Servants of Knowledge
Uttar Pradesh Extraordinary Gazette · Government of Uttar Pradesh

Superseding Notification No. 229-24-P-3-2015, dated March 4, 2015.

Published 14 August 2026

Department
Energy Department
Type
Extraordinary
Notification no.
365/24-पी-3-2026
Subdepartment
Anubhag-3
Identifier
in.gazette.uttarpradesh_extraordinary.2026-08-14.c_202609111332343864
Languages
English, Hindi
Published at
Original source ↗

click here for IIIF manifest

Øe-la[;k&248

jftLVªs'kuuEcj&,lå,låihå@,yå&

MCywå@,uåihå&91@2014&16

ykblsUlVwiksLV ,sVdUls'kuyjsV

—

¼ifjfu;r vkns'k½

mRrj izns'k 'kklu

la[;k 365@24-ih-3–2026

y[kuÅ] 14 vxLr] 2026

&&&&&&

vf/klwpuk

dsUæh; fo|qr çkf/kdj.k ¼lqj{kk ,oa fo|qr vkiwfrZ ls lEcaf/kr mik;½ fofu;e] 2023 ds fofu;e 31 ds mi&fofue ¼1½ rFkk fofu;e 45 ds mi&fofue ¼1½ ds v/khu çnÙk 'kfDr;ksa dk ç;ksx djds rFkk vf/klwpuk la[;k 229-24-ih-3&2015] fnukad 4 ekpZ] 2015 dk mu ckrksa ds flok; vf/kØe.k djds tks ,sls vf/kØe.k ls iwoZ dh x;h gksa ;k fd;s tkus gsrq yksfir gksa] jkT;iky yksdfgr esa funs'k nsrs gaS fd lkj.kh&1 esa ;Fkk mfYyf[kr fuEufyf[kr fo|qr dusD'kuksa ds fy, ÅthZ—r djus ls iwoZ ¼d½ fo|qr lqj{kk funs'kky; }kjk fujh{k.k djk;s tkus vkSj rRi'pkr~ vukifÙk çek.k-i= çkIr djus vkSj@;k ¼[k½ jkT; ljdkj }kjk ykblsal çkIr fo|qr Bsdsnkj }kjk tkjh dk;Ziwjd çek.k-i= çkIr djus ds ctk;] miHkksDrk }kjk vkiwfrZdrkZ dks Lo-?kks"k.kk çLrqr djuk i;kZIr gksxk%&

lkj.kh&1

Ø0 la0 miHkksDrk dh Js.kh dusD VsM yksM de ;k cjkcj
1 ,y0,e0oh0&1 ¼?kjsyw cR rh vkSj ia[kk½ 50 fdyksokV
2 ,y0,e0oh0&2 ¼dkef'kZ;y cR rh vkSj ia[kk½ 50 fdyksokV ¼uhps uksV&*d* ds v/ ;/khu½
3 ,y0,e0oh0&4 ¼lkoZtfud@futh laLFkku½ 50 fdyksokV ¼uhps uksV&*d* ds v/ ;/khu½
4 ,y0,e0oh0&5 ¼futh uydwi½ 50 fdyksokV
5 ,y0,e0oh0&9 vLFkk;h lI ykbZ ¼futh ?kj ds fuekZ.k gsrq vLFkk;h dusD 'ku½ 50 fdyksokV ¼uhps uksV&*[k* ds v/ ;/khu½
6 ,y0,e0oh0&11 ¼bysfDVªd O ghdy pkftaZx½ ¼cslesaV es çfr" Bkiu ls fHkU u ekeys½ a 50 fdyksokV ¼uhps uksV&*x* ds v/ ;/khu½
7 ,p0oh0&4 ¼fy¶V] flapkbZ½ 50 fdyksokV

