GOVERNMENT OF TAMIL NADU 2021
[Regd. No. TN/CCN/467/2012-14.
[R. Dis. No. 197/2009.
[Price : Rs. 11.20 Paise.
| TAMIL NADU GOVERNMENT GAZETTE PUBLISHED BY AUTHORITY | ||
No. 4] CHENNAI, WEDNESDAY, JANUARY 27, 2021 Thai 14 Saarvari, Thiruvalluvar Aandu–2052
Part VI—Section 2
Notifications of interest to a section of the public
issued by Heads of Departments, etc.
NOTIFICATIONS BY HEADS OF DEPARTMENTS, ETC.
CONTENTS
Pages.Pages.
TAMIL NADU ELECTRICITY REGULATORY COMMISSION, CHENNAI.
Amendment to the Tamil Nadu Electricity Supply Code. .. .. 24-2524-25 Amendments to the Tamil Nadu Electricity Distribution Code. .. .. 25-4925-49
[23]
DTP—VI-2 (4)[Part VI—Sec. 2 24 TAMIL NADU GOVERNMENT GAZETTE
NOTIFICATIONS BY HEADS OF DEPARTMENTS, ETC.
TAMIL NADU ELECTRICITY REGULATORY COMMISSION, CHENNAI.
Amendment to the Tamil Nadu Electricity Supply Code.
(Notifi cation No. TNERC/SC/7–44 dated 24-12-2020).
(Lr. No.TNERC/DD(L)/F, Notifi cation / D.No. 1438/2021,)
No. VI(2)/16/2021.
In exercise of the powers conferred by Section 181 read with Section 50 of the Electricity Act, 2003 (Central Act 36 of 2003) and all other powers enabling it in this behalf, the Tamil Nadu Electricity Regulatory Commission hereby makes the following amendments to the Tamil Nadu Electricity Supply Code, the draft of the same having been previously published, as required under sub-section (3) of the said Section 181.
A(cid:3477)(cid:3469)(cid:3478)(cid:3468)(cid:3477)(cid:3469)(cid:3478)(cid:3484)
1. In the said Supply Code, in regulation 6, for the following sentences,
"6. Minimum charges–The consumer shall pay to the Licensee minimum charges in respect of every connection as detailed below. The minimum monthly charges are payable even when no electricity was consumed or supply disconnected by orders of Court or when the price of electricity supplied is less than the minimum charges.",
the following shall be substituted namely:-
"6. Minimum Charges–The consumer shall pay to the Licensee minimum charges / fi xed charges in respect of every connection as detailed below :
The monthly minimum charges / fi xed charges are payable even when no electricity was consumed or in the event of disconnection of services for any reasons including the reasons by orders of Court or when the price of electricity supplied is less than the minimum charges.
Explanation: The term 'monthly minimum charges / minimum charges' wherever it occurs in the Tamil Nadu Electricity Supply code/Distribution code refer to the minimum charges / fi xed charges as prescribed in the Commission's Tariff orders from time to time. For the LT services of sanctioned demand above 112KW, the monthly minimum charges / fi xed charges shall be as applicable to HT services but for full sanctioned demand".
(By Order of the Tamil Nadu Electricity Regulatory Commission)
S. CHINNARAJALU, Chennai-600 032, 8th January 2021.
Secretary,
Tamil Nadu Electricity Regulatory Commission.
E(cid:3488)(cid:3480)(cid:3476)(cid:3465)(cid:3478)(cid:3465)(cid:3484)(cid:3479)(cid:3482)(cid:3489) S(cid:3484)(cid:3465)(cid:3484)(cid:3469)(cid:3477)(cid:3469)(cid:3478)(cid:3484)
The minimum charges applicable to LT consumers are in effect the fi xed charges specifi ed in the Tariff Order by the Commission from time to time and hence for the purpose of clarity, it is necessary to amend the Regulation 6 of Supply code. The proposed amendment seeks to give effect to the said proposal.
(By order of the Tamil Nadu Electricity Regulatory Commission)
S. CHINNARAJALU,
Secretary,
Tamil Nadu Electricity Regulatory Commission.
Jan. 27, 2021] TAMIL NADU GOVERNMENT GAZETTE 25Annexure
Tamil Nadu Electricity Supply Code
| Sl. No. | Existing regulation (1) | Regulation as amended (2) |
| 1. | 6. Minimum Charges The consumer shall pay to the Licensee minimum charges in respect of every connection as detailed below. The minimum monthly charges are payable even when no electricity was consumed or supply disconnected by orders of Court or when the price of electricity supplied is less than the minimum charges xxx | 6. Minimum Charges The consumer shall pay to the Licensee minimum charges / fi xed charges in respect of every connection as detailed below : The monthly minimum charges / fi xed charges are payable even when no electricity was consumed or in the event of disconnection of services for any reasons including the reasons by orders of Court or when the price of electricity supplied is less than the minimum charges Explanation: The term 'monthly minimum charges/ minimum charges' wherever it occurs in the Tamil Nadu Electricity Supply code / Distribution code refer to the minimum charges/ fi xed charges as prescribed in the Commission's Tariff orders from time to time. For the LT services of sanctioned demand above 112KW, the monthly minimum charges / fi xed charges shall be as applicable to HT services but for full sanctioned demand". xxx |
(By Order of the Tamil Nadu Elecricity Regulatory Commission)
S. CHINNARAJALU, Chennai-600 032, 8th January 2021.
Secretary,
Tamil Nadu Electricity Regulatory Commission.
Amendments to the Tamil Nadu Electricity Distribution Code.
Notifi cation No. TNERC/DC/8–28 dated 24-12-2020.
(Lr. No.TNERC/DD(L)/F, Notifi cation / D.No. 1438/2021,)
No. VI(2)/17/2021.
In exercise of the powers conferred by Section 181 read with Section 46 of the Electricity Act, 2003 (Central Act 36 of 2003) and all other powers enabling it in this behalf, the Tamil Nadu Electricity Regulatory Commission hereby makes the following amendments to the Tamil Nadu Electricity Distribution Code, the draft of the same having been previously published, as required under sub-section (3) of the said Section 181.
A(cid:3477)(cid:3469)(cid:3478)(cid:3468)(cid:3477)(cid:3469)(cid:3478)(cid:3484)(cid:3483)
In the said Distribution Code, -
1. in regulation 2, after clause (a), the following clause shall be inserted, namely:-
"(aa) "Authority" means the Central Electricity Authority referred to in sub section (1) of Section 70 of Electricity Act
2003";
2. in regulation 16, after sub-regulation (2), the following sub-regulation shall be inserted, namely:-
"(2A) EARTH LEAKAGE PROTECTIVE DEVICE / RESIDUAL CURRENT DEVICE (ELPD / RCD ):
(i) The supply of electricity to every installation of low voltage (240 V) and medium voltage(415V) including installations
of Temporary supply shall be controlled by a Residual Current (operated) Device (RCD), whose rated residual operating current
shall not exceed 30 milliampere for protection against electric shock, so as to disconnect the supply on the occurrence of earth
fault or leakage of current.
(ii) In the case of installations having large number of motors, equipment, appliances of loads totalling above 10 kW,
one common RCD at the point of commencement of supply with rated residual operating current of 300 milliampere for protection
against electrical fi re shall be provided, in addition to RCD of not exceeding 30 milliampere rating for protection against electric
shock.
[Part VI—Sec. 2 26 TAMIL NADU GOVERNMENT GAZETTE(iii) An installation, where there are a large number of loads giving rise to a sum of permissible leakage currents exceeding
30 milliampere, shall be subdivided into circuits to avoid nuisance tripping and each sub-divided circuit shall be provided with an
independent RCD with leakage current sensitivity rating not exceeding 30 milliampere at appropriate location(s).
Explanation–RCD is a generic term which embraces the various types of RCCBs, (Residual Current operated Circuit
Breaker), RCBOs (Residual Current operated Circuit Breaker with integral Overcurrent protection), etc., RCCB is also called as
RCB for convenience (RCCB/RCB). The term ELCB (Earth Leakage Circuit Breaker ) is not used in Standards.";
3. in regulation 27,-
(a) for sub-regulation (3), excluding the Note, the following sub-regulation shall be substituted, namely :-
"(3) The application for HT service connection shall be in FORM-4. Application for LT service connection (other
than Temporary supply, Agriculture and Hut), Temporary service connection, LT Agriculture service connection and LT Hut service
connection shall be in FORM–1, 1A, 2 and 3 respectively.";
(b) after sub-regulation 11, the following sub-regulations shall be inserted, namely:-
"(11A) Where the requisition for supply is for a multi-storeyed building, the applicant shall enclose the planning
permission along with building plan approval with the application. The Licensee shall verify the height of the building from the
planning permission / building plan approval enclosed by the applicant. Physical measurement is not necessary. If the height of
the multi-storeyed building is more than 15 metre as given in the planning permission / building plan approval, necessary approval
from the Electrical Inspector in compliance with CEA (Measures relating to Safety and Electric Supply) Regulations 2010 as
amended, shall be furnished by the applicant.
