GOVERNMENT OF KERALA
REVENUE (B) DEPARTMENT
NOTIFICATION
G.O.(P)No.2/2024/RD
Dated,03/01/2024
Thiruvananthapuram, S. R. O. No. 1/2024
In exercise of the powers conferred by 1st proviso to section 14 of the Right to Fair Compensation and Transparency in land Acquisition, Rehabilitation and Resettlement Act, 2013 (Central Act 30 of 2013), the Government of Kerala hereby extend the time limit in publishing the Notification as per sub-section (1) of Section 11 of LARR Act, 2013, from the date of appraisal of the Social Impact Assessment report by the Expert Group namely:
2Extension
G.O.(P)No.92/2022/RD dated 11.03.2022 and published in the Extra Ordinary Gazette No 824 dated 15.03.2022 has been issued in accordance with the provisions as per section (1) of section 4 of the Right to Fair Compensation and Transparency in land Acquisition, Rehabilitation and Resettlement Act, 2013 (Central Act 30 of 2013) with regard to the acquisition of 12.34 Hectares of land in Nadama and Manakunnam Villages of Ernakulam district for four laning of road from SN Junction (Tripunithura) to Poothotta.
AND WHEREAS, the District Collector, Ernakulam has informed that as per section 14 of LARR Act, 2013 where a preliminary notification under sub-section (1) of section 11 is not issued within twelve months from the date of appraisal of the Social Impact Assessment report submitted by the Expert Group under section 7, then, such report shall be deemed to have lapsed and a fresh Social Impact Assessment shall be required to be undertaken prior to acquisition proceedings under section 11. The date of appraisal of the Social Impact Assessment report by the Expert Group under section 7 was submitted on 11/11/2022 and the Notification under sub-section (1) of section 11 needs to be issued on or before 11/11/2023.
AND WHEREAS, the District Collector, Ernakulam has informed that as per 1st proviso to section 14 of LARR Act, 2013, Government have the power to extend the period of twelve months, if in its opinion circumstances exist justifying the same and hence requested to extend the time limit in publishing the Notification as per sub-section (1) of Section 11 of LARR Act, 2013 from the date of expiry.
NOW THEREFORE, sanction is accorded to extend the time limit for a further period of 6 months from the date of expiry ie. 11.11.2023 in publishing the Notification under subsection (1) of section 11 by invoking the provisions contained in 1st proviso to section 14 of LARR Act, 2013 with regard to the acquisition of 12.34 Hectares of land in Nadama and Manakunnam Villages of Ernakulam district for four laning of road from SN Junction (Tripunithura) to Poothotta subject to the condition that no more extension be granted under any circumstances.
By order of the Governor, ABDUL NASAR B
ADDITIONAL SECRETARY TO GOVERNMENT
Explanatory Note
(This does not form part of the notification, but is intended to indicate its general purport) G.O.(P)No. 92/2022/RD dated 11.03.2022 and published in the Extra Ordinary Gazette No 824 dated 15.03.2022 has been issued in accordance with the provisions of section (1) of section 4 of the Right to Fair Compensation and Transparency in land Acquisition, Rehabilitation and Resettlement Act, 2013 (Central Act 30 of 2013) with regard to the acquisition of 12.34 Hectares of land in Nadama and Manakunnam Villages of Ernakulam district for four laning of road from SN Junction (Tripunithura) to Poothotta. As per section 14 of LARR Act, 2013 where a preliminary notification under sub-section (1) of section 11 is not issued within twelve months from the date of appraisal of the Social Impact Assessment report submitted by the Expert Group under section 7, then, such report shall be deemed to have lapsed and a fresh Social Impact Assessment shall be required to be undertaken prior to acquisition proceedings under section 11. The date of appraisal of the Social Impact Assessment report by the Expert Group under section 7 was submitted on 11.11.2022 and the Notification as per sub-section (1) of section 11 needs to be issued on or before 11.11.2023. 1st proviso to section 14 of LARR Act, 2013 specifies that Government shall have the power to extend the period of twelve
3months, if in its opinion circumstances exist justifying the same and hereby extend the time limit for a further period of 6 months from the date of expiry ie. 11.11.2023 in publishing the Notification under sub-section (1) of section 11.
The notification is intended to achieve the above object.