NOTIFICATION
G.O.(P) No.272/2026/RD Dated, Thiruvananthapuram, 02nd September, 2026.
S. R. O. No. 734/2026
2 ExtensionProceedings No.DCPKD/112081/2022-C1 dated 21st July 2025 and published in the Extraordinary Gazette No.2767 dated 28th July 2025 has been issued in accordance with the provisions of sub-section (1) of section 11 of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 with regard to the acquisition of land in Pattambi and Thrithala villages of Palakkad district for the construction of new bridge at Pattambi across Bharathapuzha.
AND WHEREAS, the District Collector, Palakkad has reported that as per Section 19(7) of LARR Act, 2013 mentions that the 19(1) Declaration has to be published within 12 months from the date of issuance of 11(1) Notification (preliminary notification) and that the 11(1) Notification issued as per Proceedings No.DCPKD/112081/2022-C1 dated 21st July 2025 and published in the Extraordinary Gazette No.2767 dated 28th July 2025 expired on 27-07-2026 and therefore requested to extend the time limit for publishing the 19(1) Declaration.
NOW, THEREFORE, sanction is accorded to extend the time limit in publishing the Declaration for a further period of six months from 28-07-2026 by invoking the provisions contained in 2nd proviso to Section 19(7) of the LARR Act, 2013 with regard to the acquisition of land in Pattambi and Thrithala villages of Palakkad district for the construction of new bridge at Pattambi across Bharathapuzha.
By order of the Governor, GEETHA A.
Additional Secretary to Government.
Explanatory Note
(This does not form part of the notification, but is intended to indicate its general purport.) Proceedings No.DCPKD/112081/2022-C1 dated 21st July 2025 and published in the Extraordinary Gazette No.2767 dated 28th July 2025 has been issued in accordance with the provisions of sub-section (1) of section 11 of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 with regard to the acquisition of land in Pattambi and Thrithala villages of Palakkad district for the construction of new bridge at Pattambi across Bharathapuzha. As per Section 19(7) of LARR Act, 2013, the 19(1)Declaration has to be published within 12 months from the date of issuance of 11(1) Notification (preliminary notification) and that the 11(1) Notification issued as per Proceedings No.DCPKD/112081/2022-C1 dated 21 st July 2025 and published in the Extraordinary Gazette No.2767 dated 28 th July 2025 expired on 27-07-2026 and therefore extend the time limit for publishing the 19(1) Declaration.
The notification is intended to achieve the above object.