Reg. No. G-2/RNP/GOA/32/2015-2017
SERIES II No. 30
Panaji, 30th October, 2017 (Kartika 8, 1939)
EXTRAORDINARY
No. 2
GOVERNMENT OF GOA
Department of Public Grievances
___
Notification
No. 1/22/2013-14/DPG/GPGRAMS/206(A)
In exercise of the powers conferred by sub-sections (1) and (2) of section 4 and clause (b) of section 2 of the Goa (Right of Citizens to Time-Bound Delivery of Public Services) Act, 2013 (Goa Act 19 of 2013), read with section 21 of the General Clauses Act, 1897 (Central Act 10 of 1897), the Government of Goa hereby amends the Government Notification No. 1/22/2013-14/DPG/GPGRAMS/III/1(2) dated 08-04-2015, published in the Official Gazette, Series II No. 3, dated 16-4-2015 (hereinafter referred to as the "principal Notification") as follows, namely:—
In the Schedule to the principal Notification,—
(i) after the existing entry at serial No. 67, the following entry shall be inserted, namely:—
| 67 A | Certification of Electrical Installation by Electrical Inspector Manufacturing/Service | 15 days to month from the date of inspection or compliance to the observation into by the applicant and subsequent inspections to confirm compliance adhered to whichever is later |
(ii) after the existing entry at serial No. 71, the following entry shall be inserted, namely:—
| 71A | Grant of Drugs Wholesale License | Dy. Director of Food and Drugs Administration | 30 days | Director of Food and Drugs Administration |
1 Suggestions are welcomed on e-mail: dir–[email protected] 1759OFFICIAL GAZETTE — GOVT. OF GOA SERIES II No. 30 (EXTRAORDINARY No. 2) 30TH OCTOBER, 2017 (iii) after the existing entry at serial No. 80, the following entries shall be inserted, namely:—
| 80 A | Grants of Fresh Drugs/Cosmetics Manufacturing License with maximum five products | Dy. Director of Foods and Drugs Administration | 30 days from the receipt of completed application | Director of Food and Drugs Administration |
| 80 B | Grants of Renewal of Drugs/ /Cosmetics Manufacturing License | Dy. Director of Foods and Drugs Administration | 30 days from the receipt of completed application | Director of Food and Drugs Administration |
(iv) after the existing entry at serial No. 86, the following entries shall be inserted, namely:—
| 86 A | Application for Registration under The Building and Other Construction Workers (Regulation of Employment and Conditions of Service) Act, 1996 | Deputy Labour Commissioner | Fifteen working days | Labour Commissioner |
(v) after the existing entry at serial No. 93, the following entries shall be inserted, namely:—
| 93 A Making of the application to the concerned Sub-Division and processing for ascertaining technical feasibility | Assistant Engineer | 4 days | Executive Engineer | |
| Carrying out site inspection and preparations of feasibility report by Engineer-in-charge | Assistant Engineer | 12 days | Executive Engineer | |
| Preparation of installation bill by Sub-Division | Assistant Engineer | 4 days | Executive Engineer | |
| Payments of installation bill by consumers | Assistant Engineer | 3 days | Executive Engineer | |
| Releasing of Water Supply Connection and providing water meter | Assistant Engineer | 7 days | Executive Engineer | |
| Total | 30 days |
(vi) after the existing entry at serial No. 94, the following entry shall be inserted, namely:-
| 94 A | Site inspection by the Sub-Division Office | Assistant Engineer | 0 to 15 days | Executive Engineer |
| Inspection Report prepared by Sub-Division Office and submitted to Office Executive Engineer | Assistant Engineer | 0 to 30 days | Executive Engineer | |
| Inspection Report to be verified by the Office of Executive Engineer | Executive Engineer | 0 to 8 days | Superintending Engineer | |
| Applicant is granted Road Cutting Permission | Executive Engineer | 0 to 45 days | Superintending Engineer |
This Notification shall come into force from the date of its publication in the Official Gazette.
By order and in the name of the Governor of Goa.
Shaila Bhosle, Under Secretary (Public Grievances).
Porvorim, 30th October, 2017.