(11B) The supply of electricity to every installation of low voltage (240 V) and medium voltage (415V) including
installations of Temporary supply shall be controlled by a Residual Current (operated) Device (RCD) as specifi ed in sub-regulation
(2A) of Regulation 16 of this Code, to ensure safety against electric shock and fi re hazards.";
4. in regulation 29,-
(a) for sub-regulations (11) and (12), the following sub-regulations shall be substituted, namely:-
"(11) In storeyed building and for any building / premises requiring LT service connection(s) having either (a) total fl oor
area of 900 square metre and above (excluding the stilt fl oor / basement fl oor) or (b) the total demand of all the LT services in
the building exceeds 112kW, suffi cient space shall be made available free of cost to the Licensee for installing transformers,
switchgears etc., as stated below:
(a) an electrical room with RCC roof having clear fl oor area 6 metre x 4 metre with a vertical clearance of 2.75 metre
with locking facility, exhaust fans and adequate size of cable duct, shall be provided at the ground fl oor within the consumer
premises of storeyed buildings nearer to the main entrance for installing fl oor mounted distribution transformer and associated
switchgear (or)
(b) a clear space of 10 metre x 4 metre or 5 metre x 5 metre open to the sky for double pole structure or 4 meter x 4
meter open to sky for single pole structure according to site and load conditions, shall be provided within the consumer premises
preferably at the main entrance for installing structure mounted or plinth/concrete pillar mounted distribution transformer and
associated switchgears. In case of concrete/plinth mounted arrangment, such mounting arrangement shall be carried out by the
applicant at his cost.
(c) Installation of Distribution Transformer with associated equipment / accessories viz. AB switch, HG fuse, DT structure/
pole shall be carried out by the Licensee at the Licensee's cost. The cost of installation works from the Distribution Transformer to
the consumer's meter including portion of any HT line within the consumer's premises when the Distribution transformer is erected
in the consumer's premises, shall be borne by the applicant.
(d) While carrying out the work, it should be ensured that the electrical clearance from ground, horizontal/vertical
clearances from building, working clearance etc., as stipulated in the safety regulations are strictly followed.
Jan. 27, 2021] TAMIL NADU GOVERNMENT GAZETTE 27(12) (a) Space as per the following norms shall be allotted by the applicant free of cost for establishment of a sub-station/switching
station in places requiring service connections (except industrial service connections other than IT related purposes ) where either
(a) the total demand of all the electrical services in the projects including the loads that will be incident in future exceeds /would
exceed 5 MVA or (b) total fl oor area of 30,000 square metre and above is constructed or proposed to be constructed (excluding
the stilt fl oor / basement fl oor).
(b) The requirement of land for establishment of sub-stations shall be the minimum limit with confi guration given below:
| Voltage level of the sub- station | Land Requirement in Sq.mts. | |
| Normal sub-station | Compact sub-station | |
| 33 KV sub-station | 850 (indoor) 3160 (outdoor) | 400 (size of 20x20 or 10x40 with approaches on any two adjacent sides) |
| 110 KV sub-station | 4000 (outdoor) | 1050 |
| 230 KV sub-station | 16000(outdoor) | 1750 |
When the developers/owners of the premises apply for additional load / develops additional constructions in phases etc.,
the above requirement of space for establishment of sub-station shall be applicable for the total load or total area of construction
that includes both the existing and additional load / area of construction.
(c) The area earmarked for establishment of sub-station shall be specifi cally shown in the plan including the areas of
constructions, road approaches and other amenities of the premises along with plot development if any for the future and furnished
to the Distribution Licensee by the developers/owners at the time of applying for temporary service connection for construction
purposes.
(d) Where the total demand exceeds /would exceed 5 MVA or the total fl oor area of 30,000 square metre and above is
constructed or proposed to be constructed (excluding the stilt fl oor / basement fl oor), the applicant shall allot the land suitable for
establishing a conventional outdoor Air Insulated Switchgear (AIS) sub-station. In case, the applicant chooses to opt for allotting
land suitable for Compact or Indoor sub-station other than conventional outdoor AIS sub-station, the applicant shall bear the
difference in cost between the Compact or Indoor sub-station for which the space is offered and the conventional outdoor AIS
sub-station. The applicant has to allot the land for establishment of sub-station commensurate with the quantum of demand
applied or the demand assessed by the Licensee, whichever is higher.
Explanation: (i) While calculating the difference in cost between the sub-stations of compact and outdoor type or between the
sub-stations of indoor and outdoor type, following methodology shall be adopted:
(ii) The portion pertaining to HV side equipment, only one power transformer that feeds the applicant(s), its allied LV
breaker, CTs, switches , panels, number of its LV feeders feeding the applicant, feeder equipment, panels, cables, accessories,
etc., shall be taken in to account for comparison with the corresponding counterparts of the outdoor sub-station and for computation
of difference in cost between them.
(iii) The portion of cost pertaining to remaining Power Transformer(s), their allied HV switches, LV breakers, CTs,
switches, panels, LV feeders feeding other areas, feeder equipment, panels, cables, accessories etc., shall be entirely borne by
the Licensee.
[Part VI—Sec. 2 28 TAMIL NADU GOVERNMENT GAZETTE(e) The Licensee may consider establishment of sub-stations operating at various voltage levels commensurate with the
demand as below, in the space provided by the applicants:
| Total demand | Voltage level of the sub-station |
| Exceeding 5 MVA but not above 10 MVA | 33 KV |
| Exceeding 10 MVA but not above 50 MVA | 110 KV |
| Exceeding 50 MVA | 230 KV |
";
(b) in sub-regulation (14), for clause (b), the following clause shall be substituted, namely :-
"(b) For outdoor metering, a clear space of 10 metre x 4 metre or 5 metre x 5 metre open to sky shall be provided. This
enclosure shall be at the periphery of the building and shall be cut off from other portions of the premises by fi re resistance walls.
These areas shall be specifi cally shown in the plan. Before the plan is sent to the competent authority for approval, it shall be sent
to the Engineer and got approved. The point of supply shall be within 30 metre from the main entry gate easily accessible for lorry
movement from public road and clearly visible from the public road and satisfactory with regards to security aspects. The metering
set, incoming and outgoing HT line of the metering set etc., shall be clearly visible from the public road, even when the gate is in
closed condition.:
Provided that the Chief Executive Offi cer or any other Offi cer, not less than in the rank of a Chief Engineer, authorized by the
Chief Executive Offi cer may approve the point of supply in cases where the applicant is unable to get the metering point erected
within 30 metre from main entry gate as above or able to get the metering point erected within 30 metre, but only in a gate other
than the main entry gate , if he is satisfi ed that such place is-
(i) easily accessible for lorry movement from road located outside the applicant's premises and clearly visible to the
offi cials of the Licensee from that road even when the gate is in closed condition;
(ii) is safe and secure;
(iii) is not susceptible to malpractice; and
(iv) it is feasible to erect a check metering point outside the applicant's premises.
(c) There shall be no compromise on technical grounds, while relaxing the distance and the location criteria. The
applicants who are unable to get the metering point erected within 30 metre from main entry gate or able to get the metering point
erected within 30 metre, but only in a gate other than the main entry gate, shall bear the cost of installation of check metering point
outside the premises in a location decided by the Licensee.
Failure to comply with the above requirements will result in denial of supply.
5. in regulation 31, for sub-regulation (3), the following sub-regulation shall be substituted, namely :-
"(3) If the intending consumer fails to avail the supply within the above period, a further three months extension in case
of HT and one month extension in case of LT will be granted by the Licensee, after collecting the monthly minimum for the notice
period including the extended period in advance. If he does not avail himself the supply during this notice period, the application
will be treated as lapsed and cancelled in the case of Low Tension supply and the application shall be treated as cancelled,
terminating the agreement, in the case of High Tension supply. The service connection charges, security deposit, development
charges, monthly minimum charges etc., except meter caution deposit will be forfeited. In case the intending consumer could not
avail the supply under force majeure conditions, the security deposit and meter caution deposit shall be refunded to the intending
consumer."
