Servants of Knowledge
Goa Gazette · Government of Goa

Goa Gazette, No. 2223-3, 27 April 2022

Published 27 April 2022

Type
EOG
Gazette no.
2223-3
Num
2
Series
SI
Identifier
in.goa.egaz.2223-3.SI/2223-3-SI-EOG-2
Languages
English, Portuguese
Published at
Original source ↗

click here for IIIF manifest

Reg. No. RNP/GOA/32/2021-2023

RNI No. GOAENG/2002/6410

Panaji, 27th April, 2022 (Vaisakha 7, 1944) SERIES I No. 3 PUBLISHED BY AUTHORITY

EXTRAORDINARY

No. 2

the Joint Electricity Regulatory Commission GOVERNMENT OF GOA Department of Power

Office of the Chief Electrical Engineer

__

Notification

120/03/MYT22-23 to 24-25/CEE/Tech/

The Electricity Department, Government

of Goa, according to the Regulations and as

per the procedures outlined in section 61,

62, & 64 of the Electricity Act, 2003 had filed

Petition for approval of Aggregate Revenue

Requirement (ARR) for 3rd MYT Control

Period from FY 2022-23 to FY 2024-25 and

Determination of Retail Tariff for FY 2022-23

before the Hon'ble Joint Electricity Regulatory

Commission for the States of Goa and Union

Territories.

In exercise of the powers conferred under

various sections of the Electricity Act, 2003

and all powers enabling therein, on behalf of for the state of Goa and Union Territories has

issued the Tariff Order dated 31st March, 2022

for approval of Aggregate Revenue

Requirement (ARR) for 3rd MYT Control

Period from FY 2022-23 to FY 2024-25 and

Determination of Retail Tariff for FY 2022-23

for Electricity Department, Government of Goa

which is given herebelow. The said Tariff

Order is effective from 1st April, 2022 and

shall, unless amended or revoked, continue

to be in force till further orders of the

Commission.

The above is hereby brought to the notice

of the public.

By order and in the name of the Governor

of Goa.

Stephen Fernandes, Chief Electrical

Engineer & ex officio Additional Secretary.

Panaji, 26th April, 2022.

55 Suggestions are welcomed on e-mail: dir–[email protected] OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022

TARIFF ORDER

Approval of Aggregate Revenue Requirements (ARR) for 3rd MYT Control Period from FY 2022-23 to FY 2024-25 and Determination of Retail Tariff for FY 2022-23

Petition No. 63/2021

for

Electricity Department, Government of Goa (ED-Goa)

31stMarch2022

JOINT ELECTRICITY REGULATORY COMMISSION

For the State of Goa and Union Territories,

3rd and 4th Floor, Plot No. 55-56, Sector -18, UdyogVihar - Phase IV

Gurugram, (122015) Haryana

Telephone: +91(124) 4684705 Telefax: +91(124) 4684706

Website: www.jercuts.gov.in

E-mail: [email protected]

56 Joint Electricity Regulatory Commission (JERC) OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022

Table of Contents

1. Chapter 1: Introduction

(cid:20)(cid:17)(cid:20)(cid:17)(cid:3)(cid:36)(cid:69)(cid:82)(cid:88)(cid:87)(cid:3)(cid:45)(cid:82)(cid:76)(cid:81)(cid:87)(cid:3)(cid:40)(cid:79)(cid:72)(cid:70)(cid:87)(cid:85)(cid:76)(cid:70)(cid:76)(cid:87)(cid:92)(cid:3)(cid:53)(cid:72)(cid:74)(cid:88)(cid:79)(cid:68)(cid:87)(cid:82)(cid:85)(cid:92)(cid:3)(cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:3)(cid:73)(cid:82)(cid:85)(cid:3)(cid:87)(cid:75)(cid:72)(cid:3)(cid:54)(cid:87)(cid:68)(cid:87)(cid:72)(cid:3)(cid:82)(cid:73)(cid:3)(cid:42)(cid:82)(cid:68)(cid:3)(cid:68)(cid:81)(cid:71)(cid:3)(cid:56)(cid:55)(cid:182)(cid:86)(cid:3)(cid:11)(cid:45)(cid:40)(cid:53)(cid:38)(cid:12)

1.2. About Goa

1.3. About Electricity Department, Government of Goa (EDG)

1.4. Multi Year Tariff Regulations, 2021

1.5. Filing and Admission of the Present Petition

1.6. Interaction with the Petitioner

1.7. Notice for Public Hearing

1.8. Public Hearing

2. Chapter 2: Summary of Suggestions/Objections received, Response from the Petitioner and

(cid:87)(cid:75)(cid:72)(cid:3)(cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:182)(cid:86)(cid:3)(cid:57)(cid:76)(cid:72)(cid:90)(cid:86)

2.1. Regulatory Process

2.2. Suggestions/ Objections, Response of the Petitioner and Commi(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:182)(cid:86)(cid:3)(cid:57)(cid:76)(cid:72)(cid:90)(cid:86)

2.2.1. Delayed response post Cyclone Tauktae in Raia Village

2.2.2. Problem of live sagging wire and cracked pole

2.2.3. Computation of Cross Subsidy Surcharge (CSS)

2.2.4. Consideration of Tariff Policy while Computing Cross Subsidy Surcharge (CSS)

2.2.5. Additional Surcharge on stranded power due to Open Access

2.2.6. Computation of Additional Surcharge

2.2.7. Fulfilment of RPO Obligations through IEX products

2.2.8. Tariff Shock due to high revenue gap

2.2.9. High rate of return on equity

2.2.10. Formation of District Committee to help monitor loss reduction measures

2.2.11. Reduction in Electricity Duty

2.2.12. kVAh based Tariff for LT consumers

2.2.13. Reduction in delayed payment charges

2.2.14. Tariff on Street lighting within a compound

2.2.15. Consideration of Cold storage units as Agriculture allied Industry

2.2.16. Reliability linked tariff

2.2.17. Pumped Hydro Storage Systems (PHSS)

2.2.18. Low standards of O&M practices

2.2.19. Analyzing metering data

2.2.20. Audit of Annual Accounts

2.2.21. Periodical education of customers

2.2.22. Continuous Staff training, Long-term solution for power interruption and improvement of distribution efficiency

3. Chapter 3: True-up of the FY 2017-18, FY 2018-19, FY 2019-20 and FY 2020-21

3.1. Applicable provisions

3.2. Approach for the True-up of the FY 2017-18, FY 2018-19, FY 2019-20 and FY 2020-2157 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 3 Electricity Department, Government of Goa Joint Electricity Regulatory Commission (JERC) OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022

4. Chapter 4: Annual Performance Review of FY 2021-22

4.1. Applicable Provisions and Background

4.2. Approach for the Review for the FY 2021-22

5. Chapter 5: Determination of Aggregate Revenue Requirement for the 3rd MYT Control Period

5.1. Background

5.2. Approach for determination of ARR for each year of the 3rd MYT Control Period

5.3. Projection of Number of consumers, Connected Load and Energy Sales

5.4. Inter-State transmission loss

5.5. Intra-State Transmission & Distribution (T&D) Losses

5.6. Power Purchase Quantum & Cost

5.6.1. Power Purchase Quantum

5.6.2. Power Purchase Cost

5.6.3. Transmission Charges

5.6.4. Total power purchase quantum and cost

5.6.5. Energy Balance

5.6.6. Renewable Purchase Obligation 5.7. Operation & Maintenance Expenses

5.7.1. Employee Expenses

5.7.2. Administrative and General (A&G) Expenses

5.7.3. Repair & Maintenance Expenses (R&M)

5.7.4. Summary of O&M Expenses 5.8. Gross Fixed Assets (GFA) and Capitalization

5.9. Capital Structure

5.10. Depreciation

5.11. Interest on Loan

5.12. Return on Equity (RoE)

5.13. Interest on Security Deposits

5.14. Interest on Working Capital

5.15. Income Tax

5.16. Provision for Bad & Doubtful Debts

5.17. Non-Tariff Income (NTI)

5.18. Aggregate Revenue Requirement (ARR)

5.19. Revenue at existing Retail Tariff

5.20. Standalone Revenue Gap/ Surplus for FY 2022-23

6. Chapter 6: Tariff Principles and Design

6.1. Overall Approach

6.2. Applicable Regulations

6.3. Standalone and Consolidated Revenue Gap/ Surplus at existing tariff

6.4. Treatment of the Revenue Gap/ Surplus and Tariff Design58 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 4 Electricity Department, Government of Goa Joint Electricity Regulatory Commission (JERC) OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022 6.4.1. Tariff Design

6.4.2. Approved Final Tariff Schedule

6.4.3. Revenue from Approved Retail Tariff for FY 2022-23

6.4.4. Revenue Gap/ (Surplus) at Approved Tariff

6.4.5. Government Budgetary Support

6.4.6. Highlights of the Tariff Structure

7. Chapter 7: Open Access Charges for the FY 2022-23

7.1. Wheeling Charges

7.1.1. Allocation Matrix - Allocation of ARR into Wheeling and Retail Supply of Electricity 7.2. Additional Surcharge

7.3. Cross-Subsidy Surcharge

8. Chapter 8: Fuel and Power Purchase Adjustment Mechanism

8.1. Legal Provisions

8.2. Formula

9. Chapter 9: Directives

9.1. Directives continued in this Order

9.1.1. Annual Statement of Accounts

9.1.2. Preparation of Fixed Asset Register

9.1.3. Energy Audit Reports

9.1.4. Employee Cost / Manpower study

9.1.5. Interest on Consumer Security Deposit

9.1.6. Sub-Divisions as Strategic Business Units

9.1.7. Installation of Pre-Paid Meters

9.1.8. Unbundling of Electricity Department

9.1.9. Renewable Purchase Obligation

9.1.10. Billing and Collection Efficiency

9.1.11. Determination of Category wise/ Voltage wise Cost of supply

9.1.12. Submission of Petition for True up of FY 2016-17, FY 2017-18, FY 2018-19 and FY 2019-20 and APR of FY 2020-21

9.1.13. Collection of data based on consumer type

9.1.14. kVAh based tariff for LT-Industrial and LT-Commercial categories

10. Chapter 10: Tariff Schedule

10.1. Tariff Schedule

10.2. Applicability

10.3. General Terms and Conditions

10.4. Schedule of Miscellaneous Charges

Annexures

Annexure 1: List of Stakeholders59 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 5 Electricity Department, Government of Goa Joint Electricity Regulatory Commission (JERC) OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022

List of Tables

Table 1: Standalone Revenue Gap/ (Surplus) at existing tariff for the FY 2022-23 (INR Cr.) .................................. Table 2: Standalone Revenue Gap/ (Surplus) at proposed/approved tariff for the FY 2022-23 (INR Cr.).............. Table 3: Timelines of the interaction with the Petitioner ............................................................................................ Table 4: Details of Public Notices published by the Commission................................................................................ Table 5: Details of Public Notices published by the Petitioner .................................................................................... Table 6: Category-wise number of consumers proposed by the Petitioner for 3rd MYT Control Period ................... Table 7: Category-wise connected load (kW) proposed by the Petitioner for 3rd MYT Control Period ..................... Table 8: Category-wise energy sales (MUs) proposed by the Petitioner for 3rd MYT Control Period ....................... Table 9: Category-wise number of consumers approved by the Commission for 3rd MYT Control Period .............. Table 10: Category-wise connected load (kW) approved by the Commission for 3rd MYT Control Period .............. Table 11: Category-wise energy sales (MU) approved by the Commission for 3rd MYT Control Period ................... Table 12: Inter-state transmission losses considered by the Petitioner for FY 2021-22 and the 3rd MYT Control Period .............................................................................................................................................................................. Table 13: Inter-state losses approved by the Commission for 3rd MYT Control Period ............................................. Table 14: Intra-State Distribution Losses (%) submitted by the Petitioner ................................................................ Table 15: Intra-State Distribution Losses (%) approved by the Commission ............................................................. Table 16: Power Purchase quantum (MU) and Cost (In INR Cr) submitted by Petitioner for the 3rd Control Period .............................................................................................................................................................................. Table 17: Power purchase quantum at state periphery approved by the Commission for the 3rd Control Period .... Table 18: Power Purchase Quantum (MU) and cost (INR Cr) approved for the 3rd MYT Control Period ................ Table 19: Average Power Purchase Cost (APPC) for the FY 2022-23.......................................................................... Table 20: Energy Balance submitted by the Petitioner (MU) ...................................................................................... Table 21: Energy Balance approved by Commission (MU) .......................................................................................... Table 22: RPO plan submitted by the Petitioner for the 3rd MYT Control Period (MU) ............................................ Table 23: Renewable Purchase Obligation (RPO) approved by the Commission for 3rd MYT Control Period......... Table 24: Calculation of CPI rate considered for Employee Cost projection .............................................................. Table 25: Calculations of Employee Expenses for base year as submitted by the Petitioner (INR Crore) ............... Table 26: Employee Expense as submitted by the Petitioner for 3rd Control Period (INR Cr).................................. Table 27: Computation of Base Employee Expenses (INR Cr.) ................................................................................... Table 28: CPI inflation computed for 3rd Control Period ........................................................................................... Table 29: Employee Expense approved by the Commission for 3rd Control Period ................................................... Table 30: Calculation of CPI rate considered for A&G Expenses projection ............................................................ Table 31: Calculations of A&G Expenses for base year as submitted by the Petitioner (INR Crore) ...................... Table 32: A&G Expense as submitted by the Petitioner for 3rd MYT Control Period ................................................. Table 33: A&G Expense approved by the Commission for 3rd Control Period ........................................................... Table 34: Calculation of WPI rate considered for R&M Expenses projection ............................................................ Table 35: Calculation (cid:82)(cid:73)(cid:3)(cid:181)(cid:46)(cid:182)(cid:3)(cid:68)(cid:86)(cid:3)(cid:86)(cid:88)(cid:69)(cid:80)(cid:76)(cid:87)(cid:87)(cid:72)(cid:71)(cid:3)(cid:69)(cid:92)(cid:3)(cid:87)(cid:75)(cid:72)(cid:3)(cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:3)(cid:73)(cid:82)(cid:85)(cid:3)(cid:22)rd Control Period..................................................... Table 36: R&M Expense submitted by the Petitioner for 3rd Control Period ............................................................. (cid:55)(cid:68)(cid:69)(cid:79)(cid:72)(cid:3)(cid:22)(cid:26)(cid:29)(cid:3)(cid:181)(cid:46)(cid:182)(cid:3)(cid:70)(cid:82)(cid:80)(cid:83)(cid:88)(cid:87)(cid:68)(cid:87)(cid:76)(cid:82)(cid:81)(cid:3)(cid:69)(cid:92)(cid:3)(cid:87)(cid:75)(cid:72)(cid:3)(cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:3)(cid:73)(cid:82)(cid:85)(cid:3)(cid:22)(cid:85)(cid:71)(cid:3)(cid:48)(cid:60)(cid:55)(cid:3)(cid:38)(cid:82)(cid:81)trol Period .............................................................. Table 38: CPI inflation computed for 3rd MYT Control Period .................................................................................. Table 39: R&M Expense approved by the Commission for the 3rd MYT Control Period (in INR Cr.) ..................... Table 40: Summary of O&M expenses submitted by the Petitioner for the 3rd MYT Control Period (in INR Cr.) . Table 41: Summary of O&M expenses approved by the Commission for the 3rd MYT Control Period (in INR Cr.) Table 42: Capital Expenditure submitted by the Petitioner for the 3rd MYT Control Period (INR Cr) ..................... Table 43: Capitalization submitted by the Petitioner for the 3rd MYT Control Period (INR Cr) ............................... Table 44: Capital Expenditure & Capitalisation considered by the Commission for 3rd Control Period (INR Cr.) Table 45: Funding Plan as proposed by the Petitioner for the 3rd Control period (INR Crore) ............................... Table 46: Capital Structure submitted by the Petitioner for 3rd MYT Control Period (INR Crore) .......................... Table 47: Capital Structure considered by the Commission (INR Cr.) .......................................................................

60 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 6 Electricity Department, Government of Goa Joint Electricity Regulatory Commission (JERC) OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022

Table 48: GFA (including GFA addition through Electricity Duty Fund, Govt. Grants and Consumer Contribution) considered by the Commission for 3rd MYT Control Period (INR Cr.) ............................................... Table 49: GFA (excluding GFA addition through Electricity Duty Fund, Govt. Grants and Consumer Contribution) considered by the Commission for 3rd MYT Control Period (INR Cr.) ............................................... Table 50: Reconciliation of normative loan up to FY 2021-22 based on provisional information submitted by the Petitioner (INR Cr.) ........................................................................................................................................................ Table 51: Reconciliation of normative equity up to FY 2021-22 based on provisional information submitted by the Petitioner (INR Cr.) .................................................................................................................................................. Table 52: Depreciation submitted by the Petitioner for the 3rd MYT Control Period (INR Cr) ................................. Table 53: Asset-wise depreciation rate considered by the Commission for weighted average rate for 3rd MYT Control Period (%) .......................................................................................................................................................... Table 54: Depreciation considered by the Commission for 3rd MYT Control Period (INR Cr.) ................................ Table 55: Interest on Normative Loan submitted by the Petitioner for the 3rd MYT Control Period (INR Cr) ........ Table 56: Interest on Loan considered by the Commission for 3rd MYT Control Period (INR Cr.) .......................... Table 57: Return on Equity submitted by the Petitioner for the 3rd MYT Control Period (INR Cr) .......................... Table 58: Return on Equity considered by the Commission for 3rd Control Period (INR Cr.) ................................. Table 59: Interest on Security Deposit submitted by the Petitioner for the 3rd MYT Control Period (INR Cr)........ Table 60: Interest on Consumer security considered by the Commission for 3rd Control Period (INR Cr.) ........... Table 61: Interest on Working Capital submitted by the Petitioner for the 3rd MYT Control Period (In INR Cr) ... Table 62: Interest on working capital considered by the Commission for 3rd MYT Control Period (INR Cr.) ......... Table 63: Non-Tariff Income claimed by the Petitioner for the 3rd MYT Control Period (INR Cr) ........................... Table 64: Non-Tariff Income considered by the Commission for 3rd MYT Control Period (INR Cr.) ...................... Table 65: ARR submitted by the Petitioner for 3rd MYT Control Period (INR Cr.) .................................................... Table 66: ARR approved by the Commission for the 3rd MYT Control Period (INR Cr.) .......................................... Table 67: Revenue at existing tariff submitted by the Petitioner for FY 2022-23 (INR Cr.) ..................................... Table 68: Revenue at existing tariff approved by the Commission for FY 2022-23 (INR Cr.) .................................. Table 69: Standalone Revenue Gap/ (Surplus) at existing tariff approved by Commission for FY 2022-23 (In INR Cr) ............................................................................................................................................................................ Table 70: Standalone Revenue Gap/ (Surplus) submitted by Petitioner for FY 2022-23 (In Rs Cr) ........................ Table 71: Cumulative Revenue Gap/ (Surplus) submitted by Petitioner for FY 2022-23 (In Rs Cr) ........................ Table 72: Standalone Revenue Gap/ (Surplus) at existing tariff approved by Commission for FY 2022-23 (In INR Cr) ............................................................................................................................................................................ Table 73: Tariff Schedule proposed by the Petitioner for FY 2022-23 ........................................................................ Table 74: Existing and approved tariff .......................................................................................................................... Table 75: Revenue from approved retail tariff determined by Commission (In INR Cr)........................................... Table 76: Tariff increase approved by Commission ..................................................................................................... Table 77: Revenue Gap/ (Surplus) approved by Commission for FY 2022-23 (In INR Cr) ...................................... Table 78: Allocation matrix as submitted by the Petitioner......................................................................................... Table 79: Wheeling Charge calculation as submitted by Petitioner ............................................................................ Table 80: Allocation matrix approved by Commission ................................................................................................ Table 81: Parameters assumed for voltage wise allocation of wheeling costs............................................................. Table 82: Allocation of costs based on voltage level ..................................................................................................... Table 83: Wheeling Charges approved by Commission ............................................................................................... Table 84: Additional Surcharge calculation as submitted by Petitioner ..................................................................... Table 85: Additional Surcharge approved by Commission .......................................................................................... Table 86: Cross-Subsidy Surcharge as proposed by the Petitioner ............................................................................. Table 87: Voltage wise losses assumed by Commission ............................................................................................... Table 88: Energy Input at each voltage level (MU) ...................................................................................................... Table 89: Parameters used for allocation of fixed costs ............................................................................................... Table 90: Voltage Wise Cost of Supply (VCoS) ............................................................................................................. Table 91: Cross-Subsidy Surcharge approved by Commission (INR/kWh) ............................................................... Table 92: Rapproved determined by Commission for FY 2022-23 ............................................................................. Table 93: Tariff Schedule ...............................................................................................................................................

61 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 7 Electricity Department, Government of Goa Joint Electricity Regulatory Commission (JERC) OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022

Joint Electricity Regulatory Commission (JERC) Table 94: Applicability of Tariff Schedule ..................................................................................................................... Table 95: Applicability of ToD Tariff ............................................................................................................................. Table 96: Schedule of Miscellaneous Charges .............................................................................................................. Table 97: List of participants in Public Hearing ...........................................................................................................

List of abbreviations

Abbreviation Full Form
A&G Administrative and General
ACoS Average Cost of Supply
Act The Electricity Act, 2003
AMR Automatic Meter Reading
APR Annual Performance Review
ARR Aggregate Revenue Requirement
ATE Appellate Tribunal of Electricity
BPL Below Poverty Line
CAGR Compound Annualized Growth rate
Capex Capital Expenditure
CC Current Consumption
CEA Central Electricity Authority
CERC Central Electricity Regulatory Commission
CGRF Consumer Grievance Redressal Forum
CGS Central Generating Stations
COD Commercial Operation Date
Cr Crores
DDUGJY DeenDayalUpadhyaya Gram JyotiYojana
Discom Distribution Company
DSM Deviation Settlement Mechanism
DT Distribution Transformer
ED Electricity Department
EHT Extra High Tension
ERP Enterprise Resource Planning
FPPCA Fuel and Power Purchase Cost Adjustment
FY Financial Year
GFA Gross Fixed Assets
HT High Tension
IEX Indian Energy Exchange Limited
IPDS Integrated Power Development Scheme
IPP Independent Power Producer
ISTS Inter-State Transmission System
JERC Joint Electricity Regulatory Commission for the state of Goa and Union Territories
KSEB Kerala State Electricity Board Limited
LT Low Tension
MCLR Marginal Cost of funds based Lending Rate
MU Million Units
MYT Multi-Year Tariff
NFA Net Fixed Assets
NTI Non-Tariff Income
NTPC NTPC Ltd.
OHOB One Hut One Bulb
O&M Operation and Maintenance
PLF Plant Load Factor
PLR Prime Lending Rate
PSDF Power System Development Fund
PPA Power Purchase Agreement
R&M Repair and Maintenance
R-APDRP Restructured Accelerated Power Development and Reforms Programme
REC Renewable Energy Certificate
RLDC Regional Load Despatch Centre
RoE Return on Equity
RPO Renewable Purchase Obligation
SBI PLR SBI Prime Lending Rate
SERC State Electricity Regulatory Commission
SLDC State Load Despatch Center
SOP Standard of Performance
T&D Transmission & Distribution
TVS Technical Validation Session
UI Unscheduled Interchange
UT Union Territory
Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 9 Electricity Department, Government of Goa 62 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 8 Electricity Department, Government of Goa Joint Electricity Regulatory Commission (JERC) OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022 63 OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022

Before the

Joint Electricity Regulatory Commission

For the State of Goa and Union Territories, Gurugram

QUORUM

Ms.Jyoti Prasad, Member

Petition No. 63/2021

In the matter of

Approval of Aggregate Revenue Requirements (ARR) for 3rd MYT Control Period from FY 2022-23 to FY 2024- 25 and Determination of Retail Tariff for FY 2022-23.

And in the matter of

Electricity Department, Government of Goa (ED-Goa) (cid:171)(cid:171)(cid:171)(cid:171)(cid:171)(cid:17)(cid:171)(cid:171)(cid:171)(cid:171)(cid:171)(cid:171)(cid:171)(cid:171)(cid:171)(cid:171)(cid:171)(cid:171)(cid:171)(cid:17)(cid:17)Petitioner

ORDER

Dated:31stMarch2022

1) This Order is passed in respect of the Petition filed by the Electricity Department, Government of Goa (ED-Goa)(cid:11)(cid:75)(cid:72)(cid:85)(cid:72)(cid:76)(cid:81)(cid:3)(cid:68)(cid:73)(cid:87)(cid:72)(cid:85)(cid:3)(cid:85)(cid:72)(cid:73)(cid:72)(cid:85)(cid:85)(cid:72)(cid:71)(cid:3)(cid:87)(cid:82)(cid:3)(cid:68)(cid:86)(cid:3)(cid:179)(cid:55)(cid:75)(cid:72)(cid:3)(cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:180)(cid:3)(cid:82)(cid:85)(cid:3)(cid:179)ED-Goa(cid:180)(cid:3)(cid:82)(cid:85)(cid:3)(cid:179)(cid:55)(cid:75)(cid:72)(cid:3)(cid:47)(cid:76)(cid:70)(cid:72)(cid:81)(cid:86)(cid:72)(cid:72)(cid:180)(cid:12)(cid:3)for Approval of Annual Performance Review for FY 2021-22 and Aggregate Revenue Requirement (ARR) for 3rd MYTControl Period and determination of Retail Tariff for the FY 2022-23before the Joint Electricity Regulatory Commission (herein (cid:68)(cid:73)(cid:87)(cid:72)(cid:85)(cid:3)(cid:85)(cid:72)(cid:73)(cid:72)(cid:85)(cid:85)(cid:72)(cid:71)(cid:3)(cid:87)(cid:82)(cid:3)(cid:68)(cid:86)(cid:3)(cid:179)(cid:55)(cid:75)(cid:72)(cid:3)(cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:180)(cid:3)(cid:82)(cid:85)(cid:3)(cid:179)(cid:45)(cid:40)(cid:53)(cid:38)(cid:180)(cid:12).

2) The Commission scrutinised the said Petition and generally found it in order. The Commission admitted the Petition on 30thDecember 2021. The Commission thereafter requisitioned further information/ clarifications on the data gaps observed to take a prudent view of the said Petition. The Commission also held a Technical Validation Session to determine sufficiency of data and the veracity of the information submitted.Further, due to the COVID-19 pandemic that had adversely impacted the movement of people as per the guidelines of GoI which had suggested avoiding of travel and gathering of people as far as possible, the Commission had decided to conduct the Public Hearing virtually. The virtual Public Hearing was held on 24thJanuary 2022, and all the Stakeholders/Electricity Consumers present in the Public Hearing were heard.Further, suggestions/ comments/ views and objections were invited from the Stakeholders and Electricity Consumers.

3) (cid:55)(cid:75)(cid:72)(cid:3) (cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:3) (cid:69)(cid:68)(cid:86)(cid:72)(cid:71)(cid:3) (cid:82)(cid:81)(cid:3) (cid:87)(cid:75)(cid:72)(cid:3) (cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3) (cid:86)(cid:88)(cid:69)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:15)(cid:3) (cid:85)(cid:72)(cid:79)(cid:72)(cid:89)(cid:68)(cid:81)(cid:87)(cid:3) JERC MYT Regulations, facts of the matter, rules and provisions of the Electricity Act, 2003 and after proper due diligenceand prudence check, has approved theAggregate Revenue Requirement (ARR) for 3rd MYTControl Period and determination of Retail Tariff for the FY 2022-23.

4) A Summary has been provided as follows:

(a) The following table provides ARR, Revenue and Standalone Gap/ (Surplus) at existing tariff as submitted by the Petitioner and approved by the Commission for the FY 2022-23:

64 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 11 Electricity Department, Government of Goa Joint Electricity Regulatory Commission (JERC) OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022
S. No. Particulars Petitioner¶s Submission Approved by Commission
1 Net Revenue Requirement 2,361.15 2,408.15
2 Revenue from Retail Sales at Existing Tariff 2,109.47 1,992.53
Net Revenue Gap/ (Surplus) 251.69 415.62

(b) The following table provides ARR, Revenue and Standalone Gap/ (Surplus) at approved tariff as approved by the Commission for the FY 2022-23:

Table 2: Standalone Revenue Gap/ (Surplus) at proposed/approved tariff for the FY 2022-23

(INR Cr.)

S. No. Particulars Petitioner¶s Submission Approved by Commission
1 Net Revenue Requirement 2,361.15 2,408.15
2 Revenue from Retail Sales at Approved Tariff 2001.02 2,024.02
3 Gap / (Surplus) for the year 360.13 384.13
4 Upfront assurance of Budgetary support from Govt. 360.13 384.13
Net Revenue Gap/ (Surplus) 0.00 0.00

(c) The Petitioner has proposed a reduction in average tariff rate thereby estimating a reduction of INR 108.44 Cr. from the projected revenue in FY 2022-23.

(d) The Commission has approved an average tariff hike of 1.58% to further reduce the reliance of the Petitioner on budgetary support from the Govt. of Goa. The Commission has also introduced fixed charges based on connected load for all Domestic and Commercial slabs.The Commission has approved the Average Billing Rate (ABR) of INR 4.77/kWh against the approved Average Cost of Supply (ACoS) of INR 5.68/kWh. The entire revenue gap shall be met through the budgetary support as per assurance letter of the Govt. of Goa dated 29th December 2021. The Commission acknowledges this letter of assurance from the Government of Goa towards meeting any prospective revenue gap for FY 2022-23, and hence the revenue gap for FY 2022-23 has been considered as nil.

(e) The Commission has increased the tariff levels for cross-subsidized categories by higher than the average hike and has reduced/maintained the tariff levels at lower than average tariff hike for cross-subsidizing categories.

