M/s C.R. Auluck and Sons Private Limited having its manufacturing unit located at 426, Inustrial Are

Published 20 December 2024

Department
Power
Type
Ordinary
Notification no.
No.10/77/2023-EV4/3134
Gazetteid
CHD/0092/2024-2026
Identifier
in.gazette.punjabdsa.2024-12-20.64473
Languages
English, Punjabi

click here for IIIF manifest

PART I] PUNJAB GOVT. GAZ., DECEMBER 20, 2024 (AGHN 29, 1946 SAKA) 999

Published by Authority

No. 51] CHANDIGARH, FRIDAY, DECEMBER 20, 2024 (AGRAHAYANA 29, 1946 SAKA)

PART I

Punjab Government Notifications and Orders

GOVERNMENT OF PUNJAB

DEPARTMENT OF POWER

(ENERGY BRANCH)

NOTIFICATION

The 11th July, 2023

No.10/77/2023-EV4/3134.-In exercise of the powers conferred by section 12 of the Punjab Electricity (Duty) Act, 2005 (Punjab Act 9 of 2005), and all other powers enabling him in this behalf, the Governor of Punjab is pleased to grant hundred percent (100%) exemption to M/s C.R. Auluck and Sons Private Limited having its manufacturing unit located at 426, Inustrial Area A, Ludhiana from the payment of electricity duty (except Social Security Fund) for a period of seven years, in terms of the Detailed Schemes and Operational Guidelines, 2018 (Industrial and Business Development Policy, 2017) in public interest subject to the following conditions, namely:-

CONDITIONS

(i) the exemption, shall be granted to the said Firm to manufactue of other iron and steel casting and products thereof, sewing machines, sewing machine heads and sewing machine needles (whether or not for household use) Manufacture of other articles n.e.c. as per the conditions contained in the Eligibility Certificate issued by the Convener-cum-General Manager, District Level Committee, Ludhiana vide Endorsement No.DIC/ LDH/832; dated the 10th March, 2023;

(ii) the exemption shall be granted from the 1st October, 2021 to 30th September, 2028 or the date of exhaustion or utilization of quantum of eligible incentive i.e. rupees 3,28,77,000 (rupees three crore, twenty-eight lakh, seventy-seven thousand only) which is earlier, as per the Eligibility Certificate dated the 10th March, 2023 However, the date of commercial production of the Unit after expansion is certified as 1st October, 2021;

(iii) in the event of any revision of rate of electricity duty at any subsequent point of time, the exemption to the extent of revised levied rate of electricity duty (except contributions out of electricity duty e.g. Social Security Fund etc.) shall be applicable to the Unit;

(iv) the usage of the power by the Firm during the aforesaid period shall be regulated through a transparent metering arrangement installed or approved by the Punjab State Power Corporation Limited and the Chief ( 999 ) 1000 PUNJAB GOVT. GAZ., DECEMBER 20, 2024 (AGHN 29, 1946 SAKA) PART I] Electrical Inspector to record the consumption of the Unit under exemption; (v) the exemption shall not be applicable for the residential area of the said premises and to that effect an undertaking shall be submitted by the Unit that no residential area exists in the premises. If there is a

residential area in the premises, in that event, a separate meter has to be installed or a separate electricity connection shall be obtained in order to record the electricity consumption of that residential area, which shall be excluded from the total electricity consumption of the Unit;

(vi) it shall be ensured that the Firm does not connect the load of any other Unit with this Unit for the purpose of availing exemption from electricity duty;

(vii) the exemption shall be strictly in accordance with the Eligibility Certificate issued by the Convener-cum- General Manager, District Level Committee, Ludhiana vide Endorsement No. DIC/LDH/832, dated the 10th March, 2023; and

(viii) in case any exemption claimed in excess is detected at any point of time, it shall be liable for recovery and penal action under the provisions of the said Act.

To ensure the compliance of the above conditions and proper utilization of incentive, the Auditor of the office of the Chief Electrical Inspector may inspect the Unit at any time. In case, any violation of any of the provisions of the said Act and the rules made thereunder and the above conditions is detected, the owner of the Unit, shall be liable for action under section 8 of the said Act and the rules made thereunder and the exemption shall automatically cease for which the owner of the Unit shall be responsible.

Sd/-

TEJVEER SINGH,

Chandigarh

Principal Secretary to Government of Punjab, The 06th July, 2023