Jan. 27, 2021] TAMIL NADU GOVERNMENT GAZETTE 296. In ANNEXURE III,-
(a) for FORM – 1, the following shall be substituted, namely:-
"FORM I
Application Form for L.T Service Connection( except Temporary supply , Agricultural and Hut )
FORM OF REQUISITION FOR SUPPLY OF LOW TENSION ENERGY ( SINGLE PHASE / THREE PHASE)
[Refer regulation27(3)]
To
The Designated Engineer
Applicant(s)' (Address of the Licensee)
Photo(s) Sir,
1.I/We,Thiru/Tmty……………………………………………………………….........................................................................
.
S/o/D/o/W/o/………………………………………………………………………………………………………...… hereby request you to
supply electrical energy for the purpose of …..………………………………………………………………………. to the
premises hereinafter described.
2. I / We agree to pay for said energy, service connection charges, the deposit of such security, meter rent,
development charges and any other charges as may be demanded in accordance with the scale of rates prescribed under
Tamil Nadu Electricity Distribution Code, Supply Code, notifi cations and orders issued in this regard by Tamil Nadu Electricity
Regulatory Commission.
3. I / We wish to be charged under Tariff ………… under schedule of the TNERC tariff order in force.
4. I / We agree to avail supply and utilize the energy in the premises described hereunder for my/our bonafi de use.
5. In case, I/We sell or otherwise dispose of the property / vacate the premises while the supply is continued, I/We
agree to give one Calendar month notice in writing and pay all the arrears to the Licensee. Failing such notice, I/We hold myself/
ourselves liable for payment of arrears of current consumption charges, other dues if any and claims that may arise in the event
of termination of agreement and undertake for loading the dues to other service connection(s) that may stand in my/our name(s).
6. Description of the premises
a) Door No. and / or name of the house or premises :
b) Street :
c) Town / village and Taluk :
d) Owned by (Name in Block Letters) :
e) Tenanted by (Name in Block Letters) :
f) Applicant(s)' address for correspondence :
g) Contact No. and e-mail id :
[Part VI—Sec. 2 30 TAMIL NADU GOVERNMENT GAZETTE7. The following are my / our requirements :
(A) Lighting Number of Wattage of Total
Points Points
wattage
(i) Lights
-
-
-
(ii) Fans
-
-
-
(iii) Convenient wall plugs -
-
-
(B) Domestic electrical apparatus:
(i) Cookers
-
-
-
(ii) Water heaters
-
-
-
(iii) Refrigerator
-
-
-
(iv) Air Conditioners
(v) Lifts/Elevator/Escalators -
-
-
(vi) Other purpose
-
-
-
(vii) Convenient wall plugs -
-
-
(C) Power Loads
-
-
-
(i) Domestic
-
-
-
(ii) Industrial
-
-
-
(iii) Welding
-
-
-
(iv) Other purposes -
-
-
(v) Convenient Wall Plugs -
-
-
8. Demand applied for in KW :
9. Whether the installation is provided with earth protective device (RCD) as per Tamilnadu Electricity Distribution Code :
10. The wiring has been completed on :
11. Details of existing service connection(s) of the applicant(s) if any :
12. Whether any current consumption charges or any other charges are due to TANGEDCO in the name(s) of the
applicant(s) or premises :
If yes, give details ( with SC No, Name of Section/Circle etc ) :
PRECAUTION TO BE ADOPTED BY CONSUMERS, OWNERS, OCCUPIERS, ELECTRICAL CONTRACTORS,
ELECTRICAL WORKMEN AND SUPPLIERS
No electrical installation work, including additions, alterations, repairs and adjustments to existing installations, except such
replacement of lamps, fans, fuses, switches, domestic appliances of voltage not exceeding 250V and fi ttings as in no way alters
its capacity or character, shall be carried out upon the premises of or on behalf of any consumer, supplier, owner or occupier for
the purpose of supply to such consumer, supplier, owner or occupier except by an electrical contractor licensed in this behalf by
the State Government and under the direct supervision of a person holding a certifi cate of competency and by a person holding
a permit issued or recognized by the State Government.
I / We certify that we are aware of the above precaution and agree to abide by it.
I / We agree to pay to the Licensee at the applicable tariff/minimum rates/fi xed charges/surcharge etc., that may be decided
by the Commission from time to time.
I / We agree to abide under all specifi cations, conditions and provisions laid down in Tamil Nadu Electricity Regulatory Supply
Code, Distribution Code and the applicable Act, Codes, Rules and Regulations and of any modifi cation or re-enactment thereof for
the time being in force and subject to the conditions of revisions, amendments approved from time to time.
Jan. 27, 2021] TAMIL NADU GOVERNMENT GAZETTE 31(Note : This undertaking does not preclude execution of a separate written contract to be entered with Licensee)
Signature of the
Applicant(s)
Name(s) in Block
Letters.
Place:
Date:
Note: The application shall be accompanied with the following documents:
(i) Self attested copy of proof of ownership such as sale deed (or) partition deed (or) gift settlement (or) allotment letter
(or) computer patta (or) ownership certifi cate issued by revenue department offi cials (or) court judgment or recent
property tax receipt.
(ii) In case of joint property, self attested copies of proof of ownership along with parent documents specifi ed in note
(i) above and consent letters from co-owners. If consent letter is not produced, an indemnity bond with enhanced
security deposits.
(iii) If the applicant is not the owner, consent letter from owner in FORM No.5 or valid proof of occupancy and indemnity
bond in FORM No.6
FOR LICENSEE'S USE ONLY
ACKOWLEDGEMENT
Applicant(s)' name :
Address :
Date of receipt :
Reference No. :
Category of Supply :
Signature and seal of Distribution Licensee
Name and designation.";
[Part VI—Sec. 2 32 TAMIL NADU GOVERNMENT GAZETTE(b) after FORM I as so substituted, the following Form shall be inserted, namely:-
"FORM IA
Application Form for Temporary Service Connection
FORM OF REQUISITION FOR TEMPORARY SUPPLY (SINGLE PHASE / THREE PHASE)
[Refer regulation 27(3)]
To
The Designated Engineer
(Address of the Licensee)
Applicant(s)' Photo(s)
Sir,
1. I/We, /Thiru/Tmty……………………………………………………….
S/o/D/o/W/o/………………………………………………………………………..…….…………………………………………
hereby request you to supply electrical energy, temporarily for the purpose of………………………………………………………
…………………………….. …..………………………………………………………………………. …… to the premises (or) location
hereinafter described.
2. I / We agree to pay for said energy, service connection charges, the deposit of such security, meter rent, development
charges and any other charges as may be demanded in accordance with the scale of rates prescribed under Tamil Nadu Electricity
Distribution Code, Supply Code, notifi cations and orders issued in this regard by Tamil Nadu Electricity Regulatory Commission.
3. I/ We wish to be charged under Tariff ………… under schedule of the TNERC tariff order in force.
4. I/ We agree to avail temporary supply and utilize the energy in the premises/ location described hereunder for my/our
bonafi de use.
5. In case, I/We sell or otherwise dispose of the property / vacate the premises while the supply is continued, I/We agree to
give one month notice in writing and pay all the arrears to the Licensee, failing which , I/We hold myself/ourselves responsible for
the energy consumed in the premises for the entire period of Temporary supply availed. If any due arises in this service connection,
I/We agree to include such dues in my/our existing service connections No(s): ………………………………………………………...(if
available)
6. Ownership of the premises / location where temporary supply is required:
a. SF No./ Door No. :
b. Street :
c. Town / village :
d. Land mark of premises :
e. Taluk :
f. District :
g. Owned by (Name in Block Letters) :
h. Tenanted by (Name in Block Letters) :
i. Applicant(s)' address for correspondence :
j. Contact No. and e-mail id :
Jan. 27, 2021] TAMIL NADU GOVERNMENT GAZETTE 337. Description of the premises
a. Plot area :
b. Total building area/Floor area of all fl oors :
c. Number of the Floors to be constructed :
(Basement /stilt /ground fl oor/other fl oors to be furnished in detail )
d. Whether the planning permission with building plan approval is obtained from competent authority for above
mentioned fl oors and construction :
e. Whether copy of planning permission with building plan approval is enclosed :
f. Height of the building as per planning permission/ plan approval :
( If height of the building is more than 15 metre as shown in the planning permission, approval from Electrical
Inspector is required )
g. Whether Gen set /Lift is proposed to be erected :
(If yes , approval from Electrical Inspectorate to be obtained)
h. Any HT/LT line is passing inside or adjacent to the premise :
(If yes, building should be constructed with adequate safe clearance as per the Safety Regulations in force or
otherwise the lines should be got deviated at the cost of Applicant, subject to feasibility)
8. Whether the service connection is required permanently after the period of temporary service connection is over :
If No,(i) Specifi c purpose for which Temporary supply is requested :
(ii) Period of Temporary supply required :
9. Details of Loads to be Connected:
(A) Lighting
Number of
Points
Wattage of
points
Total
wattage
(i) Lights
- – - (ii) Fans
-
-
-
-
-
(iii) Convenient wall
plugs–
(B) Power Loads
-
-
- (i) Motors
-
-
- (ii) Welding -
-
- (iii) Cutting machine
(iv) Portable appliances -
-
- (v) Lifts/elevators -
-
- (vi) Other apparatus
-
-
-
-
-
- (vii) Convenient Wall Plugs -
10. Demand applied for in KW :
11. Whether the installation is provided with earth protective device (RCD) as per Tamil Nadu Electricity Distribution Code
:
12. The wiring has been completed on :
13. Details of existing service connection(s) of the applicant(s), if any :
14. Whether any current consumption charges or any other charges are due to TANGEDCO in the name(s) of the applicant(s)
or premises :
If yes, give details ( with SC No, Name of Section/Circle etc ) :
SPACE TO BE PROVIDED BY APPLICANT(s)
1. In storeyed building and for any building / premises requiring LT service connection(s) having either (a) total fl oor area of
900 square metre and above (excluding the stilt fl oor / basement fl oor) or (b) the total demand of all the LT services
in the building exceeds 112kW, suffi cient space shall be made available free of cost to the Licensee for installing
transformers, switchgears etc., as stated in Regulation 29 (11) of the TNE Distribution Code.
