Published by AuthorityPublished by AuthorityPublished by AuthorityPublished by AuthorityPublished by Authority
No. 32] CHANDIGARH, FRIDAY, AUGUST 7, 2020 (SRAVANA 16, 1942 SAKA)
PART III/
Notifications by High Court ; Labour Commissioner ; Advertisements ;
Director of Lotteries, Punjab and Notices, etc.
PUNJAB STATE TRANSMISSION CORPORATION LIMITED
(A Punjab Govt. Undertaking)
(Regd. Office: PSEB Head Office, The Mall, Patiala-147001)
Corporate Identity Number: U40109PB2010SGC033814 www.pstcl.org
O/o EIC/TS, PSTCL, Patiala Tel. & Fax No. 0175-2207774 E.mail: [email protected]
NOTIFICATION
The 30th July, 2020
No. 43/TS/ST-6016/Vol.-IV.-It is hereby notified that Punjab State Transmission Corporation Ltd. (PSTCL) proposes to undertake the following schemes/transmission works necessary for the dispersal/distribution of power for the improvement of the transmission and distribution system of the Punjab State Transmission Corporation Ltd.
TRANSMISSION WORKS FOR THE YEAR 2020-21
Sr. Name of Work
Scope of work, Size of ACSR No.
(Approx. Length conductor
of line). (Nominal
Aluminium
Area in mm2) 1. Regarding Route plan for 220KV D/C line from 400KV S/Stn. Length of Line of 420 Rajpura to 220 KV S/Stn. Bassi Pathana. The above line crosses part route plan
through following villages.
24.267 km.
1. ChanduaKhurd 2. DaruGarh 3. Dharamgarh 4. Alluna 5. Miapur
6. Basantpura 7. Jiwanpura 8. Shahpur 9. PatarsiChoota
10. Patarsi Wada 11. ChanduMajra 12. Rajindergarh
13. ChunniMajra 14. Sadhugarh15. RaiMajra
16. Mathi 17. Rampur (Be-Chirag) 18. Bora
( 262 )PART III] PUNJAB GOVT. GAZ., AUGUST 7, 2020 (SRAVANA 16, 1942 SAKA) 263 19. Randhawa 20.Ramgarh Saniyan 21. Balhara 22. Rashidpura
23. ChhotiBalhari 24. Manupur 25. Bharonpur and Bharonpur Basti
26. KotlaBajwada 27. Raipur Gajran 28. Mirpur 29. Jodhpur
30. Mahadiyan 31. FatehpurRaiyan 32. Mahimudpur 33. Shahidgarh
34. Ghamandgarh 35. Rasulpur 36. Bassi Pathana
2. Raising of Height of 132 KV S/C Jalandhar- Khanpur line in the land No change 200 of Sh. Avtar Singh Junior (TL-11 to 12) Deposit Work. TL-11A is
dismantled and new tower 11A is proposed at new location. The
above line crossunder/nearby HP Petro Plaza, Suriya Enclave opp.
Indian Oil corp. Ltd. Pathankot Bye Pass Jalandhar.
3. Regarding Route Plan of raising of height of 220KV DhandariKalan- No change 420 LaltonKalan line from TL 10 to TL-13 (P&M Deposit work). TL-11
and 12 are dismantled and proposed at new location. The above line
cross under/nearlyFocal Point Ludhiana.
4. Revised Route Plan of LILO of 220KV line Sunam-Mansa at 400KV No change 420 PGCIL Patran from TL-125 to TL-128. Location of TL no.126 and
127 are changed.The above line cross near Lakhmirwala village.
5. Proposed Route Plan for restoration of supply of 220KV GHTP Length of Line 420 LehraMohabbat-Himmatpura D/C on DC line due to fallen of tower's is 5.365 km and
on 21.6.2020.TL no.40,41,43,44,45,50 and 51 are proposed at resagging of line
new location.
will be carried out.
The above line crosses through following villages:-
1. Salbra 2. BhaiRupa.
6. Proposed Route plan for LILO of one ckt. of 132 KV Ropar- Length of part 200 Ghulal line for M/S CN IFFCO village Sehjo Majra/Rattipur route is 30 mtrs.
(Contributory work). 161-A is proposed between 161-162. The above
line cross through:-SehjoMajra/Rattipura.