¼d½ ,y0,e0oh0&2 vkSj ,y0,e0oh0&4 Jsf.k;ksa ds v/khu ,sls çfr"Bkuksa ds fy, ftudk

dusDVsM yksM 50 fd0ok0 ls de ;k mlds cjkcj gS%&463 RPH 2026 (Urja Anubhag-3) data 1e 2 mRrj izns'k vlk/kkj.k xtV] 14 vxLr] 2026 ¼,d½ tgk¡ 100 ;k mlls vf/kd O;fDr;ksa ds ,d= gksus dh laHkkouk gks] ogk¡ fo|qr dusD'ku tkjh djus ls iwoZ fo|qr lqj{kk funs'kky; }kjk fo|qr lqj{kk fujh{k.k ds mijkar tkjh vukifÙk çek.k-i= rFkk ykblsal çkIr fo|qr Bsdsnkj }kjk tkjh dk;Ziwjd çek.k-i= çkIr djuk vfuok;Z gksxkA

¼nks½ 10 ;k mlls vf/kd fcLrjksa okys vLirky ;k uflaZx gkse] 'kS{kf.kd laLFkku ¼Iys Ldwy lfgr½] iqLrdky;] cSaDosV g'y ¼LFkk;h ;k vLFkk;h½] Nk=kokl] ohfM;ks xse ikyZj] esys] çn'kZuh LFky] dyk nh?kkZ,¡] f'k'kqd{k] Iys tksu] fFk,Vj] laxzgky; vkSj 150 oxZ ehVj ls vf/kd {ks=Qy okys jsLVksjsUV ¼lHkh eaftyksa lesr½ tSls çfr"Bkuksa ds fy,] Hkys gh ogk¡ ,d= gksus okys O;fDr;ksa dh laHkkfor la[;k 100 ls de gks] lkoZtfud lqj{kk ds fgr esa] fo|qr dusD'ku tkjh djus ls iwoZ fo|qr lqj{kk funs'kky; }kjk fo|qr lqj{kk fujh{k.k ds mijkUr tkjh vukifÙk çek.k-i= rFkk ykblsal çkIr fo|qr Bsdsnkj }kjk tkjh dk;Z iwjd çek.k-i= çkIr djuk vfuok;Z gksxkA

¼rhu½ blds vfrfjDr] ,sls vU; çfr"Bkiuksa ;k ifjljksa ds fy,] tks fdlh Hkh dkj.k ls lkoZtfud lqj{kk ds ifjçs{; esa laosnu'khy gksa] fo|qr fujh{kd vkiwfrZdrkZ dks fo|qr dusD'ku tkjh djus ls igys ;k mlds i'pkr~ fo|qr lqj{kk funs'kky; ls tkjh vukifÙk çek.k-i= çkIr djus rFkk ifjlj ds Lokeh ls fo|qr dusD'ku tkjh djus ls iwoZ ykblsal çkIr fo|qr Bsdsnkj }kjk tkjh dk;Ziwjd çek.k-i= çkIr djus dk funs'k ns ldrk gSA ¼[k½ ,y0,e0oh0&9 Js.kh ds v/khu futh vkoklksa ds fuekZ.k ds fy, vko';d 50 fd0ok0 ls de ;k mlds cjkcj yksM okys vLFkk;h dusD'kuksa dks NksM+dj] vU; lHkh ekeyksa esa fo|qr lqj{kk fujh{k.k ds mijkUr fo|qr lqj{kk funs'kky; }kjk tkjh vukifÙk çek.k-i= rFkk ykblsal çkIr fo|qr Bsdsnkj }kjk tkjh dk;Ziwjd çek.k-i= çkIr djuk vfuok;Z gksxkA ¼x½ ,y0,e0oh0&11 Js.kh ds v/khu Hkou ds cslesaV esa fLFkr fdlh Hkh {kerk ds fo|qr çfr"Bkiuksa ds fy, fo|qr lqj{kk ls fujh{k.k ds mijkUr fo|qr lqj{kk funs'kky; }kjk tkjh vukifÙk çek.k-i= rFkk ykblsUl çkIr fo|qr Bsdsnkj }kjk tkjh dk;Ziwjd çek.k-i= çkIr djuk vfuok;Z gksxkA

