-JUIDCO Ltd./Water Supply Ranchi (Part-C)/DPR/436-2016-5301--
2
(
3.
BoQ
BoQ
| SL. No. | Details | Present Amount in Lakhs |
| 1 | Administrative Approval as per Govt. Resolution 3620 Dated 13.07.2018 | 26143.02 |
| 2 | Revised Project Cost as per JSOR-2018 without GST | 22183.09 |
| 3 | Added GST according to JSOR 2018-19 | 2661.92 |
| 4 | Total Project Cost after adding GST (B) | 24845.18 |
| 5 | Labour Cess @1 % of Total (B) | 248.45 |
| DPR charges | 204.25 | |
| 6 | PMC Charges @2.06 % of Total (B) | 511.81 |
| 7 | JUIDCOCharges (-- 3201 04.11.2016 ) | 630.57 |
| 8 | CAPEX | 26440.26 |
| 9 | Comprehensive 5 Years O&M Cost with Centralized SCADA Centre | 1353.90 |
| 10 | Total OPEX | 1353.90 |
| Total Cost of the Project (CAPEX + OPEX) | 27794.17 |