Servants of Knowledge
Extraordinary Gazette of India · Government of India

Amendment to the Guidelines for Tariff Based Competitive Bidding Process for Procurement Power from Grid Connected Wind Power Projects

Published 02 February 2024

Ministry
Ministry of Power
Department
Not Applicable
Office
Not Applicable
Gazetteid
CG-DL-E-02022024-251732
Identifier
in.gazette.central.e.2024-02-02.251732
Languages
English, Hindi
Published at
Original source ↗

click here for IIIF manifest

रजिस्ट्री सं. डी.एल.- 33004/99 REGD. No. D. L.-33004/99

xxxGIDHxxx xxxGIDExxx

सी.जी.-डी.एल.-अ.-02022024-251732

CG-DL-E-02022024-251732

असाधारण

EXTRAORDINARY

भाग I—खण्ड 1

PART I—Section 1

प्राधिकार से प्रकाशित

PUBLISHED BY AUTHORITY

सं. 23] नई दिल्ली, शुक्रवार, फरवरी 2, 2024/माध 13, 1945

No. 23] NEW DELHI, FRIDAY, FEBRUARY 2, 2024/MAGHA 13, 1945

विद्युत मंत्रालय

संकल्प

नई दिल्ली, 2 फरवरी, 2024

ग्रिड कनेक्टेड पवन विद्युत परियोजनाओं से विद्युत की खरीद के लिए टैरिफ आधारित प्रतिस्पर्धी बोली प्रक्रिया के दिशानिर्देशों में संशोधन

सं. 48-19/2/2024-एनआरई.—ग्रिड कनेक्टेड पवन विद्युत परियोजनाओं से विद्युत की खरीद के लिए टैरिफ आधारित प्रतिस्पर्धी बोली प्रक्रिया के दिशानिर्देशों को दिनांक 26 जुलाई, 2023 को भारत के राजपत्र (असाधारण) (भाग 1 - खंड 1) में प्रकाशित संकल्प संख्या 27/02/2023-आरसीएम के माध्यम से अधिसूचित किया गया है।

2. कें द्र सरकार एतद्द्वारा दिनांक 26 जुलाई, 2023 के उक्त दिशानिर्देशों में निम्नलिखित संशोधन को अधिसूचित करती है:

मौजूदा दिशानिर्देशों के खंड 14.5 को निम्नानुसार संशोधित किया गया है:-

खंड 14.5: विद्युत की आपूर्ति की शुरूआत में विलंब :

खंड 14.5 (ख) (ii) हटा दिया गया माना जाए।

हेमंत कु मार पाण्डेय, मुख्य अभियंता (आर एंड आर)677 GI/2024 (1) 2 THE GAZETTE OF INDIA : EXTRAORDINARY [PART I—SEC.1] MINISTRY OF POWER RESOLUTION

New Delhi, the 2nd February, 2024

Amendment to the Guidelines for Tariff Based Competitive Bidding Process for Procurement Power from Grid

Connected Wind Power Projects

No. 48-19/2/2024-NRE.—The Guidelines for Tariff Based Competitive Bidding Process for Procurement of Power from Grid Connected Wind Power Projects have been notified vide Resolution No.27/02/2023-RCM published in the Gazette of India (Extraordinary) (Part1 - Section 1) on 26th July 2023.

2. The Central Government hereby notifies the following amendment in the said guidelines dated 26th July, 2023:-

Clause 14.5 of the existing guidelines is modified as follows: -

Clause 14.5. Delay incommencement of supply of power:

Clause 14.5 (b)(ii) shall stand deleted.

HEMANT KUMAR PANDEY, Chief Engineer (R&R) Uploaded by Dte. of Printing at Government of India Press, Ring Road, Mayapuri, New Delhi-110064 and Published by the Controller of Publications, Delhi-110054.

Cite this issue. Extraordinary Gazette of India, Government of India, 02 February 2024. Indian Gazettes, https://egazette.servantsofknowledge.in/details/in.gazette.central.e.2024-02-02.251732/. Archive identifier in.gazette.central.e.2024-02-02.251732.