[Part VI—Sec. 2 34 TAMIL NADU GOVERNMENT GAZETTE2. Space as per the norms specifi ed in Regulation 29(12) of the TNE Distribution Code shall be allotted by the applicant
free of cost for establishment of a sub-station/switching station in places requiring service connections (except
industrial service connections other than IT related purposes) where either (a) the total demand of all the electrical
services in the projects including the loads that will be incident in future exceeds /would exceed 5 MVA or (b) total
fl oor area of 30,000 square metre and above is constructed or proposed to be constructed (excluding the stilt fl oor /
basement fl oor).
3. For High Tension Service connections of indoor metering, an electrical room with RCC roof having a clear fl oor area 5m
x 6m with vertical clearance of 3.7 metre between fl oor and ceiling/ beam bottom with locking facility, exhaust fan and
adequate size of cable duct shall be provided at the ground/ basement fl oor for installing the Licensee's equipment,
etc. This room shall be of fi reproof and weatherproof ; For outdoor metering a clear space of 10 metre x 4 metre or
5 metre x 5 metre open to sky shall be provided. This enclosure shall be at the periphery of the building and shall
be cut off from other portions of the premises by fi re resistance walls. These areas shall be specifi cally shown in
the plan. Before the plan is sent to the competent authority for approval, it shall be sent to the area engineer of the
Licensee and got approved. The point of supply shall be within 30 metre from the main gate easily accessible for lorry
movement from public road and clearly visible from the public road and satisfactory with regards to security aspects.
PRECAUTION TO BE ADOPTED BY CONSUMERS, OWNERS, OCCUPIERS, ELECTRICAL CONTRACTORS,
ELECTRICAL WORKMEN AND SUPPLIERS
No electrical installation work, including additions, alterations, repairs and adjustments to existing installations, except such
replacement of lamps, fans, fuses, switches, domestic appliances of voltage not exceeding 250V and fi ttings as in no way alters
its capacity or character, shall be carried out upon the premises of or on behalf of any consumer, supplier, owner or occupier for
the purpose of supply to such consumer, supplier, owner or occupier except by an electrical contractor licensed in this behalf by
the State Government and under the direct supervision of a person holding a certifi cate of competency and by a person holding
a permit issued or recognized by the State Government.
I / We certify that we are aware of the above precaution and agree to abide by it.
I / We agree to pay to the Licensee at the applicable tariff/minimum rates/fi xed charges/surcharge etc that may be decided
by the Commission from time to time.
I / We agree to abide under all specifi cations, conditions and provisions laid down in Tamil Nadu Electricity Regulatory
Supply Code, Distribution Code and the applicable Act, Codes, Rules and Regulations and of any modifi cation or re-enactment
thereof for the time being in force and subject to the conditions of revisions, amendments approved from time to time.
(Note: This undertaking does not preclude a separate written contract to be entered with Licensee )
Signature of the Applicant(s)
Name(s) in Block Letters.
Place:
Date:
Note:
1. The application shall be accompanied with the following documents:
(i) Self attested copy of proof of ownership such as sale deed (or) partition deed (or) gift settlement (or) allotment letter
(or) computer patta (or) ownership certifi cate issued by revenue department offi cials (or) court judgment or recent
property tax receipt.
(ii) In case of joint property, self attested copies of proof of ownership along with parent documents specifi ed in note (i)
above and consent letters from co-owners. If consent letter is not produced, an indemnity bond with enhanced security
deposits.
(iii) If the applicant is not the owner, consent letter from owner in FORM No.5 or valid proof of occupancy and indemnity
bond in FORM No.6
(iv) Plan approval with area earmarked for installing transformer, in case of fl oor area of 900 square metre and above or
the demand exceeds 112KW, in case of LT service connections as per sub regulation 29 (11) of the TNE Distribution
Code
Jan. 27, 2021] TAMIL NADU GOVERNMENT GAZETTE 35OR
Plan approval with area earmarked for establishment of sub-station and road approaches, in case of demand /
area exceeds the limit as specifi ed with conditions in sub regulation 29 (12) of the TNE Distribution Code
OR
Plan approval with area earmarked for indoor / outdoor metering , and location of metering point with road approaches
in case of HT service connection as specifi ed with conditions in sub regulation 29(14) of the TNE Distribution Code.
FOR LICENSEE'S USE ONLY
ACKOWLEDGEMENT
Applicant(s)' name :
Address :
Date of receipt :
Reference No. :
Category of Supply : Signature and seal of Distribution Licensee
Name and designation".
(By order of the Tamil Nadu Electricity Regulatory Commission)
S. CHINNARAJALU, Chennai-600 032. 8th January 2021.
Secretary,
Tamil Nadu Electricity Regulatory Commission.
E(cid:3488)(cid:3480)(cid:3476)(cid:3465)(cid:3478)(cid:3465)(cid:3484)(cid:3479)(cid:3482)(cid:3489) S(cid:3484)(cid:3465)(cid:3484)(cid:3469)(cid:3477)(cid:3469)(cid:3478)(cid:3484)
In order to ensure that the safety norms and regulations mandated in the CEA regulations such as provision of Residual Current Device inside the premises of consumers and production of necessary approval from Electrical Inspector are to be specifically provided in the Distribution Code for creating awareness among the consumers and for effective implementation to ensure public safety against electric shock and fire hazards. Further the expression 'authority' needs to be defined with clarity.
The LT application needs to be provisioned for joint application by the co-owners as the present format is suitable only for a single applicant.
To define the conditions for metering point location in HT service to make it more practicable so as to ensure that the Licensee is able to reach the location easily during surprise inspection and viable alternate solution where there is no feasibility to erect metering point within the specified distance from main gate or specified location.
To add provision to erect single pole type Transformer inside consumer's premises in addition to existing provision for erecting conventional double pole type.
There being exclusive conditions for Temporary supply, the specific requirements to provide space and other provisions for erection of Transformer or sub-station need to be made more specific to the applicant at the initial stage itself and for that purpose it is proposed to prescribe a separate format for the said category.
To add clarity in computing the difference in cost between the types of sub-station when the applicant chooses to provide space for a type of sub-station other than the type preferred by the Licensee.
The monthly minimum charges to be paid in regard to supply availability notice period has to be made specific to avoid ambiguity.
The amendment seeks to address the above issues.
(By order of the Tamil Nadu Electricity Regulatory Commission)
S. CHINNARAJALU, Chennai-600 032. 8th January 2021.
Secretary,
Tamil Nadu Electricity Regulatory Commission.
