THE
JHARKHAND GAZETTE
EXTRAORDINARY
PUBLISHED BY AUTHORITY
23 JYESTH 1946 (S)
No. 391
RANCHI, THURSDAY 13th JUNE, 2024
JHARKHAND STATE ELECTRICITY REGULATORY COMMISSION,
RANCHI
JSERC (Rooftop Solar PV Grid Interactive System and Net/Gross Metering) (Fourth Amendment) Regulations, 2024 -------- NOTIFICATION 29th May, 2024
Notification no.102--In order to promote generation of Renewable Energy in the state of Jharkhand, the Commission in exercise of powers conferred upon it under Section 181(1), read with Sections 61 (h), and 86(1)(a), (b) and (e) of the Electricity Act, 2003 (36 of 2003) and all other powers enabling it in that behalf, the Jharkhand State Electricity Regulatory Commission hereby makes the following Regulations to amend the JSERC (Rooftop Solar PV Grid Interactive System and Net/Gross Metering) Regulation, 2015 (hereinafter referred to as the 'Principal Regulations').
1. Short Title and Commencement
1.1. These Regulations may be called the JSERC(Rooftop Solar PV Grid Interactive System and Net/Gross Metering) (Fourth Amendment) Regulations, 2024.
Jharkhand Gazette (Extraordinary), Thursday, 13th June, 2024 2 2. Amendment to Regulation A7In the Principal Regulations, under chapter A7in clause 7.3a new proviso shall be inserted as below:
7.3 In order of priority, the Distribution Licensee shall complete the feasibility analysis for connecting the rooftop solar PV system to the distribution system within fifteen (15) days from the date of receipt of the application. The feasibility shall be valid for a period of one month unless extended by the Distribution Licensee. Provided that if the Distribution Licensee determines that an interconnection study is necessary, the Distribution Licensee shall intimate feasibility or otherwise within thirty (30) days from the receipt of the completed application.
Provided that the applications for roof top solar photo voltaic systems upto 10 kW
capacity, complete in all respects shall be deemed to have been accepted without
requiring technical feasibility study and any commensurate enhancement of the
sanctioned load of the consumer, as may be required, shall be carried out by the
distribution licensee.
By Order of the Commission,
R.P.Nayak, Secretary