NOTIFICATION
G.O.(P)No.19/2024/RD
Dated,16/01/2024
Thiruvananthapuram, S. R. O. No. 37/2024
2 ExtensionProceedings No. G3-2109/2020 dated 05th January 2023 and published in the Extra Ordinary Gazette No.31 dated 06th January 2023 has been issued in accordance with the provisions of subsection (1) of section 11 of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 with regard to the acquisition of land in Kunnamma & Champakulam villages of Alappuzha district for the construction of Pulinkunnu bridge & its approach road.
AND WHEREAS, the District Collector, Alappuzha has reported that as per Section 19(7) of LARR Act, 2013 mentions that the 19(1) Declaration has to be published within 12 months from the date of issuance of 11(1) Notification (preliminary notification) and that the 11(1) Notification issued as per Proceedings No. G3-2109/2020 dated 05th January 2023 and published in the Extra Ordinary Gazette No.31 dated 06th January 2023, expired on 05/01/2024 and therefore requested to extend the time limit for publishing the 19(1) Declaration.
NOW THEREFORE, sanction is accorded to extend the time limit in publishing the Declaration for a further period of 6 months from the date of expiry of the 11(1) notification ie. 05/01/2024 by invoking the provisions contained in 2nd proviso to Section 19(7) of the LARR Act, 2013 with regard to the acquisition of land in Kunnamma & Champakulam villages of Alappuzha district for the construction of Pulinkunnu bridge & its approach road, subject to the condition that no more extension be allowed under any circumstances.
By order of the Governor, ABDUL NASAR B
ADDITIONAL SECRETARY TO GOVERNMENT
Explanatory Note
(This does not form part of the notification, but is intended to indicate its general purport) Proceedings No. G3-2109/2020 dated 05th January 2023 and published in the Extra Ordinary Gazette No.31 dated 06th January 2023, has been issued in accordance with the provisions of subsection (1) of section 11 of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 with regard to the acquisition of land in Kunnamma & Champakulam villages of Alappuzha district for the construction of Pulinkunnu bridge & its approach road. As per Section 19(7) of LARR Act, 2013, the 19(1) Declaration has to be published within 12 months from the date of issuance of 11(1) Notification (preliminary notification) and that the 11(1) Notification issued as per Proceedings No. G3-2109/2020 dated 05th January 2023 and published in the Extra Ordinary Gazette No. 31 dated 06th January 2023, expired on 05/01/2024 and hereby extend the time limit for publishing the 19(1) Declaration.
The notification is intended to achieve the above object.