OFFICIAL GAZETTE — GOVT. OF GOA SERIES II No. 30 (EXTRAORDINARY No. 2) 30TH OCTOBER, 2017Notification
No. 1/22/2013-14/DPG/GPGRAMS/206(B)
In exercise of the powers conferred by sub-sections (1) and (2) of section 4 and clause (b) of section 2 of the Goa (Right of Citizens to Time-Bound Delivery of Public Services) Act, 2013 (Goa Act 19 of 2013), read with section 21 of the General Clauses Act, 1897 (Central Act 10 of 1897), the Government of Goa hereby amends the Government Notification No. 1/22/2013-14/DPG/GPGRAMS/III/1(2)/1168 dated 21-12-2015, published in the Official Gazette, Series II No. 39 dated 24-12-2015 (hereinafter referred to as the "principal Notification) as follows, namely:—
In the Schedule to the principal Notification,—
(i) for the existing entries at serial Nos. 2 and 3, the following entries shall be substituted, namely:—
| 2 | Registration of Society under section 8 of the Goa Co-operative Societies Act, 2001 (Goa Act 36 of 2001) | Registrar of Co-operative Societies | 45 days | Secretary of the Department of Co- -operation |
| 3 | Approval for amendment in the Bye-Laws of the Society under section 8 of the Goa Co-operative Societies Act, 2001 (Goa Act 36 of 2001) | Assistant Registrar of Co-operative Societies | 45 days | Registrar of Co-operative Societies |
(ii) (a) after entry at serial No. 132, the following entry shall be inserted, namely:—
| 132 A The Goa | State Incentives to Encourage Investments Schemes, 2017 | Incentives to industries for Certification and Patenting Scheme | Director of Industries, Trade & Commerce— Sanction limit amount upto Rs. 10 Lakh per disbursement per scheme | Sanctioning 30 days if designated officer agres with recommendation of the Task Force Committee | Secretary of Industries if sanction amount is upto Rs. 10 Lakh per disbursement per scheme. Chief Secretary if sanction amount is above Rs. 10 Lakh upto Rs. 20 Lakh per disburse- ment per scheme. |
| Employment Subsidy Scheme, 2017 and Employment Subsidy Scheme, 2008 | |||||
| The State Mission for Food Processing Scheme (SMFP), 2017 | Secretary of Department of Industries— Sanction Limit amount above Rs. 10 Lakh and upto Rs. 20 Lakh per disburse- ment per scheme | Sanctioning 45 days if designated officer agrees with recommendation of Task Force Committee | |||
| Training Linked Incentives Scheme | Disbursal 15 days after receiving sanction order | ||||
| Incentives to Consumption of Local Raw Material Scheme | |||||
| Incentive to Green Investments Scheme (Audit Component and Capital) | |||||
| Interest Subsidy Scheme, 2017 Interest Subsidy Scheme, 2008 |
(b) after entry at serial No. 136, the following entry shall be inserted, namely:—
| 136 A | Building Plan sanction including Plinth inspection | Field Manager/ /Area Manager of concerned Industrial Estate | 7 days | Managing Director |
| Regional Manager/ /Deputy General Manager | 7 days | Managing Director | ||
| General Manager | 16 days | Managing Director | ||
| Total | 30 days from complete submission of documents and payment of fees | |||
| Occupancy Certificate | Field Manager/ /Area Manager of concerned Industrial Estate | 3 days | Managing Director | |
| Regional Manager/ /Deputy General Manager | 2 days | Managing Director | ||
| General Manager | 3 days | Managing Director | ||
| Total | 8 days | |||
| Issue of site plans/layout plans | General Manager (Engineering Section) | 5 days | Managing Director | |
| Release of water connection to Industrial units 1 and above | Field Manager/ /Area Manager | 3 days | Managing Director | |
| Regional Manager/Deputy General Manager | 3 days | Managing Director | ||
| General Manager (Engineering)/ /Regional Manager (Head Office) | 5 days | Managing Director | ||
| Regional Manager/Deputy General Manager | 3 days | Managing Director | ||
| Total | 14 days | |||
| Release of water connection to Industrial units ½ and ¾ | Field Manager/ /Area Manager | 3 days | Managing Director | |
| Regional Manager/Deputy General Manager | 3 days | Managing Director | ||
| Total | 6 days | |||
| NOC for electric connection | Field Manager/ /Area Manager | 3 days | Managing Director | |
| Regional Manager/Deputy General Manager | 2 days | Managing Director | ||
| General Manager (Engineering)/ /Regional Manager (Head Office) | 3 days | Managing Director | ||
| Total | 8 days |
(iii) for the existing entries at serial Nos. 160 to 168, the following entries shall be substituted, namely:—