2μ fo|qr miHkksDrkvksa dh Jsf.k;ksa ds fy, fo|qr lqj{kk ls lEcfU/kr vukifÙk çek.k-i= ,oa dk;Ziwjd çek.k-i= çkIr djuk vfuok;Z gksxk] ftUgsa bl vf/klwpuk ds v/khu ,slh vko';drk ls NwV çkIr ugha gSA

3&miqZDr NwV çkIr ekeyksa esa miHkksDrk vkiwfrZdrkZ@ykblsal/kkjh dks fuEufyf[kr çk:i esa ?kks"k.kk çLrqr djsxk%&

Lo&?kks"k.kk

1&ÞeSa] -----------------------------------------iq=@iq=h@iRuh Jh------------------------------------ fuoklh ---------------------------------------] ,rn~}kjk ?kks"k.kk djrk@djrh gw¡ fd eSaus---------------------¼dusD'ku dk LFkku½ ij ------------------------------------------ Js.kh esa fo|qr dusD'ku gsrq vkiwfrZdrkZ@ykblsal/kkjh ¼iwokaZpy@if'pekapy@e/;kapy@nf{k.kkapy fo|qr forj.k fuxe fyfeVsM@dsLdks@,uihlh,y@vU;½ ds le{k vkosnu fd;k gSA

ÞeSa] ------------------------------------------iq=@iq=h@iRuh ------------------------------------------------------------ ¼QeZ@dEiuh dk uke vkSj QeZ ,oa daiuh dk irk½ -------------------------------------dh vksj ls ,rn~}kjk ?kks"k.kk djrk@djrh gw¡ fd eSaus@geus ---- ---------------------------------------------------------------¼dusD'ku dk LFkku½ ij -------------------------------------------------Js.kh esa fo|qr dusD'ku gsrq vkiwfrZdrkZ@ykblsal/kkjh ¼iwokaZpy@if'pekapy@e/;kapy@nf{k.kkapy fo|qr forj.k fuxe fyfeVsM@dsLdks@ ,uihlh,y@vU;½ ds le{k vkosnu fd;k gSA

2&esjs ifjlj ds fo|qr çfr"Bkiu ls lEcaf/kr dk;Z jkT; ljdkj }kjk ekU;rk çkIr ykblsal çkIr fo|qr Bsdsnkj }kjk fd;k x;k gSA

3&mDr fo|qr çfr"Bkiu dsaæh; fo|qr çkf/kdj.k ¼lqj{kk vkSj fo|qr vkiwfrZ ls lEcaf/kr mik;½ fofu;e] 2023 ds mica/kksa dk vuqikyu djrk gS vkSj fo|qr lqj{kk ds ekudksa dks iwjk djrk gSA

4&mDr fo|qr çfr"Bkiu ls gksus okyh fdlh Hkh nq?kZVuk ds fy, eSa iw.kZr% Lo;a ftEesnkj jgw¡xk@jgw¡xhA

5&bl ?kks"k.kk esa mfYyf[kr çR;sd rF; esjh loksZÙke tkudkjh vkSj fo'okl ds vuqlkj lR; gSA ;fn bl ?kks"k.kk esa mfYyf[kr dksb Hkh rF; xyr ;k vlR; ik;k tkrk gS] rks mldh iw.kZ ftEesnkjh esjh gksxhA463 RPH 2026 (Urja Anubhag-3) data 1e mRrj izns'k vlk/kkj.k xtV] 14 vxLr] 2026 3 6&fo|qr dusD'ku dk fooj.k fuEufyf[kr gS%&

