ( टी पी एस -1, टी पी एस II , प्रक्रम 1 और 2 विस्तारण ) -75% सं. एल -7/ 25( 5 )/2003 - सीईआरसी. केंद्रीय विद्युत विनियामक आयोग , विद्युत अधिनियम , 2003 ( 2003 का 36 ) की धारा 178 के अधीन प्रदत्त शक्तियों का और इस निमित्त सामर्थ्यकारी सभी अन्य शक्तियों का प्रयोग करते हुए , और पूर्व प्रकाशन के पश्चात्, केन्द्रीय विद्युत विनियामक आयोग ( टैरिफ के निबंधन और शर्तें ) विनियम , 2004 , जिसे इसे इसमें इसके पश्चात्, " मूल विनियम" कहा गया है , का और संशोधन करने के लिए निम्नलिखित विनियम बनाता है , अर्थात्:-

(iii ) सकल केंद्र हीट दर -

(क) नीचे खंड ( ख) और ( ग ) मैं दिए गए केन्द्रों के. सिवाय कोयला आधारित ताप ऊर्जा उत्पादन केन्द्र 1. संक्षिप्त नाम तथा प्रारंभ. ( 1 ) इन विनियमों का संक्षिप्त नाम केंद्रीय विद्युत विनियामक आयोग ( टैरिफ के निबंधन और शर्तें) (तीसरा संशोधन ) विनियम , 2007 है ।

200/210/250

(2) ये विनियम 1-10-2007 से प्रवृत्तं होंगे ।

500 मेगावाट और उससे ऊपर के सैट

मेगावाट सैट

2600 कि. कैलोरी/

स्थिरीकरण अवधि

2. विनियम 16 का संशोधन मूल विनियम के विनियम 16 के स्थान पर , निम्नलिखित विनियम रखा जाएगा , अर्थात्:-

250कि. कैलोरी/ किलोवाट घंटा

किलोवाट घंटा

के दौरान

" 16. प्रचालन के संनियम प्रचालन के संनियम जो नीचे दिए गए हैं, निम्नलिखित को लागू होंगे -

पश्चात्वर्ती अवधि

2450कि. कैलोरी/ किलोवाट घंटा

2500कि. कैलोरी/ किलोवाट घंटा

( i ) पूर्ण क्षमता ( नियत ) प्रभारों की वसूली के लिए लक्ष्य उपलब्धता

(क ) नीचे खंड ( ख ) के अधीन आने वाले स्टेशनों के सिवाय सभी ताप ऊर्जा उत्पादन केंद्र -80%

टिप्पण 1 : 500 मेगावाट और उससे ऊपर के यूनिटों के संबंध में , जहां बायलर फीड पम्प विद्युत से प्रचालित किए जाते हैंवहां कुल उत्पादन ताप दर उपरोक्त उपदर्शित उत्पादन ताप दर से 40 कि. कैलोरी /किलोवाट घंटा कम होगी ।

(ख) नेवेली लिग्नाइट कारपोरेशन लि. के ताप ऊर्जा उत्पादन केंद्र ( टी पी एस -1 , टी पी एस II , प्रक्रम

टिप्पण 2 : ऐसे उत्पादन केन्द्रों के लिए , जिनके पास 200/210/250 मेगावाट सैट और 500 मेगावाट और उससे ऊपर के 1 और 2 और टी पी एस -1 विस्तारण ) -75 %

4061 GI/2007

(1) 2

THE GAZETTE OF INDIA : EXTRAORDINARY

सैट का संयोजन है , मानकीय सकल उत्पादन केन्द्र ताप दर, भारित औसत उत्पादन केन्द्र ताप दर होगी ।

(ख) तलचर ताप ऊर्जा केन्द्र

2975 कि. कैलोरी/ किलोवाट घंटा

( ग) यंडा ताप ऊर्जा केन्द्र

2850 कि. कैलोरी/ किलोवाट घंटा

( घ ) लिग्नाइट से चलने वाले तापीय ऊर्जा उत्पादन केन्द्र

( 1 ) कोयला आधारित ताप ऊर्जा उत्पादन केन्द्रों के लिए

ऊपर खंड ( क) के अधीन विनिर्दिष्ट सकल उत्पादन केन्द्र ताप की दरें नेवेली लिग्नाइट कारपोरेशन लिमिटेड के टीपीएस -1 और टीपी