(f) The ABR without the Government Budgetary support has been calculated considering the per unit gap of INR 0.91/kWh (difference between ACoS and ABR at Approved Tariff with Govt. Budgetary Support). However, the Commission would like to highlight that in case this gap had to be entirely fulfilled by revenue from consumers then it would have demanded an additional average tariff increase of 18.98%.

5) This Order shall come into force with effect from 1st April 2022 and shall, unless amended or revoked, continue to be in force till further orders of the Commission.

6) The licensee shall publish the Tariff Schedule and salient features of Tariff as determined by the Commission in this Order within one week of receipt of the Order in three daily newspapers in the respective local languages of the region, besides English, having wide circulation in their respective areas of supply and also upload the Tariff Order on its website.

65 Joint Electricity Regulatory Commission (JERC) OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022

7) Ordered accordingly, the attached documents giving detailed reasons, grounds and conditions are the Integral part of this Order.

(Jyoti Prasad)

Member

Place: Gurugram

Date: 31stMarch2022

Certified Copy

(Rakesh Kumar)

Secretary, JERC

66 OFFICIAL GAZETTE — GOVT. OF GOA Introduction Joint Electricity Regulatory Commission (JERC) SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022

1. Chapter 1: Introduction

1.1. About Joint Electricity Regulatory Commission for the State of

(cid:42)(cid:82)(cid:68)(cid:3)(cid:68)(cid:81)(cid:71)(cid:3)(cid:56)(cid:55)(cid:182)(cid:86)(cid:3)(cid:11)(cid:45)(cid:40)(cid:53)(cid:38)(cid:12)

In exercise of powers conferred by the Electricity Act 2003, the Central Government constituted the Joint (cid:40)(cid:79)(cid:72)(cid:70)(cid:87)(cid:85)(cid:76)(cid:70)(cid:76)(cid:87)(cid:92)(cid:3)(cid:53)(cid:72)(cid:74)(cid:88)(cid:79)(cid:68)(cid:87)(cid:82)(cid:85)(cid:92)(cid:3)(cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:3)(cid:73)(cid:82)(cid:85)(cid:3)(cid:68)(cid:79)(cid:79)(cid:3)(cid:87)(cid:75)(cid:72)(cid:3)(cid:56)(cid:81)(cid:76)(cid:82)(cid:81)(cid:3)(cid:55)(cid:72)(cid:85)(cid:85)(cid:76)(cid:87)(cid:82)(cid:85)(cid:76)(cid:72)(cid:86)(cid:3)(cid:72)(cid:91)(cid:70)(cid:72)(cid:83)(cid:87)(cid:3)(cid:39)(cid:72)(cid:79)(cid:75)(cid:76)(cid:3)(cid:87)(cid:82)(cid:3)(cid:69)(cid:72)(cid:3)(cid:78)(cid:81)(cid:82)(cid:90)(cid:81)(cid:3)(cid:68)(cid:86)(cid:3)(cid:179)(cid:45)(cid:82)(cid:76)(cid:81)(cid:87)(cid:3)(cid:40)(cid:79)(cid:72)(cid:70)(cid:87)(cid:85)(cid:76)(cid:70)(cid:76)(cid:87)(cid:92)(cid:3) (cid:53)(cid:72)(cid:74)(cid:88)(cid:79)(cid:68)(cid:87)(cid:82)(cid:85)(cid:92)(cid:3)(cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:3)(cid:73)(cid:82)(cid:85)(cid:3)(cid:87)(cid:75)(cid:72)(cid:3)(cid:56)(cid:81)(cid:76)(cid:82)(cid:81)(cid:3)(cid:55)(cid:72)(cid:85)(cid:85)(cid:76)(cid:87)(cid:82)(cid:85)(cid:76)(cid:72)(cid:86)(cid:180)(cid:3)(cid:89)(cid:76)(cid:71)(cid:72)(cid:3)(cid:81)(cid:82)(cid:87)(cid:76)(cid:73)(cid:76)(cid:70)(cid:68)(cid:87)(cid:76)(cid:82)(cid:81)(cid:3)(cid:81)(cid:82)(cid:17)(cid:3)(cid:21)(cid:22)(cid:18)(cid:24)(cid:21)(cid:18)(cid:21)(cid:19)(cid:19)(cid:22)-R&R dated 2ndMay 2005. Later with the joining of the Sta(cid:87)(cid:72)(cid:3)(cid:82)(cid:73)(cid:3)(cid:42)(cid:82)(cid:68)(cid:15)(cid:3)(cid:87)(cid:75)(cid:72)(cid:3)(cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:3)(cid:70)(cid:68)(cid:80)(cid:72)(cid:3)(cid:87)(cid:82)(cid:3)(cid:69)(cid:72)(cid:3)(cid:78)(cid:81)(cid:82)(cid:90)(cid:81)(cid:3)(cid:68)(cid:86)(cid:3)(cid:179)(cid:45)(cid:82)(cid:76)(cid:81)(cid:87)(cid:3)(cid:40)(cid:79)(cid:72)(cid:70)(cid:87)(cid:85)(cid:76)(cid:70)(cid:76)(cid:87)(cid:92)(cid:3)(cid:53)(cid:72)(cid:74)(cid:88)(cid:79)(cid:68)(cid:87)(cid:82)(cid:85)(cid:92)(cid:3) (cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:3) (cid:73)(cid:82)(cid:85)(cid:3) (cid:87)(cid:75)(cid:72)(cid:3) (cid:54)(cid:87)(cid:68)(cid:87)(cid:72)(cid:3) (cid:82)(cid:73)(cid:3) (cid:42)(cid:82)(cid:68)(cid:3) (cid:68)(cid:81)(cid:71)(cid:3) (cid:56)(cid:81)(cid:76)(cid:82)(cid:81)(cid:3) (cid:55)(cid:72)(cid:85)(cid:85)(cid:76)(cid:87)(cid:82)(cid:85)(cid:76)(cid:72)(cid:86)(cid:180)(cid:3) (cid:11)(cid:75)(cid:72)(cid:85)(cid:72)(cid:76)(cid:81)(cid:68)(cid:73)(cid:87)(cid:72)(cid:85)(cid:3) (cid:85)(cid:72)(cid:73)(cid:72)(cid:85)(cid:85)(cid:72)(cid:71)(cid:3) (cid:87)(cid:82)(cid:3) (cid:68)(cid:86)(cid:3) (cid:179)(cid:45)(cid:40)(cid:53)(cid:38)(cid:180)(cid:3) (cid:82)(cid:85)(cid:3) (cid:179)(cid:87)(cid:75)(cid:72)(cid:3) (cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:180)(cid:12)(cid:3)(cid:89)(cid:76)(cid:71)(cid:72)(cid:3)(cid:81)(cid:82)(cid:87)(cid:76)(cid:73)(cid:76)(cid:70)(cid:68)(cid:87)(cid:76)(cid:82)(cid:81)(cid:3)(cid:81)(cid:82)(cid:17)(cid:3)(cid:21)(cid:22)(cid:18)(cid:24)(cid:21)(cid:18)(cid:21)(cid:19)(cid:19)(cid:22)-R&R (Vol. II) dated 30thMay 2008.

JERC is a statutorybody responsible for regulation of the Power Sector in the State of Goa and Union Territories of Andaman & Nicobar Islands, Lakshadweep, Chandigarh, Daman & Diu, Dadra & Nagar Haveli and Puducherry, consisting of generation, transmission, distribution, trading and use of electricity etc. Its primary objective includes taking measures conducive to the development of the electricity industry, promoting competition therein, protecting the interests of consumers and ensuring supply of electricity to all areas.

1.2. About Goa

Goa is a state on the southwestern coast of India within the

region known as the Konkan, and geographically separated

from the Deccan highlands by the Western Ghats. It is

surrounded by the Indian states of Maharashtra to the north

and Karnataka to the east and south, with the Arabian Sea

forming its western coast. It is India's smallest state by area

and the fourth-smallest by population. The state is divided

into two districts: North Goa and South Goa.North Goa is divided into three subdivisions (cid:178) Panaji, Mapusa, and Bicholim and further into five talukas (subdistricts). South Goa is divided into five subdivisions (cid:178) Ponda, Mormugao- Vasco, Margao, Quepem, and Dharbandora and further into

seven talukas(subdistricts).

Goa has the highest GDP per capita among all Indian

states,two and a half times that of the country. The state of

Goa is famous for its excellent beaches, churches, and

temples. Tourism is Goa's primary industry,it gets 12% of

foreign tourist arrivals in India.The state is also rich in

minerals and ores, and mining forms the second largest

industry. Iron, bauxite, manganese, clays, limestone, and silica are mined extensively in Goa.

Goa is often described as a fusion between Eastern and Western culture with Portuguese culture having a dominant position in the state in its architectural, cultural or social settings.

1.3. About Electricity Department, Government of Goa (EDG)

(cid:55)(cid:75)(cid:72)(cid:3)(cid:40)(cid:79)(cid:72)(cid:70)(cid:87)(cid:85)(cid:76)(cid:70)(cid:76)(cid:87)(cid:92)(cid:3)(cid:39)(cid:72)(cid:83)(cid:68)(cid:85)(cid:87)(cid:80)(cid:72)(cid:81)(cid:87)(cid:15)(cid:3)(cid:42)(cid:82)(cid:89)(cid:72)(cid:85)(cid:81)(cid:80)(cid:72)(cid:81)(cid:87)(cid:3)(cid:82)(cid:73)(cid:3)(cid:42)(cid:82)(cid:68)(cid:3)(cid:11)(cid:75)(cid:72)(cid:85)(cid:72)(cid:76)(cid:81)(cid:68)(cid:73)(cid:87)(cid:72)(cid:85)(cid:3)(cid:85)(cid:72)(cid:73)(cid:72)(cid:85)(cid:85)(cid:72)(cid:71)(cid:3)(cid:87)(cid:82)(cid:3)(cid:68)(cid:86)(cid:3)(cid:179)(cid:40)(cid:39)-(cid:42)(cid:82)(cid:68)(cid:180)(cid:3)(cid:82)(cid:85)(cid:3)(cid:179)(cid:40)(cid:39)(cid:42)(cid:180) (cid:82)(cid:85)(cid:3)(cid:181)(cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:182)) is a deemed Distribution Licensee within the meaning of Section 2 (17) of Electricity Act 2003 and pursuant to the Section 14 of the Electricity Act. Further, Section 42 and 43 of the Electricity Act 2003 prescribes the following duties of the deemed Distribution Licensee:

67 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 14 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA Introduction Joint Electricity Regulatory Commission (JERC) SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022

(cid:120) To develop and maintain an efficient, coordinated and economical distribution system;

(cid:120) To supply electricity on an application by any person, in accordance with the provisions specified in the Electricity Act 2003;

(cid:120) To provide non-discriminatory open access to the consumers;

(cid:120) To establish a forum for redressal of grievances of the consumers.

The primary objective of EDG is to undertake the transmission, distribution and retail supply of electricity in its license area and for this purpose plan, construct, and manage the power system network in all its aspects. EDG is further responsible for carrying out the business of purchasing and selling of electricity along with activities such as billing and collection in the area.

1.4. Multi Year Tariff Regulations, 2021

The Commission notified the Joint Electricity Regulatory Commission for the State of Goa and Union Territories (Generation, Transmission and Distribution Multi Year Tariff) Regulations, 2021(hereinafter referred to as MYT Regulations, 2021) on 22thMarch 2021. These Regulations are applicable in the 3rdMYT Control Period comprising of three financial years from FY 2022- 23 to FY 2024-25. These Regulations are applicable to all the generation companies, transmission and distribution licensees in the State of Goa and Union Territories of Andaman & Nicobar Islands, Lakshadweep, Chandigarh, Daman & Diu, Dadra & Nagar Haveli and Puducherry.

1.5. Filing and Admission of the Present Petition

The present Petition was admitted on 30th December 2021 and marked as Petition No. 63 of 2021.The Commission and the Petitioner subsequently uploaded the Petition on their respective websites.

1.6. Interaction with the Petitioner

A preliminary scrutiny/analysis of the Petition was conducted, and certain deficiencies were observed.

Accordingly, discrepancy notes were issued to the Petitioner. Further, additional information/clarifications were solicited from the Petitioner as and when required. The Commission and the Petitioner also discussed various concerns of the Petitioner and key data gaps, which included retail sales, revenue from retail tariff, capitalization, tariff proposal etc. The Petitioner submitted its response to the issues through various letters/emails.

(cid:55)(cid:75)(cid:72)(cid:3) (cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:3) (cid:70)(cid:82)(cid:81)(cid:71)(cid:88)(cid:70)(cid:87)(cid:72)(cid:71)(cid:3) (cid:87)(cid:75)(cid:72)(cid:3) (cid:55)(cid:72)(cid:70)(cid:75)(cid:81)(cid:76)(cid:70)(cid:68)(cid:79)(cid:3) (cid:57)(cid:68)(cid:79)(cid:76)(cid:71)(cid:68)(cid:87)(cid:76)(cid:82)(cid:81)(cid:3) (cid:54)(cid:72)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:3) (cid:11)(cid:55)(cid:57)(cid:54)(cid:12)(cid:3) (cid:90)(cid:76)(cid:87)(cid:75)(cid:3) (cid:87)(cid:75)(cid:72)(cid:3) (cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:3) (cid:68)(cid:87)(cid:3) (cid:87)(cid:75)(cid:72)(cid:3) (cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:182)(cid:86)(cid:3) office in Gurugram, during which the discrepancies in the Petition were conveyed and additional information required by the Commission was sought. Subsequently, the Petitioner submitted replies to the issues raised in this session and provided documentary evidence to substantiate its claims regarding various submissions. The following table provides the list of interactions with the Petitioner along with the dates:

S. No Subject Date
1 Public Hearing 24th January 2022
2 Issue of First Deficiency Note 28th January 2022
3 Reply received from Petitioner 17th February 2022
4 Technical Validation Session 21st February 2022
5 Issue of Second Deficiency Note 22nd February 2022
6 Replies received from Petitioner 28th February 2022 & 4th March 2022
68 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 15 Electricity Department, Government of Goa Introduction Joint Electricity Regulatory Commission (JERC) OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022

1.7. Notice for Public Hearing

Public Notices were published by the Commission in the leading newspapers as tabled below, giving due intimation to the stakeholders, consumers and the public at large about the Public Hearing to be conducted by the Commission. These notices were also (cid:88)(cid:83)(cid:79)(cid:82)(cid:68)(cid:71)(cid:72)(cid:71)(cid:3)(cid:82)(cid:81)(cid:3)(cid:87)(cid:75)(cid:72)(cid:3)(cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:182)(cid:86)(cid:3)(cid:90)(cid:72)(cid:69)(cid:86)(cid:76)(cid:87)(cid:72)

Table 4: Details of Public Notices published by the Commission

Sl. No. Date Name of Newspaper Language Place of Circulation
1 1stJanuary 2022 &22nd January 2022 Gomantak Konkani Goa
2 The Times of India English Goa
3 The Navhind times English Goa
4 oHeraldo English Goa

The Public Notice was published by the Petitioner in the following newspapers for inviting objections/ suggestionsfrom the stakeholders on the Tariff Petition:

Table 5: Details of Public Notices published by the Petitioner

S. No. Date Name of Newspaper Language Place of Circulation
1. 15th January 2022 The Navhind times English Goa
2. The Times of India English Goa
3. Gomantak Marathi Goa
4. BhaangarBhuin Konkani Goa

1.8. Public Hearing

The COVID-19 pandemic had adversely impacted the movement of people. The guidelines of GoI had accordingly suggested avoiding of travel and gathering of people as far as possible. In view of above, the physical conduct of proceedings by the Commission was not possible. So, the Commission deemed it is necessary to provide an access to all the stakeholders by conducting proceedings remotely, by the use of audio and video enabled hearings in the matters of Petition submitted by Electricity Department, Goa. Therefore, the Commission has decided that the comments/suggestions of the stakeholders need to be heard virtually through video conferencing for seeking their opinion.

Accordingly, the Virtual Public Hearing was held on 24th January 2022 to discuss the issues, if any, related to the Petition filed by the Petitioner. The issues and concerns raised by the stakeholders in writing and as voiced by them during the Public Hearing have been examined by the Commission. The names of the stakeholders who attended the Public Hearing are provided in Annexure-I. The major issues discussed, the responses of the Petitioner thereon and the views of the Commission have been summarized in Chapter 2 of this Order.

69 OFFICIAL GAZETTE — GOVT. OF GOA Stakeholder Comments Joint Electricity Regulatory Commission (JERC) SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022

2. Chapter 2: Summary of

Suggestions/Objections received,

Response from the Petitioner and the

(cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:182)(cid:86)(cid:3)(cid:57)(cid:76)(cid:72)(cid:90)(cid:86)

2.1. Regulatory Process

On admitting the Petition, the Commission directed the Petitioner to make copies of the Petition available to the public, upload the Petition on the website and also publish the same in the newspapers in an abridged form in the given format duly inviting comments/objections from the public as per the provisions of the MYT Regulations, 2021.

The COVID-19 pandemic has adversely impacted the movement of people as per the guidelines of GoI. These guidelines have also suggested avoiding of travel and gathering of people as far as possible. In view of the above, the physical conduct of proceedings by the Commission was not possible. So, The Commission deemed it is necessary to provide an access to all the stakeholders by conducting proceedings remotely, by the use of audio and video enabled hearings in the matters of Petition submitted by the Petitioner. Therefore, the Commission decided that the comments/suggestions of the stakeholders need to be heard virtually through video conferencing for seeking their opinion.

Accordingly, the Virtual Public Hearing was held on 24th January 2022 to discuss the issues, if any, related to the Petition filed by the Petitioner. The issues and concerns raised by the stakeholders in writing and as voiced by them during the Public Hearing have been examined by the Commission. The names of the stakeholders who attended the Public Hearing are provided in Annexure-I.

2.2. Suggestions/ Objections, Response of the Petitioner and

(cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:182)(cid:86)(cid:3)(cid:57)(cid:76)(cid:72)(cid:90)(cid:86)

The Commission is appreciative of the efforts of various stakeholders in providing their suggestions/comments/ observations to make the process responsive and efficient. The relevant observations of the stakeholders have been suitably considered by the Commission while finalizing this Tariff Order. The submissions of the stakeholders, response of the Petitioner and views of the Commission are summarized below:

2.2.1. Delayed response post CycloneTauktae in Raia Village

(cid:54)(cid:87)(cid:68)(cid:78)(cid:72)(cid:75)(cid:82)(cid:79)(cid:71)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:38)(cid:82)(cid:80)(cid:80)(cid:72)(cid:81)(cid:87)(cid:29)

The Cyclone hit Goa on May 15, 2021 and parts of Raia Village were affected and were in dark for 3-4 days.

Heavy infrastructure damage like falling of huge trees, electricity poles and lines has occurred, and several roads were blocked. The Village Panchayat of Raia acted swiftly and cleared the roads by 10.00 am on the same day. However, there was no JE or any staff at the Electrical Sub-Station for people of Raia to interact with the consumers.

The JE arrived the next day (Monday) at 10.00 am and again was not available in the office to guide the public on Damage Assessment and Restoration Plan. Elderly People, Covid Patients, children, etc were suffering for 3 to 4 days without electricity. After 3 days the power was restored. Still, few of the cracked poles and the sagging electrical live wires are to be repaired.

(cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:53)(cid:72)(cid:86)(cid:83)(cid:82)(cid:81)(cid:86)(cid:72)(cid:29)

70 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 17 Electricity Department, Government of Goa Stakeholder Comments Joint Electricity Regulatory Commission (JERC) OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022

The cyclone "Tauktae" that hit Goa on 16/05/2021 has led to huge damage and destruction to the electrical infrastructure and the power distribution network in the entire state of Goa which affected power supply to more than 70% of the power consumers of the State.

All the Department staff were engaged in the restoration works so as to restore the power supply to the consumers at the earliest. A war room was setup to provide directions and monitor the restoration process.

Prior to the cyclone, large number of local contractors were assigned for restoration works and further, more contractors were airlifted from other states to increase the pace of the work.

The temporary restoration works were completed to the extent of 70% within 48 hours and up to 95% within 72 hours and simultaneously strengthening and permanent infrastructure restoration was continued and completed.

As the entire network of the State of Goa was down due to the hit, all the departmental staffs and contractors worked round the clock to restore the power stage by stage ranging from the upstream level (i.e 33kV) to downstream level (i.e 440 V).

However, the extent of damage caused by cyclone to the Department infrastructure was massive and carrying out restoration works with only Department staff would have delayed restoration works and consequently would have delayed power supply to consumers across the State especially in remote parts. On instructions of the Minister of Power, it was therefore decided to engage the services of external contractors to carry out power restoration works. Thus, external contractors from Goa and other states were requisitioned immediately to assist the Departmental staff in the restoration works.

In view of above, allegations made by Mr. Martin Rodrigues are denied by ED Goa. It is submitted that ED-Goa is fully committed to provide timely and satisfactory services to its consumers and is striving hard to achieve.

(cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:182)(cid:86)(cid:3)(cid:57)(cid:76)(cid:72)(cid:90)(cid:29)

The stakeholder may note the response of the Petitioner. Further, the Commission directs the Petitioner to maintain the quality and reliability of supply as per the JERC Supply Code Regulations, 2018 and JERC Standards of Supply Regulations, 2015.

2.2.2. Problem of live sagging wire and cracked pole

(cid:54)(cid:87)(cid:68)(cid:78)(cid:72)(cid:75)(cid:82)(cid:79)(cid:71)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:38)(cid:82)(cid:80)(cid:80)(cid:72)(cid:81)(cid:87)(cid:29)

The sagging live wires are between Pole no. CLR/F1/2 and the other pole towards its south (there is no number on this pole) with the distance between the poles is about. 60.00ms.The cracked pole and the sagging live wires pose danger to human lives any moment and the same is persisting for 8 months. Kindly, resolve this problem on urgent basis.

(cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:53)(cid:72)(cid:86)(cid:83)(cid:82)(cid:81)(cid:86)(cid:72)(cid:29)

ED-Goa has resolved the grievance of Mr. Martin Rodrigues raised in the Public Hearing. The cracked poles have been replaced and sagging line has been tightened. The span length between pole No. CLR/F1/2 and other poles was measured and found to be 48 m instead of 60 m as claimed by the party. However, the existing LT line was strung along an old HT pole which was present along the existing line after completing fit up of 2 pin and 4 pin cross arms and the line span is now divided into 18 m on one side and 30 m on the other.

(cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:182)(cid:86)(cid:3)(cid:57)(cid:76)(cid:72)(cid:90)(cid:29)

71 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 18 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA Stakeholder Comments Joint Electricity Regulatory Commission (JERC) SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022

The stakeholder may note the response of the Petitioner. Further, the Commission directs the Petitioner to maintain the quality and reliability of supply as per the Electricity act,2003 and Regulations made thereunder.

2.2.3. Computation of Cross Subsidy Surcharge (CSS)

(cid:54)(cid:87)(cid:68)(cid:78)(cid:72)(cid:75)(cid:82)(cid:79)(cid:71)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:38)(cid:82)(cid:80)(cid:80)(cid:72)(cid:81)(cid:87)(cid:29)

The IEX has submitted that, it has observed that the Petitioner has proposed a decrease in the energy charge (@30 paise/ unit decrease for the HT industrial category) against the tariff approved for FY 2021-22. However, while computing the CSS, an increase in the Average Billing Rate (ABR) has been considered compared to the ABR approved by the Commission in the Tariff Order for FY 2021-22, which was computed basis the electricity tariff approved for FY 2021-22. The Commission is requested to consider the impact of the proposed decrease in electricity tariff on the computation of ABR while determining the CSS, so that the effect of the proposed tariff rationalization is reflected in CSS also.

(cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:53)(cid:72)(cid:86)(cid:83)(cid:82)(cid:81)(cid:86)(cid:72)(cid:29)

It is submitted that in FY 2021-22, Commission estimated total HT sales of 2178 MUs and revenue of Rs. 1268 Crores arriving of ABR of Rs. 5.82 per kWh. Further, for FY 2022-23 the Petitioner has estimated sales of 2158 MUs based on actual figures of FY 2020-21 and revised projections of FY 2021-22. Further, it is submitted that the impact of kVAh billing for HT/EHT revenue is more than envisaged in FY 2021-22, and the same has been considered in while estimating revenue of FY 2022-23, accordingly revenue for Rs. 1387 MUs has been estimated. Hence, due to increase in revenue estimated and reduction of sales estimated, the ABR of FY 2022- 23 comes to Rs. 6.42 per kWh, compared to approved ABR of FY 2021-22.

(cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:182)(cid:86)(cid:3)(cid:57)(cid:76)(cid:72)(cid:90)(cid:29)

The Commission has determined the CSS for the FY 2022-23 based on the approved ARR. The Commission believes that the tariff should progressively reflect the cost of supply. The Commission while determining the tariff for FY 2022-23 has considered the prudent cost of the Petitioner and has accordingly determined the Open Access charges and tariff for each consumer category. The stakeholder may refer to the relevant Chapter for the detailed rationale.

2.2.4. Consideration of Tariff Policy while Computing Cross Subsidy

Surcharge (CSS)

(cid:54)(cid:87)(cid:68)(cid:78)(cid:72)(cid:75)(cid:82)(cid:79)(cid:71)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:38)(cid:82)(cid:80)(cid:80)(cid:72)(cid:81)(cid:87)(cid:29)

The Petitioner has not considered the proviso mentioned in the Tariff Policy to restrict the CSS to 20% of ABR in the Tariff Petitions. Such omission will restrict the ability of open access consumers to avail power to optimise their cost of power purchase

(cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:53)(cid:72)(cid:86)(cid:83)(cid:82)(cid:81)(cid:86)(cid:72)(cid:29)

ED-Goa submits that as per the provision of Section 42 (2) of the Electricity Act 2003, the cross-subsidy surcharge needs to be based on the current level of cross subsidy. Accordingly, the consumers who opted for Open Access need to be charged for the compensation of current level of cross subsidy which prevailed during that period and in order to avoid the burden of the same getting passed on to the other consumers who are with the Distribution Licensee. However, The Tariff Policy 2016 restricts Cross Subsidy Surcharge at 20% of the consumer tariff, this will result in lower CSS applicable than current level of cross subsidy leading to incomplete recovery of Cross Subsidy from Open Access consumers. In this process, Open Access consumers unduly get72 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 19 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA Stakeholder Comments Joint Electricity Regulatory Commission (JERC) SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022 benefited due to less cross subsidy surcharge and Industrial and commercial consumers who are subsidizing consumers, the more impact gets loaded onto the Industrial and commercial category, raising its tariff further.

Further, there is no such provision provided in JERC MYT Regulations or Open Access Regulations, therefore, in order to avoid burden on other consumers of ED-Goa, it has requested to the Commission to consider the current level of cross subsidy surcharge without any ceiling.

(cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:182)(cid:86)(cid:3)(cid:57)(cid:76)(cid:72)(cid:90)(cid:29)

The Commission has determined the CSS for the FY 2022-23 based on the approved ARR. The Commission while determining the tariff for FY 2022-23 has considered the prudent cost of the Petitioner and has accordingly determined the Open Access charges and tariff for each consumer category. The stakeholder may refer to the relevant Chapter for the detailed rationale.

2.2.5. Additional Surcharge on stranded power due to Open Access

(cid:54)(cid:87)(cid:68)(cid:78)(cid:72)(cid:75)(cid:82)(cid:79)(cid:71)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:38)(cid:82)(cid:80)(cid:80)(cid:72)(cid:81)(cid:87)(cid:29)

The Commission is requested to allow Additional Surcharge on stranded power due to Open Access, only when the same is demonstrated through data.

(cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:53)(cid:72)(cid:86)(cid:83)(cid:82)(cid:81)(cid:86)(cid:72)(cid:29)

ED-Goa submits that there are no such Open Access Consumers in the State of Goa and the same cannot be demonstrated with data.

(cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:182)(cid:86)(cid:3)(cid:57)(cid:76)(cid:72)(cid:90)(cid:29)

The suggestion of the Stakeholder is noted. The Petitioner is directed to submit a report on the quarterly details of power stranded for the last 3 years along with the Petition of Tariff Determination for FY 2023-24.

2.2.6. Computation of Additional Surcharge

(cid:54)(cid:87)(cid:68)(cid:78)(cid:72)(cid:75)(cid:82)(cid:79)(cid:71)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:38)(cid:82)(cid:80)(cid:80)(cid:72)(cid:81)(cid:87)(cid:29)

It is requested that the Commission may propose a scientific methodology for additional surcharge (eg: Gujarat, Telangana, etc.) which is also aligned with the Tariff Policy. The basic premise ought to be conclusive demonstration of stranded capacity on account of open access. In the absence of any open access, the question of stranded capacity on its account does not arise.

(cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:53)(cid:72)(cid:86)(cid:83)(cid:82)(cid:81)(cid:86)(cid:72)(cid:29)

ED-Goa submits that it shall be following any such methodology as approved by the Commission.

(cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:182)(cid:86)(cid:3)(cid:57)(cid:76)(cid:72)(cid:90)(cid:29)

The Additional Surcharge is determined in line with the Tariff Policy and the JERC MYT Tariff Regulations, 2021.

2.2.7. Fulfilment of RPO Obligations through IEX products

(cid:54)(cid:87)(cid:68)(cid:78)(cid:72)(cid:75)(cid:82)(cid:79)(cid:71)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:38)(cid:82)(cid:80)(cid:80)(cid:72)(cid:81)(cid:87)(cid:29)

IEX submitted that the Commission and the Petitioner may consider option to fulfil their RPO obligations by procuring RE power from short term market through Green-DAM and Green-TAM products available at IEX platform while assessing the power purchase of Discoms.