flaxy Qst lIykbZ 220/ 230 oksYV Fkzh Qst lIykbZ 440/400 oksYV
Qst&1 Qst&2 Qst&3 3&Qst vkiwfrZ ij pyus okys midj.k dqy tqMk gqvk ;k visf{kr Hkkj ¼okV½
la[ ;k dqy tqM+k gqvk ;k visf{kr Hkkj ¼okV½ la[;k dqy tqM+k gqvk ;k visf{kr Hkkj ¼okV½ la[;k dqy tqM+k gqvk ;k visf{kr Hkkj ¼okV½ la[;k dqy tqM+k gqvk ;k visf{kr Hkkj ¼okV½ la[;k dqy tqM+k gqvk ;k visf{kr Hkkj ¼okV½
1&cR rh I okbaV~l
2&ia[kk IokbaV~l
3&5 ,Eih;j Iyx I okbaV~l
4&Vhåohå
5&ghVj
6&okVj ghVj@xhtj
7&okf'kax e'khu@Mªk;j
8& jsfÝtsjsVj@ Mhi Ýhtj@ is;ty okVj dwyj
9&fdpu midj.k
10&MstVZ dwyj@okVj dwyj
11&,0lh0 flaxy Qst
12&,0lh0 Fkzh Qst × × × × × × × ×
13&15 ,Eih;j Iyx I okbaV~l
14&eksVj flaxy Qst
15&eksVj Fkzh Qst × × × × × × × ×
16&vU midj.k flaxy Qst
17&vU midj.k Fkzh Qst × × × × × × × ×

7&eSa@ge çekf.kr djrs gSa fd Åij mfYyf[kr çfr"Bkiu esjs@gekjs }kjk LFkkfir vkSj ijh{k.k fd;k x;k gS] vkSj esjs@gekjs loksZÙke Kku vkSj fo'okl ds vuqlkj] ;g le;-le; ij la'kksf/kr dsaæh; fo|qr çkf/kdj.k ¼lqj{kk vkSj fo|qr vkiwfrZ ls lEcaf/kr mik;½ fofu;e] 2023 dk vuqikyu djrk gS] rFkk Hkkjrh; ekud C;wjks vkSj Hkkjr ds jk"Vªh; fo|qr lafgrk ds laxr mica/kksa dk Hkh vuqikyu djrk gSA463 RPH 2026 (Urja Anubhag-3) data 1e 4 mRrj izns'k vlk/kkj.k xtV] 14 vxLr] 2026 8&eSa@ge çekf.kr djrs gSa fd vkiwfrZdrkZ ds vkiwfrZ fcanq ls vkxs vkosnd@miHkksDrk ds çfr"Bkiu ds fy, fuEufyf[kr fuca/kuksa ,oa 'krksaZ dk ikyu fd;k x;k gS%&

¼,d½ vkosnd miHkksDrk fo|qr vkiwfrZ ds çkjafHkd fcanq ds ikl mi;Dr jsfVax okyk ,uDykstj lfgr ,e0lh0ch0 laLFkkfir djsxk vkSj Mh0ih0 fLop laLFkkfir ugha djsxkA

¼nks½ vkosnd@miHkksDrk] ;fn oksYVst 250 oksYV ls vf/kd gks] rks çfr"Bkiu ds fy, viuh Lo;a dh vfFkaZx ç.kkyh miyC/k djk,xkA

¼rhu½ vkosnd@miHkksDrk] ;fn Loh—r yksM 2 fdyksokV ls vf/kd gks] rks vFkZ yhdst lqj{kk midj.k laLFkkfir djsxkA

miHkksDrk ds gLrk{kj % --------------------------------------- uke % ------------------------------------------------------------------------

fnukad % ------------------------------------------------------------------- LFkku % ----------------------------------------------------------------------

vkKk ls] MkW0 vk'kh"k dqekj xks;y] vij eq[; lfpoA

&&&&&&

IN pursuance of the provisions of clause (3) of Article 348 of the Constitution, the Governor is pleased to order the publication of the following English translation of notification no. 365/24-P-3–2026] dated August 14, 2026:

No. 365/24-P-3–2026

Dated Lucknow, August 14, 2026

IN exercise of the powers under sub-regulation (1) of regulation 31 and sub-regulation (1) of regulation 45 of the Central Electricity Authority (Measures relating to Safety and Electric Supply) Regulations, 2023 and in supersession of notification no. 229-24-P-3-2015 dated March 4, 2015, except as respects things done or omitted to be done before such supersession, the Governor is pleased to direct in public interest that, for the following electricity connections, as mentioned in Table-1, instead of (a) undergoing an inspection and obtaining a subsequent No Objection Certificate from the Directorate of Electrical Safety, and/or (b) obtaining a Work Completion Certificate issued by a State Government- licensed electrical contractor, prior to energisation, it shall be sufficient for the consumer to submit a self-declaration to the supplier:–