एस- II ( प्रक्रम 1 और 2 ) के सिवाय नीचे दिए गए गुणक कारकों का उपयोग करते हुए , संशोधित की जाएगी:-

(i ) 50% आर्द्रता वाली लिग्नाइट के लिए 1.10 का गुणनकारक;

( ii ) 40% आर्द्रता वाली लिग्नाइट के लिए 1.07 का गुणनकारक;

(iii) 30% आर्द्रता वाली लिग्नाइट के लिए : 1.04 का गुणनकारक;

( iv ) आर्द्रता अंतर्वस्तु के अन्य मूल्यों के लिए , गुणककारक उपरोक्त उप- खंड ( i ) से खंड ( iii ) में दी गई

अपनी- अपनी रेंज के लिए गुणककारक के रेटेड मूल्यों पर निर्भर रहते हुए , 30-40 और 40-50 की बीच की आर्द्रता अंतर्वस्तु हेतु अनुपात में निर्धारित की जाएगी ।

(2) नेवेली लिग्नाइट कारपोरेशन लिमिटेड के टीपीएस -1 और टीपीएस- II ( प्रक्रम 1 और 2) :

टीपीएस -1

3900 कि. कैलोरी/किलोवाट घंटा

टीपीएस -11 2850 कि. कैलोरी/किलोवाट घंटा

( ङ) गैस टर्बाइन/संयुक्त आवर्तन ऊर्जा उत्पादन केन्द्र-

(i ) एनटीपीसी लि. के स्वामित्वाधीन विद्यमान उत्पादन केन्द्र

संयुक्त आवर्तन

उत्पादन केन्द्र का नाम

(साइकिल)

खुला आवर्तन (कि. कैलोरी/किलोवाट)

(कि. कैलोरी/किलोवाट)

गंधार जीपीएस

2000

2900

2075

3010 कवास जीपीएस

अन्ता जीपीएस

2075

3010

* दादरी जीपीएस

2075

3010

2100

औरेयाजीपीएस

3045

2000

फरीदाबाद जीपीएस

2900

2000

2900 कायमकुलम जीपीएस

[PART III-SEC . 4]

(ii) 1-4-2004 को या उसके पश्चात् वाणिज्यिक प्रचालन के अधीन घोषित उत्पादन केन्द्र :

उन्नत श्रेणी मशीन ई/ईए/ईसी/ई 2 श्रेणी मशीन

खुला आवर्तन 2685 कि. कैलोरी/ किलोवाट घंटा

2830कि. कैलोरी/ किलोवाट घंटा

संयुक्त आवर्तन 1850 कि. कैलोरी/ किलोवाट घंटा

1950कि. कैलोरी/ किलोवाट घंटा

( iii ) लघु गैस टर्बाइन ऊर्जा उत्पादन केन्द्र :

( क) असम गैस आधारित ऊर्जा केन्द्र , कैथलगुड़ी :

खुला आवर्तन 3225 कि.कैलोरी/किलोवाट घंटा

संयुक्त आवर्तन 2250 कि.कैलोरी/किलोवाट घंटा

(ख) अगरतला गैस आधारित ऊर्जा केन्द्र, रामचन्द्रनगर

खुला आवर्तन 3580 कि. कैलारी/किलोवाट घंटा

( ग ) उपरोक्त ( क ) और ( ख ) को छोड़कर

प्राकृतिक गैस सहित द्रव ईंधन सहित

3125 कि. कैलारी/

खुला आवर्तन

1.02 × 3125 कि. कैलोरी/ किलोवाट घंटा किलोवाट घंटा

संयुक्त आवर्तन 2030 कि. कैलोरी/ किलोवाट घंटा

1.02 × 2030 कि. कैलोरी/ किलोवाट घंटा

( iv ) गौण ईंधन तेल खपत

(क) कोयला आधारित उत्पादन केन्द्र :

( i) सभी कोयला आधारित ताप ऊर्जा उत्पादन केन्द्र

स्थिरीकरण अवधि के दौरान पश्चात्वर्ती अवधि

4.5 मि.ली. /किलोवाट घंटा 2.0 मि.ली./किलोवाट

घंटा

(ख) लिग्नाइट आधारित ताप ऊर्जा उत्पादन केन्द्र :

स्थिरीकरण अवधि के दौरान

पश्चात्वर्ती अवधि

5.0 मि.ली./किलोवाट घटा 3.0 मि.ली./किलोवाट घंटा असाधारण

भारत का राजपत्र

[ भाग III- खण्ड 4 ]

