pw¡fd Hkwfe vtZu] iquokZlu vkSj iquO;ZoLFkkiu esa mfpr çfrdj vkSj ikjnf'kZrk dk vf/kdkj vf/kfu;e] 2013 ¼vf/kfu;e la[;k 30] lu~ 2013½ dh /kkjk 11 dh mi/kkjk ¼1½ ds v/khu çkjafHkd vf/klwpuk] jkT; ljdkj }kjk xzke-papfy;k iukjh Vksyk xq#j ijxuk-vxksjh] rglhy&vkscjk] ftyk lksuHkæ esa dqy 72-9230 gsDVs;j Hkwfe ds yksd ç;kstu vFkkZr ftyk lksuHkæ esa mÙkj çns'k jkT; fo|qr mRiknu fuxe fyfeVsM ds ek/;e ls 2x660 esxkokV vkscjk lh rkih; ifj;kstuk ds jk[k ck¡/k ds fuekZ.k ds fy, vf/klwpuk la[;k 1511/24&03&2023&1294&2020] fnukad 12 flrEcj] 2023 }kjk vtZu djus ds fy, tkjh dh xbZ Fkh; 2&vkSj] pwafd iwoksZä vf/kfu;e dh /kkjk 19 dh mi/kkjk ¼1½ ds v/khu ?kks"k.kk çkjafHkd vf/klwpuk ds fnukad ls 12 ekg ds Hkhrj tkjh ugha dh tk ldh;
3&vkSj] pwafd iwoksZä vf/kfu;e dh /kkjk 19 dh mi/kkjk ¼7½ ds vuqlkj] tgka çkjafHkd vf/klwpuk ds fnukad ls ckjg ekg ds Hkhrj /kkjk 19 dh mi/kkjk ¼1½ ds v/khu dksbZ ?kks"k.kk ugha dh tkrh gS] rks ,slh vf/klwpuk fo[kafMr dj nh xbZ le>h tk,xh;
4&vkSj] pwafd ftyk eftLVªsV lksuHkæ us ckjg ekg dh vof/k c<+kus dk dkj.k lfgr vuqjks/k fd;k gS vkSj jkT; ljdkj dh jk; gS fd vlko/kkuho'k foyac ds fy, ifjfLFkfr;ka fo|eku Fkh;
5&vr,o] vc] Hkwfe vtZu] iquokZlu vkSj iquO;ZoLFkkiu esa mfpr çfrdj vkSj ikjnf'kZrk dk vf/kdkj vf/kfu;e] 2013 dh /kkjk 19 dh mi/kkjk ¼7½ ds vafre ijUrqd }kjk çnr 'kfä;ksa dk ç;ksx djds jkT;iky iwoksZä vf/kfu;e dh /kkjk 19 dh mi/kkjk ¼1½ ds v/khu ?kks"k.kk ds fy, 06 ekg dh vof/k foLrkfjr djrh gSaA 2 mRrj izns'k vlk/kkj.k xtV] 4 uoEcj] 2024 IN pursuance of the provisions of clause (3) of Article 348 of the Constitution, the Governor is pleased to order the publication of the following English translation of notification no. 845/XXIV-P-3- 2024-1294-2020, dated November 4, 2024:
No. 845/XXIV-P-3-2024-1294-2020
Dated Lucknow, November 4, 2024
WHERE the preliminary notification under sub-section (1) of section 11 of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (Act No. 30 of 2013), was issued by the State Government for the acquisition of total 72.9230 hectares of land in village Chanchalia Panari Tola Gurur Pargana Agori, Tehsil Obra, District Sonbhadra for public purpose i.e. construction of ash dam of 2x660 MW Obra C Thermal Project through Uttar Pradesh State Electricity Generation Corporation Limited in District Sonbhadra vide notification no. 1511/24-03-2023-1294-2020, dated September 12, 2023.
2. AND, WHEREAS, declaration under sub-section (1) of the section 19 of the aforesaid Act could not be issued within 12 month from the date of preliminary notification.
3. AND, WHEREAS, as per sub-section (7) of section 19 of the aforesaid Act, where no declaration is made under sub-section (1) of section 19 within twelve months from the date of preliminarily notification, then such notification shall be deemed to have been rescinded;
4. AND, WHEREAS, the District Magistrate Sonbhadra has requested with reason to extend the period of twelve months and the State Government is of the opinon that circumstances existed for the inadvertent delay;
5. NOW, THEREFORE, in exercise of the powers conferred by the last proviso to sub-section (7) of section 19 of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, the Governor is pleased to extend for a period of 06 months for declaration under sub-section (1) of the section 19 aforesaid Act.
By order,
NARENDRA BHOOSHAN,
Pramukh Sachiv.