[Part VI—Sec. 2 36 TAMIL NADU GOVERNMENT GAZETTEANNEXURE
Tamil Nadu Electricity Distribution Code
| Sl. No. | Existing regulation | Regulation as amended |
| 1. | 2. Defi nitions (1) xxx (a) xxx (b) xxx | 2. Defi nitions (1) xxx (a) xxx (aa) "Authority" means the Central Electricity Authority referred to in sub section (1) of Section 70 of Electricity Act, 2003 (b) xxx |
| 2. | 16. Safety Aspects: (1) xxx (2) xxx (3) xxx | 16. Safety Aspects: (1) xxx (2) xxx (2A) "EARTH LEAKAGE PROTECTIVE DEVICE/ RESIDUAL CURRENT DEVICE (ELPD / RCD ): (i) The supply of electricity to every installation of low voltage (240 V) and medium voltage(415V) including installations of temporary supply shall be controlled by a Residual Current (operated) Device (RCD), whose rated residual operating current shall not exceed 30 milliampere for protection against electric shock, so as to disconnect the supply on the occurrence of earth fault or leakage of current. (ii) In the case of installations having large number of motors, equipment, appliances of loads totaling above 10 kW, one common RCD at the point of commencement of supply with rated residual operating current of 300 milliampere for protection against electrical fi re shall be provided, in addition to RCD of not exceeding 30 milliampere rating for protection against electric shock. (iii) An installation, where there are a large number of loads giving rise to a sum of permissible leakage currents exceeding 30 milliampere, shall be subdivided into circuits to avoid nuisance tripping and each sub-divided circuit shall be provided with an independent RCD with leakage current sensitivity rating not exceeding 30 milliampere at appropriate location(s). Explanation–RCD is a generic term which embraces the various types of RCCBs, (Residual Current operated Circuit Breaker), RCBOs (Residual Current operated Circuit Breaker with integral Overcurrent protection), etc., RCCB is also called as RCB for convenience (RCCB/RCB). The term ELCB (Earth Leakage Circuit Breaker ) is not used in Standards. (3) xxx |
| 3(a) | 27. Requisitions for Supply of Energy (3). The application for HT service connection shall be in Form 4. Application for LT service connection (other than Agriculture and Hut), LT Agricultural service connection and LT Hut service connection shall be in FORM- 1,2 and 3 respectively. Note: xxx | 27. Requisitions for Supply of Energy (3) The application for HT service connection shall be in FORM-4. Application for LT service connection (other than Temporary supply, Agriculture and Hut), Temporary service connection, LT Agriculture service connection and LT Hut service connection shall be in FORM–1, 1A, 2 and 3 respectively. Note: xxx |
| 3(b) | 27. Requisitions for Supply of Energy (11) xxx | 27. Requisitions for Supply of Energy (11) xxx (11A) Where the requisition for supply is for a multi-storeyed building, the applicant shall enclose the planning permission along with building plan approval with the application. The Licensee shall verify the height of the building from the planning permission / building plan approval enclosed by the applicant. Physical measurement is not necessary. If the height of the multi-storeyed building is more than 15 metre as given in the planning permission / building plan approval, necessary approval from the Electrical Inspector in compliance with CEA (Measures relating to Safety and Electric Supply) Regulations 2010 as amended, shall be furnished by the applicant. (11B) The supply of electricity to every installation of low voltage (240 V) and medium voltage (415V) including installations of temporary supply shall be controlled by a Residual Current (operated) Device (RCD) as specifi ed in sub- regulation (2A) of Regulation 16 of this Code, to ensure safety against electric shock and fi re hazards. |
| 4(a) | 29. Service Lines: (11) In storied building suffi cient space at a suitable place shall be made available free of cost to the Licensee for installing transformers, switchgears etc., in addition to the space requirements stated below: | 29. Service Lines: (11) In storeyed building and for any building / premises requiring LT service connection(s) having either (a) total fl oor area of 900 square metre and above (excluding the stilt fl oor / basement fl oor) or (b) the total demand of all the LT services in the building exceeds 112kW, suffi cient space shall be made available free of cost to the Licensee for installing transformers, switchgears etc., as stated below: |
| (12) For any building / premises requiring LT service connection(s) having either (a) total fl oor area of 900 square meter and above (excluding the stilt fl oor / basement fl oor) or (b) the total demand of all the LT services in the building exceeds 150 kW. (i) (a) an electrical room with RCC roof having clear fl oor area 6 meters x 4 meters with a vertical clearance of 2.75 meters with locking facility, exhaust fans and adequate size of cable duct, shall be provided at the ground fl oor within the consumer premises of storied buildings nearer to the main entrance for installing fl oor mounted distribution transformer and associated switchgear or | (a) an electrical room with RCC roof having clear fl oor area 6 metre x 4 metre with a vertical clearance of 2.75 metre with locking facility, exhaust fans and adequate size of cable duct, shall be provided at the ground fl oor within the consumer premises of storeyed buildings nearer to the main entrance for installing fl oor mounted distribution transformer and associated switchgear (or) | |
| (b) a clear space of 10 metre x 4 metre or 5 metre x 5 metre open to the sky shall be provided within the consumer premises preferably at the main entrance for installing structure mounted distribution transformer and associated switchgears, and | (b) a clear space of 10 metre x 4 metre or 5 metre x 5 metre open to the sky for double pole structure or 4 metre x 4 metre open to sky for single pole structure according to site and load conditions, shall be provided within the consumer premises preferably at the main entrance for installing structure mounted or plinth/concrete pillar mounted distribution transformer and associated switchgears. In case of concrete/plinth mounted arrangement, such mounting arrangement shall be carried out by the applicant at his cost. |
| Sl. No. | Existing regulation | Regulation as amended | ||||||||
| (c) Installation of Distribution Transformer with associated equipment / accessories viz. AB switch, HG fuse, DT structure/ pole shall be carried out by the Licensee at the Licensee's cost. The cost of installation works from the Distribution Transformer to the consumer's meter including portion of any HT line within the consumer's premises when the Distribution transformer is erected in the consumer's premises, shall be borne by the applicant. (d) While carrying out the work, it should be ensured that the electrical clearance from ground, horizontal/vertical clearances from building, working clearance etc., as stipulated in the safety regulations are strictly followed. | ||||||||||
| 29. Service Lines: 12 (ii)(a) Space as per the norms specifi ed in clause (b) of this sub-regulation shall be allotted for establishment of a sub-station / switching station in places requiring service connections (except industrial service connections) where (i) the total demand of the projects including expansions, incidence of loads in near future exceeds/ would exceed 5MVA (ii) the total area of construction/ area that would be constructed in the near future is of 30000 sq.mt and above (excluding the stilt fl oor/ basement fl oor ) (b)The requirement of land for establishment of sub-stations shall not exceed the limit given below: | 29. Service Lines: (12) (a) Space as per the following norms shall be allotted by the applicant free of cost for establishment of a sub-station/ switching station in places requiring service connections (except industrial service connections other than IT related purposes) where either (a) the total demand of all the electrical services in the projects including the loads that will be incident in future exceeds/would exceed 5 MVA or (b) total fl oor area of 30,000 square metre and above is constructed or proposed to be constructed (excluding the stilt fl oor / basement fl oor). (b)The requirement of land for establishment of sub- stations shall be the minimum limit with confi guration given below: | |||||||||
| When the developers/owners of the premises apply for additional load / develops additional constructions in phases etc., the above requirement of space for establishment of sub- station shall be applicable for the total load or total area of construction that includes both the existing and additional load / area of construction. | ||||||||||
| Voltage level of the sub-station | Land Requirements in Sq.mts. | Voltage level of the sub-station | Land Requirements in Sq.mts. | |||||||
| Normal sub- station | Compact sub-station | |||||||||
| Normal sub-station | Compact sub-station | |||||||||
| 33 KV Sub-station | 850 (indoor) 3160 (outdoor) | 400 (size of 20x20 or 10x40 with approaches on any two adjacent sides) | ||||||||
| 33 kV Sub- station | 850 (indoor) 3160 (outdoor) | 400 | ||||||||
| 110 kV sub- station | 4000 (outdoor) | 1050 | ||||||||
| 110 KV sub-station | 4000 (outdoor) | 1050 | ||||||||
| 230 kV sub- station | 16000 (outdoor) | 1750 | ||||||||
| 230 KV sub- station | 16000 (outdoor) | 1750 | ||||||||
| Sl. No. | Existing regulation | Regulation as amended |
| (c) The area earmarked for establishment of sub-station shall be specifi cally shown in the plan and furnished to the Distribution Licensee by the developers/ owners at the time of applying for temporary service connection for construction purposes. | (c) The area earmarked for establishment of sub-station shall be specifi cally shown in the plan including the areas of constructions, road approaches and other amenities of the premises along with plot development if any for the future and furnished to the Distribution Licensee by the developers/ owners at the time of applying for temporary service connection for construction purposes. | |
