The Gujarat Government Gazette
EXTRAORDINARY
PUBLISHED BY AUTHORITY
Vol. LXVII ] MONDAY, OCTOBER 5, 2026 / ASVINA 13, 1948
Separate paging is given to this Part in order that it may be filed as a Separate Compilation.
PART IV-B
Rules and Orders (Other than those published in Parts I, I-A, and I-L) made
by the Government of Gujarat under the Gujarat Acts
URBAN DEVELOPMENT AND URBAN HOUSING DEPARTMENT
NOTIFICATION
Sachivalaya, Gandhinagar, 5th October, 2026
THE GUJARAT TOWN PLANNING AND URBAN DEVELOPMENT ACT, 1976.
No.GH/V/187 OF 2026/UDUHD/TPS/e-file/18/2025/8082/L: WHEREAS, under Government Notification, Urban Development and Urban Housing Department No. GH/V/101 of 1998/TPS-1496-3657-L, dated 22.07.1998 the Government of Gujarat, in exercise of the powers conferred by section 48(2) of the Gujarat Town Planning and Urban Development Act, 1976 (President's Act No. 27 of 1976) (hereinafter referred to as "the said Act") sanctioned the Draft Town Planning Scheme No. 27 (Bhatar-Majura) (hereinafter referred to as "the said Draft Scheme") submitted by the Surat Municipal Corporation, Surat (hereinafter referred to as "the said Authority");
AND WHEREAS, in exercise of the powers conferred by section 50 of the said Act, the Government of Gujarat appointed the Town Planning Officer for finalizing the said Draft Scheme;
AND WHEREAS, under Government Notification, Urban Development and Urban Housing Department No.GH/V/116 of 2022/TPS-142008-305-L, dated 01.09.2022 the Government of Gujarat, in exercise of the powers conferred by section 65 of the said Act 1976, sanctioned the Preliminary Town Planning Scheme No. 27 (Bhatar-Majura);
284-2 GUJARAT GOVERNMENT GAZETTE, EX., 05-10-2026 [ PART IV-B NOW THEREFORE, in exercise of the powers conferred by section 65 of the said Act, the Government of Gujarat hereby: - (a) Sanction "the said Final Scheme" with modifications enumerated in SCHEDULE below;(b) State that the said Final Scheme shall be kept open for inspection by the public at the office of the said authority during office hours of all working days;
(c) Fix the date of this notification as the date for the purpose of clause (b) of sub-section (2) of the section 65.
SCHEDULE
1. The execution period of scheme in cost of works shall be two years as per section 65(4) of the said Act.
By order and in the name of the Governor of Gujarat,
H V DORIWALA,
Officer on Special Duty & Ex-Officio
Deputy Secretary to Government.
----------