(v ) अतिरिक्त ऊर्जा खपत

(क) कोयला आधारित उत्पादन केन्द्र :

शीतलन ( कूलिंग )

शीतलन (कूलिंग )

टावर सहित टावर के बिना

8.5%

9.0%

(i ) 200 मेगावाटश्रृंखला

(ii) 500 मेगावाट श्रृंखला

7.0%

7.5%

भाप 'चालित बायलर

फीड पम्प

8.5%

9.0%

विद्युत चालित बायलर फीड पम्प

10.5%

(iii ) तलचर ताप ऊर्जा केन्द्र

12.0%

( iv ) टांडा ताप ऊर्जा केन्द्र

( ख ) गैस टर्बाइन/संयुक्त आवर्तन उत्पादन केन्द्र:

3.0%

( i ) संयुक्त आवर्तन

1.0%

(ii ) खुला आवर्तन

(ग ) लिग्नाइट आधारित ताप ऊर्जा उत्पादन केन्द्र :

( i ) नेवेली लिग्नाइट कारपोरेशन लिमिटेड के टीपीएस -1 और टीपीएस- II (प्रक्रम 1 और II ) के सिवाय सभी उत्पादन केन्द्र:

उपरोक्त ( v ) ( क ) ( i ) और ( ii ) पर कोयला आधारित उत्पादन केन्द्र के सहायक ऊर्जा खपत संनियम का प्रतिशतता बिंदु अतिरिक्त ऊर्जा खपत संनियम से अधिक 0.5 % होगा ।

(ii ) नेवेली लिग्नाइट कारपोरेशन लिमिटेड के टीपीएस -1 और

टीपीएस- II प्रक्रम I और II :

12.0%

टीपीएस -1

10.0%

टीपीएस- II

टिप्पण: स्थिरीकरण अवधि के दौरान , मानकीय अतिरिक्त खपत ऊपर खंड ( क) , ( ख ) और ( ग ) में उपदर्शित संनियमों से अधिक 0.5 % तक मानी जाएगी ।

(vi ) स्थिरीकरण अवधि

यूनिट के संबंध में, उस यूनिट के वाणिज्यिक प्रचालन की तारीख से प्रारंभ होने वाली स्थिरीकरण अवधि निम्नानुसार मानी जाएगी, अर्थात्:-

(क) कोयला आधारित और लिग्नाइट चालित उत्पादन केन्द्र

180दिन

90दिन ( ख ) गैस टर्बाइन/संयुक्त आवर्तन उत्पादन केन्द्र

टिप्पण:

स्थिरीकरण अवधि और स्थिरीकरण अवधि के दौरान लागू शिथिल संनियम 1-4-2006 से लागू न होंगे । " के. एस. ढींगरा , प्रमुख ( विधि)

[ विज्ञापन III/IV/ 150/2007/असा. ]

पाद-टिप्पण :

मूल विनियम भारत के राजपत्र ( असाधारण ) भाग- III , खंड 4 में तारीख 29-3-2004 को अधिसूचित किए गए थे और समय - समय पर निम्नानुसार संशोधित किए गए थे :

3

(i ) भारत के राजपत्र ( असाधारण ) , भाग III , खंड 4 , तारीख 9-9-2004 को अधिसूचित केन्द्रीय विद्युत विनियामक आयोग ( टैरिफ के निबंधन और शर्तें ) ( पहला संशोधन) विनियम, 2004 ।

(ii ) भारत के राजपत्र ( असाधारण ) , भाग III , खंड 4 , तारीख 25-8-2005 को अधिसूचित केन्द्रीय विद्युत विनियामक आयोग ( टैरिफ के निबंधन और शर्तें ) (संशोधन ) विनियम , 2005 ।

(iii ) भारत के राजपत्र ( असाधारण ) , भाग III , खंड 4 , तारीख 8-6-2006 को अधिसूचित केन्द्रीय विद्युत विनियामक आयोग ( टैरिफ के निबंधन और शर्तें ) ( पहला संशोधन ) विनियम , 2006 ।

(iv ) भारत के राजपत्र ( असाधारण ) , भाग III , खंड 4 , तारीख 14-3-2007 को अधिसूचित केन्द्रीय विद्युत विनियामक आयोग ( टैरिफ के निबंधन और शर्तें ) ( संशोधन ) विनियम , 2007 1

