, Rs. 17,37,01,700/-
/PMAY/Birsa Munda Park/196/2017-3867--
(DPR)2 ( 7 Blocks G+4 Model
9 Blocks G+3 Model
(DPR)
(DPR)
| Comparetive Statement of Administrative Approved and Revised Technical Approved Cost of houses at BirsaMunda Smriti Park under PMAY (U) | NaN | |||
| Admistrative Approved Project Details | Revised Technical Approved Project Details | NaN | ||
| Administrative Approval Cost | Rs 14,36,26,300 | Revised Cost | Rs 17,37,01,700 | NaN |
| Type of Building Structure | G+4 (without lift) | Type of Building Structure | G+3 (without lift) | NaN |
| No. of Blocks | 7 | No. of Blocks | 9 | NaN |
| No. of Dwelling units | 175 | No. of Dwelling units | 180 | NaN |
| No. of DU's per floor | 5 | No. of DU's per floor | 5 | NaN |
| Per DU Cost | Rs 8,20,721.71 | **Per DU Cost | Rs 9,65,009.44 | NaN |
| Cost per sqft | Rs 2,620.19 | Cost per sqft | Rs 3,080.80 | NaN |
| **Cost changed due to change in design of foundation, provision of RCC covered drain (average size 3m wide X 2.5m depth X 187m long) so as to cater whole catchment area, addition of 2 building blocks & provision of dewatering of the site. | NaN | |||
| Abstract of Cost for Construction of Houses at Birsa Munda Smriti Park under PMAY (U) at Ranchi | NaN | |||
| Sl. No. | Particulars | Amount in Rs. | NaN | |
| 1 | For 1 Block G+3 Building (5 units per floor) | NaN | ||
| i. Cost of Civil Work | 1,46,54,984.00 | NaN | ||
| ii. Cost of Sanitary Work | 9,13,734.00 | NaN | ||
| iii. Cost of Electrical Work | 15,86,170.00 | NaN | ||
| Total | 1,71,54,888.00 | NaN | ||
| For 9 Nos. of Blocks | 15,43,93,992.00 | NaN | ||
| 2. | Cost of PCC Road | 25,23,050.00 | NaN | |
| 3. | Cost of Boundary Work | 15,16,752.00 | NaN | |
| 4. | Cost of Gate | 44,247.00 | NaN | |
| 5. | Cost of Drain | 78,92,765.00 | NaN | |
| 6. | Cost of Sump | 2,96,018.00 | NaN | |
| 7. | Cost of Boring | 10,55,900.00 | NaN | |
| 8. | Cost of Water Recharge Pit | 11,98,393.00 | NaN | |
| 9. | Cost of Septic Tank | 30,60,760.00 | NaN | |
| Total (A) | 17,19,81,876.62 | NaN | ||
| 10. | Add 1% Labour Cess (B) | 17,19,818.77 | NaN | |
| Grand Total (A+B) | 17,37,01,695.49 | NaN | ||
| Say | 17,37,01,700.00 | NaN |
JUIDCO Ltd. Centage ChargeCentageCharge DPRs PMC
PMAY(U)
Integration PFMS (Public Finance Management System)
Jharkhand Affordable Housing Development Fund (JAHDF)
(SLSMC)