| 160 | Approval of Factory Plans | Chief Inspector of Factories & Boilers | 90 days | Secretary (Factories & Boilers) |
| 161 | Registration & Grant of Factories License | Chief Inspector of Factories & Boilers | 21 days | In accor- dance with section 19 (1) prescribed under the Goa (Right of Citizens to Time Bound Delivery of Public Services) Act, 2013 |
| 162 | Renewal of Factory License | Chief Inspector of Factories & Boilers | 21 days | Secretary (Factories & Boilers) |
| 163 | Amendment of Factory License | Chief Inspector of Factories & Boilers | 21 days | Secretary (Factories & Boilers) |
| 164 | Transfer of Factory License | Chief Inspector of Factories & Boilers | 21 days | Secretary (Factories & Boilers) |
| 165 | Approval of Notice of Period of Work for Adult Workers | Inspector of Factories | 21 days | Chief Inspector of Factories & Boilers |
| 166 | Issue of Certificate of Fitness to Young Person | Medical Inspector of Factories/ /Certifying Surgeon | 21 days | Chief Inspector of Factories & Boilers |
| 167 | Confirmation of appointment for conducting Medical Examination of Workers | Medical Inspector of Factories/ /Certifying Surgeon | 05 days | Chief Inspector of Factories & Boilers |
| 168 | Confirmation of appointment for conducting Industrial Hygiene Survey | Chemist | 05 days | Chief Inspector of Factories & Boilers |
| 168 A | Confirmation of dates of training programme to be organised | Training Assistant | 05 days | Chief Inspector of Factories & Boilers |
| 168 B | Issue of Provisional Order in Form-V after registration inspection | Inspector of Boilers | 02 days | Chief Inspector of Factories & Boilers |
| 168 C | Assigning of registration No. for boilers having heating surface area of less than 1000 Sq. meters | Inspector of Boilers | 30 days | Chief Inspector of Factories & Boilers |
| 168 D | Issue of Certificate for use of Boiler having heating surface are of more than 1000 Sq. meters | Chief Inspector of Factories & Boilers | 30 days | Secretary (Factories & Boilers) |
| 168 E | Steam Test of Boiler | Inspector of Boilers | 30 days | Chief Inspector of Factories & Boilers |
| 168 | Issue of Certificate for use of Boiler | Inspector of Boilers | 02 days | Chief Inspector of Factories & Boilers |
| 168 F | Permission to carry our repairs/ /alterations to Boilers | Chief Inspector of Factories & Boilers | 02 days | Secretary (Factories & Boilers) |
| 168 G | Inspection of material as per Indian Boiler Regulations, 1950 | Inspector of Boilers | 21 days | Chief Inspector of Factories & Boilers |
| 168 H Approval of drawings related to steam pipeline | Inspector of Boilers | 21 days | Chief Inspector of Factories & Boilers | |
| 168 I | Recognition of Boiler & steam pipeline repairers | Chief Inspector of Factories & Boilers | 30 days | Secretary (Factories & Boilers) |
| 168 J | Issue of certificate for manufacture and test | Chief Inspector of Factories & Boilers | (i) 03 days for Boiler component (ii) 07 days for Boiler | Secretary Boilers) |
(iv) (a) for the existing entry at serial No. 262, the following entry shall be substituted, namely:—
| 262 | Building Plan sanction / /New Construction License | Examination Site Inspection and submission of the papers to Chief Officer | Municipal Engineer | Twelve days | Chief Officer |
| Decision on the Application | Chief Officer/ /Commissioner | Three days | D.M.A. | ||
| Convey the decision to applicant | Municipal Engineer | Two days | Chief Officer/ /Commissioner | ||
| Issue of License | Chief Officer/ /Commissioner | Two days from the date of deposit of license fees | D.M.A. | ||
| Renewal of Construction License | Decision | Chief Officer/ /Commissioner | Five days | Chief Officer |
(b) after entry at serial No. 262, the following entry shall be inserted, namely:—
| 262 A | Plinth Inspection Certificate/ /Alignment Certificate | Inspection and issue of Certificate | Municipal Engineer | Seven days | Chief Officer/ /Commissioner |
This Notification shall come into force from the date of its publication in the Official Gazette.
By order and in the name of the Governor of Goa.
Shaila Bhosle, Under Secretary (Public Grievances).
Porvorim, 30th October, 2017.
www.goaprintingpress.gov.in
Published and Printed by the Director, Printing & Stationery, Government Printing Press, Mahatma Gandhi Road, Panaji-Goa 403 001.
Price–Rs. 7.00
PRINTED AT GOVERNMENT PRINTING PRESS, PANAJI-GOA—283/200—10/2017.