| (d) Where the developer/applicant chooses to allot land for a compact sub station, the diff erence in cost between establishment of a conventional sub station and compact sub station shall be borne by them. Note: (a) in places situated within 60 Kilo Meters from the periphery of the Metropolitan/Corporation limit, the Licensee may establish the compact sub-station; (b) in places situated within 30 Kilo Meters from the periphery of the Municipality limit, the Licensee may establish the compact sub-station; (c) in places situated within 10 Kilo Meters from the periphery of the Town Panchayat limit, the Licensee may establish the compact sub-station; (d) in other places, the Licensee may establish the sub-station of his choice (e) the land area should have the proper approach road at least on any one side of the land for easy transporting of power transformer. (f) the dimension of the land area shall be as per the suggestions of the Licensee to the consumer. | (d) Where the total demand exceeds /would exceed 5 MVA or the total fl oor area of 30,000 square metre and above is constructed or proposed to be constructed (excluding the stilt fl oor / basement fl oor), the applicant shall allot the land suitable for establishing a conventional outdoor Air Insulated Switchgear (AIS) sub-station. In case, the applicant chooses to opt for allotting land suitable for Compact or Indoor sub-station other than conventional outdoor AIS sub-station, the applicant shall bear the diff erence in cost between the Compact or Indoor sub-station for which the space is off ered and the conventional outdoor AIS sub-station. The applicant has to allot the land for establishment of sub-station commensurate with the quantum of demand applied or the demand assessed by the Licensee, whichever is higher. Explanation: (i) While calculating the diff erence in cost between the sub-stations of compact and outdoor type or between the sub-stations of indoor and outdoor type, following methodology shall be adopted: (ii) The portion pertaining to HV side equipment, only one power transformer that feeds the applicant(s) , its allied LV breaker, CTs, switches , panels, number of its LV feeders feeding the applicant, feeder equipment, panels, cables, accessories , etc., shall be taken in to account for comparison with the corresponding counterparts of the outdoor sub-station and for computation of diff erence in cost between them . (iii) The portion of cost pertaining to remaining Power Transformer(s), their allied HV switches, LV breakers, CTs, switches, panels, LV feeders feeding other areas, feeder equipment , panels, cables, accessories etc., shall be entirely borne by the Licensee. (e) The Licensee may consider establishment of sub- stations operating at various voltage levels commensurate with the demand as below, in the space provided by the applicants: |
| Sl. No. | Existing regulation | Regulation as amended | |||
| - Deleted – ( Note :a,b,c,d, e and f) | |||||
| Total demand | Voltage level of the sub- station | ||||
| Exceeding 5 MVA but not above 10 MVA | 33 KV | ||||
| Exceeding 10 MVA but not above 50 MVA | 110 KV | ||||
| Exceeding 50 MVA | 230 KV | ||||
| 4(b) | 29. Service Lines 14(b) For outdoor metering, a clear space of 10 metre x 4 metre or 5 metre x 5 metre open to sky shall be provided. | 29. Service Lines xxx | |||
| This enclosure shall be at the periphery of the building and shall be cut off from other portions of the premises by fi re resistance walls. These areas shall be specifi cally shown in the plan. Before the plan is sent to the competent authority for approval, it shall be sent to the Engineer and got approved. The point of supply shall be within 30 meters from the main gate easily accessible and visible and satisfactory with regards to security aspects. Failure to comply with the above requirements will result in denial of supply. Provided that the Chief Executive Offi cer or any other Offi cer, not less than in the rank of a Chief Engineer, authorized by the Chief Executive Offi cer may approve the point of supply at a place beyond 30 meters from the main gate, if he is satisfi ed that such place is - (a) easily accessible and visible to the offi cials of the Licensee; (b) is safe and secure; and (c) is not susceptible to malpractice. Also there shall be no compromise on technical grounds, while relaxing the distance criteria. | This enclosure shall be at the periphery of the building and shall be cut off from other portions of the premises by fi re resistance walls. These areas shall be specifi cally shown in the plan. Before the plan is sent to the competent authority for approval, it shall be sent to the Engineer and got approved. The point of supply shall be within 30 metre from the main entry gate easily accessible for lorry movement from public road and clearly visible from the public road and satisfactory with regards to security aspects. The metering set, incoming and outgoing HT line of the metering set etc., shall be clearly visible from the public road, even when the gate is in closed condition.: Provided that the Chief Executive Offi cer or any other Offi cer, not less than in the rank of a Chief Engineer, authorized by the Chief Executive Offi cer may approve the point of supply in cases where the applicant is unable to get the metering point erected within 30 metre from main entry gate as above or able to get the metering point erected within 30 metre, but only in a gate other than the main entry gate , if he is satisfi ed that such place is - (i) easily accessible for lorry movement from road located outside the applicant's premises and clearly visible to the offi cials of the Licensee from that road even when the gate is in closed condition; (ii) is safe and secure; (iii) is not susceptible to malpractice; and (iv) it is feasible to erect a check metering point outside the applicant's premises. |
| Sl. No. | Existing regulation | Regulation as amended |
| (c) There shall be no compromise on technical grounds, while relaxing the distance and the location criteria. The applicants who are unable to get the metering point erected within 30 metre from main entry gate or able to get the metering point erected within 30 metre, but only in a gate other than the main entry gate, shall bear the cost of installation of check metering point outside the premises in a location decided by the Licensee. Failure to comply with the above requirements will result in denial of supply. | ||
| 5. | 31. INSPECTIONS , TESTING AND EFFECTING SUPPLY: (3) If the intending consumer fails to avail the supply within the above period, a further three months notice in case of HT and one-month notice in case of LT will be sent to the intending consumer to avail the supply. If he does not avail himself the supply during this notice period, the application will be treated as lapsed and cancelled in the case of Low Tension supply and the application shall be treated as cancelled, terminating the agreement, in the case of High Tension supply. The service connection charges and the Security Deposit / development charges, etc. except Meter Caution Deposit will be forfeited. In case the intending consumer could not avail the supply under force majuere conditions, the Security Deposit and meter caution deposit shall be refunded to the intending consumer. | 31 INSPECTIONS, TESTING AND EFFECTING SUPPLY: "(3) If the intending consumer fails to avail the supply within the above period, a further three months extension in case of HT and one month extension in case of LT will be granted by the Licensee, after collecting the monthly minimum for the notice period including the extended period in advance. If he does not avail himself the supply during this notice period, the application will be treated as lapsed and cancelled in the case of Low Tension supply and the application shall be treated as cancelled, terminating the agreement, in the case of High Tension supply. The service connection charges, security deposit, development charges, monthly minimum charges etc., except meter caution deposit will be forfeited . In case, the intending consumer could not avail the supply under force majeure conditions, the security deposit and meter caution deposit shall be refunded to the intending consumer. |
| 6. | ANNEXURE III : FORMATS Application Form for L.T. Service FORM 1> Connection (except agriculture and hut) FORM 2> Application Form for Agriculture Service Connection FORM 3> A pplication Form for Hut Service Connection FORM 4> Application Form for H.T. Service Connections (including additional demand) Owner Consent FORM 5> Letter for getting New Supply Indemnity Bond FORM 6> from the Occupier when there is no Consent letter from owner L.T. Agreement FORM 7> for Industrial / Agricultural Services FORM 8> H.T. Agreement Form | ANNEXURE III : FORMATS FORM 1 Application Form for L.T. Service Connection (except Temporary supply, agriculture and hut) FORM 1A Application Form for Temporary Service Connection. FORM 2 xxx FORM 3 xxx FORM 4 xxx FORM 5 xxx FORM 6 xxx FORM 7 xxx FORM 8 xxx |
| FORM I | "FORM I | ||||
| Application Form for L.T Service Connection( except Agriculture and Hut ) | Application Form for L.T Service Connection(except Temporary Supply, Agriculture and Hut ) | ||||
| FORM OF REQUISITION FOR SUPPLY OF LOW TENSION ENERGY ( SINGLE PHASE / THREE PHASE) | FORM OF REQUISITION FOR SUPPLY OF LOW TENSION ENERGY ( SINGLE PHASE / THREE PHASE) | ||||
| [Refer regulation 27(3)] | [Refer regulation 27(3)] | ||||
| To | To | ||||
| The Designated Engineer (Address of the Licensee) | The Designated Engineer (Address of the Licensee) | ||||
| Applicant's photo | Applicant's photo | ||||