Sl. no. Consumer Category Connected Load less than or equal to
1 LMV-1 (Domestic Light & fan) 50 kW
2 LMV-2 ( Commercial Light & Fan) 50 kW (subject to Note A below)
3 LMV-4 (Public/Private Institutions) 50 kW (subject to Note A below)
4 LMV-5 (Private Tubewells) 50 kW
5 LMV-9 Temporary Supply (temporary connection only for the purpose of construction of private residence) 50 kW (subject to Note B below)
6 LMV-11 (Electric Vehicle Charging) (cases other than installations in basements) 50 kW (subject to Note C below)
7 HV-4 (Lift Irrigation) 50 kW

Note- (A) For establishments under the categories LMV-2 and LMV-4 with a connected load less than or equal to 50 kW:-

(i) Where there is a likelihood of 100 or more persons gathering, it shall be mandatory to obtain a No Objection Certificate (NOC), issued by the Directorate of Electrical Safety following an electrical safety inspection, and a Work Completion Certificate issued by a licensed electrical contractor, prior to the release of the electricity connection.

463 RPH 2026 (Urja Anubhag-3) data 1e

mRrj izns'k vlk/kkj.k xtV] 14 vxLr] 2026 5 (ii) For establishments such as hospitals or nursing homes with 10 or more beds, educational institutions (including play schools), libraries, banquet halls (permanent or temporary), hostels, video game parlours, fairs, exhibition venues, art galleries, crèches, play zones, theatres, museum and restaurants with an area exceeding 150 square metres (inclusive of all floors) — even if the number of persons likely to gather therein is fewer than 100 — in the interest of public safety, it shall be mandatory to obtain a No Objection Certificate (NOC), issued by the Directorate of Electrical Safety following an electrical safety inspection, and a Work Completion Certificate issued by a licensed electrical contractor, prior to the release of the electricity connection.

(iii) Additionally, for other such installations or premises that may be considered sensitive from the perspective of public safety for any reason, the Electrical Inspector may direct the supplier to require a No Objection Certificate (NOC) issued from the Directorate of Electrical Safety, either before or after the release of the electricity connection, and a Work Completion Certificate issued by a licensed electrical contractor, before the release of the electricity connection, from the owner of the premises.

NOTE:- (B) Under the LMV-9 category, barring temporary connections with load less than or equal to 50 kW required for construction of private residences, it shall be mandatory to obtain a No Objection Certificate (NOC), issued from the Directorate of Electrical Safety following an electric safety inspection, and a Work Completion Certificate issued by a licensed electrical contractor in all other cases.

NOTE:- (C) Under the LMV-11 category, it shall be mandatory to obtain a No Objection Certificate (NOC), issued from the Directorate of Electrical Safety following an electric safety inspection, and a Work Completion Certificate issued by a licensed electrical contractor, for electrical installations of any capacity located in the basement of a building.

2. It shall be mandatory to obtain an Electrical Safety No Objection Certificate (NOC) & Work Completion Certificate for those categories of electricity consumers that are not exempted from such requirement under this notification.

3.In the cases exempted above, the consumer shall submit a declaration in the following format to the Supplier/Licensee:-

Self-Declaration

1. I,......................................., son/daughter/wife of Shri ......................................., resident of ......................................., hereby declare that I have applied to the Supplier/Licensee (Purvanchal/ Paschimanchal/ Madhyanchal/Dakshinanchal Vidyut Vitran Nigam Ltd./KESCO /NPCL/Other) for an electrical connection at ......................................... (place of connection) in the ..........................................

category.