(v ) भारत के राजपत्र ( असाधारण ) , भाग III , खंड 4 , तारीख 27-4-2007 को अधिसूचित केन्द्रीय विद्युत विनियामक आयोग ( टैरिफ के निबंधन और शर्तें ) ( दूसरा संशोधन ) विनियम , 2007 ।

CENTRAL ELECTRICITY REGULATORY COMMISSION

NOTIFICATION

New Delhi, the 27th September , 2007

No. L- 7/ 25 (5 ) /2003-CERC.-In exercise ofpowers conferred under Section 178 of the Electricity Act , 2003 (36 of2003) , and all other powers enabling it in this behalf, and after previous publication, the Central Electricity Regulatory Commission hereby makes the following regulations to further amend the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations , 2004, hereinafter referred to as "the principal regulations", namely:-

1. Short title and commencement:-( 1 ) These regulations may be called the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) (Third Amendment) Regulations , 2007 .

(2) These regulations shall come into force on 1-10-2007 .

2. Amendment of Regulation 16:-Regulation 16 of the principal regulations shall be substituted as under :

"16. Norms of Operation : The norms of operation as given hereunder shall apply:

4

THE GAZETTE OF INDIA : EXTRAORDINARY

(i) Target Availability for recovery of full Capacity ( fixed ) charges

-80% (a) All thermal power generating stations , except those covered under clause (b ) below

(b) Thermal power generating stations of Neyveli Lignite Corporation Ltd. (TPS- I , TPS - II , Stage I & II and TPS - I Expansion) . -75%

Note:

Recovery of capacity ( fixed) charges below the level of target availability shall be on pro rata basis . At zero availability , no capacity charges shall be payable .

(ii) Target Plant Load Factor for Incentive

-80 % (a) All thermal power generating stations , except those covered under clause (b ) below

-75% (b) Thermal power generating stations of Neyveli Lignite Corporation Ltd. , (TPS- I , TPS - II , Stage I & II and TPS - I Expansion).

(iii) Gross Station Heat Rate

(a) Coal -based thermal power generating stations , other than those covered under clauses (b) and (c) below :

200/210/250 MW sets

500 MW and abovesets

During stabilization 2600 KCal/kWh 2550 KCal /kWh

period

2500 KCal/kWh 2450 KCal/kWh Subsequent period

Note 1:

Inrespect of 500 MW and above units where the boiler feedpumps are electrically operated , the gross station heat rate, shall be 40 kCal/kWh lower than the station heat rate indicated above .

Note 2:

For generating stations having combination of 200/210/ 250MW sets and 500 MW and above sets , the normative gross station heat rate shall be the weighted average station heat rate .

2975 kCal/KWh (b) Talcher Thermal Power Station

2850 kCal/kWh (c) Tanda Thermal Power Station

(d) Lignite- fired thermal power generating stations:

(1) For lignite- fired generating stations except for TPS - I and TPS - II ( Stage I & II) of Neyveli Lignite Corporation Ltd. , the gross station heat

[PART III-SEC. 4]

rates specified under clause (a) above for coal- based thermal power generating stations shall be corrected, using multiplying factors as given below:

(i) For lignite having 50 % moisture: Multiplying factor of 1.10

(ii) For lignite having 40 % moisture :Multiplying factor of1.07

(iii) For lignite having 30% moisture : Multiplying factor of 1.04

(iv) For other values of moisture content , multiplying factor shall be pro- rated for moisture/content between 30-40 and 40-50 depending upon the rated values of multiplying factor for the respective range given under Sub- clauses (i) to ( iii ) above .

(2) TPS - I and TPS - II ( Stage I & II ) of Neyveli Lignite Corporation Ltd.

TPS- I 3900 kCal/kWh

TPS - II 2850 kCal/kWh

(e) Gas Turbine/ Combined Cycle generating stations:

Existing generating stations owned by National Thermal Power Corporation Ltd. (1)

Name of Generating station

Open cycle (kCal/kWh

Combined cycle (kCal/kWh)

2000

2900 GandharGPS

2075

Kawas GPS

3010

2075

3010 Anta GPS

3010 Dadri GPS

2075

2100

3045 Auraiya GPS

2000

2900 Faridabad GPS

2900

2000

Kayamkulam GPS

(ii) Generating stations declared under commercial operation on or after 1-4-2004.