| Sir, 1. I Thiru / Tmty…… …………………......... ……………………………….........……... ....... S/o/D/o/W/o/........................................................................... ………………………………………........................................ ………....................….......…hereby request you to s u p p l y e l e c t r i c a l e n e r g y f o r t h e p u r p o s e o f . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ..........................................to the premises hereinafter described. | Sir, 1. I / We , Thiru /Tmty…………………………….......... ……………………………………........................................... ....................S/o/D/o/W/o/……………………………………… ………………………………………………………............... …………………….................hereby request you to supply electrical energy for the purpose of …..……………… ………………………............................. to the premises hereinafter described. | ||||
| (Note : This undertaking does not preclude a separate written contract being entered into, if so desired by the Licensee or the consumer.) | |||||
| 2. I agree to pay for said energy, service connection charges, the deposit of such security,meter rent, development charges and any other charges as may be demanded in accordance with the scale of rates prescribed under Tamil Nadu Electricity Distribution Code, Supply Code, notifi cations and orders issued in this regard by Tamil Nadu Electricity Regulatory Commission. | 2. I / We agree to pay for said energy, service connection charges, the deposit of such security, meter rent, development charges and any other charges as may be demanded in accordance with the scale of rates prescribed under Tamil Nadu Electricity Distribution Code, Supply Code, notifi cations and orders issued in this regard by Tamil Nadu Electricity Regulatory Commission. | ||||
| 3. I wish to be charged under Tariff ………… under the schedule of the TNERC tariff order dated……………. | 3. I / We wish to be charged under Tariff ………… under schedule of the TNERC tariff order in force. | ||||
| 4. I agree to take supply for ……………. years and utilize the energy in the premises described hereunder or outside the premises for my bonafi de use. | 4. I / We agree to avail supply and utilize the energy in the premises described hereunder for my/our bonafi de use. |
| 5. In case I sell or otherwise dispose of the property / vacate the premises while the supply is continued, I agree to give one Calendar month notice in writing and pay all the arrears to the Licensee. Failing such notice, I hold myself responsible for energy consumed in the premises till such notice is given to the Licensee. | 5. In case, I/We sell or otherwise dispose of the property / vacate the premises while the supply is continued, I/We agree to give one Calendar month notice in writing and pay all the arrears to the Licensee. Failing such notice, I /We hold myself /ourselves liable for payment of arrears of current consumption charges, other dues if any and claims that may arise in the event of termination of agreement and undertake for loading the dues to other service connection(s) that may stand in my/our name(s). |
| 6. Description of the premises Door No. and/ or name of the house or premises: Street : Town / Village and Taluk : Owned by (Name in Block letters) : Tenanted by (Name in block letters) : Applicant(s)' address for correspondence : Contact No. and e-mail id : | 6. Description of the premises a) Door No. and / or name of the house or premises : b) Street : c) Town / Village and Taluk : d) Owned by (Name in Block Letters) : e) Tenanted by (Name in Block Letters) : f) Applicant(s)' address for correspondence: g) Contact No. and e-mail id : |
| 7. The following are my requirements : Number of Wattage of Total Points points wattage (A) Lighting - - (i) Lights - - (ii) Fans - - (iii) Convenient - - wall plugs (B) Domestic electrical apparatus: (i) Cookers - - (ii) Water - - heaters (iii) Refrigerator - - (iv) Air Conditioners - - (v) Other purpose - - (vi) Convenient - - wall plugs (C) Power Loads : (i) Domestic - - (ii) Industrial - - (iii) Welding - - (iv) Other purposes - - (v) Convenient - - Wall Plugs | 7. The following are my / our requirements Number of Wattage of Total Points points wattage (A) Lighting - - (i) Lights - - (ii) Fans - - (iii) Convenient - - wall plugs (B) Domestic electrical apparatus: (i) Cookers - - (ii) Water - - heaters (iii) Refrigerator - - (iv) AirConditioners - - (v) Lifts/Elevator/ - - Escalators (vi) Other purpose (vii) Convenient wall - - plugs (C) Power Loads : (i) Domestic - - (ii) Industrial - - (iii) Welding - - (iv) Other purposes - - (v) Convenient - - Wall Plugs |
| 8. Demand applied for in KW : | 8. Demand applied for in KW : |
| 9.The wiring has been completed on : | 9. Whether the installation is provided withearth protective device (RCD) as per Tamil Nadu Electricity Distribution Code: |
| 10. Details of existing service connections of the applicant, if any. 11. Details of pending dues if any to the premises to which service connection is sought in this application] Place Signature of the applicant Date Name(in Block letters) Note: The application Shall be accompanied with the following documents. Certifi ed copy of Proof of ownership such as sale deed /Partition deed/gift settlement/allotment letter/computer patta /ownership certifi cate issued by revenue department offi cials/ court judgment or recent property tax receipt. In case of joint property, certifi ed copies of proof of ownership such as legal heir certifi cate along with parent documents specifi ed in note (i) above and consent letters from co-owners. If consent letter is not produced, an indemnity bond with enhanced security deposit. If the applicant is not the owner, consent letter from owner in FORM No.5 or valid proof of occupancy and indemnity bond in FORM No.6 FOR LICENSEE'S USE ONLY Application registered as No. dated Note:1. In case of transfer of the service, fresh application should be signed by the transferee. 2.Additions or omissions to the connected load to be notifi ed to the Licensee before eff ecting the electricity connections. | 10. The wiring has been completed on: 11. Details of existing service connection(s) of the applicant(s), if any : 12. Whether any current consumption charges or any other charges are due to TANGEDCO in the name(s) of the applicant(s) or premises : If yes, give details (with SC No, Name of Section/Circle etc) : |
| PRECAUTION TO BE ADOPTED BY CONSUMERS, OWNERS, ELECTRICAL CONTRACTORS, ELECTRICAL WORKMEN AND OTHER SUPPLIERS OF ENERGY | PRECAUTION TO BE ADOPTED BY CONSUMERS, OWNERS, OCCUPIERS, ELECTRICAL CONTRACTORS, ELECTRICAL WORKMEN AND SUPPLIERS |
| No electrical installation work, including additions, alterations, repairs and adjustments to existing installations except such replacement of lamps, fans, fuses, switches and other component parts of the installations as in no way alter its capacity or character shall be carried out upon the premises or on behalf of any consumer or owner for the purpose of supply of energy to such consumer or owner, except by an authorized person specifi ed by the Authority. | No electrical installation work, including additions, alterations, repairs and adjustments to existing installations, except such replacement of lamps, fans, fuses, switches, domestic appliances of voltage not exceeding 250V and fi ttings as in no way alters its capacity or character, shall be carried out upon the premises of or on behalf of any consumer, supplier, owner or occupier for the purpose of supply to such consumer, supplier, owner or occupier except by an electrical contractor licensed in this behalf by the State Government and under the direct supervision of a person holding a certifi cate of competency and by a person holding a permit issued or recognized by the State Government. |
| ACKOWLEDGEMENT Applicant(s)' name : Address : Date of receipt : Reference No. : Category of Supply : Signature and seal of Distribution Licensee Name and designation. | I / We certify that we are aware of the above precaution and agree to abide by it. I / We agree to pay to the Licensee at the applicable tariff /minimum rates/fi xed charges/surcharge etc., that may be decided by the Commission from time to time. I / We agree to abide under all specifi cations, conditions and provisions laid down in Tamil Nadu Electricity Regulatory Supply Code, Distribution Code and the applicable Act, Codes, Rules and Regulations and of any modifi cation or re-enactment thereof for the time being in force and subject to the conditions of revisions, amendments approved from time to time. (Note : This undertaking does not preclude execution of a separate written contract to be entered with Licensee) Place: Signature of the applicant(s) Date: Name(s) in Block Letters Note: The application shall be accompanied with the following documents: (i) Self attested copy of proof of ownership such as sale deed (or) partition deed (or) gift settlement (or) allotment letter (or) computer patta (or) ownership certifi cate issued by revenue department offi cials (or) court judgment or recent property tax receipt. (ii) In case of joint property, self attested copies of proof of ownership along with parent documents specifi ed in note (i) above and consent letters from co-owners. If consent letter is not produced, an indemnity bond with enhanced security deposits. (iii) If the applicant is not the owner, consent letter from owner in FORM No.5 or valid proof of occupancy and indemnity bond in FORM No.6 |
| FOR LICENSEE'S USE ONLY ACKOWLEDGEMENT Applicant(s)' name : Address : Date of receipt : Reference No. : Category of Supply : Signature and seal of Distribution Licensee Name and designation." |
"FORM IA
Application Form for Temporary Service Connection
FORM OF REQUISITION FOR TEMPORARY SUPPLY ( SINGLE PHASE / THREE PHASE)
[Refer regulation 27(3)]
To
The Designated Engineer
(Address of the Licensee)
Applicant(s)' Photo(s)
Sir,
1. I/We, /Thiru/Tmty……………………………………………………….........................................................................................
S/o/D/o/W/o/………………………………………………………………………..…….…………………………………………
hereby request you to supply electrical energy, temporarily for the purpose of………………………………………………………
…………………………….. …..………………………………………………………………………. …… to the premises (or) location
hereinafter described.