OR

I.............................................son/daughter/wife of Shri………………................………on behalf of………………………………....................……………. (Name of Firm/Company and Address of firm and Company) hereby declare that I/we have applied to the Supplier/Licensee (Purvanchal/ Paschimanchal/Madhyanchal/Dakshinanchal Vidyut Vitran Nigam Ltd./KESCO/NPCL/Other) for an electrical connection at ......................................... (place of connection) in the ..........................................

category.

2. The work regarding my electrical installation has been carried out by a licensed electrical contractor recognized by the State Government.

3. The said electrical installation complies with the provisions of the Central Electricity Authority (Measures relating to Safety and Electric Supply) Regulations, 2023, and meets the standards of electrical safety.

4. I shall be solely responsible for any accident arising from the said electrical installation.

5. Every fact mentioned in this declaration is true to the best of my knowledge and belief. I shall bear full responsibility if any fact mentioned in this declaration is found to be incorrect or false.

463 RPH 2026 (Urja Anubhag-3) data 1e 6 mRrj izns'k vlk/kkj.k xtV] 14 vxLr] 2026 6. The details of the electricity connection are as follows:–
Single Phase Supply (230/220 Volts) Three Phase Supply (440/400 Volts)
Number Total Load connected or anticipated (W) Phase1 Phase2 Phase3 Equipments running on 3-phase supply Total Load connected or anticipated (W)
Number Total Load connected or anticipated (W) Number Total Load connected or anticipated (W) Number Total Load connected or anticipated (W) Number Total Load connected or anticipated (W)
1. Light Points
2. Fan Points
3. 5 Ampere Plug Points
4. TV
5. Heater
6. Water Heater/ Geyser
7. Washing Machine/Dryer
8.Refrigerator/ Deep Freezer/ Drinking Water Cooler
9. Kitchen equipments
10. Desert Cooler/ Water Cooler
11. AC single phase
12. AC three phase × × × × × × × ×
13. 15Ampere Plug Point
14. Motor single phase
15. Motor three phase × × × × × × × ×
16. Other devices single phase
17. Other devices three phase × × × × × × × ×
Total

7. I/We certify that the installation detailed above has been installed by me/us and tested, and that, to the best of my/our knowledge and belief, it complies with the Central Electricity Authority (Measures relating to Safety and Electric Supply) Regulations, 2023, as amended up-to-date, and also the relevant provisions of the Bureau of Indian Standards and the National Electrical Code of India.

8. I/We certify that we have abided by the following Terms & Conditions for the Applicant/Consumer's installation beyond the point of supply of the Supplier:–

(i) The Applicant/Consumer shall install an appropriately rated MCB with enclosure near the start of the electricity supply and shall not install a DP switch.

(ii) The Applicant/Consumer, if having voltage exceeding 250 volts, shall provide his/her own earthing system for the installation.

463 RPH 2026 (Urja Anubhag-3) data 1e

mRrj izns'k vlk/kkj.k xtV] 14 vxLr] 2026 7 (iii) The Applicant/Consumer, if having a sanctioned load above 2 kW, shall install an earth leakage protection device.

Signature of Consumer: ______________________

Name: ______________________

Date: ______________________

Place: ______________________

By order,

DR. ASHISH KUMAR GOEL,

Apar Mukhya Sachiv.

ih0,l0;w0ih0&,0ih0 463 jkti=&2026&¼1140½&599 izfr;ka ¼Mh0Vh0ih0@vkWQlsV½A ih0,l0;w0ih0&,0ih0 5 lk0 ÅtkZ&2026&¼1141½&250 izfr;ka ¼Mh0Vh0ih0@vkWQlsV½A463 RPH 2026 (Urja Anubhag-3) data 1e

Cite this issue. Uttar Pradesh Extraordinary Gazette, Government of Uttar Pradesh, 14 August 2026. Indian Gazettes, https://egazette.servantsofknowledge.in/details/in.gazette.uttarpradesh_extraordinary.2026-08-14.c_202609111332343864/. Archive identifier in.gazette.uttarpradesh_extraordinary.2026-08-14.c_202609111332343864.