73 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 20 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA Stakeholder Comments Joint Electricity Regulatory Commission (JERC) SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022

(cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:53)(cid:72)(cid:86)(cid:83)(cid:82)(cid:81)(cid:86)(cid:72)(cid:29)

The ED-Goa submits that it has taken a note of the suggestion of IEX and EDG is aware of the facilities available at IEX. The SLDC-Goa will take a call on real time basis as and when required. However, the quantum available at GTAM is very less and unpredictable and therefore we cannot rely fully on GTAM to optimise the cost of supply as per our requirement.

(cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:182)(cid:86)(cid:3)(cid:57)(cid:76)(cid:72)(cid:90)(cid:29)

(cid:55)(cid:75)(cid:72)(cid:3)(cid:86)(cid:87)(cid:68)(cid:78)(cid:72)(cid:75)(cid:82)(cid:79)(cid:71)(cid:72)(cid:85)(cid:3)(cid:80)(cid:68)(cid:92)(cid:3)(cid:81)(cid:82)(cid:87)(cid:72)(cid:3)(cid:87)(cid:75)(cid:72)(cid:3)(cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:53)(cid:72)(cid:86)(cid:83)(cid:82)(cid:81)(cid:86)(cid:72)(cid:17)(cid:3) The Commission further observes that the Petitioner has proposed to procure power from the Renewable Sources to meet its RPO obligations.

2.2.8. Tariff Shock due to high revenue gap

(cid:54)(cid:87)(cid:68)(cid:78)(cid:72)(cid:75)(cid:82)(cid:79)(cid:71)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:38)(cid:82)(cid:80)(cid:80)(cid:72)(cid:81)(cid:87)(cid:29)

GCCI has mentioned in the FY 2024-25, the revenue gap (based on commercial accounting) is expected to be Rs.651 Crores (24% of ARR) which may lead to tariff Shock.

(cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:53)(cid:72)(cid:86)(cid:83)(cid:82)(cid:81)(cid:86)(cid:72)(cid:29)

ED-Goa submits that, as per the JERC MYT Regulations the ARR for the MYT Control Period FY 2022-23 to FY 2024-25 are projected. As per prevailing scenario, the projections were carried out for FY 2024-25, which may show the Revenue Gap of Rs.651 Cr. w.r.t revenue computed at the tariff proposed for FY 2022-23. However, (cid:87)(cid:75)(cid:72)(cid:3)(cid:86)(cid:68)(cid:80)(cid:72)(cid:3)(cid:76)(cid:86)(cid:3)(cid:86)(cid:88)(cid:69)(cid:77)(cid:72)(cid:70)(cid:87)(cid:72)(cid:71)(cid:3)(cid:87)(cid:82)(cid:3)(cid:69)(cid:72)(cid:3)(cid:85)(cid:72)(cid:89)(cid:76)(cid:86)(cid:72)(cid:71)(cid:3)(cid:76)(cid:81)(cid:3)(cid:87)(cid:75)(cid:72)(cid:3)(cid:85)(cid:72)(cid:86)(cid:83)(cid:72)(cid:70)(cid:87)(cid:76)(cid:89)(cid:72)(cid:3)(cid:92)(cid:72)(cid:68)(cid:85)(cid:182)(cid:86)(cid:3)(cid:36)(cid:53)(cid:53).

(cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:182)(cid:86)(cid:3)(cid:57)(cid:76)(cid:72)(cid:90)(cid:29)

The Commission has determined the Revenue gap for the FY 2022-23 based on the approved ARR. The Commission while determining the tariff for FY 2022-23 has considered the prudent cost of the Petitioner and has accordingly determined the tariff for each consumer category. The stakeholder may refer to the relevant Chapter for the detailed rationale.

2.2.9. High rate of return on equity

(cid:54)(cid:87)(cid:68)(cid:78)(cid:72)(cid:75)(cid:82)(cid:79)(cid:71)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:38)(cid:82)(cid:80)(cid:80)(cid:72)(cid:81)(cid:87)(cid:29)

GCCI has submitted that Return on equity is considered as 16% (Table 5.22). Norm for ROE was fixed in the earlier year of 2000, based on bank lending rate +3%. Currently, lending rate is less than 9% and hence ROE may be calculated at 11% or 12%. For a risk-free business with captive consumers, ROE of 11% is a reasonable return. Commission is requested to revise the same.

(cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:53)(cid:72)(cid:86)(cid:83)(cid:82)(cid:81)(cid:86)(cid:72)(cid:29)

EDG has considered Return on Equity is 16% per cent per annum as per the Regulations 28 of JERC MYT Regulations for MYT Control Period FY 2022-23 to FY 2024-25.

Quote

(cid:179)(cid:55)(cid:75)(cid:72)(cid:3) (cid:85)(cid:72)(cid:87)(cid:88)(cid:85)(cid:81)(cid:3) (cid:82)(cid:81)(cid:3) (cid:72)(cid:84)(cid:88)(cid:76)(cid:87)(cid:92)(cid:3) (cid:73)(cid:82)(cid:85)(cid:3) (cid:87)(cid:75)(cid:72)(cid:3) (cid:53)(cid:72)(cid:87)(cid:68)(cid:76)(cid:79)(cid:3) (cid:54)(cid:88)(cid:83)(cid:83)(cid:79)(cid:92)(cid:3) (cid:37)(cid:88)(cid:86)(cid:76)(cid:81)(cid:72)(cid:86)(cid:86)(cid:3) (cid:86)(cid:75)(cid:68)(cid:79)(cid:79)(cid:3) (cid:69)(cid:72)(cid:3) (cid:68)(cid:79)(cid:79)(cid:82)(cid:90)(cid:72)(cid:71)(cid:3) (cid:82)(cid:81)(cid:3) (cid:87)(cid:75)(cid:72)(cid:3) (cid:72)(cid:84)(cid:88)(cid:76)(cid:87)(cid:92)(cid:3) (cid:70)(cid:68)(cid:83)(cid:76)(cid:87)(cid:68)(cid:79)(cid:3) (cid:71)(cid:72)(cid:87)(cid:72)(cid:85)(cid:80)(cid:76)(cid:81)(cid:72)(cid:71)(cid:3) (cid:76)(cid:81)(cid:3)

accordanc(cid:72)(cid:3)(cid:90)(cid:76)(cid:87)(cid:75)(cid:3)(cid:53)(cid:72)(cid:74)(cid:88)(cid:79)(cid:68)(cid:87)(cid:76)(cid:82)(cid:81)(cid:3)(cid:21)(cid:26)(cid:3)(cid:73)(cid:82)(cid:85)(cid:3)(cid:87)(cid:75)(cid:72)(cid:3)(cid:68)(cid:86)(cid:86)(cid:72)(cid:87)(cid:86)(cid:3)(cid:83)(cid:88)(cid:87)(cid:3)(cid:87)(cid:82)(cid:3)(cid:88)(cid:86)(cid:72)(cid:15)(cid:3)(cid:68)(cid:87)(cid:3)(cid:87)(cid:75)(cid:72)(cid:3)(cid:85)(cid:68)(cid:87)(cid:72)(cid:3)(cid:82)(cid:73)(cid:3)(cid:86)(cid:76)(cid:91)(cid:87)(cid:72)(cid:72)(cid:81)(cid:3)(cid:11)(cid:20)(cid:25)(cid:12)(cid:3)(cid:83)(cid:72)(cid:85)(cid:3)(cid:70)(cid:72)(cid:81)(cid:87)(cid:3)(cid:83)(cid:72)(cid:85)(cid:3)(cid:68)(cid:81)(cid:81)(cid:88)(cid:80)(cid:17)(cid:180)(cid:3)

Unquote.

74 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 21 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA Stakeholder Comments Joint Electricity Regulatory Commission (JERC) SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022

(cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:182)(cid:86)(cid:3)(cid:57)(cid:76)(cid:72)(cid:90)(cid:29)

The Commission has considered the rate of return on equity as per JERC MYT Regulations, 2021 for MYT Control Period from FY 2022-23 to FY 2024-25.

2.2.10. Formation of District Committee to help monitor loss reduction

measures

(cid:54)(cid:87)(cid:68)(cid:78)(cid:72)(cid:75)(cid:82)(cid:79)(cid:71)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:38)(cid:82)(cid:80)(cid:80)(cid:72)(cid:81)(cid:87)(cid:29)

GCCI has submitted that the AT&C loss is reported as 11.90% for FY 2021-22. This together with inter-state transmission loss of 3.35%, for WR and 7.95 for SR, total ATC loss works out to be 15.8%. Aggressive loss reduction to 9.85%is essential to avoid tariff shock. The loss reduction measures such as completion of 400 kV interstate line, associated 220 kV system and augmentation of intra state transmission and distribution lines are to be monitored and completed aggressively. Forming district committees as per section 166(5) of IE act 2003 will help in monitoring the same. The Commission is requested to recommend formation of District Committees.

(cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:53)(cid:72)(cid:86)(cid:83)(cid:82)(cid:81)(cid:86)(cid:72)(cid:29)

ED-Goa submits that the Commission may take appropriate decision on this matter. However, it is suggested that since Goa is a small state so formation of one co-ordination committee will be feasible and sufficient for entire state of goa.

(cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:182)(cid:86)(cid:3)(cid:57)(cid:76)(cid:72)(cid:90)(cid:29)

The suggestion of the stakeholder is noted.

2.2.11. Reduction in Electricity Duty

(cid:54)(cid:87)(cid:68)(cid:78)(cid:72)(cid:75)(cid:82)(cid:79)(cid:71)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:38)(cid:82)(cid:80)(cid:80)(cid:72)(cid:81)(cid:87)(cid:29)

The GCCI submitted that ED-Goa creates a fund by levy of Electricity Duty of Rs.0.70 per kWh towards capital expenditure. This amount is not fully utilised in any given year and carried over to the subsequent year.

Presently the kitty has nearly Rs. 1000 Cr.. It is requested that ED-Goa provide for interest on accrued fund and treat it as income. We request JERC to recommend Govt. of Goa to reduce Electricity Duty to Rs. 0.40 per kWh.

(cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:53)(cid:72)(cid:86)(cid:83)(cid:82)(cid:81)(cid:86)(cid:72)(cid:29)

Electricity Duty is basically the State Government tax levied by ED Goa as per Electricity Duty Act 1986. The Government of Goa collects Electricity Duty from all the Consumers of ED-Goa, through the electricity bill of the Consumers. Funds collected are utilised for various schemes for the development of Electrical infrastructure to ensure stability of power, development of project. Since the execution of projects takes time, funds collected during the year cannot be completely utilised in the respective year.

(cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:182)(cid:86)(cid:3)(cid:57)(cid:76)(cid:72)(cid:90)(cid:29)

The levy of Electricity Duty fund comes under the ambit of the Government of Goa. The Commission has no jurisdiction in the matter.

75 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 22 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA Stakeholder Comments Joint Electricity Regulatory Commission (JERC) SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022

2.2.12. kVAh based Tariff for LT consumers

(cid:54)(cid:87)(cid:68)(cid:78)(cid:72)(cid:75)(cid:82)(cid:79)(cid:71)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:38)(cid:82)(cid:80)(cid:80)(cid:72)(cid:81)(cid:87)(cid:29)

GCCI submitted that, in FY 2021-22, ED-Goa adopted kVAh based billing instead of kWh based for HT Consumers. Its impact is nearly 12%. It is said that kVAh billing will be extended to LT consumers. Such a move will adversely impact economy. The tariff will indirectly increase by 10-12% as has happened in the HT Consumers who are in a position to implement corrective measure which may not be viable. We request the JERC to kindly drop any plans to extend the same for LT Consumers.

(cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:53)(cid:72)(cid:86)(cid:83)(cid:82)(cid:81)(cid:86)(cid:72)(cid:29)

ED-Goa has around 1 Lakh LT Commercial Consumers and 5,000 LT Industrial consumers. Some of the meters installed for these consumer categories are capable of recording kWh reading only. KVAh reading for the all the consumers can be obtained once the old meters are replaced with the Smart/ Prepaid meters. Hence at this stage it is not feasible to get ready for implementation of KVAh based tariff for LT Industrial and Commercial categories as it involves replacement of old Meter/high financial investment.

ED-Goa is in the process of installing smart meters and the Proof of Concept (PoC) for the Smart Meter has also been carried out successfully. The kVAh based billing will be carried out for LT Commercial and LT Industrial after installation of the Smart Meters and as per directions of the Commission.

Comm(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:182)(cid:86)(cid:3)(cid:57)(cid:76)(cid:72)(cid:90)(cid:29)

The Commission shall examine the matter of introducing kVAh tariff to LT consumers post installation of the Smart Meters.Appropriate decision shall be taken in line with the provisions of the Electricity Act, 2003, the prevalent Tariff Policy and the prevalent JERC MYT Regulations.

2.2.13. Reduction in delayed payment charges

(cid:54)(cid:87)(cid:68)(cid:78)(cid:72)(cid:75)(cid:82)(cid:79)(cid:71)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:38)(cid:82)(cid:80)(cid:80)(cid:72)(cid:81)(cid:87)(cid:29)

The GCCI submitted that incase the Electricity bills are not paid within the due date mentioned on the bill, delayed payment charges of two percent (2%) (Computed on daily basis on outstanding bill from the due date till date of payment) are levied on the bill amount. ED Goa proposes to continue to levy 2% per month (works out to be 27.1% per annum). Considering the current economic situation & prevailing bank interest rates of 8%,it is submitted to the JERC to reduce it to 0.5% per month cumulative which is below the working capital interest rate.

(cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:53)(cid:72)(cid:86)(cid:83)(cid:82)(cid:81)(cid:86)(cid:72)(cid:29)

ED-Goa submits that it has not proposed any changes in the rate of delayed payment charges in the instant petition. The delayed payment charges of 2% is accordance with the Tariff Order dated 19th May 2020 and as approved by Commission from time to time.

(cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:182)(cid:86)(cid:3)(cid:57)(cid:76)(cid:72)(cid:90)(cid:29)

The Commission has considered the suggestion and accordingly has reduced the late payment surcharge to 1.5% per month.

2.2.14. Tariff on Street lighting within a compound

(cid:54)(cid:87)(cid:68)(cid:78)(cid:72)(cid:75)(cid:82)(cid:79)(cid:71)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:38)(cid:82)(cid:80)(cid:80)(cid:72)(cid:81)(cid:87)(cid:29)

76 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 23 Electricity Department, Government of Goa Stakeholder Comments Joint Electricity Regulatory Commission (JERC) OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022

GCCI submitted that the Street lighting within a compound (residential complex, commercial complex etc) to be charged at residential, commercial, industrial rates etc on the basis of associated activity. Please avoid categorization of Street Lighting charges in residential Complex at Commercial rates.

(cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:53)(cid:72)(cid:86)(cid:83)(cid:82)(cid:81)(cid:86)(cid:72)(cid:29)

The EDG submits that the Street lighting within a compound of residential complex, commercial complex,etc.

are charged at the tariff as per the respective Category on the basis of associated activity only. In this regard, if the Consumer has any grievances, can approach the EDG.

(cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:182)(cid:86)(cid:3)(cid:57)(cid:76)(cid:72)(cid:90)(cid:29)

The stakeholder may (cid:81)(cid:82)(cid:87)(cid:72)(cid:3)(cid:87)(cid:75)(cid:72)(cid:3)(cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:85)(cid:72)(cid:86)(cid:83)(cid:82)(cid:81)(cid:86)(cid:72)(cid:17)

2.2.15. Consideration of Cold storage units as Agriculture allied Industry

(cid:54)(cid:87)(cid:68)(cid:78)(cid:72)(cid:75)(cid:82)(cid:79)(cid:71)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:38)(cid:82)(cid:80)(cid:80)(cid:72)(cid:81)(cid:87)(cid:29)

GCCI submitted that, it appears that cold storage units are purposely targeted at. Cold storage units provide 24 hrs base load with a flat load curve. It helps the utility. Cold Storage prevents wastage, extends shelf life, enhance export market. Cold Storage thus helps the economy. We kindly request that cold storage wherever it is located & used, to be considered as Agriculture allied Industry irrespective of the Sector. In this connection we are enclosing herewith the judgement of Maharashtra State Electricity Distribution Co. (MSEDCL) Consumer Grievance Redressal Forum Case No 05/2017.

(cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:53)(cid:72)(cid:86)(cid:83)(cid:82)(cid:81)(cid:86)(cid:72)(cid:29)

EDG submits that cold storage is billed as per the Rate Schedule and applicable tariff category approved by Commission in Tariff Order.

(cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:182)(cid:86)(cid:3)(cid:57)(cid:76)(cid:72)(cid:90)(cid:29)

The suggestion of the Stakeholder is noted. The Petitioner shall continue to charge the tariff rates as per the Tariff Schedule approved by the Commission.

2.2.16. Reliability linked tariff

(cid:54)(cid:87)(cid:68)(cid:78)(cid:72)(cid:75)(cid:82)(cid:79)(cid:71)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:38)(cid:82)(cid:80)(cid:80)(cid:72)(cid:81)(cid:87)(cid:29)

In general, the business plan is a well written document, without spelling out, area wise growth, reduction in losses and improvement in reliability.

There are initiatives like GIS substation, but it will be effective only if reliability of lines is nearly 100%. Even in Panaji, there are numerous tripping which will harm GIS operation. It is suggested to ED-Goa, to declare reliable distribution areas. A reliability linked tariff will be welcome step since consumers will save on diesel.

(cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:53)(cid:72)(cid:86)(cid:83)(cid:82)(cid:81)(cid:86)(cid:72)(cid:29)

ED, Goa has undertaken numerous initiatives for overall improvement of power system reliability in the state of Goa. This includes commission of new substations, conversion of overhead lines to underground system and conversion of existing conductor to High Amperage conductor. Anumber of new similar projects are also in pipeline and the same has been included in the Business Plan. However, Commission to take a view of tariff.

77 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 24 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA Stakeholder Comments Joint Electricity Regulatory Commission (JERC) SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022

(cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:182)(cid:86)(cid:3)(cid:57)(cid:76)(cid:72)(cid:90)(cid:29)

The suggestion of the Stakeholder is noted.The Commission has determined the tariff for the FY 2022-23 based on the approved ARR and as per the JERC MYT Regulations, 2021.Further, the Commission in the Business Plan Order dated 31st March 2022.has also prescribed targets of reliability indices for the 3rdMYT Control Period.

2.2.17. Pumped Hydro Storage Systems (PHSS)

(cid:54)(cid:87)(cid:68)(cid:78)(cid:72)(cid:75)(cid:82)(cid:79)(cid:71)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:38)(cid:82)(cid:80)(cid:80)(cid:72)(cid:81)(cid:87)(cid:29)

The high peak power due to growth in tourism, will be a huge challenge for peak power procurement. Pumped hydro storage is a green power, matured, cost effective technology for energy storage. PHSS works by storing energy in water in an upper reservoir, pumped from second reservoir at a lower elevation when there is excess power in the system. When there is demand for energy the water in the upper reservoir is released and as it falls it rotates turbines that generate power. A consultant may be appointed to study the possibility of developing pumped hydro storage systems in goa.

(cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:53)(cid:72)(cid:86)(cid:83)(cid:82)(cid:81)(cid:86)(cid:72)(cid:29)

No such initiatives are to be taken in near future by Government of Goa. Further, the Pumped Hydro storage Systems are Capital intensive projects are only used for Supporting the Grid during the Peak power compensation. ED Goa is trying to sign innovative PPAs with additional support during peak hours.

(cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:182)(cid:86)(cid:3)(cid:57)(cid:76)(cid:72)(cid:90)(cid:29)

(cid:55)(cid:75)(cid:72)(cid:3) (cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:3) (cid:80)(cid:68)(cid:92)(cid:3) (cid:81)(cid:82)(cid:87)(cid:72)(cid:3) (cid:87)(cid:75)(cid:72)(cid:3) (cid:54)(cid:87)(cid:68)(cid:78)(cid:72)(cid:75)(cid:82)(cid:79)(cid:71)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3) (cid:70)(cid:82)(cid:80)(cid:80)(cid:72)(cid:81)(cid:87). The Commission directs the Petitioner to explore the feasibility of the proposal suggested by the stakeholder.

2.2.18. Low standards of O&M practices

(cid:54)(cid:87)(cid:68)(cid:78)(cid:72)(cid:75)(cid:82)(cid:79)(cid:71)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:38)(cid:82)(cid:80)(cid:80)(cid:72)(cid:81)(cid:87)(cid:29)

The GCCI has submitted that the maintenance & Construction standards of ED are well below benchmark standards. There is no proper supervision & inspection during erection & thereafter left to the local linesman to do temporary jobs. The quality of the material/equipment also play a major role in the failures. Open distribution boxes, broken hinges, undresses wires, tilted poles, unclean insulators sparking are common occurrences. The ED should have strict material inspection facility & also carryout preventive maintenance on a regular basis. ED is already using SAP. There is a Plant Maintenance (PM) module which can be used. The repair history, material equipment used, causes of failure & remedial action taken can be updated which will help in cutting down failure rates.

(cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:53)(cid:72)(cid:86)(cid:83)(cid:82)(cid:81)(cid:86)(cid:72)(cid:29)

There has been a substantial improvement in regard to the Reliability Indices and the losses in regard to the Distribution Network of ED, Goa. The figures indicate improved O&M practices. The Plant Maintenance Module of SAP is made operational for carrying out periodic O&M works related to feeders and transformers.

Nodal officers at the level of Junior Engineer are appointed for each project and the projects are directly monitored by the Office of the Superintending Engineer of the concerned circles. Quality Inspector is appointed to carry out surprise checks whilst execution of the project. Further, RECPDCL has been appointed as PMC for supervision of major projects carried out by ED, Goa. Their scope includes approving of GTP/drawings, inspection of material and supervision of onsite works.

78 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 25 Electricity Department, Government of Goa Stakeholder Comments Joint Electricity Regulatory Commission (JERC) OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022

(cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:182)(cid:86)(cid:3)(cid:57)(cid:76)(cid:72)(cid:90)(cid:29)

The suggestion of the Stakeholder is noted. The Stakeholder may also (cid:81)(cid:82)(cid:87)(cid:72)(cid:3) (cid:87)(cid:75)(cid:72)(cid:3) (cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3) (cid:85)(cid:72)(cid:86)(cid:83)(cid:82)(cid:81)(cid:86)(cid:72)(cid:17)Further, the Commission has already notified SOP Regulations providing limits/timelines for various individual /overall Standard of Performance.

2.2.19. Analyzing metering data

(cid:54)(cid:87)(cid:68)(cid:78)(cid:72)(cid:75)(cid:82)(cid:79)(cid:71)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:38)(cid:82)(cid:80)(cid:80)(cid:72)(cid:81)(cid:87)(cid:29)

ED-(cid:42)(cid:82)(cid:68)(cid:3)(cid:68)(cid:79)(cid:85)(cid:72)(cid:68)(cid:71)(cid:92)(cid:3)(cid:75)(cid:68)(cid:86)(cid:3)(cid:80)(cid:72)(cid:87)(cid:72)(cid:85)(cid:76)(cid:81)(cid:74)(cid:3)(cid:68)(cid:87)(cid:3)(cid:39)(cid:55)(cid:38)(cid:182)(cid:86)(cid:17)(cid:3)(cid:43)(cid:82)(cid:90)(cid:72)(cid:89)(cid:72)(cid:85)(cid:15)(cid:3)(cid:87)(cid:75)(cid:72)(cid:3)(cid:71)(cid:68)(cid:87)(cid:68)(cid:3)(cid:68)(cid:89)(cid:68)(cid:76)(cid:79)(cid:68)(cid:69)(cid:79)(cid:72)(cid:3)(cid:76)(cid:86)(cid:3)(cid:81)(cid:82)(cid:87)(cid:3)(cid:68)(cid:81)(cid:68)(cid:79)(cid:92)(cid:86)(cid:72)(cid:71)(cid:17)(cid:3)(cid:53)(cid:72)(cid:83)(cid:88)(cid:87)(cid:72)(cid:71)(cid:3)(cid:44)(cid:81)(cid:86)(cid:87)(cid:76)(cid:87)(cid:88)(cid:87)(cid:72)(cid:86)(cid:3)(cid:79)(cid:76)(cid:78)(cid:72)(cid:3)(cid:42)(cid:82)(cid:68)(cid:3) Institute of Management can be roped in to analyse the data based on which suggestions for improvement, mismatch in supply & distribution, consumption,etc can be obtained.

(cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:53)(cid:72)(cid:86)(cid:83)(cid:82)(cid:81)(cid:86)(cid:72)(cid:29)

The data available through Automated Meter Reading (AMR) instrument located at each DTC is made available in the Meter Data Management (MDM) system. The data is periodically analysed for checking the loading trend of the DTC, balancing of the load, losses, lower PF cases, etc.

(cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:182)(cid:86)(cid:3)(cid:57)(cid:76)(cid:72)(cid:90)(cid:29)

(cid:55)(cid:75)(cid:72)(cid:3)(cid:54)(cid:87)(cid:68)(cid:78)(cid:72)(cid:75)(cid:82)(cid:79)(cid:71)(cid:72)(cid:85)(cid:3)(cid:80)(cid:68)(cid:92)(cid:3)(cid:81)(cid:82)(cid:87)(cid:72)(cid:3)(cid:87)(cid:75)(cid:72)(cid:3)(cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:85)(cid:72)(cid:86)(cid:83)(cid:82)(cid:81)(cid:86)(cid:72)(cid:17)

2.2.20. Audit of Annual Accounts

(cid:54)(cid:87)(cid:68)(cid:78)(cid:72)(cid:75)(cid:82)(cid:79)(cid:71)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:38)(cid:82)(cid:80)(cid:80)(cid:72)(cid:81)(cid:87)(cid:29)

GCCI submitted that they congratulate the current CEE for following up & completing the ED Goa Accounts up to 2018. They were pending since FY 2012 onwards. Without audit no accounts can be verified. We understand the Audit is currently on by CAG. We request that the accounts be bought upto date so that the exact figures can be made public. We are sure that this will be completed by the current CEE.

(cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:53)(cid:72)(cid:86)(cid:83)(cid:82)(cid:81)(cid:86)(cid:72)(cid:29)

ED-Goa submits that once the audit of accounts for FY 2017-18 to FY 2019-20 is completed, the respective details will be submitted to the public. Drafting of provisional accounts for FY 2020-21 is in process, upon completion the same will be submitted for CAG audit.

(cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:182)(cid:86)(cid:3)(cid:57)(cid:76)(cid:72)(cid:90)(cid:29)

The Commission directs the Petitioner to complete the audit of accounts up to FY 2020-21 and submit the same to the Commission along with True-up Petition within 3 months of the issuance of this Order. Further, the audit of FY 2021-22 should be completed and submitted to the Commission along with True-up Petition while filing the Tariff Petition for FY 2023-24.

2.2.21. Periodicaleducation of customers

(cid:54)(cid:87)(cid:68)(cid:78)(cid:72)(cid:75)(cid:82)(cid:79)(cid:71)(cid:72)(cid:85)(cid:182)(cid:86) Comment:

GCCI submitted that ED-Goa should include periodical education of Customers on issues like connected load, procedures, Energy Efficiency for flattening of load curve. Plan may include this aspect.

79 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 26 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA Stakeholder Comments Joint Electricity Regulatory Commission (JERC) SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022

(cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:53)(cid:72)(cid:86)(cid:83)(cid:82)(cid:81)(cid:86)(cid:72)(cid:29)

EDG submits that, continuous efforts are being taken in creating awareness and educating the people and future generations through various modes and methods provided in the following:

(cid:120) Launching of Energy Conservation Mobile Van. The movable mobile Van hired for publicity consisting of a structure with message on Energy Conservation tips through a banner was conveyed to teachers and students of Government High Schools/KendriyaVidhyalayas/JawaharNavodayaVidhyalayas across entire state of Goa and also energy conservation awareness material i.e. poster/sticker to schools was distributed.

(cid:120) Creation of Energy Clubs by encouraging participation of young children in energy efficiency movement on Energy Saving/Conservation in Government High Schools including KendriyaVidyalayas, JawaharNavodaya Schools which will be selected for Model Energy Efficient Schools in the State of Goa. The Work Order has been issued to M/s LILA Digital & Environmental Solutions Pvt. Ltd. on 08/09/2020. The agency has completed online training sessions in all the 25 schools. Balance work is in progress.

(cid:120) Conversion of 16 nos. of Government high Schools including 5 nos. of KendriyaVidyalayas and 2 nos. of JawaharNavodayaVidyalaya to Model Energy Efficient Schools. The Work Order has been issued to M/s Energy Efficiency Services Limited, New Delhi on 21/09/2020 and the work is completed.

(cid:120) Conversion of Government High School, Dona Paula to Model Energy Efficient School by replacing all existing conventional appliances as a pilot project. The Work Order had been issued to M/s Energy Efficiency Services Limited, New Delhi on 26/08/2020 and the work is completed.

(cid:120) Organized Energy Conservation Week programme at Institute Menezes Braganza Conference Hall on 21/12/2021, the programme included Training to Government High

(cid:120) Schools/KendriyaVidhyalayas/JawaharNavodayaVidhayala Teachers w.r.t. Energy Clubs, quiz Competition for finalists, Awareness/Interactive session on Energy Conservation Building Code and Painting and quiz competition prize distribution to students w.r.t. Energy Clubs.

(cid:120) Work of Implementation of DSM based Efficient Lighting Programme in the State of Goa by providing 3 nos. of 7W/9W LED Bulbs to each Registered Domestic Consumer of GED at free of cost as a step towards energy conservation. Distributed of 8,04,735 nos. of 9W LED Bulbs to 2,68,245 nos. of Consumers with estimated saving of 106 MUs of annually.

(cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:182)(cid:86)(cid:3)(cid:57)(cid:76)(cid:72)(cid:90)(cid:29)

(cid:55)(cid:75)(cid:72)(cid:3)(cid:54)(cid:87)(cid:68)(cid:78)(cid:72)(cid:75)(cid:82)(cid:79)(cid:71)(cid:72)(cid:85)(cid:3)(cid:80)(cid:68)(cid:92)(cid:3)(cid:81)(cid:82)(cid:87)(cid:72)(cid:3)(cid:87)(cid:75)(cid:72)(cid:3)(cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:85)(cid:72)(cid:86)(cid:83)(cid:82)(cid:81)(cid:86)(cid:72)(cid:17)

2.2.22. Continuous Staff training, Long-term solution for power

interruption and improvement of distribution efficiency

(cid:54)(cid:87)(cid:68)(cid:78)(cid:72)(cid:75)(cid:82)(cid:79)(cid:71)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:38)(cid:82)(cid:80)(cid:80)(cid:72)(cid:81)(cid:87)(cid:29)

Continuous training of engineers, Managers and administrative staff is essential. About 2% of HR expenses may be allocated to the same. There are numerous short duration transient failures & some failures in the

(cid:71)(cid:76)(cid:86)(cid:87)(cid:85)(cid:76)(cid:69)(cid:88)(cid:87)(cid:76)(cid:82)(cid:81)(cid:3)(cid:86)(cid:92)(cid:86)(cid:87)(cid:72)(cid:80)(cid:3) (cid:76)(cid:81)(cid:3) (cid:74)(cid:82)(cid:68)(cid:17)(cid:3)(cid:37)(cid:72)(cid:86)(cid:76)(cid:71)(cid:72)(cid:86)(cid:3)(cid:70)(cid:68)(cid:85)(cid:85)(cid:92)(cid:76)(cid:81)(cid:74)(cid:3)(cid:82)(cid:88)(cid:87)(cid:3) (cid:85)(cid:72)(cid:83)(cid:68)(cid:76)(cid:85)(cid:86)(cid:3)(cid:9)(cid:3)(cid:68)(cid:71)(cid:82)(cid:83)(cid:87)(cid:76)(cid:81)(cid:74)(cid:3)(cid:179)(cid:45)(cid:88)(cid:74)(cid:68)(cid:71)(cid:180)(cid:3)(cid:86)(cid:82)(cid:79)(cid:88)(cid:87)(cid:76)(cid:82)(cid:81)(cid:86)(cid:15)(cid:3) (cid:76)(cid:87)(cid:3) (cid:76)(cid:86)(cid:3)(cid:81)(cid:72)(cid:70)(cid:72)(cid:86)(cid:86)(cid:68)(cid:85)(cid:92)(cid:3)(cid:87)(cid:82)(cid:3)(cid:70)(cid:68)(cid:85)(cid:85)(cid:92)(cid:3) out Root Cause Analysis (RCA) and find long term effective solution in terms of material, specification, procedure & processes by forming separate dedicated groups. It is also necessary to take up pilot projects such as HV Distribution with an objective to improve distribution efficiency.

(cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:53)(cid:72)(cid:86)(cid:83)(cid:82)(cid:81)(cid:86)(cid:72)(cid:29)

EDG submits the reply in three parts provided in the following:

Training: The ED, Goa Training Centre at Ponda has been made fully functional and carries out periodic training for Technical and Clerical staff. Some of these trainings are carried out in association with reputed80 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 27 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA Stakeholder Comments Joint Electricity Regulatory Commission (JERC) SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022 organizations such as RECL, NTPI and NTPC. Hands on training is also provided by reputed OEM for O&M staff. Trainings related to Safety such as Safe Practices, Use of PEEs, etc. are also provided.

Root Cause Analysis and long-term effective solution: The major cause of power interruption is due to falling of trees / branches on the overhead lines especially during the monsoon season. Further, the existing overhead system is aged and the frequent snapping of the lines causes further deteriorations effecting power supply reliability severely. The Departments has taken up numerous projects for conversion of overhead network to under ground system across the state of Goa to include major cities and towns and also hinterlands and the coastal belts. The projects are under various stage of completions.

HV Distribution: The HV Distribution is for High Load concentrated areas wherein independent transformer is installed to supply large number of consumers located at one location. The system avoids use of long LT lines thereby reducing losses and changes of theft. The system is ideal for Metro cities wherein large cluster of consumers are located very closely. In Goa, individual transformers are provided for multi consumers complexes and single dwelling consumers are supplied through 11/0.433 KV Distribution transformer of requisite ratings.

(cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:182)(cid:86)(cid:3)(cid:57)(cid:76)(cid:72)(cid:90)(cid:29)

(cid:55)(cid:75)(cid:72)(cid:3) (cid:54)(cid:87)(cid:68)(cid:78)(cid:72)(cid:75)(cid:82)(cid:79)(cid:71)(cid:72)(cid:85)(cid:3) (cid:80)(cid:68)(cid:92)(cid:3) (cid:81)(cid:82)(cid:87)(cid:72)(cid:3) (cid:87)(cid:75)(cid:72)(cid:3) (cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3) (cid:85)(cid:72)(cid:86)(cid:83)(cid:82)(cid:81)(cid:86)(cid:72)(cid:17)(cid:3) (cid:41)(cid:88)(cid:85)(cid:87)(cid:75)(cid:72)(cid:85)(cid:15)(cid:3) (cid:87)(cid:75)(cid:72)(cid:3) (cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:3) (cid:75)(cid:68)(cid:86)(cid:3) (cid:68)(cid:79)(cid:85)(cid:72)(cid:68)(cid:71)(cid:92)(cid:3) (cid:81)(cid:82)(cid:87)(cid:76)(cid:73)(cid:76)(cid:72)(cid:71)(cid:3) (cid:54)(cid:50)(cid:51)(cid:3) Regulations providing limits/timelines for various individual /overall Standard of Performance.

81 OFFICIAL GAZETTE — GOVT. OF GOA True-up of the FY 2017-18, FY 2018-19, FY 2019-20 and FY 2020-21 Joint Electricity Regulatory Commission (JERC) SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022

3. Chapter 3: True-up of the FY 2017-18,

FY 2018-19, FY 2019-20 and FY 2020-

21

3.1. Applicable provisions

The True-up of FY 2017-18 and FY 2018-19 are to be carried out as per Regulation8 (2) of the JERC MYT Regulations, 2014:

(cid:179)8. Annual Review of Performance and True-up

(cid:171)

(2)After audited accounts of a year are made available, the Commission shall undertake similar exercise as

above with reference to the final actual figures or the provisional actual accounts as available as per the

audited accounts. This exercise with reference to audited accounts shall be called 'Truing Up'.

The Truing Up for any year will ordinarily not be considered after more than one year of 'Review'.

(3)The revenue gap/surplus, if any, of the ensuing year shall be adjusted as a result of review and truing up

exercises.

(4)While approving such expenses/revenue to be adjusted in the future years as arising out of the Review

and/or Truing up exercises, the Commission may allow the carrying costs as determined by the Commission

of such expenses/revenue. Carrying costs shall be limited to the interest rate approved for working capital

borrowings.

(5)For any revision in approvals, the licensee would be required to satisfy the Commission that the revision is

due to conditions beyond its control.

(6)In case additional supply is required to be made to any particular category, the licensee may, any time

during the year make an application to the Commission for its approval. The application will demonstrate the

need for such additional supply of power and also indicate the manner in which the licensee proposes to meet

the cost for such additional supply of power.(cid:180)

Further, the True-up of FY 2019-20 and FY 2020-21 are to be carried out as per Regulation11 of the JERC MYT Regulations, 2018:

(cid:179)11. Annual Performance Review, Truing-up and tariff determination during the Control

Period

11.1 The Generating Company, Transmission Licensee and Distribution Licensee shall be subject to

annualperformance review and truing up of expenses and revenue during the Control Period in accordance

withthese Regulations.

11.2 The Generating Company, Transmission Licensee andDistribution Licensee shall file an application

fortheannual performance review of the current year,truing up of the previous Year or the Year for which

theaudited accounts are available and determination of tariff for the ensuing Yearon or before 30thNovember

ofeach Year, in formats specified by the Commission from time to time:

Provided that the Generating Company, Transmission Licensee or Distribution Licensee, as the case may

be,shall submit to the Commission information in such form as may be specified by the Commission,

togetherwith the audited accounts, extracts of books of account and such other details as the Commission may

requireto assess the reasons for and extent of any variation in financial performance from the approved

forecast ofAggregate Revenue Requirement and Expected Revenue from Tariff and Charges.

82 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 29 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA True-up of the FY 2017-18, FY 2018-19, FY 2019-20 and FY 2020-21 Joint Electricity Regulatory Commission (JERC) SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022

11.3 The scope of the annual performance review, truing up and tariff determination shall be a comparison of

theperformance of the Generating Company, Transmission Licensee or Distribution Licensee with the

approvedforecast of Aggregate Revenue Requirement and Expected Revenue from Tariff and Charges and

shallcomprise of the following:

a) True-up: a comparison of the audited performance of the Applicant for the Financial Yearfor which

thetrue up is being carried out with the approved forecast for such previous Financial Year, subject to

theprudence check;

(cid:171)(cid:171)(cid:171)(cid:17)(cid:180)

3.2. Approach for the True-up of the FY 2017-18, FY 2018-19, FY

2019-20 and FY 2020-21

(cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:86)(cid:88)(cid:69)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:29)

The Petitioner has not submitted the True-Up Petition for FY 2017-18, FY 2018-19, FY 2019-20 and FY 2020- 21. Further, the Petitioner has submitted that that audit works is in progress for FY 2017-18 by CAG. The accounts for FY 2018-19 and FY 2019-20 are completed and submitted to CAG, the process of auditing is yet to start. Further the accounts of FY 2020-21 will be finalized by ED-Goa by 31stDecember 2021 and the same will be submitted to CAG for auditing purposes.

(cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:182)(cid:86)(cid:3)(cid:68)(cid:81)(cid:68)(cid:79)(cid:92)(cid:86)(cid:76)(cid:86)(cid:29)

The Commission in its previous Orders had stressed upon the requirement of the audited accounts to reflect the true picture and bring in accuracy in the estimates made by the Commission. The JERC MYT Regulations, 2014and JERC MYT Regulations, 2018 also require the licensee to file the True up along with the audited accounts in the filing.

The Commission reiterates its direction to the Petitioner to prepare and submit the audited accounts for FY 2017-18, FY 2018-19, FY 2019-20 and FY 2020-21based on commercial principles along with the True-up Petitions by 30thNovember 2022.

The True-up would therefore be taken up only after submission of the audited accounts. Accordingly, the Commission has decided not to take up True-up for FY 2017-18, FY 2018-19, FY 2019-20 and FY 2020-21 in the current Order.

83 OFFICIAL GAZETTE — GOVT. OF GOA APR of FY 2021-22 Joint Electricity Regulatory Commission (JERC) SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022

4. Chapter 4: Annual Performance

Review of FY 2021-22

4.1. Applicable Provisions and Background

The MYT Order for each year of the Control Period fromFY 2019-20 to FY 2021-22 was issued by the Commission on 20th May 2019 approving the Aggregate Revenue Requirement (ARR) and tariff for the FY 2019-20. The ARR for FY 2021-22 was further revised and the tariff for FY 2021-22 was approved by the Commission in its Tariff Order dated by the Commission in its Tariff Order dated 30th March 2021. The Annual Performance Review for the FY 2021-22 is to be carried out in accordance with the Regulation 11 of the JERC MYT Regulations 2018:

(cid:179)11. Annual Performance Review, Truing-up and tariff determination during the Control

Period

11.1 The Generating Company, Transmission Licensee and Distribution Licensee shall be subject to

annualperformance review and truing up of expenses and revenue during the Control Period in accordance

withthese Regulations.

11.2 The Generating Company, Transmission Licensee andDistribution Licensee shall file an application

fortheannual performance review of the current year,truing up of the previous Year or the Year for which

theaudited accounts are available and determination of tariff for the ensuing Yearon or before 30 thNovember

ofeach Year, in formats specified by the Commission from time to time:

Provided that the Generating Company, Transmission Licensee or Distribution Licensee, as the case may

be,shall submit to the Commission information in such form as may be specified by the Commission,

togetherwith the audited accounts, extracts of books of account and such other details as the Commission may

requireto assess the reasons for and extent of any variation in financial performance from the approved

forecast ofAggregate Revenue Requirement and Expected Revenue from Tariff and Charges.

11.3 The scope of the annual performance review, truing up and tariff determination shall be a comparison of

theperformance of the Generating Company, Transmission Licensee or Distribution Licensee with the

approvedforecast of Aggregate Revenue Requirement and Expected Revenue from Tariff and Charges and

shallcomprise of the following:

(cid:171)

b) Annual Performance Review: a comparison of the revised performance targets of the Applicant for

thecurrent Financial Year with the approved forecast in the Tariff Order corresponding to the Control

Periodfor the current Financial Year subject to prudence check;

(cid:171)(cid:171)(cid:171)(cid:17)(cid:180)

4.2. Approach for the Review for the FY 2021-22

(cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:86)(cid:88)(cid:69)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:29)

The Petitioner has submitted the APR of FY 2021-22 based on the actual performance during the H1 (April- September 2021) of the year and the revised estimates for H2 (Oct0ber - March 2022) of the year. The projections for H2 of FY 2021-22 are arrived at by expected escalation over performance of H1.

Commi(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:182)(cid:86)(cid:3)(cid:68)(cid:81)(cid:68)(cid:79)(cid:92)(cid:86)(cid:76)(cid:86)(cid:29)

The Commission for the purpose of estimating the energy demand of the State sought the information of month-wise historical sales, number of consumers and connected load of the from FY 2017-18 toFY 2021-22(tillOrder on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 31 Electricity Department, Government of Goa 84 OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022 APR of FY 2021-22 Joint Electricity Regulatory Commission (JERC) H1) from the Petitionerin the first Deficiency Note dated 28th January 2022. Various anomalies and gaps were

observed in the data provided.

APR of FY 2021-22 Joint Electricity Regulatory Commission (JERC)

In addition to the issues in respect of commercial data such as sales, number of consumers, connected load and H1) from the Petitionerin the first Deficiency Note dated 28th January 2022. Various anomalies and gaps were power purchase, the Commission observes that due to the unavailability of audited annual accounts for FY observed in the data provided. 2017-18, FY 2018-19, FY 2019-20 and FY 2020-21, it is difficult to ascertain the accuracy of the data in respect In addition to the issues in respect of commercial data such as sales, number of consumers, connected load and of capital expenditure and capitalisation during this period thereby leading to unreliable estimates of ARR power purchase, the Commission observes that due to the unavailability of audited annual accounts for FY parameters. 2017-18, FY 2018-19, FY 2019-20 and FY 2020-21, it is difficult to ascertain the accuracy of the data in respect

of capital expenditure and capitalisation during this period thereby leading to unreliable estimates of ARR Therefore, the Commission believes that it is not prudent to approve the revised power purchase requirement parameters. and revenue from retail sale on the basis of the unreliable information presently available. Therefore, the Therefore, the Commission believes that it is not prudent to approve the revised power purchase requirement Commission shall consider the actual performance at the time of the True-up of the FY 2021-22 once the and revenue from retail sale on the basis of the unreliable information presently available. Therefore, the audited accounts are submitted by the Petitioner. Commission shall consider the actual performance at the time of the True-up of the FY 2021-22 once the audited accounts are submitted by the Petitioner. Accordingly, the Commission has decided not to undertake the Annual Performance Review of the FY 2021-22. Accordingly, the Commission has decided not to undertake the Annual Performance Review of the FY 2021-22. The Commission directs the Petitioner to submit the True-up of FY 2021-22 and the APR of FY 2022-23 based The Commission directs the Petitioner to submit the True-up of FY 2021-22 and the APR of FY 2022-23 based on reliable data by 30th November 2022. on reliable data by 30th November 2022.

Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 32 Electricity Department, Government of Goa85 ARR for the 3rd MYT Control Period Joint Electricity Regulatory Commission (JERC) OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022

5. Chapter 5: Determination of

Aggregate Revenue Requirement for

the 3rdMYT Control Period

5.1. Background

In this Chapter, the Commission has determined the Aggregate Revenue Requirement (ARR) for the 3rd MYT Control Period. The determination of Aggregate Revenue Requirement has been done in accordance with the JERC MYT Regulations, 2021.

5.2. Approach for determination of ARR for each year of the 3rd

MYT Control Period

The Commission has computed the individual elements constituting the Aggregate Revenue Requirement for each year based on figures approved in the Business Plan Order dated 31st March 2022 and the provisional information of various parameters for the previous financial years. The ARR has been determined for each financial year of the 3rd Control Period whereas the revenue at existing tariff is determined only for the FY 2022-23 to arrive at the revenue gap/surplus for the FY 2022-23.

5.3. Projection of Number of consumers, Connected Load and

Energy Sales

(cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:54)(cid:88)(cid:69)(cid:80)ission

The Petitioner has considered the same number of consumers, connected load and energy sales as proposed by the Petitioner in the Business Plan.

Table 6: Category-wise number of consumers proposed by the Petitioner for 3rdMYT Control

Period

Sl.N o. Particulars Projected No. of Consumers
FY 2022-23 FY 2023-24 FY 2024-25
1(a) Tariff LTD/Domestic 547790 559603 571670
1(b) Tariff LTIG/Low Income Group 877 877 877
2 Tariff LTC/Commercial 103827 105798 107806
3 Tariff LTI/Industry 5649 5649 5649
4 Tariff LTP/Mixed (Hotel Industries) 116 116 116
5A Tariff LTAG/Agriculture (Pump sets / Irrigation) 12481 12875 13281
B Tariff LTAG/Agriculture (Allied Activities) 256 269 282
6 Tariff LTPL/ Public Lighting 5726 6012 6313
7 Tariff LTH/ Hoarding and Signboards 61 61 61
8 Tariff-LTTS/ Temporary Supply 2726 2726 2726
9 Tariff-HTI/ Industrial 798 814 831
10 Tariff HTFS Industrial (Ferro Metallurgical/ Steel Melting/ Power Intensive/ Steel Rolling) 22 22 22
11 Tariff HTC/ Commercial 289 303 318
12 A Tariff HTAG/ Agriculture (Pump Sets/ irrigation) 43 43 44
B Tariff HTAG/ Agriculture (allied activity) 3 3 3
13 Tariff HTD/ Domestic 4 4 5
14 Tariff HTMES/ Defense Establishment 15 15 16
15 Tariff HTTS/ Temporary Supply 16 17 17
16 Single Point Supply 1 1 1
Total 680699 695208 710037
86 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 33 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022 ARR for the 3rd MYT Control Period Joint Electricity Regulatory Commission (JERC)

Table 7: Category-wise connected load (kW) proposed by the Petitioner for 3rd MYT Control

Period

Sl. No. Connected Load (MU) Proposed Connected Load (kW)
FY 2022-23 FY 2023-24 FY 2024-25
1(a) Tariff LTD/Domestic 1722919.38 1789067.48 1857755.21
1(b) Tariff LTIG/Low Income Group 85.00 85.00 85.00
2 Tariff LTC/Commercial 390009.09 406751.31 424212.23
3 Tariff LTI/Industry 145742.80 146392.49 147045.07
4 Tariff LTP/Mixed (Hotel Industries) 2295.00 2295.00 2295.00
5A Tariff LTAG/Agriculture (Pump sets / Irrigation) 48595.81 50444.35 52363.21
B Tariff LTAG/Agriculture (Allied Activities) 2308.95 2424.40 2545.62
6 Tariff LTPL/ Public Lighting 12192.25 12801.87 13441.96
7 Tariff LTH/ Hoarding and Signboards 514.00 514.00 514.00
8 Tariff-LTTS/ Temporary Supply 9248.00 9248.00 9248.00
9 Tariff-HTI/ Industrial 570982.14 581226.85 591655.37
10 Tariff HTFS Industrial (Ferro Metallurgical/ Steel Melting/ Power Intensive/ Steel Rolling) 93250.00 93250.00 93250.00
11 Tariff HTC/ Commercial 108614.10 114044.81 119747.05
12 A Tariff HTAG/ Agriculture (Pump Sets/ irrigation) 9476.30 9697.65 9924.17
B Tariff HTAG/ Agriculture (allied activity) 2200.00 2200.00 2200.00
13 Tariff HTD/ Domestic 420.00 441.00 463.05
14 Tariff HTMES/ Defense Establishment 8709.75 9145.24 9602.50
15 Tariff HTTS/ Temporary Supply 5663.70 5946.89 6244.23
16 Single Point Supply 4035.00 4035.00 4035.00
Total 3137261.27 3240011.32 3346626.6 7

Table 8: Category-wise energy sales (MUs) proposed by the Petitioner for 3rd MYT Control

Period

Sl. No. Particulars Projected Sales (MU)
FY 2022-23 FY 2023-24 FY 2024-25
1(a) Tariff LTD/Domestic 1325.53 1379.16 1434.96
1(b) Tariff LTIG/Low Income Group 1.27 1.27 1.27
2 Tariff LTC/Commercial 436.59 448.26 460.24
3 Tariff LTI/Industry 80.91 80.91 80.91
4 Tariff LTP/Mixed (Hotel Industries) 4.48 4.48 4.48
5A Tariff LTAG/Agriculture (Pump sets / Irrigation) 17.25 17.71 18.18
B Tariff LTAG/Agriculture (Allied Activities) 0.99 0.99 0.99
6 Tariff LTPL/ Public Lighting 50.41 52.93 55.58
7 Tariff LTH/ Hoarding and Signboards 0.16 0.16 0.16
8 Tariff-LTTS/ Temporary Supply 9.77 9.77 9.77
9 Tariff-HTI/ Industrial 1483.35 1512.88 1543.01
10 Tariff HTFS Industrial (Ferro Metallurgical/ Steel Melting/ Power Intensive/ Steel Rolling) 506.83 530.35 554.97
11 Tariff HTC/ Commercial 116.74 122.58 128.71
12 A Tariff HTAG/ Agriculture (Pump Sets/ irrigation) 5.30 5.30 5.30
B Tariff HTAG/ Agriculture (allied activity) 9.36 9.82 10.32
13 Tariff HTD/ Domestic 0.43 0.45 0.47
14 Tariff HTMES/ Defense Establishment 27.86 27.86 27.86
15 Tariff HTTS/ Temporary Supply 3.51 3.69 3.87
16 Single Point Supply 5.55 5.60 5.65
Total 4086.29 4214.18 4346.69
87 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 34 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022 ARR for the 3rd MYT Control Period Joint Electricity Regulatory Commission (JERC)

(cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:182)(cid:86)(cid:3)(cid:68)(cid:81)(cid:68)(cid:79)(cid:92)(cid:86)(cid:76)(cid:86)

The Commission in the Business Plan Order dated 31st March 2022 had estimated the category wise energy sales, number of consumers and connected load based on historical trends. The detailed methodology has been discussed in the Business Plan Orderfor the 3rd MYT Control Period. The Commission retains the same energy sales, connected load and number of consumers as approved in the Business Plan.

Table 9: Category-wise number of consumersapproved by the Commission for 3rdMYT Control

Period

Sl. No. Consumer Category Consumer growth projections
Base Year (Estimated) Control Period (Approved)
FY 2021-22 FY 2022-23 FY 2023-24 FY 2024-25
1 LTD/Domestic 565,369 588,323 612,209 637,065
2 LT-LIG/Low Income Group 1,314 1,314 1,314 1,314
3 LTC/Commercial 105,325 108,137 111,025 113,989
4 LTI/Industrial 5,799 5,799 5,799 5,799
5 LT Mixed/ LT-P Hotel Industries 125 125 125 125
6 LTAG/Agriculture 12,402 12,634 12,870 13,111
7 LT Temporary 2,609 2,609 2,609 2,609
8 HTD Domestic 3 3 3 3
9 HTC Commercial 285 302 321 341
10 HTI Industrial 855 915 978 1,046
11 High Tension-Ferro/SM/PI/SR 26 26 26 26
12 HTAG/Agriculture 46 47 48 49
13 Military Engineering Services/Defense Establishments 14 14 14 15
14 Public Lighting 1,097 1,097 1,097 1,097
15 Hoardings/Signboards 47 47 47 47
16 HT Temporary 11 11 11 11
17 Single Point Supply 1 1 1 1
Total 695,328 721,405 748,498 776,648

Table 10: Category-wise connected load (kW) approved by the Commission for 3rdMYT Control

Period

Sl. No. Consumer Category Connected load growth projections (kW)
Base Year (Estimated) Control Period (Approved)
FY 2021-22 FY 2022-23 FY 2023-24 FY 2024-25
1 LTD/Domestic 1,713,671 1,808,437 1,908,443 2,013,980
2 LT-LIG/Low Income Group 117 117 117 117
3 LTC/Commercial 388,838 407,424 426,899 447,305
4 LTI/Industrial 144,633 146,918 149,240 151,598
5 LT Mixed/ LT-P Hotel Industries 2,757 2,757 2,757 2,757
6 LTAG/Agriculture 50,692 52,385 54,134 55,942
7 LT Temporary 9,107 9,107 9,107 9,107
8 HTD Domestic 300 300 300 300
9 HTC Commercial 88,125 90,575 93,093 95,681
10 HTI Industrial 589,357 619,237 650,632 683,619
11 High Tension-Ferro/SM/PI/SR 95,340 95,340 95,340 95,340
12 HTAG/Agriculture 12,152 12,610 13,085 13,579
13 Military Engineering Services/Defense Establishments 8,196 8,470 8,753 9,045
14 Public Lighting 3,212 3,212 3,212 3,212
15 Hoardings/Signboards 567 567 567 567
16 HT Temporary 2,468 2,468 2,468 2,468
17 Single Point Supply 4,035 4,035 4,035 4,035
Total 3,113,566 3,263,959 3,422,183 3,588,653
88 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 35 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022 ARR for the 3rd MYT Control Period Joint Electricity Regulatory Commission (JERC)

Table 11: Category-wise energy sales (MU) approved by the Commission for 3rd MYT Control

Period

Sl. No. Consumer Category Energy sales growth projections (MU)
Base Year (Estimated) Control Period (Approved)
FY 2021-22 FY 2022-23 FY 2023-24 FY 2024-25
1 LTD/Domestic 1,320.92 1,384.58 1,451.32 1,521.28
2 LT-LIG/Low Income Group 1.37 1.37 1.37 1.37
3 LTC/Commercial 460.23 472.52 485.13 498.09
4 LTI/Industrial 80.91 80.91 80.91 80.91
5 LT Mixed/ LT-P Hotel Industries 4.48 4.48 4.48 4.48
6 LTAG/Agriculture 18.08 18.08 18.08 18.08
7 LT Temporary 9.77 9.77 9.77 9.77
8 HTD Domestic 0.38 0.38 0.38 0.38
9 HTC Commercial 128.26 135.02 142.13 149.62
10 HTI Industrial 1,469.87 1,499.12 1,528.95 1,559.37
11 High Tension-Ferro/SM/PI/SR 530.72 555.35 581.12 608.08
12 HTAG/Agriculture 14.13 15.54 17.09 18.79
13 Military Engineering Services/Defense Establishments 26.66 26.96 27.27 27.58
14 Public Lighting 29.61 29.61 29.61 29.61
15 Hoardings/Signboards 0.16 0.16 0.16 0.16
16 HT Temporary 2.33 2.33 2.33 2.33
17 Single Point Supply 5.65 5.69 5.74 5.79
Total 4,103.52 4,241.87 4,385.84 4,535.68

5.4. Inter-State transmission loss

(cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:54)(cid:88)(cid:69)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)

89 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 36 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022 ARR for the 3rd MYT Control Period Joint Electricity Regulatory Commission (JERC)

The Petitioner had submitted Inter-State Transmission Losses for the 3rdMYT Control Periodin its Business Plan Petition as follows:

Table 12: Inter-state transmission losses considered by the Petitioner for FY 2021-22 and the

3rd MYT Control Period

Particulars Projections
Base Year FY 2021-22 FY 2022-23 FY 2023-24 FY 2024-25
Western Region 3.35% 3.34% 3.31% 3.29%
Southern Region 7.95% 7.92% 7.85% 7.80%

(cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:182)(cid:86)(cid:3)(cid:68)(cid:81)(cid:68)(cid:79)(cid:92)(cid:86)(cid:76)(cid:86)

The Commission accepts the projections submitted by the Petitioner. The same shall be revised based on actuals during the truing up of the respective years as per respective Regulations.The following table provides the Inter-State Transmission Losses approved by the Commission for the 3rd MYT Control Period:

Particulars FY 2022-23 FY 2023-24 FY 2024-25
Western Region 3.34% 3.31% 3.29%
Southern Region 7.92% 7.85% 7.80%

5.5. Intra-State Transmission &Distribution (T&D) Losses

(cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:54)(cid:88)(cid:69)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)

The Petitioner has submitted Intra-State Distribution Losses for the 3rd MYT Control Period as submittedin the Business Plan Petition, which are as follows:

Consumer Category FY 2022-23 FY 2023-24 FY 2024-25
Intra-state T&D losses 10.15% 10.00% 9.85%

(cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:182)(cid:86)(cid:3)(cid:68)(cid:81)(cid:68)(cid:79)(cid:92)(cid:86)(cid:76)(cid:86)

The Commission has approved the same Intra-State T&D losses approved in Business Plan of3rd MYT Control Periodin Order dated 31st March 2022.