2. I / We agree to pay for said energy, service connection charges, the deposit of such security, meter rent, development
charges and any other charges as may be demanded in accordance with the scale of rates prescribed under Tamil Nadu Electricity
Distribution Code, Supply Code, notifi cations and orders issued in this regard by Tamil Nadu Electricity Regulatory Commission.
3. I/ We wish to be charged under Tariff ………… under schedule of the TNERC tariff order in force.
4. I/ We agree to avail temporary supply and utilize the energy in the premises/ location described hereunder for my/our
bonafi de use.
5. In case, I/We sell or otherwise dispose of the property / vacate the premises while the supply is continued, I/We agree to
give one month notice in writing and pay all the arrears to the Licensee, failing which, I/We hold myself/ourselves responsible for
the energy consumed in the premises for the entire period of Temporary supply availed. If any due arises in this service connection,
I/We agree to include such dues in my/our existing service connections No(s): ………………………………………………………...
(if available)
6. Ownership of the premises / location where temporary supply is required:
a. SF No./ Door No. :
b. Street :
c. Town / village :
d. Land mark of premises :
e. Taluk :
f. District :
g. Owned by (Name in Block Letters) :
h. Tenanted by (Name in Block Letters) :
i. Applicant(s)' address for correspondence :
j. Contact No. and e-mail id :
Jan. 27, 2021] TAMIL NADU GOVERNMENT GAZETTE 477. Description of the premises
a. Plot area :
b. Total building area/Floor area of all fl oors :
c. Number of the Floors to be constructed :
(Basement /stilt /ground fl oor/other Floors to be furnished in detail )
d. Whether the planning permission with building plan approval is obtained from competent authority for above
mentioned fl oors and construction :
e. Whether copy of Planning permission with building plan approval is enclosed :
f. Height of the building as per planning permission/ Plan approval :
(If height of the building is more than 15 metre as shown in the planning permission, approval from Electrical Inspector
is required)
g. Whether Gen set /Lift is proposed to be erected :
(If yes , approval from Electrical Inspectorate to be obtained)
h. Any HT/LT line is passing inside or adjacent to the premise :
(If yes, building should be constructed with adequate safe clearance as per the Safety Regulations in force or
otherwise the lines should be got deviated at the cost of applicant, subject to feasibility)
8. Whether the service connection is required permanently after the period of temporary service connection is over :
If No, (i) Specifi c purpose for which Temporary supply is requested :
(ii) Period of Temporary supply required :
9. Details of Loads to be Connected:
(A) Lighting Number of Wattage of Total
Points points wattage
(i) Lights
-
-
-
(ii) Fans
-
-
-
(iii) Convenient wall plugs
-
-
(B) Power Loads
(i) Motors
-
-
-
(ii) Welding
-
-
-
(iii) Cutting machine
(iv) Portable appliances
-
-
(v) Lifts/elevators
-
-
-
(vi) Other apparatus
-
-
-
(vii) Convenient Wall Plugs -
-
10. Demand applied for in KW :
11. Whether the installation is provided with earth protective device (RCD) as per Tamilnadu Electricity Distribution Code:
12. The wiring has been completed on :
13. Details of existing service connection(s) of the applicant(s), if any :
14. Whether any current consumption charges or any other charges are due to TANGEDCO in the name(s) of the applicant(s)
or premises :
[Part VI—Sec. 2 48 TAMIL NADU GOVERNMENT GAZETTEIf yes, give details ( with SC No, Name of Section/Circle etc ) :
SPACE TO BE PROVIDED BY APPLICANT(s)
1. In storeyed building and for any building / premises requiring LT service connection(s) having either (a) total fl oor
area of 900 square metre and above (excluding the stilt fl oor / basement fl oor) or (b) the total demand of all the LT
services in the building exceeds 112kW, suffi cient space shall be made available free of cost to the Licensee for
installing transformers, switchgears etc., as stated in Regulation 29 (11) of the TNE Distribution Code.
2. Space as per the norms specifi ed in Regulation 29(12) of the TNE Distribution Code shall be allotted by the applicant
free of cost for establishment of a sub-station/switching station in places requiring service connections (except
industrial service connections other than IT related purposes) where either (a) the total demand of all the electrical
services in the projects including the loads that will be incident in future exceeds /would exceed 5 MVA or (b) total
fl oor area of 30,000 square metre and above is constructed or proposed to be constructed (excluding the stilt fl oor /
basement fl oor).
3. For High Tension Service connections of indoor metering, an electrical room with RCC roof having a clear fl oor
area 5 metre x 6 metre with vertical clearance of 3.7 metre between fl oor and ceiling/ beam bottom with locking
facility, exhaust fan and adequate size of cable duct shall be provided at the ground/ basement fl oor for installing the
Licensee's equipments, etc. This room shall be of fi reproof and weatherproof ; For outdoor metering a clear space
of 10 metre x 4 metre or 5 metre x 5 metre open to sky shall be provided. This enclosure shall be at the periphery
of the building and shall be cut off from other portions of the premises by fi re resistance walls. These areas shall be
specifi cally shown in the plan. Before the plan is sent to the competent authority for approval, it shall be sent to the
area Engineer of the Licensee and got approved. The point of supply shall be within 30 metre from the main gate
easily accessible for lorry movement from public road and clearly visible from the public road and satisfactory with
regards to security aspects.
PRECAUTION TO BE ADOPTED BY CONSUMERS, OWNERS, OCCUPIERS, ELECTRICAL CONTRACTORS,
ELECTRICAL WORKMEN AND SUPPLIERS
No electrical installation work, including additions, alterations, repairs and adjustments to existing installations, except such
replacement of lamps, fans, fuses, switches, domestic appliances of voltage not exceeding 250V and fi ttings as in no way alters
its capacity or character, shall be carried out upon the premises of or on behalf of any consumer, supplier, owner or occupier for
the purpose of supply to such consumer, supplier, owner or occupier except by an electrical contractor licensed in this behalf by
the State Government and under the direct supervision of a person holding a certifi cate of competency and by a person holding a
permit issued or recognized by the State Government.
I / We certify that we are aware of the above precaution and agree to abide by it.
I / We agree to pay to the Licensee at the applicable tariff/minimum rates/fi xed charges/surcharge etc that may be decided
by the Commission from time to time.
I / We agree to abide under all specifi cations, conditions and provisions laid down in Tamil Nadu Electricity Regulatory Supply
Code, Distribution Code and the applicable Act, Codes, Rules and Regulations and of any modifi cation or re-enactment thereof for
the time being in force and subject to the conditions of revisions, amendments approved from time to time.
(Note: This undertaking does not preclude a separate written contract to be entered with Licensee )
Signature of the Applicant(s)
Name(s) in Block Letters.
Place:
Date:
Note:
1. The application shall be accompanied with the following documents:
(i) Self attested copy of proof of ownership such as sale deed (or) partition deed (or) gift settlement (or) allotment
letter (or) computer patta (or) ownership certifi cate issued by revenue department offi cials (or) court judgment or recent
property tax receipt.
Jan. 27, 2021] TAMIL NADU GOVERNMENT GAZETTE 49(ii) In case of joint property, self attested copies of proof of ownership along with parent documents specifi ed in note
(i) above and consent letters from co-owners. If consent letter is not produced, an indemnity bond with enhanced security
deposits.
(iii) If the applicant is not the owner, consent letter from owner in FORM No.5 or valid proof of occupancy and
indemnity bond in FORM No.6
(iv) Plan approval with area earmarked for installing transformer, in case of fl oor area of 900 square metre and above
or the demand exceeds 112KW, in case of LT service connections as per sub regulation 29 (11) of the TNE Distribution
Code
OR
Plan approval with area earmarked for establishment of sub-station and road approaches, in case of demand / area
exceeds the limit as specifi ed with conditions in sub regulation 29 (12) of the TNE Distribution Code
OR
Plan approval with area earmarked for Indoor / outdoor metering , and location of metering point with road approaches
in case of HT service connection as specifi ed with conditions in sub regulation 29(14) of the TNE Distribution Code.
FOR LICENSEE'S USE ONLY
ACKNOWLEDGEMENT
Applicant(s)' name :
Address :
Date of receipt :
Reference No. :
Category of Supply :
Signature and seal of Distribution Licensee
Name and designation"
( By order of the Tamil Nadu Electricity Regulatory Commission )
Chennai-600 032, S.CHINNARAJALU,
8th January 2021. Secretary,
Tamil Nadu Electricity Regulatory Commission.
PRINTED AND PUBLISHED BY THE COMMISSIONER OF STATIONERY AND PRINTING, CHENNAI ON BEHALF OF THE GOVERNMENT OF TAMIL NADU