7. Route plan for Restoration of supply of 220 KV RTP-Ghulal and No change 520 220 KV RTP-Gaunsgarh line due to damage of tower no. 154 due to
wind storm on night between 28.06.2020 and 29.06.2020. 154A is
proposed at new location.The above line cross through-Machhiwara
Village.
8. Rotue plan for raising of 220KV Sarna-Wadala Garanthian DC line Length of part 420 (Ckt.-I &II) Railway crossing between Batala-Quadian at Km 8/9-9/0 route is 130 mtrs
(Railway Deposit Work).Tower no. 167 is dismantled and 2 no. tower
166A and 167 is proposed at new location. The above line crosses
through following villages:-
1. Wadala Garanthian 2. Talwandi Chhungla.
9. Rotue plan for raising of 132KV Verpal- Naraingarh DC line Railway Length of part line 200 crossing Section between Cheratte- Khasa at no. 519/9-520/0 (Railway is 344 mtrs
Deposit Work). Tower no. 48 and 49 are dismantled and proposed at
new location. The above line crosses through following villages:-
1 .Ghumanpura 2. Municipal Corporation Amritsar.
264 PUNJAB GOVT. GAZ., AUGUST 7, 2020 (SRAVANA 16, 1942 SAKA) [PART III10 Route Plan for 132KV line from 132KV S/StnFaridkot to Kotkapura Length of Line 200 2 SC on DC towers. The above line crosses through following villages. is 21.976 km.
1. Faridkot 2. Araiyawala 3. PakhiKalan 4. Bholuwala
5. PakkaKalan6. Tehna7. Chahal8. Bhana 9. Chahal Beed
10. Nathewala 11. Sikhanwala12.DhaniTehal Singh 13. Sandhwan
14. Kotkapura.
Further TL no. 62 to 63of the above line crosses through 220kV No change in 420 MogaMukatsar Line, TL No. 112 is dismantled and four new towers length of line
are proposed for raising of line. The line crosses through the
following villages. 1. Sikhanwala 2.Dhani Tehal Singh
11 Route plan for Restoration of supply of 220 KV Kot Karor No change 420 (Talwandi Bhai)-Ferozepur line LILO at 220KV G/S/S Bottian
Wala due to damage of TL No.5 due to wind storm on 21.07.2020.
TL No.5 is proposed at new location. The above linecross
through-Bholuwala Village.
It is hereby notified that the PSTCL is undertaking and executing the sanctioned scheme and shall have the powers for placing of any Wires, Poles, Stays, Apparatus and Appliances for the Transmission and Distribution of Electricity or for Transmission of telegraphic or telephonic communications necessary for proper coordination of the works of PSTCL for the areas indicated above for which the Telegraph Authority possess under Part-III of the Telegraphs Act. 1885 (13 of 1885) in respect of telegraphs established or maintained and the provisions of section 12 to 16, 18 and 19 of the Indian Electricity Act 1910 shall not apply to the same and therefore no separate notice of the scheme of PSTCL is required to be given.
This notification has been issued with reference to the relevant clauses of Indian Electricity Act 1910 alongwith latest statutory amendments, modifications, upto date over riding enactments if any and the provisions made under Section 164 of the Indian Electricity Act 2003 and Govt. of Punjab, Deptt. of Power Endst.
No. 11/95/2011-PE 3/2344 dated 28.06.2011 wherein powers of Telegraph Authority under part-III of the Indian Telegraph Act, 1885 (13 of 1885) have been decided to be conferred and exercised on PSTCL. Notice is hereby given that any person may raise objections if any/and or make any suggestions against the above scheme/ transmission works within two month of issue of this notification. Thereafter no objections and or suggestions will be entertained and all schemes/transmission works will be deemed to be sanctioned with or without modifications as approved by the PSTCL. Necessary plans showing the tentative route of the Transmission Lines may be seen on any working day in the office of Dy. CE/TLSC Circle, PSTCL, Patiala. Objections and/or suggestions in respect of the above schemes if any should be sent to the undersigned.
Benefits of the above Scheme:-
The above works have been planned to augment/add 400KV/220KV/132KV transmission network in the State of Punjab so as to ensure quality and uninterrupted power supply to all types of existing/prospective electricity consumers of the State and are urgently required.
Sd/-
ER. SAJEEV GUPTA,
CE/TS,PSTCL, Patiala.
[97-1] 2073/8-2020/Pb. Govt. Press, S.A.S. Nagar