Consumer Category FY 2022-23 FY 2023-24 FY 2024-25
Intra-state T&D losses 10.25% 10.00% 9.75%

5.6. Power Purchase Quantum & Cost

Petitioners Submission

1. Power Purchase Quantum

90 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 37 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022 ARR for the 3rd MYT Control Period Joint Electricity Regulatory Commission (JERC)

The power purchase quantum for the Control period has been considered as the quantum projected by the petitioner in Business Plan petition for FY 2022-23 to FY 2024-25.The Petitioner has projected the net power purchase quantum for the MYT Control period, as 4,548MU, 4,582 MU and 4,834 MU for FY 2022-23, FY 2023-24, FY 2024-25respectively.

2. Power Purchase Cost

The Petitioner has submitted in Business Plan petition, EDG had submitted the power purchase procurement plan along with power purchase cost. Following assumptions have been considered for projecting the cost of power purchase:

Fixed Charges:The Petitioner has submitted that the Fixed costs for the Control Periodhas still not been issued by CERC for most of the Plant, therefore,the Petitioner has considered actual fixed charges paid to the plant in Q1 of FY 2021-22 and extrapolated them to arrive at the revised projections of base year FY 2021-22 for respective Central Generating Stations. Further, projection of fixed charged for the Control Period has been done, considering the CAGR of past 3 yrs of each plant, with a cap of 5% for the Control Period.

Variable Charges:The Petitioner has considered the actual per unit variable costs of FY 2021-22 Q1 and has calculated the revised projections of base year FY 2021-22 w.r.t to power purchase projections for respective Central Generating Stations. Further, year on year projections has been done by considering 3 year CAGR on energy charges for each plant, with an escalation cap of 5% for purpose of estimation of the variable charges for the control period. Escalation % with negative CAGR are considered to be NIL.

Solar and Non-solar:The Petitioner has considered the rates as per the PPAfor the entire Control Period from FY 2022-23 to FY 2024-25 without any escalation. Further, to fulfil the RPO compliance, the deficit renewable power as per RPO is compensated by procuring renewable power (Solar and Non-Solar) from the Short-Term Market. The Petitioner has considered the market rates as per the actuals of Q1 FY 2021-22 for the base year FY 2021-22 and also for the entire Control Period from FY 2022-23 to FY 2024-25 without any escalation.

The Petitioner has submitted that it has been procuring power from the Renewable Sources where 6 MW Solar Power is procured from NVVNL and 25 MW from SECI to meet its RPO obligations. The NVVNL tie-up will be till FY 22-23 only (4 or 5 months). Hence, power purchase from NVVNL has been considered in revised projections of FY 2021-22 and FY 2022-23 upto August only. Power Purchase from SECI has been considered as 48 MU as per the PPA and the entire control period.

The Petitioner has submitted that any shortfall (if any) and to fulfil the Solar RPO obligation, EDG shall purchase power through short term (Traders) through DEEP portal, GTAM.

In order to meet its Non- solar RPO, the Petitioner has submitted that it would be procuring power during MYT control period through short term on DEEP portal. The Petitioner has also submitted that it is also procuring 2 MUs (for FY 2024-25 it is 0.5 MUs) every year from Hindustan Waste Energy Ltd and the same has been envisaged to buy during the entire control period. Further, the Petitioner has also tied up with SECI Tranche II 50 MW Wind power and procuring the power at a rate of Rs. 2.72/unit plus trading margin of Rs. 0.07/kWh at goa periphery.

The Petitioner has submitted that no upcoming power purchase planned from the thermal generating stations.

It has planned the tie-ups of Renewable energy both outside and within the state during the control period to meet its RPO obligations.

Apart from the above sources, the Petitionershall purchase power in Short-term from exchanges or Traders or DEEP portal to fulfil its peak requirements. Further, the Petitionermay sell surplus available during off-peak hours and would indulge in banking or sale of power in exchanges in the real time basis

Transmission Charges:The Petitioner has considered the actual transmission charges for H1 of FY 2021-22 and calculated the transmission charges per unit for PGCIL. The same per unit rate has been considered for computation of Transmission charges for the control period without any escalations

The total power purchase quantum and cost for each year of the MYT control period is as under:

91 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 38 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022

.

-

5

.

-

5 1

2 1

6 1

3 7

6 7

2 7

5 6

5 6

-

3 1

3 1 7 5

5 3

5 9

4 3

4 6

9 8

.

. .

8 2

.

.

.

.

.

4 3

5 8

2 6

4 6

4 0

2 5

.

.

9 3

.

.

.

.

.

.

.

r C

3 2

7 1

1 1 .

0 1

4 1

7 5

4 2

3 3

. .

.

.

.

.

-

2 5 1 3

5 4

7 2

5 2

2 6

1 9 1 5 2

s

4 3 3

t s o C

4 2 0 2

2 5 0

R

1

)

-

2 1

6 1

5 7

3 7

4 7

3 5

3 6

3 5

5 3

4 3

3 4

6 3

2 5 -

3 6

-

1 2

1 2

7 5

7 3

2 7

9 5

4 3

4 2

9 4

4 6

9 8

8 0

5 9

. .

.

.

.

.

.

4 6

4 9

4 8

3 7

.

.

.

.

6 0

.

.

.

.

.

.

.

.

.

) r C

7 1

.

1 1

0 1

7 5

4 1

4 2

. .

.

-

.

3 7 1 5

5 4

7 2

4 3

5 2

2 6

3 2

3 3

C V + C F

4 2

e s a h c r u P

s

1 9 1 d o

(

0 3 3

i

3 2 0 2

3 4 0

R

(

1

r e

s n o

r e P

8

l

.

-

5 1 5 3

0 3

2 4

4 3

3 7 -

2 6

-

5 1

3 1

2 1

1 4 w o P

2 7

4 7

2 6

9 4

4 6

6 9

9 8

9 7

.

6 5

5 4

3 3

3 6

9 3

7 0

7 0

4 4

4 9

.

8 7

.

.

.

.

.

.

.

.

.

.

.

l

i t c e

j

7 1

a

4 1

0 1

1 1 .

.

.

.

.

.

.

.

.

9 1 -

.

5 2

7 5

4 2

o r t

3 2

3 3

2 6

6 2 3

t

3 2

0 9 1

5 3 0

2 2 0 2

o r P

o T

1

n o C

d r

7 1 -

1 5

5 1

5 1

5 1

8 1

3 6

6 3

6 9 0 5

1 4

9 1

7 2

5 4

5 3

9 2

3 3

4 3

9 1 -

0 6

5

4

.

.

1 5

3 1

3 1 7 3

5 3

9 9

2 8

4 8

8 8

.

.

.

.

.

6 6

.

3

.

.

.

4 0

9 0

2 5

.

.

.

9 3

.

.

.

.

.

.

.

2 ) .

7

2

8

-

5 1

6 1

6 1

.

.

.

-

7 1

4 1 3 1

6 1

2 5

3 1

9 3

0 3 5 2

3 4 1

2 3 2

e h

)

r C

1 2 6

t

4 2 0 2

.

s

t s o C

C V

R

(

r o

f

-

1

.

7 2

0 1

6 3

0 2

2 5 -

3 6

5

.

1 7

-

5 1

5 1

4 1

8 1

3 5

7 8

3 6

5 8

6 3

4 8 1 5

1 2

1 2 7 3

2 7

9 3

4 3

9 9

3 7

.

. .

3 3

.

.

.

.

.

.

.

.

.

C V

2

7

2

8

5 1

8 0

.

.

.

.

6 0

.

.

.

.

.

-

.

4 1

3 1

t s o C

(

6 1

3 4 1

6 1

9 3

0 3 4 2

e

8 2 2

r e n o

7 1 6

l

3 2 0 2

e s a h c r u P

s n o

b a

i t i t

i

r e

3 1

3 7 6 1

7 1

0 1

7 2

4 3

0 2

3 7 -

2 6

6

i t c e

S. No. Source Net Generation (MU) Projections of Energy Quantum Power Purchase Cost - Fixed Cost (FC) (Rs. Cr) Power Purchase Cost - Variable Cost (VC) Total Power Purchase Cost - (Rs. Cr)
Projections (FC Rs. Cr.) Projections (VC- Rs. Cr.) Projections (FC+VC) Rs. Cr.
2022-23 2023-24 2024- 25 2022- 23 2023- 24 2024- 25 2022- 23 2023- 24 2024- 25 2022- 23 2023- 24 2024- 25
A Central Sector Power Stations
I NTPC 3628.75 3483.08 3484.48 3485.41 422.80 426.62 430.62 612.98 617.33 621.66 1035.79 1043.95 1052.28
1 KSTPS 1627.27 1572.89 1573.40 1573.74 102.21 102.21 102.21 224.59 228.53 232.51 326.8 330.74 334.72
2 VSTPS - I 261.6 252.86 252.94 252.99 22.76 22.76 22.76 39.85 39.87 39.88 62.62 62.63 62.64
3 VSTPS - II 110.31 106.62 106.66 106.68 7.35 7.35 7.35 16.14 16.14 16.15 23.49 23.49 23.5
4 VSTPS -III 104.32 100.83 100.87 100.89 9.58 9.58 9.58 15.14 15.15 15.15 24.72 24.73 24.73
5 VSTPS-IV 112.18 108.44 108.47 108.49 17.5 17.5 17.5 16.14 16.15 16.15 33.64 33.64 33.65
6 VSTPS-V 56.39 54.5 54.52 54.53 8.76 8.76 8.76 8.36 8.36 8.36 17.12 17.12 17.12
7 KGPP 17.74 17.15 17.15 17.16 7.53 7.53 7.53 2.63 2.63 2.63 10.15 10.16 10.16
8 GGPP 13.45 13 13.01 13.01 9.71 9.71 9.71 2.18 2.18 2.18 11.89 11.89 11.89
9 SIPAT- I 223.04 215.58 215.65 215.7 26.91 26.91 26.91 30.83 30.84 30.84 57.74 57.75 57.76
11 KSTPS-VII 53.48 55.33 55.35 55.36 6.69 6.69 6.69 7.73 7.85 7.96 14.41 14.53 14.65
14 RSTPS 612.22 563.73 564.19 564.49 47.98 47.98 47.98 142.98 143.1 143.17 190.96 191.08 191.15
15 SIPAT- II 94.59 91.43 91.46 91.48 11.52 11.52 11.52 13.6 13.71 13.82 25.13 25.24 25.34
16 Solapur 59.6 57.61 57.63 57.64 25.48 25.48 25.48 20.08 20.08 20.09 45.56 45.57 45.57
17 Gadarwara 61.3 59.25 59.27 59.28 33.78 35.47 37.25 16.36 16.37 16.37 50.15 51.84 53.62
18 Lara 53.61 51.82 51.84 51.85 18.46 19.38 20.35 10.99 10.99 10.99 29.45 30.37 31.34
19 Khargone 65.92 63.71 63.73 63.75 24 25.2 26.46 17.39 17.39 17.4 41.39 42.59 43.85
20 Mouda I 54.85 53.01 53.03 53.04 21.14 21.14 21.14 14.49 14.5 14.5 35.63 35.64 35.64
21 Mouda II 46.86 45.3 45.31 45.32 21.43 21.43 21.43 13.51 13.51 13.51 34.94 34.94 34.95
Add/ Less: Other Adjustments -
III NPCIL 222.63 215 215 215 - - - 60.78 62.06 63.39 60.78 62.06 63.39
KAPS 123.48 119.36 119.39 119.42 - - - 27.33 27.34 27.35 27.33 27.34 27.35
TAPS 99.15 95.84 95.87 95.89 - - - 33.44 34.72 36.04 33.44 34.72 36.04
IV Short-Term Purchase -77 -301 -219.39 -19 -73 -52 -19 -73 -52
a) IEX PURCHASE AND SALES -76.55 -300.90 -219.39 - - - -19.07 -73.21 -52.13 -19.07 -73.21 -52.13
A1) IEX PURCHASE
A2) IEX SALES 76.55 300.90 219.39 19.07 73.21 52.13 19.07 73.21 52.13
b) Traders - - - - - -

e P

4 4 4             1
1 1 1             5
OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022

- -

- - - -

.

-

-

1 8

4 7 -

-

-

-

4

.

1 7

7 3

9 7

4 5

2 3

9 3

5 9

.

.

2 2

4 4

8 4

8 4

9 5

9 2

.

.

.

.

.

.

.

r C

.

.

.

.

.

.

1

1 2 .

2 1 5 2

5 3 s

t s o C

4 2 0 2

R

)

- -

- - - -

-

1 8

4 7

5

6 2

0

1 3

5 4

4 2

2 2

2 6

2 3 6 8 1

7 4 4

0 6 2

-

-

-

-

4

.

7 3

5 6

4 5

9 3

5 9

.

.

7 0

2 2

1 9

8 4

3 0

8 4

9 5

9 4

.

.

.

.

.

) r C

.

.

.

.

.

.

.

.

1

1 2 .

2 1 C V + C F

4 2

e s a h c r u P

s

5 3

(

3 2 0 2

R

(

r e

s n o

- -

- - - -

-

w o P

1 8

4 7

5

6 2

0

1 3

1 3

2 1

4 5

5 4

2 3 4 7 1

5 3 4

0 6 2

-

-

-

6 4

2

.

.

.

1 6

5 7

5 7

7 3

9 3

5 9

.

.

8 4

4 8

4 8

.

4 4

4 6

.

.

.

.

.

l

i t c e

6

.

.

.

.

.

1

j

a

1 2

2 1

t

3 2

5 3 2 2 0 2

o r P

o T

-

-

-

1 8

4 7 6 2

5

0

5 1

1 2

1 3

3 1 1

8 6 1

3 0 1

7 5 1

5 2 3

-

-

4

.

1 7

7 3

9 7

4 5

2 3

9 3

5 9

.

.

2 2

4 4

8 4

8 4

9 5

9 2

.

.

.

.

.

.

.

.

.

.

.

.

.

1

) .

-

1 2

2 1 5 2

5 3

)

r C

4 2 0 2

.

s

t s o C

C V

R

(

-

-

-

-

1 8

4 7

5

6 2

0

1 3

5 4

4 2

2 2

2 6

2 3 6 8 1

7 4 4

0 6 2

-

-

4

.

7 3

5 6

4 5

9 3

5 9

.

.

7 0

2 2

1 9

8 4

3 0

8 4

9 5

9 4

.

.

.

.

.

C V

.

.

.

.

.

.

.

.

1

t s o C

(

1 2

2 1 4 2

5 3

e

l

3 2 0 2

e s a h c r u P

s n o

b a

5

6 2

0

1 3

1 3

2 1

4 5

5 4

2 3 4 7 1

5 3 4

0 6 2

S. No. Source Net Generation (MU) Projections of Energy Quantum Power Purchase Cost - Fixed Cost (FC) (Rs. Cr) Power Purchase Cost - Variable Cost (VC) Total Power Purchase Cost - (Rs. Cr)
Projections (FC Rs. Cr.) Projections (VC- Rs. Cr.) Projections (FC+VC) Rs. Cr.
2022-23 2023-24 2024- 25 2022- 23 2023- 24 2024- 25 2022- 23 2023- 24 2024- 25 2022- 23 2023- 24 2024- 25
- - -
V OVER/ UNDER DRAWAL - - - - - - - - -
OVER DRAWAL
UNDER DRAWAL
- - -
VI Banking of Power - - - - - - - - -
- - -
B Within State Generations - - -
I CO- GENERATION 150 150 150 35.95 35.95 35.95 35.95 35.95 35.95
Vedanta Plant-1 90.88 90.88 90.88 - - - 21.81 21.81 21.81 21.81 21.81 21.81
Vedanta Plant -2 53.10 53.10 53.10 - - - 12.74 12.74 12.74 12.74 12.74 12.74
Goa Sponge and private limited 5.81 5.81 5.81 - - - 1.39 1.39 1.39 1.39 1.39 1.39
- - -
C RPO Obligation 776 1,134 1,191 325.64 435.49 447.29 325.64 435.49 447.29
- - -
Solar 367.77 421.42 478.14 168.2 174.91 186.71 168.2 174.91 186.71
NVVNL Solar 12 - - - 6.6 - - 6.6 - -
Solar STOA 244.64 117.53 48 - - - 113.75 54.65 22.32 113.75 54.65 22.32
SECI Solar 48 48 48 - - - 26.4 26.4 26.4 26.4 26.4 26.4
CONVERGENCE SOLAR 43.36 86.72 173.45 15.61 31.22 62.44 15.61 31.22 62.44
Net Metering 19.76 39.52 79.04 5.84 12.03 24.79 5.84 12.03 24.79
PM KUSUM 16.64 16.64 - 5.07 5.22 - 5.07 5.22
SECI Hybrid (Solar) 113 113 45.54 45.54 45.54 45.54
Non-Solar 408.63 712.38 712.38 157.44 260.59 260.59 157.44 260.59 260.59
Non Solar - SECI Wind Tranche II LTOA 112.42 112.42 112.42 - - - 31.37 31.37 31.37 31.37 31.37 31.37
STOA (Non Solar) 220.25 - - 103.84 - - 103.84 - -
SECI Tranche-VI 75 112 112 21.75 32.48 32.48 21.75 32.48 32.48
Hindustan waste treatment plant 0.96 0.96 0.96 - - - 0.48 0.48 0.48 0.48 0.48 0.48
OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022

- -

.

-

-

6 2

.

r C

.

5 2

s

6 9 1 t s o C

4 2 0 2

R

)

- -

-

9 6

.

1 8 7 1

4 3 2

-

-

6 2

.

) r C

.

C V + C F

4 2

e s a h c r u P s

6 9 1

(

3 2 0 2

R

(

r e

s n o

- -

-

1 9

.

2 3 7 1

7 2 2

-

-

w o P

l

i t c e

j

a

t

3 2

2 2 0 2

o r P

o T

-

6 2

.

) .

-

5 2

6 9 1

)

r C

4 2 0 2

.

s

t s o C

C V

R

(

-

-

6 2

.

C V

t s o C (

4 2

6 9 1 e

l

3 2 0 2

e s a h c r u P

s n o

b a

-

-

6 3

.

0 6 6 1

1 2 2

9 6

.

1 5 3 1

4 3 2

1 9

.

6 0 3 1

7 2 2

S. No. Source Net Generation (MU) Projections of Energy Quantum Power Purchase Cost - Fixed Cost (FC) (Rs. Cr) Power Purchase Cost - Variable Cost (VC) Total Power Purchase Cost - (Rs. Cr)
Projections (FC Rs. Cr.) Projections (VC- Rs. Cr.) Projections (FC+VC) Rs. Cr.
2022-23 2023-24 2024- 25 2022- 23 2023- 24 2024- 25 2022- 23 2023- 24 2024- 25 2022- 23 2023- 24 2024- 25
Goa
SECI Hybrid (Non-Solar) 487 487 196.26 196.26 196.26 196.26
D REC Certificates - - -
- - -
E OTHER CHARGES - - -
PGCIL Transmission Charges, Wheeling, Open Access & Trading Margin & Other Charges 221.36 227.91 234.69 221.36 227.91 234.69
- - -
F Total 4548 4682 4822 423 427 431 1238 1306 1351 1660 1732 1781

2 2 0 2

n o

)

i t

t

e

N

U M

(

d o

a r e n e G

i r e P

l

o r t

s e t n o C

d

a c

) r a T Y

l

i r b y

M

o S

H

e c r u o S

d r

-

i f i t r e C

3

I

e h

t

n o N

a o G

C E S (

C E R

r o

f

.

.

D

S

R R A

o N

g n

i

r e h

t

n o

n e p O

i

O

,

d a r T

s s

,

&

i

&

g n

n

m

i

i l

L

l

I

a

t

e e h

g r a

s s e c c

R E H T O

S E G R A H C

C G P

s n a r T

s e g r a h C W A M

s e g r a h C

o T

F E94 OFFICIAL GAZETTE — GOVT. OF GOA ARR for the 3rd MYT Control Period Joint Electricity Regulatory Commission (JERC) SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022

(cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:182)(cid:86)(cid:3)(cid:68)(cid:81)(cid:68)(cid:79)(cid:92)(cid:86)(cid:76)(cid:86)

5.6.1. Power Purchase Quantum

The power purchase quantum for the 3rd Control Period was approved in the Business Plan Order dated 31st March 2022. The approved power purchase quantum is given in the following table:

Table 17: Power purchase quantum at state periphery approved by the Commission for the 3rd

Control Period

Sr. No. Source Power Purchase (MUs)
MYT Projections
2022-23 2023-24 2024-25
A Central Sector Power Stations
I NTPC 3,445.35 3,446.72 3,447.63
1 KSTPS 1,572.93 1,573.44 1,573.77
2 VSTPS - I 252.69 252.77 252.83
3 VSTPS - II 106.61 106.65 106.67
4 VSTPS -III 100.82 100.85 100.87
5 VSTPS-IV 108.45 108.49 108.51
6 VSTPS-V 54.51 54.53 54.54
7 KGPP 17.14 17.15 17.15
8 GGPP 13.01 13.01 13.01
9 SIPAT- I 215.64 215.71 215.76
10 KSTPS-VII 51.69 51.71 51.72
11 RSTPS 535.92 536.36 536.64
12 SIPAT- II 91.43 91.46 91.48
13 Solapur 55.46 55.48 55.49
14 Gadarwara 59.20 59.22 59.23
15 Lara 51.84 51.86 51.87
16 Khargone 64.15 64.17 64.19
17 Mouda I 51.27 51.29 51.30
18 Mouda II 42.56 42.58 42.59
Add/ Less: Other Adjustments -
III NPCIL 215.19 215.26 215.31
KAPS 119.36 119.39 119.42
TAPS 95.84 95.87 95.89
IV Traders 139.59 (72.42) 22.44
a) IEX PURCHASEAND SALES 139.59 (72.42) 22.44
a) IEX PURCHASE
a) IEX SALES (139.59) 72.42 (22.44)
b) Traders - - -
B Within State Generations
I CO- GENERATION 149.79 149.79 149.79
Vedanta Plant-1 90.88 90.88 90.88
Vedanta Plant -2 53.10 53.10 53.10
Goa Sponge and private limited 5.81 5.81 5.81
C RPO Obligation 776.40 1,133.80 1,190.52
Solar 367.77 421.42 478.14
NVVNL Solar 12.00
Solar STOA 244.64 117.53 48.00
SECI Solar 48.00 48.00 48.00
CONVERGENCE SOLAR 43.36 86.72 173.45
Net Metering 19.76 39.52 79.04
PM KUSUM 16.64 16.64
SECI Hybrid (Solar) 113.00 113.00
Non-Solar 408.63 712.38 712.38
Non Solar - SECI Wind Tranche II LTOA 112.42 112.42 112.42
STOA (Non Solar) 220.25 - -
SECI Tranche-VI 75.00 112.00 112.00
Hindustan waste treatment plant Goa 0.96 0.96 0.96
SECI Hybrid (Non-Solar) 487.00 487.00
D REC Certificates
F Total 4,726.31 4,873.15 5,025.69
95 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 43 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022 ARR for the 3rd MYT Control Period Joint Electricity Regulatory Commission (JERC)

5.6.2. Power Purchase Cost

The Commission has computed the power purchase cost for the 3rd MYT Control Period based on the following assumptions:

Variable Charges:

The variable charges for the existing plants have been considered based on the provisional actual cost submitted by the Petitioner for FY 2020-21. For Central generating Stations, the Commission has considered an annual escalation of 4% on the actual variable costs of the FY 2020-21, for each year from FY 2022-23to FY 2024-25.

For the remaining plants, the Commission has accepted the variable charges submitted by the Petitioner.

Fixed Charges:

The fixed charges for the existing plants have been considered based on the actual cost submitted by the Petitioner for FY 2020-21. For Central generating Stations, the Commission has considered an annual escalation of 2% on the actual fixed costs of the FY 2020-21, for each year from FY 2022-23to FY 2024-25. For the remaining plants, the Commission has accepted the fixed charges submitted by the Petitioner.

Other Charges:

Other charges have not been considered for the 3rd MYT Control Period. The same shall be considered as per actuals during the true-up of the respective years of the 3rd MYT Control Period.

5.6.3. Transmission Charges

The Commission has projected the transmission charges payable to PGCIL based on the total capacity of the transmission network allocated to the Petitioner. The transmission charges are determined based on the latest quarterly Point of Connection (PoC) rates approved by the Central Electricity Regulatory Commission (CERC).

5.6.4. Total power purchase quantum and cost

The power purchase cost approved by the Commission forthe 3rd MYT Control Period have been shown in the following tables:

96 OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022

1 5

3 1

3 1

1 4

7 6

7 4

5 4

3 2

6 4

9 3

4 6

- - -

6 1

5 2

2 3

2 4

9 2

2 4

.

.

.

2 9

.

.

.

.

. .

.

.

3 6

5 8

4 0

9 0

4 7

.

9 2

.

. .

.

.

.

.

5 2

-

5 1

3 1

9 2

6 6

7 7

4 1

0 4

0 3

0 2

.

.

.

.

.

0

7 4

7 5

0 1

2 4

6 3

6 3

0 5

8 2

3 2 2

8 6 3

8 9 1

,

t s o C

1

4 2 0 2

2 1

7 2 4 3

9 3

2 7

1

)

- - -

3 1

8 1

1 0

5 5

7 6

3 9

9 2

2 9

2 4

9 4

4 8

6 0

4 0

.

9 9

.

7 2

2 9

6 9

5 0

0 8

.

3 9

.

.

.

.

.

.

. . .

.

.

.

.

4 2

-

4 1

3 1

4 6 .

.

.

.

3 2

.

.

) 3 2

.

.

3 3

7 2

5 1

9 1

4 7

9 2

8 3

8 2

5 1 2

6 5 3

e s a h c r u P

0 6 1

,

1

r e

3 2 0 2

w o P

7 1 1 4

5 3

9 4

6 5

7 3

4 3

5 4

2 3

9 6

(

2 3 (

- - -

1 7

9 1

7 7

1 9

7 4

7 4

5 2

9 5

4 5

9 2

l

2 9

.

9 1

9 7

3 7

6 5

5 6

2 3

2 9

8 4

8 8

.

.

.

.

6 2

. .

.

.

.

.

.

.

3 2

a

-

t

3 1

7 3

2 6

2 3

2 2

.

. .

. .

.

.

.

.

.

.

6 2

9 1

4 1

2 1

2 7

7 2

8 2

8 0 2

4 4 3

4 2 1

,

o T

1

d o

2 2 0 2

i

r e P

-

7 1

6 1

7 5

7 4

6 5 2 3

7 4

4 5

3 3

3 3

6 3

4 4

0 6

9 3

7 6

0 6

- - -

-

-

5 1

5 7

5 2

3 2

2 9

9 9

0 3

0 3

9 0

0 8

.

.

3 8

.

.

l

.

6 6

4 4

4 0

.

.

.

.

.

.

.

.

.

.

.

7

7

7

9

0 1

8 1

.

.

.

4 3

2 1

4 2

0 1

8 2

0 5 5 2

8 0 1

o r t

4 4 4

4 2 0 2

n o C

-

1 1

2 1

0 1

7 9

2 9

4 3

2 2

8 1

4 2

7 2

2 2

- - -

-

-

1 5

8 7

9 2

9 9

6 9

4 6

3 8

8 6

0 2

0 0

.

.

.

.

.

.

8 4

0 3

0 0

.

.

.

.

.

.

.

.

.

.

t s o C

9

7 9

7

6 .

.

.

1 1

0 1

8 1

9 4

3 2

8 2 4 2

6 0 1

6 3 4

T Y M

3 2 0 2

d e x

i

d r

F

3

-

7 7

6 2

8 1

3 2

3 3

2 2

2 2

- - -

-

-

1 3

5 7

5 4

2 2

5 8

6 2

4 9

4 9

9 4

2 8

8 6

0 9

6 5

.

6 5

3 9

9 9

2 8

6 8

.

.

.

.

.

.

.

.

.

.

. .

.

9

.

.

. .

.

Sr. No. Source Power Purchase at State Periphery (MUs) Variable Cost Fixed Cost Total Power Purchase Cost
2022-23 2023-24 2024-25 2022-23 2023-24 2024-25 2022- 23 2023- 24 2024- 25 2022-23 2023-24 2024-25
A Central Sector Power Stations
I NTPC 3,445.35 3,446.72 3,447.63 696.70 724.88 754.09 427.56 436.11 444.83 1,124.26 1,160.99 1,198.92
1 KSTPS 1,572.93 1,573.44 1,573.77 240.04 249.72 259.76 104.26 106.34 108.47 344.29 356.06 368.23
2 VSTPS - I 252.69 252.77 252.83 49.25 51.24 53.30 23.22 23.68 24.16 72.47 74.92 77.46
3 VSTPS - II 106.61 106.65 106.67 19.97 20.78 21.61 7.49 7.64 7.80 27.47 28.42 29.41
4 VSTPS -III 100.82 100.85 100.87 18.76 19.52 20.30 9.77 9.97 10.17 28.54 29.49 30.47
5 VSTPS-IV 108.45 108.49 108.51 19.93 20.73 21.56 17.85 18.20 18.57 37.77 38.93 40.13
6 VSTPS-V 54.51 54.53 54.54 10.31 10.73 11.16 8.94 9.12 9.30 19.25 19.84 20.45
7 KGPP 17.14 17.15 17.15 5.25 5.46 5.68 7.68 7.83 7.99 12.92 13.29 13.67
8 GGPP 13.01 13.01 13.01 4.01 4.17 4.34 9.90 10.10 10.30 13.91 14.27 14.64
9 SIPAT- I 215.64 215.71 215.76 34.71 36.11 37.57 27.45 28.00 28.56 62.17 64.12 66.13
10 KSTPS-VII 51.69 51.71 51.72 7.77 8.09 8.41 6.82 6.96 7.09 14.59 15.04 15.51
11 RSTPS 535.92 536.36 536.64 159.25 165.75 172.47 48.94 49.92 50.92 208.19 215.67 223.39
12 SIPAT- II 91.43 91.46 91.48 14.96 15.56 16.19 11.75 11.99 12.23 26.71 27.55 28.42
13 Solapur 55.46 55.48 55.49 21.79 22.67 23.59 25.99 26.51 27.04 47.79 49.18 50.63
14 Gadarwara 59.20 59.22 59.23 21.91 22.79 23.71 32.82 33.48 34.15 54.73 56.27 57.85
15 Lara 51.84 51.86 51.87 14.26 14.83 15.43 17.93 18.29 18.66 32.19 33.13 34.09
16 Khargone 64.15 64.17 64.19 21.17 22.02 22.91 23.31 23.78 24.25 44.48 45.80 47.16
17 Mouda I 51.27 51.29 51.30 18.31 19.05 19.82 21.56 22.00 22.44 39.88 41.05 42.25
18 Mouda II 42.56 42.58 42.59 15.06 15.66 16.29 21.86 22.30 22.75 36.92 37.96 39.04
Add/ Less: Other Adjustments -
III NPCIL 215.19 215.26 215.31 67.22 69.93 72.74 - - - 67.22 69.93 72.74
KAPS 119.36 119.39 119.42 33.56 34.92 36.32 - - - 33.56 34.92 36.32
TAPS 95.84 95.87 95.89 33.65 35.01 36.42 - - - 33.65 35.01 36.42
IV Traders 139.59 (72.42) 22.44 60.32 (32.23) 10.29 60.32 (32.23) 10.29
a)IEX PURCHASEAND SALES 139.59 (72.42) 22.44 60.32 (32.23) 10.29 - - - 60.32 (32.23) 10.29
a)IEX PURCHASE 139.59 22.44
a)IEX SALES (72.42)
b) Traders - - - - - -
- - -
V OVER/ UNDER DRAWAL - - - - - - - - -
OVER DRAWAL

e h

OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022

- - - -

-

-

-

-

- - -

-

1 8

1 7

7 3

4 7

9 7

4 5

2 3

6 2

9 3

9 2

2 2

4 4

8 4

8 4

0 4

5 9

9 5

9 2

.