E/EA/ EC/E2 Class Machines

Advanced Class Machines

2830 kCal/kWh

2685kCal/kWh

Open cycle-

1950 kCal/kWh

1850 kCal/kWh

Combined cyle-

(iii) Small Gas Turbine Power Generating Stations:

(a) Assam Gas Based Power Station , Kathalguri:

3225 kCal/kWh OpenCycle

CombinedCycle 2250 kCal/kWh 5

भारत का राजपत्र

[ भाग III- खण्ड 4 ]

(b) Agartala Gas Based Power Station , Ramachandranagar :

3580 kCal /kWh OpenCycle

(c) Other than (a) and (b) above:

WithLiquid Fuel

WithNatural Gas

1.02 × 3125 kcal/kWh 3125 kcal/kWh

Open Cycle-

2030 kCal/kWh 1.02 × 2030 kCal/kWh Combined Cyle-

(iv) Secondary fuel oil consumption

(a) Coal -based generating stations :

(i) All coal-based thermal power generating

stations

During Stabilization period Subsequent period

4.5 ml/kWh

2.0ml/kWh

(b) Lignite - fired generating stations:

During Stabilization period Subsequent period

3.0ml/kWh 5.0ml/kWh

(v) Auxiliary Energy Consumption

(a) Coal -based generating stations:

Without cooling tower

With cooling tower

9.0%

8.5% (i) 200 MW series

(ii) 500 MW series steam driven boiler

7.0%

7.5%

feed pumps

9.0%

8.5% Electrically driven boiler feed pumps

10.5%

(iii) Talcher Thermal PowerStation

12.0%

(iv) Tanda Thermal Power Station

(b) Gas Turbine /Combined Cycle generating

stations:

(i) Combined cycle 3.0%

1.0%

(ii)Open cycle

(c) Lignite- fired thermal power generating stations:

(i) All generating stations , except TPS - I and TPS- II (Stage I & II) of Neyveli Lignite Corporation Ltd.:

The auxiliary energy consumption norms shall be 0.5 percentage point more than the above auxiliary energy consumption norms of coal- based generating stations at (v) ( a) ( i) and (ii) above .

Printed by

असाधारण

(ii) TPS - I & TPS- II Stage - I & II of Neyveli Lignite Corporation Ltd.:

TPS- I

12.0%

TPS - II

10.0%

Note:

During stabilization period , normative auxiliary consumption shall be reckoned at 0.5 percentage point more than the norms indicated at (a) , (b) and (c) above.

(vi) Stabilization period

In relation to a unit, stabilization period shall be reckoned commencing from the date of commercial operation of that unit as follows , namely :-

180days (a) Coal-based and lignite-fired generating stations

90days (b) Gas turbine /combined cycle generating stations

Note:

The stabilization period and relaxed norms applicable during the stabilization period shall cease to apply from1-4-2006 . "

K.S. DHINGRA, Chief(Law)

[ADVT . III/IV/ 150/2007-Exty. ]

Note : The principal regulations were notified in the Gazette ofIndia (Extraordinary), Part III , Section 4 on 29-3-2004 and were amended from time to time as under :-

(1) Central Electricity Regulatory Commission (Terms and Conditions of Tariff) ( First Amendment) Regulations , 2004, notified in the Gazette of India (Extraordinary) , Part III , Section 4dated 9-9-2004.

(ii) Central Electricity Regulatory Commission (Terms and Conditions of Tariff) (First Amendment) Regulations , 2005 , notified in the Gazette of India(Extraordinary), Part III , Section 4dated 25-8-2005.

(iii) Central Electricity Regulatory Commission (Terms and Conditions of Tariff) ( First Amendment ) Regulations , 2006, notified in the Gazette of India (Extraordinary) , Part III, Section 4 dated 8-6-2006.

(iv) Central Electricity Regulatory Commission (Terms and Conditions of Tariff) (Amendment) Regulations , 2007 , notified in the Gazette of India (Extraordinary) , Part III, Section 4 dated 14-3-2007.

(v) Central Electricity Regulatory Commission (Terms and Conditions of Tariff) ( Second Amendment) Regulations , 2007 , notified in the Gazette of India (Extraordinary) , Part III , Section 4dated 27-4-2007 .

the Manager, Govt. of India Press , Ring Road, Mayapuri , New Delhi - 110064 and Published by the Controller of Publications , Delhi - 110054.

4061 GI/ 07-2

Cite this issue. Extraordinary Gazette of India, Government of India, 01 October 2007. Indian Gazettes, https://egazette.servantsofknowledge.in/details/in.gazette.central.e.2007-10-01.11921/. Archive identifier in.gazette.central.e.2007-10-01.11921.