8 4

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

5 2

1

5

0

-

1 2

1 3

2 1

4 2

5 4

2 2

2 6

2 3

6 2

5 3

6 9 1

5 3 2

6 8 1

7 4 4

0 6 2

0 0 0

, t s o C

2 4 2 0 2

- - - -

-

-

-

-

- - -

-

1 8

7 3

4 7

4 5

5 6

2 2

6 2

9 3

7 0

1 9

8 4

8 4

8 6

3 0

0 4

5 9

9 5

9 4

.

.

.

.

0 8

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

4 2

1

5

0

-

1 2

1 3

2 1

1 3

2 1

4 5

5 4

2 3

6 2

5 3

6 9 1

0 3 2 e s a h c r u P

4 7 1

5 3 4

0 6 2

0 0 9

,

1 r e

3 2 0 2

- - - -

-

-

-

- - -

- w o P

5 1

1 6

5 7

1 8

5 7

7 3

4 7

9 3

l

8 4

4 8

4 8

0 6

0 4

3 5

.

5 9

.

4 4

.

4 6

.

.

0 2

.

.

.

.

.

.

.

.

.

.

.

.

.

3 2

a

1

5

6

0

-

5 1

t

1 2

1 2

1 3

2 1

6 2

3 1 1

5 3

6 2 2

3 0 1

7 5 1

8 6 1

5 2 3

9 3 8 o T

,

1 2 2 0 2

-

- - -

- - -

-

-

-

3 8

.

5 2

4 4 4 4 2 0 2

-

- - -

- - -

-

-

-

1 1

.

t s o C

4 2

6 3 4 3 2 0 2

d e x

Sr. No. Source Power Purchase at State Periphery (MUs) Variable Cost Fixed Cost Total Power Purchase Cost
2022-23 2023-24 2024-25 2022-23 2023-24 2024-25 2022- 23 2023- 24 2024- 25 2022-23 2023-24 2024-25
UNDER DRAWAL
- - -
VI Banking of Power - - - - - - - - -
- - -
B Within State Generations - - -
I CO- GENERATION 149.79 149.79 149.79 35.95 35.95 35.95 35.95 35.95 35.95
Vedanta Plant-1 90.88 90.88 90.88 21.81 21.81 21.81 - - - 21.81 21.81 21.81
Vedanta Plant -2 53.10 53.10 53.10 12.74 12.74 12.74 - - - 12.74 12.74 12.74
Goa Sponge and private limited 5.81 5.81 5.81 1.39 1.39 1.39 - - - 1.39 1.39 1.39
- - -
C RPO Obligation 776.40 1,133.80 1,190.52 325.64 435.49 447.29 325.64 435.49 447.29
- - -
Solar 367.77 421.42 478.14 168.20 174.91 186.71 168.20 174.91 186.71
NVVNL Solar 12.00 6.60 - - - - - 6.60 - -
Solar STOA 244.64 117.53 48.00 113.75 54.65 22.32 - - - 113.75 54.65 22.32
SECI Solar 48.00 48.00 48.00 26.40 26.40 26.40 - - - 26.40 26.40 26.40
CONVERGENCE SOLAR 43.36 86.72 173.45 15.61 31.22 62.44 15.61 31.22 62.44
Net Metering 19.76 39.52 79.04 5.84 12.03 24.79 5.84 12.03 24.79
PM KUSUM 16.64 16.64 - 5.07 5.22 - 5.07 5.22
SECI Hybrid (Solar) 113.00 113.00 45.54 45.54 45.54 45.54
Non-Solar 408.63 712.38 712.38 157.44 260.59 260.59 157.44 260.59 260.59
Non Solar - SECI Wind Tranche II LTOA 112.42 112.42 112.42 31.37 31.37 31.37 - - - 31.37 31.37 31.37
STOA (Non Solar) 220.25 - - 103.84 - - 103.84 - -
SECI Tranche-VI 75.00 112.00 112.00 21.75 32.48 32.48 21.75 32.48 32.48
Hindustan waste treatment plant Goa 0.96 0.96 0.96 0.48 0.48 0.48 - - - 0.48 0.48 0.48
SECI Hybrid (Non-Solar) 487.00 487.00 196.26 196.26 196.26 196.26
D REC Certificates - - -
- - -
E OTHER CHARGES - - -
PGCIL Transmission Charges, Wheeling, Open Access & Trading Margin & Other Charges 226.15 230.68 235.29 226.15 230.68 235.29
- - -
F Total 4,726.31 4,873.15 5,025.69 1,411.97 1,464.69 1,555.65 427.56 436.11 444.83 1,839.53 1,900.80 2,000.48
ARR for the 3rd MYT Control Period Joint Electricity Regulatory Commission (JERC) OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022

The Average Power Purchase Cost (APPC) for the FY 2022-23 has been determined as provided in the table below. The APPC has been computed at the UT Periphery excluding the transmission charges and cost of purchase of renewable energy. The Petitioner shall use the same for the purpose of compensation/ payment of surplus power at the end of each settlement period in case of Solar Net-metering consumers.

Particular FY 2022-23
Total Power Purchase Cost (INR Cr) 1839.53
Less: Transmission charges and Power Purchase cost from renewable energy sources (INR Cr) 551.79
Net Power Purchase Cost (INR Cr) (A) 1287.74
Total Power Purchase quantum (MU) 4726.31
Less: Quantum from renewable energy sources (MU) 776.40
Quantum of energy at State Periphery excluding quantum from renewable energy sources (MU) (B) 3949.92
APPC (INR/kWh) (A/B) 3.26

The Commission approves the Average Power Purchase Cost (APPC) as INR3.26/ kWh for the

FY 2022-23 for the purpose of compensation/payment for excess generation for prosumers.

5.6.5. Energy Balance

(cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:54)(cid:88)(cid:69)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)

The Petitioner has submitted the energy balance as shown in the following table:

Particulars Energy Balance
FY 2021-22 FY 2022-23 FY 2023-24 FY 2024-25
Energy sales within the State/UT 3,931.70 4,086.29 4,214.18 4,346.69
Distribution losses
% 10.25% 10.15% 10.00% 9.85%
MU 449.02 461.61 468.24 474.93
Energy required at State Periphery 4,380.72 4,547.90 4,682.42 4,821.62
Total Energy available at State Periphery 4,380.72 4,547.90 4,682.42 4,821.62

(cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:182)(cid:86)(cid:3)(cid:68)(cid:81)(cid:68)(cid:79)(cid:92)(cid:86)(cid:76)(cid:86)

Based on the Energy sales, Power Procurement and Inter & Intra-State Loss as approved above the Energy Balance for the 3rd MYT Control Period has been shown in following table:

Particulars Approved Projections
FY 2022-23 FY 2023-24 FY 2024-25
Energy Required
Energy sales within the State (A) 4,241.87 4,385.84 4,535.68
T&D Loss (%) (B) 10.25% 10.00% 9.75%
Energy required at State Periphery (C = A/(1- B)) 4,726.31 4,873.15 5,025.69
Within State Generation (Co-Gen) (D) 149.79 149.79 149.79
Net energy required at State Periphery (E = C ± D) Energy Available 4,576.53 4,723.37 4,875.90
Central Generating Stations including UI over/under drawl (F) 3,660.55 3,661.99 3,662.94
Renewable Power (G) 776.40 1,133.80 1,190.52
Energy available at State Periphery (H = F + G) 4,436.94 4,795.78 4,853.46
(Sale)/ Purchase in Open Market (I = E - H) 139.59 (72.42) 22.44
Net energy available at State Periphery (J = H + I) 4,576.53 4,723.37 4,875.90
99 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 47 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022 ARR for the 3rd MYT Control Period Joint Electricity Regulatory Commission (JERC)

5.6.6. Renewable Purchase Obligation

(cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:54)(cid:88)(cid:69)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81):

The Petitioner has submitted it envisages to meet its RPO obligation through purchase of physical renewable power and may even exceed the RPO obligations as cheap power is available in the market, in comparison to the conventional sources. Further, for the upcoming Control Period, since the Commission has not yet approved any trajectory, ED-Goa has assumed a 1% increase in Solar and Non-Solar RPO every year and has accordingly considered the projections for RPO fulfilment. Further, after considering all the proposed tied-up renewable energy, ED-Goa proposes to meet any shortfall to fulfil the RPO obligation, through purchase from short term (Traders) through DEEP portal and GTAM. For projection of ED-Goa does not plan to buy any REC during the upcoming MYT Control Period. Accordingly, the Petitioner has submitted its RPO plan for FY 2021-22 and the upcoming Control Period as follows:

Sl. No. Description Unit Revised Projections Projections
FY 2021-22 FY 2022-23 FY 2023-24 FY 2024-25
1 Sales Within State MUs 3,931.70 4,086.29 4,214.18 4,346.69
2 RPO Obligation %
- Solar % 8.00% 9.00% 10.00% 11.00%
- Non Solar % 9.00% 10.00% 11.00% 12.00%
3 RPO Obligation MUs
- Solar MUs 314.54 367.77 421.42 478.14
- Non Solar MUs 353.85 408.63 463.56 521.60
4 Power Purchase MUs
- Solar MUs 314.54 367.77 421.42 478.14
- Non Solar Mus 353.85 408.63 712.38 712.38

(cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:182)(cid:86)(cid:3)(cid:68)(cid:81)(cid:68)(cid:79)(cid:92)(cid:86)(cid:76)(cid:86):

The Commission has approved the Renewable Purchase Obligation (RPO) for the 3rd Control Period considering the JERC (Procurement of Renewable Energy) Regulations, 2010, as amended from time to time.

The cumulative backlog of solar and non-solar compliance up to FY 2020-21 has been considered as per the (cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:182)(cid:86)(cid:3) (cid:50)(cid:85)(cid:71)(cid:72)(cid:85)(cid:3) (cid:82)(cid:81)(cid:3) (cid:87)(cid:75)(cid:72)(cid:3) (cid:54)(cid:88)(cid:82) Moto Petition No. 61/2012 dated 5th July 2021. The solar and non-solar compliance for FY 2021-22 is considered as per the RPO compliance approved in the Tariff Order for FY 2021- 22 dated 30th March 2021. Accordingly, the RPO approved by the Commission for the 3rd MYT Control Period is as follows:

Table 23: Renewable Purchase Obligation (RPO) approved by the Commission for 3rd MYT

Control Period

Particulars FY 2022-23 FY 2023-24 FY 2024-25
Sales within State (MU) (A) 4241.87 4385.84 4535.68
Hydro Power available at State Periphery (MU) (B) - - -
T&D Loss (%) (C) 10.25% 10.00% 9.75%
T&D Loss (MU) (D = B * C) 0.00 0.00 0.00
Hydro Power Consumed (E = B - D) 0.00 0.00 0.00
Conventional Power Consumed (F = A - E) 4241.87 4385.84 4535.68
RPO obligation (%) 18.35% 19.91% 21.58%
Solar (G) 9.00% 10.00% 11.00%
Non-Solar (H) 9.35% 9.91% 10.58%
RPO obligation for the year (MU) 778.38 873.22 978.80
Solar (F * G) 381.77 438.58 498.93
Non-Solar (F * H) 396.61 434.64 479.88
RPO Compliance from Physical Power (MU) 776.40 1133.80 1190.52
Solar 367.77 421.42 478.14
Non-Solar 408.63 712.38 712.38
Standalone RPO Compliance Backlog (MU) 14.00 17.17 20.79
Solar 14.00 17.17 20.79
Non-Solar - - -
Cumulative RPO Compliance Backlog (MU) 391.41 361.47 382.26
Solar 344.30 361.47 382.26
Non-Solar 47.10 - -
100 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 48 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022 ARR for the 3rd MYT Control Period Joint Electricity Regulatory Commission (JERC)

5.7. Operation & Maintenance Expenses

The Operation & Maintenance Expenses comprise of the Employee Expenses, Administrative and General Expenses (A&G) and the Repair & Maintenance Expenses (R&M). Regulation 61 of the JERC MYT Regulation, 2021 states the following:

(cid:179)61.1 The Operation and Maintenance Expenses for the Retail Supply Business shall be computed

inaccordance with this Regulation.

61.2 O&M Expenses shall comprise of the following:

a) Employee expenses - salaries, wages, pension contribution and other employee costs;

b) Administrative and General expenses including insurance charges if any; and

c) Repairs and Maintenance expenses.

61.3 The Licensee shall submit the required O&M expenses for the Control Period as a part of MultiYear Tariff

Petition. O&M expenses for the base Year shall be approved by the Commissiontaking into account the latest

available audited accounts, business plan filed by the DistributionLicensee, estimates of the actuals for the

Base Year, prudence check and any other factorsconsidered appropriate by the Commission.

61.4 O&M expenses for the nth Year of the Control Period shall be approved based on the formulagiven below:

O&Mn = (R&Mn + EMPn + A&Gn) x (1 - Xn) + Terminal Liabilities

Where,

R&Mn = K x GFAn-1 x (1+WPIinflation)

101 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 49 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022 ARR for the 3rd MYT Control Period Joint Electricity Regulatory Commission (JERC)

EMPn = (EMPn-1) x (1+Gn) x (1+CPIinflation)

A&Gn = (A&Gn-1) x (1+CPIinflation)

(cid:181)(cid:46)(cid:182)(cid:3) (cid:76)(cid:86)(cid:3) (cid:68)(cid:3) (cid:70)(cid:82)(cid:81)(cid:86)(cid:87)(cid:68)(cid:81)(cid:87)(cid:3) (cid:11)(cid:72)(cid:91)(cid:83)(cid:85)(cid:72)(cid:86)(cid:86)(cid:72)(cid:71)(cid:3) (cid:76)(cid:81)(cid:3) (cid:8)(cid:12)(cid:17)(cid:3) (cid:57)(cid:68)(cid:79)(cid:88)(cid:72)(cid:3) (cid:82)(cid:73)(cid:3) (cid:46)(cid:3) (cid:73)(cid:82)(cid:85)(cid:3) (cid:72)(cid:68)(cid:70)(cid:75)(cid:3) (cid:60)(cid:72)(cid:68)(cid:85)(cid:3) (cid:82)(cid:73)(cid:3) (cid:87)(cid:75)(cid:72)(cid:3) (cid:38)(cid:82)(cid:81)(cid:87)(cid:85)(cid:82)(cid:79)(cid:3) (cid:51)(cid:72)(cid:85)(cid:76)(cid:82)(cid:71)(cid:3) (cid:86)(cid:75)(cid:68)(cid:79)(cid:79)(cid:3) (cid:69)(cid:72)(cid:71)(cid:72)(cid:87)(cid:72)(cid:85)(cid:80)(cid:76)(cid:81)(cid:72)(cid:71)(cid:3) (cid:69)(cid:92)(cid:3) (cid:87)(cid:75)(cid:72)(cid:3)

(cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:3) (cid:76)(cid:81)(cid:3) (cid:87)(cid:75)(cid:72)(cid:3) (cid:48)(cid:88)(cid:79)(cid:87)(cid:76)(cid:3) (cid:60)(cid:72)(cid:68)(cid:85)(cid:3) (cid:55)(cid:68)(cid:85)(cid:76)(cid:73)(cid:73)(cid:3) (cid:50)(cid:85)(cid:71)(cid:72)(cid:85)(cid:3) (cid:69)(cid:68)(cid:86)(cid:72)(cid:71)(cid:3) (cid:82)(cid:81)(cid:3) (cid:47)(cid:76)(cid:70)(cid:72)(cid:81)(cid:86)(cid:72)(cid:72)(cid:182)(cid:86)(cid:3) (cid:73)(cid:76)(cid:79)(cid:76)(cid:81)(cid:74)(cid:15)(cid:69)(cid:72)(cid:81)(cid:70)(cid:75)(cid:80)(cid:68)(cid:85)(cid:78)(cid:76)(cid:81)(cid:74)(cid:3) (cid:82)(cid:73)(cid:3) (cid:85)(cid:72)(cid:83)(cid:68)(cid:76)(cid:85)(cid:3) (cid:68)(cid:81)(cid:71)(cid:3)

maintenance expenses, approved repair and maintenance expensesvis-à-vis GFA approved by the

Commission in past and any other factor considered appropriateby the Commission;

CPIinflation (cid:177) is the average increase in Consumer Price Index (CPI) for immediately precedingthree (3)

Years before the base Year;

WPIinflation (cid:177) is the average increase in the Wholesale Price Index (CPI) for immediatelypreceding three (3)

Years before the base Year;

EMPn (cid:177) Employee expenses of the Distribution Licensee for the nth Year;

A&Gn (cid:177) Administrative and General expenses of the Distribution Licensee for the nth Year;

R&Mn (cid:177) Repair and Maintenance expenses of the Distribution Licensee for the nth Year;

GFAn-1 (cid:177) Gross Fixed Asset of the Distribution Licensee for the n-1th Year;

Xn is an efficiency factor for nth Year. Value of Xn shall be determined by the Commission in theMulti Year

(cid:55)(cid:68)(cid:85)(cid:76)(cid:73)(cid:73)(cid:3)(cid:50)(cid:85)(cid:71)(cid:72)(cid:85)(cid:3)(cid:69)(cid:68)(cid:86)(cid:72)(cid:71)(cid:3)(cid:82)(cid:81)(cid:3)(cid:47)(cid:76)(cid:70)(cid:72)(cid:81)(cid:86)(cid:72)(cid:72)(cid:182)(cid:86)(cid:3)(cid:73)(cid:76)(cid:79)(cid:76)(cid:81)(cid:74)(cid:15)(cid:3)(cid:69)(cid:72)(cid:81)(cid:70)(cid:75)(cid:80)(cid:68)(cid:85)(cid:78)(cid:76)(cid:81)(cid:74)(cid:15)(cid:3)(cid:68)(cid:83)(cid:83)(cid:85)(cid:82)(cid:89)(cid:72)(cid:71)(cid:3)(cid:70)(cid:82)(cid:86)(cid:87)(cid:3)(cid:69)(cid:92)(cid:3)(cid:87)(cid:75)(cid:72)(cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:3)(cid:76)(cid:81)(cid:3)(cid:83)(cid:68)(cid:86)(cid:87)(cid:3)(cid:68)(cid:81)(cid:71)(cid:3)(cid:68)(cid:81)(cid:92)(cid:3)(cid:82)(cid:87)(cid:75)(cid:72)(cid:85)(cid:3)

factor the Commission feels appropriate;

Gn is a growth factor for the nth Year. Value of Gn shall be determined by the Commission foreach Year in the

(cid:48)(cid:88)(cid:79)(cid:87)(cid:76)(cid:3) (cid:60)(cid:72)(cid:68)(cid:85)(cid:3) (cid:55)(cid:68)(cid:85)(cid:76)(cid:73)(cid:73)(cid:3) (cid:50)(cid:85)(cid:71)(cid:72)(cid:85)(cid:3) (cid:73)(cid:82)(cid:85)(cid:3) (cid:80)(cid:72)(cid:72)(cid:87)(cid:76)(cid:81)(cid:74)(cid:3) (cid:87)(cid:75)(cid:72)(cid:3) (cid:68)(cid:71)(cid:71)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:68)(cid:79)(cid:3) (cid:80)(cid:68)(cid:81)(cid:83)(cid:82)(cid:90)(cid:72)(cid:85)(cid:3) (cid:85)(cid:72)(cid:84)(cid:88)(cid:76)(cid:85)(cid:72)(cid:80)(cid:72)(cid:81)(cid:87)(cid:3) (cid:69)(cid:68)(cid:86)(cid:72)(cid:71)(cid:82)(cid:81)(cid:3) (cid:47)(cid:76)(cid:70)(cid:72)(cid:81)(cid:86)(cid:72)(cid:72)(cid:182)(cid:86)(cid:3) (cid:73)(cid:76)(cid:79)(cid:76)(cid:81)(cid:74)(cid:86)(cid:15)(cid:3)

benchmarking, approved cost by the Commission in past and any otherfactor that the Commission feels

appropriate:

Provided that in case the Licensee has been in operation for less than three (3) Years as on thedate of

effectiveness of these Regulations, the O&M Expenses shall be determined on a case tocase basis.

61.5 Terminal liabilities of employees of Licensee including pension expenses etc. shall be approvedas per

actuals submitted by the Licensee, subject to prudence check or be established throughactuarial studies.

Additionally, any variation due to changes recommended by the paycommission shall be allowed separately

by the Commission, subject to prudence check.

61.6 For the purpose of estimation, the same value of factors (cid:177) CPIinflation and WPIinflation shall be usedfor

all Years of the Control Period. However, the Commission shall consider the actual values ofthe factors (cid:177)

CPIinflation and WPIinflation during the truing up exercise for the Year for which true upis being carried out

and true up the O&M Expenses for that Year, only to the extent of inflation.

Provided that at the time of truing up, the variation in the normative and actual O&M expensesshall be dealt

in accordance with Regulation 15.(cid:180)

5.7.1. Employee Expenses

(cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:54)(cid:88)(cid:69)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)

The Petitioner has determined the employee expenses for each year of the Control Period based on the norms specified in the JERC MYT Regulations, 2021. The Petitioner has considered FY 2021-22 as the base year and the employee expenses for the Base Year FY 2021-22 have been estimated based on the provisional data from FY 2017-18 to FY 2020-21 due to unavailability of audited accounts. For FY 2021-22 (base year), the employee expenses are arrived by escalating the average expenses (FY 2017-18 to FY 2020-21) by CPI inflation. The working for computing employee expenses for the base year is provided in table below:

Particulars FY 2017- 18 FY 2018- 19 FY 2019- 20 FY 2020-21 FY 2021- 22
CPI based on Industrial Workers, All India 284.42 299.92 323.50 338.69 351.12
YoY 3.08% 5.45% 7.53% 5.02% 3.67%
3 years average 5.41%
102 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 50 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022 ARR for the 3rd MYT Control Period Joint Electricity Regulatory Commission (JERC)

Table 25: Calculations of Employee Expenses for base year as submitted by the Petitioner (INR

Crore)

S. No. Particulars Employee Expenses 3-Year Average 3-Year Average FY 2021-22 (Base Year)
FY 2018- 19 FY 2019- 20 FY 2020- 21
(a) (b) (c) (d) = [(a)+(b)+(c)]/3 CPI Inflation (%) (e)
1 Employee Expenses 270.41 294.08 300.81 288.43 5.41% 320.47

The growth factor (Gn) has been Nil for the control period considering the employee strength in the past few years have shown a negative growth trend.The Petitioner has projected the employee expenses for the control period in line with the MYT Regulations 2021 and is provided in the table below:

Particulars Units Base Year MYT Control period
FY 2021- 22 FY 2022- 23 FY 2023- 24 FY 2024- 25
Employee Cost for nth-1 year (A) Rs.Crs 364.31 384.01 404.77
Gn Factor (Y-O-Y) (B) % 0.00% 0.00% 0.00%
CPI Inflation (C ) % 5.41% 5.41% 5.41%
Employee Cost for nth year D= A*(1+B)*(1+C) Rs.Crs 364.31 384.01 404.77 426.65

(cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:182)(cid:86)(cid:3)(cid:68)(cid:81)(cid:68)(cid:79)(cid:92)(cid:86)(cid:76)(cid:86)

In accordance with the JERC MYT Regulations, 2021, the Commission has determined the Employee expenses for each year of the MYT Control Period. The Regulation 6 of the JERC MYT Regulations, 2021 stipulates the following:

(cid:179)(cid:25)(cid:17)(cid:3)(cid:57)(cid:68)(cid:79)(cid:88)(cid:72)(cid:86)(cid:3)(cid:73)(cid:82)(cid:85)(cid:3)(cid:37)(cid:68)(cid:86)(cid:72)(cid:3)(cid:60)(cid:72)(cid:68)(cid:85)

6.1 The values for the Base Year of the Control Period shall be determined on the basis of the audited accounts

or provisional accounts of last three (3) Years, and other factors considered relevant by the Commission:

Provided that, in absence of availability of audited accounts or provisional accounts of last three (3) Years,

the Commission may benchmark the parameters with other similar utilities to establish the values for Base

Year:

Provided further that the Commission may change the values for Base Year and consequently the trajectory of

(cid:83)(cid:68)(cid:85)(cid:68)(cid:80)(cid:72)(cid:87)(cid:72)(cid:85)(cid:86)(cid:3)(cid:73)(cid:82)(cid:85)(cid:3)(cid:38)(cid:82)(cid:81)(cid:87)(cid:85)(cid:82)(cid:79)(cid:3)(cid:51)(cid:72)(cid:85)(cid:76)(cid:82)(cid:71)(cid:15)(cid:3)(cid:70)(cid:82)(cid:81)(cid:86)(cid:76)(cid:71)(cid:72)(cid:85)(cid:76)(cid:81)(cid:74)(cid:3)(cid:87)(cid:75)(cid:72)(cid:3)(cid:68)(cid:70)(cid:87)(cid:88)(cid:68)(cid:79)(cid:3)(cid:73)(cid:76)(cid:74)(cid:88)(cid:85)(cid:72)(cid:86)(cid:3)(cid:73)(cid:85)(cid:82)(cid:80)(cid:3)(cid:68)(cid:88)(cid:71)(cid:76)(cid:87)(cid:72)(cid:71)(cid:3)(cid:68)(cid:70)(cid:70)(cid:82)(cid:88)(cid:81)(cid:87)(cid:86)(cid:17)(cid:180)

The Petitioner has failed to submit the audited accounts for FY 2017-18, FY 2018-19, FY 2019-20 and FY 2020- 21. (cid:44)(cid:81)(cid:3)(cid:85)(cid:72)(cid:86)(cid:83)(cid:82)(cid:81)(cid:86)(cid:72)(cid:3)(cid:87)(cid:82)(cid:3)(cid:87)(cid:75)(cid:72)(cid:3)(cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:182)(cid:86)(cid:3)(cid:84)(cid:88)(cid:72)(cid:85)(cid:92)(cid:3)(cid:85)(cid:72)(cid:74)(cid:68)(cid:85)(cid:71)(cid:76)(cid:81)(cid:74)(cid:3)(cid:86)(cid:88)(cid:69)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:3)(cid:82)(cid:73)(cid:3)(cid:83)(cid:85)(cid:82)(cid:89)(cid:76)(cid:86)(cid:76)(cid:82)(cid:81)(cid:68)(cid:79)(cid:3)(cid:68)(cid:70)(cid:70)(cid:82)(cid:88)(cid:81)(cid:87)(cid:86), the Petitioner vide its reply dated 28.02.2022 has submitted the provisional accounts for FY 2017-18, FY 2018-19 and FY 2019-20.

The Commission has considered the provisional employee expenses from FY 2017-18, FY 2018-19 and FY 2019- 20as follows:

103 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 51 Electricity Department, Government of Goa ARR for the 3rd MYT Control Period Joint Electricity Regulatory Commission (JERC) OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022
Particulars FY 2017-18 FY 2018-19 FY 2019-20
Base Employee Expenses (including impact of 7th Pay Commission Arrears and excluding Terminal Benefits) 326.39 318.78 336.59
Less: Impact of 7th Pay Commission Arrears 30.53 3.96 2.82
Base Employee Expenses 295.86 314.82 333.77
Base Employee Expenses (Avg.) 314.82

The Commission has arrived at the Base Year estimates i.e., forFY 2021-22 of INR357.07 Cr. based on the approved avg. increase in CPI and the growth in no. of employees based on the manpower plan submitted by the Petitioner in the Business Plan Order dated 31st March 2022.The resultant employee expenses of the Base Year have been escalated by Growth Rate determined based on the manpower plan approved in the Business Plan Order, dated 31st March 2022 and the average CPI Inflation of the last three years to arrive upon the employee expenses of each year of the 3rd Control Period.The Terminal Benefits for each year of the 3rd MYT Control Period has been allowed separately based on the average of Terminal Benefits from FY 2017-18 to FY 2019-20 as per the provisional accounts. The same shall be allowed as per actuals during the time of truing up of the respective years. The CPI inflation has been computed as follows:

FY Average of (April ± March) Increase in CPI Index Average increase In CPI indices over 3 year
FY 2017-18 284.42 6.00%
FY 2018-19 299.92 5.45%
FY 2019-20 322.50 7.53%
FY 2020-21 338.68 5.02%

Accordingly, the employee expenses approved by the Commission in the MYT Control Period have been provided in the following table:

Particular Base Year 3rd MYT Control Period
FY 2021-22 FY 2022-23 FY 2023-24 FY 2024-25
Gn (Growth factor as per the Manpower Plan approved in the Business Plan Order) -10.02% -2.94% -2.62%
CPI (3 previous year avg.) (in %) 6.00% 6.00% 6.00%
Base Employee Expenses (INR Cr) 357.07 340.57 350.41 361.70
Terminal Benefits 3.99 3.99 3.99
Total Employee Expenses 344.56 354.39 365.69

The Commission approves Employee Expenses of INR344.56Cr. for the FY 2022-23, INR354.39Cr. for the FY 2023-24 and INR365.69Cr. for the FY 2024-25. However, as the base expenses have been computed on the basis of provisional annual accounts, the trajectory shall be considered again for the 3rd MYT Control Period after the availability of audited annual accounts from FY 2017-18 to FY 2020-21.

5.7.2. Administrative and General (A&G) Expenses

(cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:54)(cid:88)(cid:69)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)

The Petitioner submitted that A&G expenses for each year of the 3rd MYT Control Period has been computed based on the norms specified in the JERC MYT Regulations, 2021 i.e., A&Gn = (A&Gn-1) x (1+CPI inflation).

The Petitioner has considered FY 2021-22 as the base year and has been projected based on the provisional104 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 52 Electricity Department, Government of Goa ARR for the 3rd MYT Control Period Joint Electricity Regulatory Commission (JERC) OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022 A&G expenses of FY 2017-18 to FY 2020-21 as the audited accounts are still under preparation. The average increase in Consumer Price Index (CPI) for the past years has been considered for projecting the A&G expenses and the working for the same is provided in the following tables:

Particulars FY 2017- 18 FY 2018- 19 FY 2019- 20 FY 2020-21 FY 2021- 22
CPI based on Industrial Workers, All India 284.42 299.92 323.50 338.69 351.12
YoY 3.08% 5.45% 7.53% 5.02% 3.67%
3 years average 5.41%
S. No. Particulars A&G Expenses 3-Year Average 3-Year Average FY 2021-22 (Base Year)
FY 2018- 19 FY 2019- 20 FY 2020- 21
(a) (b) (c) (d) = [(a)+(b)+(c)]/3 CPI Inflation (%) (e)
1 A&G Expenses 27.42 23.03 21.47 23.97 5.41% 26.63

The following table provides the A&G expenses projected for each year of the 3rdMYT Control Period along with various parameters considered.

Particulars FY 2022-23 FY 2023-24 FY 2024-25
A&G Expenses of Previous Year (A&Gn-1) 26.63 28.07 29.59
CPI Inflation 5.41% 5.41% 5.41%
A&Gn Expenses 28.07 29.59 31.19

(cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:182)(cid:86)(cid:3)(cid:68)(cid:81)(cid:68)(cid:79)(cid:92)(cid:86)(cid:76)(cid:86)

The Petitioner has failed to submit the audited accounts for FY 2017-18, FY 2018-19, FY 2019-20 and FY 2020- (cid:21)(cid:20)(cid:17)(cid:3)(cid:44)(cid:81)(cid:3)(cid:85)(cid:72)(cid:86)(cid:83)(cid:82)(cid:81)(cid:86)(cid:72)(cid:3)(cid:87)(cid:82)(cid:3)(cid:87)(cid:75)(cid:72)(cid:3)(cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:182)(cid:86)(cid:3)(cid:84)(cid:88)(cid:72)(cid:85)(cid:92)(cid:3)(cid:85)(cid:72)(cid:74)(cid:68)(cid:85)(cid:71)(cid:76)(cid:81)(cid:74)(cid:3)(cid:86)(cid:88)(cid:69)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:3)(cid:82)(cid:73)(cid:3)(cid:83)(cid:85)(cid:82)(cid:89)(cid:76)(cid:86)(cid:76)(cid:82)(cid:81)(cid:68)(cid:79)(cid:3)(cid:68)(cid:70)(cid:70)(cid:82)(cid:88)(cid:81)(cid:87)(cid:86)(cid:15)(cid:3)(cid:87)(cid:75)(cid:72)(cid:3)(cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:3)(cid:89)(cid:76)(cid:71)(cid:72)(cid:3)(cid:76)(cid:87)(cid:86)(cid:3) reply dated 28.02.2022 has submitted the provisional accounts for FY 2017-18, FY 2018-19 and FY 2019-20.

The Commission has considered the provisionalA&G expenses from FY 2017-18 to FY 2019-20as follows:

Particulars As per Prov. A&G Exp.
FY 2017-18 26.62
FY 2018-19 27.42
FY 2019-20 26.91
Avg.A&G expenses 26.98

This is escalated with the avg. CPI to arrive at the Base Year estimates. Thereafter, the Base Year estimate has been escalated by average CPI Inflation of the last three years to determine the A&G expense for each year of the Control Period. The A&G expenses approved by the Commission in the MYT Control Period have been provided in the following table:

Particular Base Year ARR
FY 2021-22 FY 2022-23 FY 2023-24 FY 2024-25
CPI (3 previous year avg.) (in %) 6.00% 6.00% 6.00%
Total A&G Expenses 32.13 34.06 36.11 38.27
105 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 53 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022 ARR for the 3rd MYT Control Period Joint Electricity Regulatory Commission (JERC)

The Commission approves the Administrative & General (A&G) expenses of INR34.06Cr. for the FY 2022-23, INR36.11Cr. for the FY 2023-24 and INR38.27Cr. for the FY 2024-25.However, as the base expenses have been computed on the basis of provisional annual accounts, the trajectory shall be considered again for the 3 rd MYT Control Period after the availability of audited annual accounts from FY 2017-18 to FY 2020-21.

5.7.3. Repair & Maintenance Expenses (R&M)

(cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:54)(cid:88)(cid:69)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)

The R&M expenses for each year of the Control Period has been projected based on the norms specified in the JERC MYT Regulations, 2021 i.e., R&Mn = K x GFAn-1 x (1+WPI inflation). The R&M expenses for the FY 2021-22 have been taken as base. The Petitioner has considered the provisional data for FY 2017-18 to FY 2020-21 to compute the base year FY 2021-22. The average increase in Wholesale Price Index (WPI) for the past years has been considered for projecting the R&M expenses and the working for the same is provided in the following tables:

Particulars FY 2017- 18 FY 2018- 19 FY 2019- 20 FY 2020-21 FY 2021- 22
WPI based on Office of Economic Advisor, GoI 114.88 119.79 121.80 123.38 134.99
YoY 2.92% 4.28% 1.68% 1.29% 9.41%
3 years average 4.13%

The 'K' factor as prescribed in the regulations has been calculated as ratio of R&M and average GFA of the last 3 years. The 'K' factor has been determined as the ratio of R&M to opening GFA for the FY 2018-19, FY 2019-20 and FY 2020-21 and averaged for three years. The 'K' factor has been computed as follows:

S.No. Particulars FY 2019-20 FY 2020-21 FY 2021-22
1 Opening GFA (INR Cr) 1,236.61 1,274.13 1,478.29
2 R&M Expenses (INR Cr) 39.46 43.21 59.62
3 K factor 3.19% 3.39% 4.03%
4 Avg of K factor 3.54%

R&M Expenses have been calculated based on the formula and methodology provided in the Regulations, R&Mn = K x GFAn-1 x (1+WPI inflation).

Particulars FY 2022-23 FY 2023-24 FY 2024-25
GFAn-1 1681.25 2091.64 3410.25
K-Factor 3.54% 3.54% 3.54%
WPI Inflation 4.13% 4.13% 4.13%
R&M Expenses 61.94 77.07 125.65

Commis(cid:86)(cid:76)(cid:82)(cid:81)(cid:182)(cid:86)(cid:3)(cid:68)(cid:81)(cid:68)(cid:79)(cid:92)(cid:86)(cid:76)(cid:86)

106 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 54 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022 ARR for the 3rd MYT Control Period Joint Electricity Regulatory Commission (JERC)

The Petitioner has failed to submit the audited accounts for FY 2017-18, FY 2018-19, FY 2019-20 and FY 2020- (cid:21)(cid:20)(cid:17)(cid:3)(cid:44)(cid:81)(cid:3)(cid:85)(cid:72)(cid:86)(cid:83)(cid:82)(cid:81)(cid:86)(cid:72)(cid:3)(cid:87)(cid:82)(cid:3)(cid:87)(cid:75)(cid:72)(cid:3)(cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:182)(cid:86)(cid:3)(cid:84)(cid:88)(cid:72)(cid:85)(cid:92)(cid:3)(cid:85)(cid:72)(cid:74)(cid:68)(cid:85)(cid:71)(cid:76)(cid:81)(cid:74)(cid:3)(cid:86)(cid:88)(cid:69)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:3)(cid:82)(cid:73)(cid:3)(cid:83)(cid:85)(cid:82)(cid:89)(cid:76)(cid:86)(cid:76)(cid:82)(cid:81)(cid:68)(cid:79)(cid:3)(cid:68)(cid:70)(cid:70)(cid:82)(cid:88)(cid:81)(cid:87)(cid:86)(cid:15)(cid:3)(cid:87)(cid:75)(cid:72)(cid:3)(cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:3)(cid:89)(cid:76)(cid:71)(cid:72)(cid:3)(cid:76)(cid:87)(cid:86)(cid:3) reply dated 28.02.2022 has submitted the provisional accounts for FY 2017-18, FY 2018-19 and FY 2019-20. (cid:55)(cid:75)(cid:72)(cid:3)(cid:181)(cid:46)(cid:182)(cid:3)(cid:73)(cid:68)(cid:70)(cid:87)(cid:82)(cid:85)(cid:3)(cid:75)(cid:68)(cid:86)(cid:3)(cid:69)(cid:72)(cid:72)(cid:81)(cid:3)(cid:71)(cid:72)(cid:87)(cid:72)(cid:85)(cid:80)(cid:76)(cid:81)(cid:72)(cid:71)(cid:3)(cid:68)(cid:86)(cid:3)(cid:87)(cid:75)(cid:72)(cid:3)(cid:85)(cid:68)(cid:87)(cid:76)(cid:82)(cid:3)(cid:82)(cid:73)(cid:3)(cid:53)(cid:9)(cid:48)(cid:3)(cid:87)(cid:82)(cid:3)(cid:82)(cid:83)(cid:72)(cid:81)(cid:76)(cid:81)(cid:74)(cid:3)(cid:42)(cid:41)(cid:36)(cid:3)(cid:73)(cid:82)(cid:85)(cid:3)(cid:87)(cid:75)(cid:72)(cid:3)FY 2017-18, FY 2018-19 and FY 2019-20 (cid:68)(cid:81)(cid:71)(cid:3)(cid:68)(cid:89)(cid:72)(cid:85)(cid:68)(cid:74)(cid:72)(cid:71)(cid:3)(cid:73)(cid:82)(cid:85)(cid:3)(cid:87)(cid:75)(cid:85)(cid:72)(cid:72)(cid:3)(cid:92)(cid:72)(cid:68)(cid:85)(cid:86)(cid:17)(cid:3)(cid:55)(cid:75)(cid:72)(cid:3)(cid:181)(cid:46)(cid:182)(cid:3)(cid:73)(cid:68)(cid:70)(cid:87)(cid:82)(cid:85)(cid:3)(cid:75)(cid:68)(cid:86)(cid:3)(cid:69)(cid:72)(cid:72)(cid:81)(cid:3)(cid:70)(cid:82)(cid:80)(cid:83)(cid:88)(cid:87)(cid:72)(cid:71)(cid:3)(cid:68)(cid:86)(cid:3)(cid:73)(cid:82)(cid:79)(cid:79)(cid:82)ws:

Particulars FY 2017-18 FY 2018-19 FY 2019-20
R&M Expenses 28.01 32.37 29.19
Opening GFA (GFAn-1) 1216.92 1244.46 1286.47
K Factor (%) 2.30% 2.60% 2.27%
K Factor Approved by the Commission (Average of 3 years) (%) 2.39%

(cid:55)(cid:75)(cid:72)(cid:3) (cid:181)(cid:46)(cid:182)(cid:3) (cid:73)(cid:68)(cid:70)(cid:87)(cid:82)(cid:85)(cid:3) (cid:76)(cid:86)(cid:3) (cid:78)(cid:72)(cid:83)(cid:87)(cid:3) (cid:70)(cid:82)(cid:81)(cid:86)(cid:87)(cid:68)(cid:81)(cid:87)(cid:3) (cid:73)(cid:82)(cid:85)(cid:3) (cid:68)(cid:79)(cid:79)(cid:3) (cid:87)(cid:75)(cid:72)(cid:3) (cid:92)(cid:72)(cid:68)(cid:85)(cid:86)(cid:3) (cid:68)(cid:81)(cid:71)(cid:3) (cid:80)(cid:88)(cid:79)(cid:87)(cid:76)(cid:83)(cid:79)(cid:76)(cid:72)(cid:71)(cid:3) (cid:90)(cid:76)(cid:87)(cid:75)(cid:3) (cid:87)(cid:75)(cid:72)(cid:3) (cid:82)(cid:83)(cid:72)(cid:81)(cid:76)(cid:81)(cid:74)(cid:3) (cid:42)(cid:41)(cid:36)(cid:3) (cid:68)(cid:83)(cid:83)(cid:85)(cid:82)(cid:89)(cid:72)(cid:71)(cid:3) (cid:73)(cid:82)(cid:85)(cid:3) (cid:87)(cid:75)(cid:72)(cid:3) (cid:11)(cid:81)-1)th year. The resultant amount is then escalated by WPI Inflation to arrive upon the R&M Expenses for each year of the Control Period. The WPI Inflation has been computed as follows:

FY Average of (April ± March) Increase in WPI Index Average increase In CPI indices over 3 year
FY 2017-18 114.88 2.42%
FY 2018-19 119.79 4.28%
FY 2019-20 121.80 1.68%
FY 2020-21 123.38 1.29%

The R&M expenses approved by the Commission for each year of the 3rdMYT Control Period have been provided in the following table:

Table 39: R&M Expense approved by the Commission for the 3rd MYT Control Period (in INR

Cr.)

Particulars FY 2022-23 FY 2023-24 FY 2024-25
Opening GFA (GFAn-1) 2103.98 3054.90 3778.49
K Factor (%) 2.39% 2.39% 2.39%
Avg. WPI Inflation (%) 2.42% 2.42% 2.42%
R&M Expenses = K x (GFA n-1) x (1+WPIinflation) 55.33 82.28 104.23

The Commission therefore approves the Repair & Maintenance (R&M) expenses of INR55.33Cr. for the FY 2022-23, INR82.28Cr. for the FY 2023-24 and INR104.23Cr. for the FY 2024-25.However, as the K factor has been computed on the basis of provisional annual accounts, the trajectory shall be considered again for the 3rd MYT Control Period after the availability of audited annual accounts from FY 2017-18 to FY 2020-21.

5.7.4. Summary of O&M Expenses

(cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:54)(cid:88)(cid:69)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)

The Summary of O&M expenses as per the Petitioner for each year of the 3rdMYT Control Period have been provided in the following table:

Table 40: Summary of O&M expensessubmitted by the Petitioner for the 3rd MYT Control

Period (in INR Cr.)

Particulars FY 2022-23 FY 2023-24 FY 2024-25
Total Employee Expenses 384.01 404.77 426.65
Total A&G expenses 28.07 29.59 31.19
Total R&M Expenses 61.94 77.07 125.65
Total O&M expenses 474.02 511.43 583.49
107 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 55 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022 ARR for the 3rd MYT Control Period Joint Electricity Regulatory Commission (JERC)

(cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:182)(cid:86)(cid:3)(cid:68)(cid:81)(cid:68)(cid:79)(cid:92)(cid:86)(cid:76)(cid:86):

The Summary of O&M expenses approved by the Commission for each year of the 3rdMYT Control Period have been provided in the following table:

Table 41: Summary of O&M expensesapproved by the Commission for the 3rd MYT Control

Period (in INR Cr.)

Particulars FY 2022-23 FY 2023-24 FY 2024-25
Total Employee Expenses 344.56 354.39 365.69
Total A&G expenses 34.06 36.11 38.27
Total R&M Expenses 55.33 82.28 104.23
Total O&M expenses 433.95 472.78 508.20

5.8. Gross Fixed Assets (GFA) and Capitalization

(cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:54)(cid:88)(cid:69)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)

The Petitioner submitted that they have considered the capital expenditure for the control period as per thie submission of capital expenditure plan in the Business Plan Petition. The details of the capital expenditure and capitalisation as proposed by the Petitioner for the 3rd Control Period is as under:

Table 42: Capital Expenditure submitted by the Petitioner for the 3rd MYT Control Period(INR

Cr)

Sl. No. Name of scheme FY 2022- 23 FY 2022- 23 FY 2022- 23
Projected Projected Projected
Existing Schemes
A1 Schedule Tribe Development Scheme (P) 55.86 28.83 -
A2 Infrastructure development through Electricity Duty (Plan) 107.78 39.01 -
A3 Erection and Augmentation of 33/11 KV S/S line (Plan) 5.00 5.00 5.00
A4 Normal Development Schemes (Plan) 6.00 6.00 6.00
A5 System Improvement Schemes (Plan) 17.23 3.00 3.00
A6 Construction of staff quarters and office buildings (Plan) 21.00 26.00 15.00
A7 Strengthening of 220 KV Transmission Network 15.00 - -
A8 Erection of 220/110/33/11 KV Sub-Station at Verna (New) - - -
A9 Restructured Accelerated Power Development and Reforms Programme Part A 18.00 18.00 18.00
A10 Underground Cabling 141.50 57.00 -
A11 R-APDRP Part B / IPDS 15.00 - -
A12 EHV new Transmission / Sub-Station / Capacitor banks schemes - - -
B1 Smart grid Development of existing network - - -
B2 Sub-transmission and distribution improvement scheme 57.00 2.00 -
Other Schemes
Public Lighting Scheme 0.10 - -
Sub- Total (existing schemes) 459.47 184.84 47.00
New Schemes
A Projects with Administrative approval 93.37 77.73 19.25
B Projects Approved by EFC 414.72 103.68 -
C Projects tendered (To start next year) 103.94 62.00 6.00
D New EHV Works 90.86 163.34 270.00
E REVAMPED Distribution Projects 255.00 450.00 225.00
F Sub-Total New Schemes 957.90 856.75 520.25
G DEPOSIT WORKS 35.37 - -
Sub- Total (New Schemes) 993.27 856.75 520.25
GRAND TOTAL 1,452.74 1,041.59 567.25
Sr. No. Particulars Projections
Capitalisation
FY 2022-23 FY 2023-24 FY 2024-25
A Existing Schemes 574.07 253.94 67.00
B New Schemes 744.54 739.91 850.25
C Deposit Works 53.37 - -
Total 1,371.98 993.85 917.25
108 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 56 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022 ARR for the 3rd MYT Control Period Joint Electricity Regulatory Commission (JERC)

(cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:182)(cid:86)(cid:3)(cid:68)(cid:81)(cid:68)(cid:79)(cid:92)(cid:86)(cid:76)(cid:86):

The Commission considered the Capital expenditure and capitalization as approved by the Commission in the Business Plan Order dated 31st March 2022. The following table provides the summary of capital expenditure and capitalization now approved by the Commission (a more detailed description of the capital expenditure plan is given in the Business Plan section of this Order):

Table 44: Capital Expenditure & Capitalisation considered by the Commission for 3rd Control

Period (INRCr.)

Particular FY 2022-23 FY 2023-24 FY 2024-25
Total Capital Expenditure 997.35 728.59 256.25
Total Capitalisation 950.92 723.59 406.25

5.9. Capital Structure

(cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:54)(cid:88)(cid:69)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)

The Petitioner has proposed the following funding plan for the capital expenditure proposed for the 3 rd control period:

Sl.N o. Sources of Funds FY 2022-23 FY 2023-24 FY 2024-25 Total
A Total Capital Expenditure (without deposit works) 1417.37 1041.59 567.25 3026.21
B Electricity Duty Fund 638.05 345.79 282.70 1266.54
C Grant 165.50 270.25 135.25 571.00
D Total Capital Expenditure (excluding Electricity Duty Fund and Grant) (A-B-C) 613.82 425.55 149.30 1188.67
E Debt (%) 70% 70% 70% 70%
F Equity (%) 30% 30% 30% 30%
G Normative Debt (D x E) 429.67 297.89 104.51 832.07
H Equity (INR Cr) (D x F) 184.15 127.67 44.79 356.60
109 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 57 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022 ARR for the 3rd MYT Control Period Joint Electricity Regulatory Commission (JERC)

The Petitioner has also provided the calculation of net GFA/Capitalisation after removal of grant and electricity duty portion, as depreciation, Interest on loan and return on equity is not allowed on the assets created through grants and electricity duty fund or any subsidy. The details are provided in the following table:

S. No. Particulars FY 2022-23 FY 2023-24 FY 2024-25
1 Total Capitalisation 1318.61 993.85 917.25
2 Less: 60% and 75% Grant Component of APDRP Part-B / IPDS scheme 13.20 0.00 0.00
3 Less: Revamped Scheme (15% Grant Prepaid Meter; 100% for DBM, billing modules etc; 60% for SCADA) 113.50 379.25 329.25
4 Less: Schemes out of ED Fund 156.78 39.01 0.00
5 Net Capitalisation excluding grant 1035.13 575.59 588.00
6 Debt (%) 70% 70% 70%
7 Equity (%) 30% 30% 30%
8 Normative Loan 724.59 402.91 411.60
9 Normative Equity 310.54 172.68 176.40

(cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:182)(cid:86)(cid:3)(cid:68)(cid:81)(cid:68)(cid:79)(cid:92)(cid:86)(cid:76)(cid:86)

Regulation 27 of the JERC MYT Regulations, 2021 specifies the following:

(cid:179)27.1 In case of Existing Projects, debt to equity ratio allowed by the Commission for determination of tariff

for the period ending March 31, 2022 shall be considered:

Provided that in case of retirement or replacement or De-capitalisation of the assets, the equity capital

approved as mentioned above, shall be reduced to the extent of 30% (or actual equity component based on

documentary evidence, if it is lower than 30%) of the original cost of such assets:

Provided further that in case of retirement or replacement or De-capitalisation of the assets, the debt capital

approved as mentioned above, shall be reduced to the extent of outstanding debt component based on

documentary evidence, or the normative loan component, as the case may be, of the original cost of such

assets.

27.2 For New Projects, the debt-equity ratio as on the Date of Commercial Operation shall be 70:30 of the

amount of capital cost approved by the Commission under Regulation 24, after prudence check for

determination of tariff:

Provided that where equity actually deployed is less than 30% of the capital cost of the capitalised asset, the

actual equity shall be considered for determination of tariff:

Provided also that if the equity actually deployed is more than 30% of the capital cost, equity in excess of 30%

shall be treated as a normative loan for the Licensee for determination of tariff:

Provided also that the Licensee shall submit documentary evidence for the actual deployment of equity and

explain the source of funds for the equity:

110 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 58 Electricity Department, Government of Goa ARR for the 3rd MYT Control Period Joint Electricity Regulatory Commission (JERC) OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022

Provided also that the equity invested in foreign currency shall be designated in Indian rupees on the date of

each investment:

Provided further that the premium, if any, raised by the Licensee while issuing share capital and investment

of internal resources created out of its free reserves, for the funding of the scheme,

shall be reckoned as paid up capital for the purpose of computing return on equity, provided such premium

amount and internal resources are actually utilised for meeting the capital expenditure of the transmission

system or the distribution system, and are within the ceiling of 30% of capital cost approved by the

Commission.

27.3 Any expenditure incurred or projected to be incurred on or after April 1, 2022, as may be admitted by the

Commission, as additional capital expenditure for determination of tariff, and renovation and modernisation

expenditure for life extension shall be serviced in the manner specified in these Regulations(cid:180)

The Petitioner has failed submit the Petition for True-up for FY 2017-18, FY 2018-19, FY 2019-20 and FY 2020- 21 based on annual audited accounts. The Commission has therefore considered actual trued up closing values of GFA, loan and equity approved for FY 2016-17 and the provisional/estimated figures of capitalisation and funding breakup in capitalisation schedule submitted by the Petitioner for FY 2017-18 (provisional), FY 2018-19 (provisional), FY 2019-20 (provisional), FY 2020-21 (provisional) and FY 2021-22 (estimated) to arrive at the opening values of GFA, loan and equity for FY 2022-23. The provisional values considered shall be trued up based on audited annual accounts during the True-up of respective years. The reconciliation of Capital Structure, GFA, normative loan and normative equity from FY 2017-18 to FY 2021-22 and that approved by the Commission for the 3rdMYT Control Periodare shown in the following tables:

S. No Particulars Reconciliation based on provisional information submitted by the Petitioner Approved for 3rd MYT Control Period
FY 17-18 FY 18- 19 FY 19- 20 FY 20- 21 FY 21- 22 FY 22- 23 FY 23- 24 FY 24- 25
1 Total Capitalisation 27.54 42.01 204.16 202.96 410.39 950.92 723.59 406.25
2 Less Capitalisation through Grant & Consumer Contribution 5.61 18.72 185.80 151.05 216.90 719.38 473.35 237.95
Electricity Duty Fund 5.57 18.48 158.08 130.31 159.07 571.31 218.10 12.70
Grant & Consumer Contribution 0.04 0.24 27.72 20.74 57.83 148.07 255.25 225.25
3 Net Capitalisation excluding Electricity Duty Fund & Govt. Grants 21.93 23.29 18.36 51.91 193.49 231.55 250.24 168.30
4 Debt (%) 70% 70% 70% 70% 70% 70% 70% 70%
5 Equity (%) 30% 30% 30% 30% 30% 30% 30% 30%
6 Normative Loan 15.35 16.30 12.85 36.34 135.44 162.08 175.17 117.81
7 Normative Equity 6.58 6.99 5.51 15.57 58.05 69.46 75.07 50.49

Table 48: GFA (including GFA addition through Electricity Duty Fund, Govt. Grants and

Consumer Contribution) considered by the Commission for 3rdMYT Control Period (INRCr.)

Sl. No. Particulars Reconciliation based on provisional information submitted by the Petitioner Approved for 3rd MYT Control Period
FY 17- 18 FY 18- 19 FY 19- 20 FY 20- 21 FY 21- 22 FY 22- 23 FY 23- 24 FY 24- 25
1 Opening Gross Fixed Assets 1,216.92 1,244.46 1,286.47 1,490.63 1,693.59 2,103.98 3,054.90 3,778.49
2 Addition During the FY 27.54 42.01 204.16 202.96 410.39 950.92 723.59 406.25
3 Adjustment/Retire ment During the FY - - - - - - - -
4 Closing Gross Fixed Assets 1,244.46 1,286.47 1,490.63 1,693.59 2,103.98 3,054.90 3,778.49 4,184.74
111 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 59 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA ARR for the 3rd MYT Control Period Joint Electricity Regulatory Commission (JERC) SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022

Table 49: GFA (excluding GFA addition through Electricity Duty Fund, Govt. Grants and

Consumer Contribution) considered by the Commission for 3rdMYT Control Period (INRCr.)

Sl. No. Particulars Reconciliation based on provisional information submitted by the Petitioner Approved for 3rd MYT Control Period
FY 17- 18 FY 18- 19 FY 19- 20 FY 20- 21 FY 21- 22 FY 22- 23 FY 23- 24 FY 24- 25
1 Opening Gross Fixed Assets 952.90 974.83 998.12 1,016.48 1,068.40 1,261.89 1,493.43 1,743.67
2 Addition During the FY 21.93 23.29 18.36 51.91 193.49 231.55 250.24 168.30
3 Adjustment/Retire ment During the FY - - - - - - - -
4 Closing Gross Fixed Assets 974.83 998.12 1,016.48 1,068.40 1,261.89 1,493.43 1,743.67 1,911.97

Table 50: Reconciliation of normative loan up to FY 2021-22 based on provisional information

submitted by the Petitioner (INRCr.)

S. No Particulars FY 17-18 FY 18-19 FY 19-20 FY 20-21 FY 21-22
1 Opening Normative Loan 242.21 202.14 161.71 136.07 132.58
2 Add: Normative Loan During the year 15.35 16.30 12.85 36.34 135.44
3 Less: Normative Repayment 55.43 56.73 38.49 39.83 44.52
4 Closing Normative Loan 202.14 161.71 136.07 132.58 223.50

Table 51: Reconciliation of normative equity up to FY 2021-22 based on provisional information

submitted by the Petitioner (INRCr.)

S. No Particulars FY 17-18 FY 18-19 FY 19-20 FY 20-21 FY 21-22
1 Opening Equity 286.46 293.04 300.03 305.54 321.11
2 Add: Equity During the year 6.58 6.99 5.51 15.57 58.05
3 Closing Equity 293.04 300.03 305.54 321.11 379.16

5.10. Depreciation

(cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:54)(cid:88)(cid:69)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)

The Petitioner submitted that the closing GFA of the FY 2021-22 as arrived at APR has been considered as opening GFA of the FY 2022-23. Further, depreciation for each year has been computed on average Gross Fixed Assets (GFA) after considering the net addition proposed during each year.

112 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 60 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022 ARR for the 3rd MYT Control Period Joint Electricity Regulatory Commission (JERC)

The Petitioner submitted that total depreciation is calculated asset block wise on the total GFA. However, since depreciation on assets created through grants, electricity duty fund or subsidies are not allowed as per Regulations. Hence, Depreciation for the GFA excluding grant and electricity duty fund arrived in the proportion of total GFA and GFA excluding grant and electricity duty fund.

Based on the methodology given in MYT Regulations, depreciation for the 3rd MYT Control Period is submitted as under:

No. Particulars FY 2022-23 FY 2023-24 FY 2024-25
1 Opening Gross Fixed Assets (excluding Grants/ consumers Contribution etc) 1357.51 2392.63 2968.22
2 Add: Gross Asset Addition 1318.61 993.85 917.25
3 Less: Contribution from Subsidies/ Grants/ Beneficiaries' Contribution / Consumers Contribution 283.48 418.26 329.25
4 Value of Asset eligible for depreciation 1035.13 575.59 588.00
5 Add: Addition During the Year 1035.13 575.59 588.00
6 Less: Decapitalisation - - -
7 Closing Gross Fixed Assets (excluding Grants/ consumers Contribution etc.) 2392.63 2968.22 3556.22
8 Average Gross Fixed Assets (excluding Grants/ consumers Contribution etc.) 1875.07 2680.43 3262.22
9 Weighted Average Rate of Depreciation (%) 4.56% 4.56% 4.56%
10 Depreciation for the year 85.51 122.24 148.77

(cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:182)(cid:86)(cid:3)(cid:68)(cid:81)(cid:68)(cid:79)(cid:92)(cid:86)(cid:76)(cid:86)

Regulation 31 of the JERC MYT Regulations, 2021 stipulates the following:

(cid:179)(cid:22)(cid:20)(cid:17)(cid:20)(cid:3) (cid:55)(cid:75)(cid:72)(cid:3) (cid:89)(cid:68)(cid:79)(cid:88)(cid:72)(cid:3) (cid:69)(cid:68)(cid:86)(cid:72)(cid:3) (cid:73)(cid:82)(cid:85)(cid:3) (cid:87)(cid:75)(cid:72)(cid:3) (cid:83)(cid:88)(cid:85)(cid:83)(cid:82)(cid:86)(cid:72)(cid:3) (cid:82)(cid:73)(cid:3) (cid:71)(cid:72)(cid:83)(cid:85)(cid:72)(cid:70)(cid:76)(cid:68)(cid:87)(cid:76)(cid:82)(cid:81)(cid:3) (cid:86)(cid:75)(cid:68)(cid:79)(cid:79)(cid:3) (cid:69)(cid:72)(cid:3) (cid:87)(cid:75)(cid:72)(cid:3) (cid:70)(cid:68)(cid:83)(cid:76)(cid:87)(cid:68)(cid:79)(cid:3) (cid:70)(cid:82)(cid:86)(cid:87)(cid:3) (cid:82)(cid:73)(cid:3) (cid:87)(cid:75)(cid:72)(cid:3) (cid:68)(cid:86)(cid:86)(cid:72)(cid:87)(cid:3) (cid:68)(cid:71)(cid:80)(cid:76)(cid:87)(cid:87)(cid:72)(cid:71)(cid:3) (cid:69)(cid:92)(cid:3) (cid:87)(cid:75)(cid:72)(cid:3)

Commission:

Provided that the depreciation shall be allowed after reducing the approved original cost of the retired or

replaced or decapitalized assets:

Provided also that the no depreciation shall be allowed on the assets financed through consumer contribution,

deposit work, capital subsidy or grant.

31.2 The salvage value of the asset shall be considered as 10% and depreciation shall be allowed up to a

maximum of 90% of the capital cost of the asset.

Provided further that the salvage value of Information Technology equipment and computer software shall be

considered at zero (0) per cent of the allowable capital cost.

31.3 Land other than the land held under lease shall not be a depreciable asset and its cost shall be excluded

from the capital cost while computing depreciable value of the assets.

31.4 In case of existing assets, the balance depreciable value as on April 1, 2022, shall be worked out by

deducting the cumulative depreciation as admitted by the Commission up to March 31, 2021, from the gross

depreciable value of the assets.

31.5 The depreciation shall be chargeable from the first Year of commercial operations. In case of projected

commercial operation of the assets during the Year, depreciation shall be computed based on the average of

113 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 61 Electricity Department, Government of Goa ARR for the 3rd MYT Control Period Joint Electricity Regulatory Commission (JERC) OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022

opening and closing value of assets:

Provided that depreciation shall be re-calculated during truing-up for assets capitalised at the time of truing

up of each Year of the Control Period, based on documentary evidence of asset capitalised by the Applicant,

subject to the prudence check of the Commission.

31.6 For Transmission Licensee, the depreciation shall be calculated at rates and norms specified in the

prevalent CERC Tariff Regulations for transmission system.

31.7 The depreciation for a Distribution Licensee shall be calculated annually, based on the Straight Line

Method, over the Useful Life of the asset at rates specified in Appendix I of these Regulations.

31.8 In addition to allowable depreciation, the Distribution Licensee shall be entitled to advance against

depreciation (AAD), computed in the manner given hereunder:

AAD = Loan (raised for capital expenditure) repayment amount based on loan repayment tenure,

subject to a ceiling of 1/10th of loan amount minus depreciation as calculated on the basis of these

Regulations:

Provided that advance against depreciation shall be permitted only if the cumulative repayment upto a

particular Year exceeds the cumulative depreciation upto that Year:

Provided further that advance against depreciation in a Year shall be restricted to the extent of difference

between cumulative repayment and cumulative depreciation upto that Year.

31.9 The Distribution Licensee shall provide the list of assets added during each Year of Control Period and list

of assets completing 90% of depreciation in the Year along with Petition for annual performance review, true-

up and tariff determination for ensuing Year.

31.10 The remaining depreciable value for a Distribution Licensee shall be spread over the balance useful life

(cid:82)(cid:73)(cid:3)(cid:87)(cid:75)(cid:72)(cid:3)(cid:68)(cid:86)(cid:86)(cid:72)(cid:87)(cid:15)(cid:3)(cid:82)(cid:81)(cid:3)(cid:85)(cid:72)(cid:83)(cid:68)(cid:92)(cid:80)(cid:72)(cid:81)(cid:87)(cid:3)(cid:82)(cid:73)(cid:3)(cid:87)(cid:75)(cid:72)(cid:3)(cid:72)(cid:81)(cid:87)(cid:76)(cid:85)(cid:72)(cid:3)(cid:79)(cid:82)(cid:68)(cid:81)(cid:17)(cid:180)

The Commission has derived the weighted average rate of depreciation based on the asset wise depreciation rate prescribed in JERC MYT Regulations, 2021, provided in the following table:

Table 53: Asset-wise depreciation rate considered by the Commission for weighted average rate

for 3rd MYT Control Period (%)

Description of Assets Rate of Depreciation
Land & Land Rights 0.00%
Buildings 1.80%
Plant & Machinery 3.60%
Transformer 3.60%
Lines & Cables (HT & LT) 3.60%
Vehicles 18.00%
Furniture & Fixtures 6.00%
Office Equipment 6.00%
IT Equipment 15.00%
Testing & Measuring Equipment 6.00%
SCADA P&M 6.00%

The opening GFA of the FY 2022-23 is considered as discussed in section5.9 of this Order. As discussed in the preceding section, GFA addition through Electricity Duty Fund, Govt. Grants and Consumer Contribution have been excluded for the computation of Depreciation. Further, depreciation for each year has been computed on average Gross Fixed Assets (GFA) after considering the net addition approved during each year. The GFA of assets that have completed 90% depreciation but still included in the GFA have not been excluded for the computation of Depreciation due to unavailability of requisite data. Accordingly, the Commission shall consider the same during the True-up of the respective years.

The following table provides the calculation of depreciation during the 3rdMYT Control Period.

114 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 62 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022 ARR for the 3rd MYT Control Period Joint Electricity Regulatory Commission (JERC)
Particular FY 2022-23 FY 2023-24 FY 2024-25
Opening Gross Fixed Assets 1261.89 1493.43 1743.67
Addition During the FY 231.55 250.24 168.30
Adjustment/Retirement during the FY 0.00 0.00 0.00
Closing Gross Fixed Assets 1493.43 1743.67 1911.97
Average Gross Fixed Assets 1377.66 1618.55 1827.82
Weighted Avg. rate of Depreciation (%) 3.82% 3.82% 3.82%
Depreciation 52.64 61.84 69.84

The Commission approves a depreciation of INR 52.64Cr. for the FY 2022-23, INR61.84Cr. for the FY 2023-24 and INR69.84Cr. for the FY 2024-25.

5.11. Interest on Loan

(cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:54)(cid:88)(cid:69)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)

Petitioner has considered the normative loan addition during the year. Repayment of the loan has been considered equivalent to the depreciation for the respective years in line with the JERC MYT Regulations, 2021.

The interest rate has been calculated based on the one (1) Year State Bank of India (SBI) MCLR as on 1st April

plus 100 basis point to project the interest on normative loans for the Control Period.Other finance charges incurred by the Petitioner shall be claimed based on actuals during true-up for the respective years.

The following table provides the normative Interest on Loan projected for the 3rd MYT Control Period based on JERC MYT regulations, 2021 as under.

Table 55: Interest on Normative Loan submitted by the Petitioner for the 3rd MYT Control

Period (INR Cr)

Sr. No. Particulars Projection
FY 2022-23 FY 2023-24 FY 2024-25
1 Opening Normative Loan 241.74 880.82 1161.49
2 Add: Normative Loan during the Year/GFA during the year 724.59 402.91 411.60
3 Less: Normative Repayment 85.51 122.24 148.77
4 Closing Normative Loan 880.82 1161.49 1424.32
4 Average Normative Loan 561.28 1021.15 1292.91
5 Rate of Interest (@SBI 1 Year MCLR rate+100 Basis Points) 8.00% 8.00% 8.00%
6 Interest on Normative Loan 44.90 81.69 103.43
7 Other Finance Charges - - -
8 Total Interest & Finance Charges 44.90 81.69 103.43

(cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:182)(cid:86)(cid:3)(cid:68)(cid:81)(cid:68)(cid:79)(cid:92)(cid:86)(cid:76)(cid:86):

Regulation 29 of the JERC MYT Regulation, 2021 states the following:

(cid:179)(cid:21)(cid:28)(cid:17)(cid:20)(cid:3) (cid:55)(cid:75)(cid:72) loans arrived at in the manner indicated in Regulation 27 on the assets put to use, shall be

considered as gross normative loan for calculation of interest on the loan:

Provided that interest and finance charges on capital works in progress shall be excluded:

115 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 63 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022 ARR for the 3rd MYT Control Period Joint Electricity Regulatory Commission (JERC)

Provided further that in case of De-capitalisation or retirement or replacement of assets, the loan capital shall

be reduced to the extent of outstanding loan component of the original cost of the decapitalized or retired or

replaced assets, based on documentary evidence.

29.2 The normative loan outstanding as on April 1, 2022, shall be worked out by deducting the cumulative

repayment as admitted by the Commission up to March 31, 2021, from the gross normative loan.

29.3 Notwithstanding any moratorium period availed by the Transmission Licensee or the Distribution

Licensee, as the case may be, the repayment of loan shall be considered from the first Year of commercial

operation of the project and shall be equal to the annual depreciation allowed in accordance with Regulation

31.

29.4 The rate of interest shall be the weighted average rate of interest calculated on the basis of the actual

loan portfolio at the beginning of each Year applicable to the Transmission Licensee or the Distribution

Licensee:

Provided that at the time of truing up, the weighted average rate of interest calculated on the basis of the

actual loan portfolio during the Year applicable to the Transmission Licensee or the Distribution Licensee

shall be considered as the rate of interest after prudence check:

Provided also that if there is no actual loan for a particular Year but normative loan is still outstanding, the

last available weighted average rate of interest for the actual loan shall be considered:

Provided further that if the Transmission Licensee or the Distribution Licensee does not have actual loan, then

one (1) Year State Bank of India (SBI) MCLR / any replacement thereof as notified by RBI for the time being

in effect applicable for one (1) Year period, as may be applicable as on 1st April of the relevant Year plus 100

basis points shall be considered as the rate of interest for the purpose of allowing the interest on the

normative loan.

29.5 The interest on loan shall be calculated on the normative average loan of the Year by applying the

weighted average rate of interest:

Provided that at the time of truing up, the normative average loan of the Year shall be considered on the basis

of the actual asset capitalisation approved by the Commission for the Year.

29.6 For new loans proposed for each Financial Year of the Control Period, interest rate shall be considered as

lower of (i) one (1) Year State Bank of India (SBI) MCLR / any replacement thereof as notified by RBI for the

time being in effect applicable for one (1) Year period, as may be applicable as on 1st April of the relevant

Year plus 100 basis points, and (ii) weighted average rate of interest proposed by the Distribution Licensee.

29.7 The above interest computation shall exclude the interest on loan amount, normative or otherwise, to the

extent of capital cost funded by consumer contribution, deposit work, capital subsidy or grant, carried out by

Transmission Licensee or Distribution Licensee.

29.8 The finance charges incurred for obtaining loans from financial institutions for any Year shall be

allowed by the Commission at the time of Truing-up, subject to prudence check.

29.9 The excess interest during construction on account of time and/or cost overrun as compared to the

approved completion schedule and capital cost or on account of excess drawal of the debt funds

disproportionate to the actual requirement based on Scheme completion status, shall be allowed or disallowed

partly or fully on a case to case basis, after prudence check by the Commission:

Provided that where the excess interest during construction is on account of delay attributable to an agency

or contractor or supplier engaged by the Transmission or Distribution Licensee, any liquidated damages

116 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 64 Electricity Department, Government of Goa ARR for the 3rd MYT Control Period Joint Electricity Regulatory Commission (JERC) OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022

recovered from such agency or contractor or supplier shall be taken into account for computation of capital

cost:

Provided further that the extent of liquidated damages to be considered shall depend on the amount of excess

interest during construction that has been allowed by the Commission.

29.10 The Transmission Licensee or the Distribution Licensee, as the case may be, shall make every effort to

re-finance the loan as long as it results in net savings on interest and in that event the costs associated with

such re-financing shall be borne by the beneficiaries and the net savings shall be shared between the equally

between the beneficiaries; i.e., the Transmission Licensee and the Distribution Licensee or the Distribution

(cid:47)(cid:76)(cid:70)(cid:72)(cid:81)(cid:86)(cid:72)(cid:72)(cid:3)(cid:68)(cid:81)(cid:71)(cid:3)(cid:87)(cid:75)(cid:72)(cid:3)(cid:38)(cid:82)(cid:81)(cid:86)(cid:88)(cid:80)(cid:72)(cid:85)(cid:86)(cid:3)(cid:82)(cid:73)(cid:3)(cid:39)(cid:76)(cid:86)(cid:87)(cid:85)(cid:76)(cid:69)(cid:88)(cid:87)(cid:76)(cid:82)(cid:81)(cid:3)(cid:47)(cid:76)(cid:70)(cid:72)(cid:81)(cid:86)(cid:72)(cid:72)(cid:17)(cid:180)

As the Petitioner only has normative loan and no actual loan i.e., no fixed assets in operation which are funded through loans, the Commission has considered the SBI 1 Year MCLR rate as on 1st April 2021, plus 100 basis points as Rate of Interest, in accordance with the JERC MYT Regulations, 2021.

The Interest on Loan has been calculated on the average loan during the year with the opening loan for the first year of the 3rd MYT Control Period considered as discussed in section 5.9 of this Order. Further, the normative loan addition during each year of the control period has been considered as per the capital structure approved in section 5.9 of this Order.

Repayment of the loan has been considered equivalent to the depreciation for the respective years as determined by the Commission in line with the JERC MYT Regulations, 2021.

The following table provides the Interest on Loan approved by the Commission for the 3rd Control Period.

Particular FY 2022-23 FY 2023-24 FY 2024-25
Opening Normative Loan 223.50 332.94 446.27
Add: Normative Loan During the year 162.08 175.17 117.81
Less: Normative Repayment= Depreciation 52.64 61.84 69.84
Closing Normative Loan 332.94 446.27 494.24
Average Normative Loan 278.22 389.61 470.25
Rate of Interest (%) 8.00% 8.00% 8.00%
Interest on Loan 22.26 31.17 37.62

The Commission approves Interest on Loan as INR22.26Cr. for the FY 2022-23, INR31.17Cr. for the FY 2023- 24 and INR37.62Cr. for the FY 2024-25.

5.12. Return on Equity (RoE)

(cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:54)(cid:88)(cid:69)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)

The Petitioner has segregated the proposed average equity (average of opening and closing equity) into average equity for Distribution Wires Business and Retail Supply Business based on the Allocation Statement provided in the JERC MYT Regulations, 2021 i.e., 90% allocation for the Distribution Wires Business and 10% allocation for the Retail Supply Business. Further, the opening equity for FY 2022-23 is taken as per closing normative equity for FY 2021-22.

In accordance with the Regulation 28.2 of the JERC MYT Regulations 2021, the Petitioner has considered a post-tax rate of 15.50% for the Distribution Wires Business (as per the prevalent CERC Regulations).

117 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 65 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022 ARR for the 3rd MYT Control Period Joint Electricity Regulatory Commission (JERC)

Further, in accordance with the Regulation 28.3 of the JERC MYT Regulations, 2021, the Petitioner has considered return on equity at the rate of 16% for the Retail Supply Business.

S. No Particulars Projection
FY 2022-23 FY 2023-24 FY 2024-25
1 Opening Balance of Equity 393.53 704.06 876.74
2 Equity Addition during year (30% of Capitalization) 310.54 172.68 176.40
3 Closing Balance of Equity 704.06 876.74 1053.14
4 Average Equity Amount 548.80 790.40 964.94
5 Average Equity-Wires Business (90%) 493.92 711.36 868.45
6 Average Equity -Retail Supply Business (10%) 54.88 79.04 96.49
7 Return on Equity for Wires Business (%) 15.50% 15.50% 15.50%
8 Return on Equity for Retail Supply Business (%) 16.00% 16.00% 16.00%
9 Return on Equity for Wires Business 76.56 110.26 134.31
10 Return on Equity for Retail Supply Business 8.78 12.65 15.44
11 Total Return on Equity 85.34 122.91 150.05

(cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:182)(cid:86)(cid:3)(cid:68)(cid:81)(cid:68)(cid:79)(cid:92)(cid:86)(cid:76)(cid:86):

Regulation 28 of the JERC MYT Regulation, 2021 states the following:

(cid:179)(cid:21)(cid:27)(cid:17)(cid:20)(cid:3) (cid:53)(cid:72)(cid:87)(cid:88)(cid:85)(cid:81)(cid:3) (cid:82)(cid:81)(cid:3) (cid:72)(cid:84)(cid:88)(cid:76)(cid:87)(cid:92)(cid:3) (cid:86)(cid:75)(cid:68)(cid:79)(cid:79)(cid:3) (cid:69)(cid:72)(cid:3) (cid:70)(cid:82)(cid:80)(cid:83)(cid:88)(cid:87)(cid:72)(cid:71)(cid:3) (cid:82)(cid:81)(cid:3) (cid:87)(cid:75)(cid:72)(cid:3) (cid:83)(cid:68)(cid:76)(cid:71)(cid:3) (cid:88)(cid:83)(cid:3) (cid:72)(cid:84)(cid:88)(cid:76)(cid:87)(cid:92)(cid:3) (cid:70)(cid:68)(cid:83)(cid:76)(cid:87)(cid:68)(cid:79)(cid:3) (cid:71)(cid:72)(cid:87)(cid:72)(cid:85)(cid:80)(cid:76)(cid:81)(cid:72)(cid:71)(cid:3) (cid:76)(cid:81)(cid:3) (cid:68)(cid:70)(cid:70)(cid:82)(cid:85)(cid:71)(cid:68)(cid:81)(cid:70)(cid:72)(cid:3) (cid:90)(cid:76)(cid:87)(cid:75)(cid:3)

Regulation 27 for the assets put to use for the Transmission Licensee and shall be allowed in accordance with

the prevalent CERC Tariff Regulations for transmission system.

28.2 The return on equity for the Distribution Wires Business shall be allowed on the equity capital

determined in accordance with Regulation 27 for the assets put to use at post-tax rate of return on equity

specified in the prevalent CERC Tariff Regulations for transmission system.

28.3 The return on equity for the Retail Supply Business shall be allowed on the equity capital determined in

accordance with Regulation 27 for the assets put to use, at the rate of sixteen (16) per cent per annum.

(cid:21)(cid:27)(cid:17)(cid:23)(cid:3)(cid:55)(cid:75)(cid:72)(cid:3)(cid:85)(cid:72)(cid:87)(cid:88)(cid:85)(cid:81)(cid:3)(cid:82)(cid:81)(cid:3)(cid:72)(cid:84)(cid:88)(cid:76)(cid:87)(cid:92)(cid:3)(cid:86)(cid:75)(cid:68)(cid:79)(cid:79)(cid:3)(cid:69)(cid:72)(cid:3)(cid:70)(cid:82)(cid:80)(cid:83)(cid:88)(cid:87)(cid:72)(cid:71)(cid:3)(cid:82)(cid:81)(cid:3)(cid:68)(cid:89)(cid:72)(cid:85)(cid:68)(cid:74)(cid:72)(cid:3)(cid:82)(cid:73)(cid:3)(cid:72)(cid:84)(cid:88)(cid:76)(cid:87)(cid:92)(cid:3)(cid:70)(cid:68)(cid:83)(cid:76)(cid:87)(cid:68)(cid:79)(cid:3)(cid:68)(cid:87)(cid:3)(cid:87)(cid:75)(cid:72)(cid:3)(cid:69)(cid:72)(cid:74)(cid:76)(cid:81)(cid:81)(cid:76)(cid:81)(cid:74)(cid:3)(cid:68)(cid:81)(cid:71)(cid:3)(cid:72)(cid:81)(cid:71)(cid:3)(cid:82)(cid:73)(cid:3)(cid:60)(cid:72)(cid:68)(cid:85)(cid:17)(cid:180)

The Commission has segregated the approved average equity (average of opening and closing equity) into average equity for Distribution Wires Business and Retail Supply Business based on the Allocation Statement provided in the JERC MYT Regulations, 2021i.e., 90% allocation for the Distribution Wires Business and 10% allocation for the Retail Supply Business.

The Commission has considered a post-tax rate of 15.50% for the Distribution Wires Business and a post-tax rate of 16% for the Retail Supply Business. The equity component has been determined in accordance with the capital structure as discussed in section 5.9 of this Order. The rate of return on equity for the Distribution Wires Business shall be trued up based on the prevalent Regulations during the True-up of the respective years. The following table provides the total return on equity approved for the 3rdMYT Control Period.

Particular FY 2022-23 FY 2023-24 FY 2024-25
Opening Equity Amount 379.16 448.62 523.70
Equity Addition during year 69.46 75.07 50.49
Closing Equity Amount 448.62 523.70 574.18
Average Equity Amount 413.89 486.16 548.94
Average Equity (Wires Business) 372.50 437.54 494.05
Average Equity (Retail Supply Business) 41.39 48.62 54.89
Return on Equity for Wires Business (%) 15.50% 15.50% 15.50%
Return on Equity for Retail Supply Business (%) 16.00% 16.00% 16.00%
Return on Equity for Wires Business 57.74 67.82 76.58
Return on Equity for Retail Supply Business 6.62 7.78 8.78
Total Return on Equity 64.36 75.60 85.36
118 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 66 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022 ARR for the 3rd MYT Control Period Joint Electricity Regulatory Commission (JERC)

The Commission approves Return on Equity of INR64.36Cr. for the FY 2022-23, INR75.60Cr. for the FY 2023- 24 and INR85.36Cr. for the FY 2024-25.

5.13. Interest on Security Deposits

(cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:54)(cid:88)(cid:69)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)

The opening security deposit is considered from the closing balance of deposit arrived for FY 2021-22. Addition of consumer security deposit projected as per new consumer expected to connect during MYT control period.

The interest rate considered is 4.25% based on the RBI Bank rate applicable on the 1st April of the financial year in which tariff Petition is being filed.

Table 59: Interest on Security Deposit submitted by the Petitioner for the 3rdMYT Control

Period(INR Cr)

No. Particulars Projections
FY 2022-23 FY 2023-24 FY 2024-25
1 Opening Security Deposit 77.02 92.31 108.09
2 Add: Deposits during the Year 15.65 16.16 16.69
3 Less: Deposits refunded 0.37 0.38 0.39
4 Less: Deposits in form of BG/FDR 0.00 0.00 0.00
5 Closing Security Deposit 92.31 108.09 124.40
6 Average Security Deposit 84.67 100.20 116.24
7 Rate of Interest (%) 4.25% 4.25% 4.25%
8 Interest on Security Deposit 3.60 4.26 4.94
9 Interest on Security Deposit to be paid and claimed in ARR 5.58 4.26 4.94

(cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:182)(cid:86)(cid:3)(cid:68)(cid:81)(cid:68)(cid:79)(cid:92)(cid:86)(cid:76)(cid:86):

Regulation 29 of the JERC MYT Regulation, 2021 states the following:

(cid:179)29.11 Interest shall be allowed on the amount held as security deposit held in cash from Retail Consumers at

the Bank Rate as on 1st April of the Financial Year in which the Petition is filed:

119 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 67 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA ARR for the 3rd MYT Control Period Joint Electricity Regulatory Commission (JERC) SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022 Provided that at the time of truing-up, the interest on the amount of security deposit for the Year shall be

considered on the basis of the actual interest paid by the Licensee during the Year, subject to prudence check

(cid:69)(cid:92)(cid:3)(cid:87)(cid:75)(cid:72)(cid:3)(cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:17)(cid:180)

The Interest on security deposits has been calculated in accordance with the JERC MYT Regulations 2021, based on the average of the opening and closing consumer security deposits during the year. The rate of interest has been considered equivalent to the prevailing RBI Bank rate. Net additions during the year have been considered for each year of the Control Period based on that considered by the Petitioner.

The following table provides the calculation of interest on consumer security deposits approved for each year of the MYT Control Period:

Table 60: Interest on Consumer security considered by the Commission for 3rd Control Period

(INRCr.)

Particular FY 2022-23 FY 2023-24 FY 2024-25
Opening Security Deposit 77.02 92.31 108.09
Add: Deposits During the year 15.65 16.16 16.69
Less: Deposits refunded 0.37 0.38 0.39
Closing Security Deposit 92.31 108.09 124.40
Average Security Deposit 84.67 100.20 116.24
RBI Bank Rate (%) 4.25% 4.25% 4.25%
Interest on Security Deposit on normative basis 3.60 4.26 4.94

The Commission approves Interest on Security Deposit as INR3.60Cr. for the FY 2022-23, INR4.26Cr. for the FY 2023-24 and INR.4.94Cr. for the FY 2024-25.

5.14. Interest on Working Capital

(cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:54)(cid:88)(cid:69)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)

The interest on working capital has been calculated based on the normative principles outlined in the MYT Regulations, 2021.

The working capital requirement for the Control Period has been computed considering the following

(cid:120) Receivable of two months of billing

(cid:120) O&M Expenses of one month

(cid:120) Maintenance Spares at 40% of repair and maintenance expenses for one month

(cid:120) Less consumer security deposit but excluding Bank Guarantee/Fixed Deposit Receipt

The interest on working capital considered is the MCLR plus 200 basis points for SBI on 1st April 2021 plus 200 basis points i.e., 9.00% has been considered for computation of interest on working capital. The following table provides the Interest on working Capital proposed for 3rd MYT Control Period.

Table 61: Interest on Working Capital submitted by the Petitioner for the 3rd MYT Control

Period (In INR Cr)

Sr. No. Particulars Projections
FY 2022-23 FY 2023-24 FY 2024-25
1 O&M Expenses for 1 month 39.50 42.62 48.62
2 Maintenance Spares (@ 40% of R&M Expenses for one (1) month) 2.06 2.57 4.19
3 Receivables equivalent to two (2) months 333.51 342.96 352.72
4 Less: Amount, if any, held as security deposits 84.67 100.20 116.24
5 Total Working Capital 290.41 287.94 289.29
6 Rate of Interest 9.0% 9.0% 9.0%
7 Interest on Working Capital 26.14 25.91 26.04
120 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 68 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022 ARR for the 3rd MYT Control Period Joint Electricity Regulatory Commission (JERC)

(cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:182)(cid:86)(cid:3)(cid:68)(cid:81)(cid:68)(cid:79)(cid:92)(cid:86)(cid:76)(cid:86):

Regulation 64 of the JERC MYT Regulation, 2021 states the following:

(cid:179)64.1The Distribution Licensee shall be allowed interest on the estimated level of working capital forthe Retail

Supply Business for the Financial Year, computed as follows:

a) O&M Expenses for one (1) month; plus

b) Maintenance spares at 40% of repair and maintenance expenses for one (1) month; plus

c) Receivables equivalent to two (2) months of the expected revenue from Consumers at theprevailing tariff;

Less

d) Power Purchase cost for one (1) month; plus

e) Amount, if any, held as security deposits under clause (b) of sub-section (1) of Section 47 ofthe Act from

Consumers except the security deposits held in the form of Bank Guarantees:

Provided that at the time of truing up for any Year, the working capital requirement shall be recalculatedon

the basis of the values of components of working capital approved by theCommission in the truing up.(cid:180)

The Commission has computed the Interest on Working Capital for each year of the Control Period in accordance with the JERC MYT Regulations, 2021. The interest rate has been considered as 9.00% (1 year MCLR as on 1st April 2021 i.e., 7.00% + 200 basis points). The computation of interest on working capital is shown in the following table:

The following table provides the Interest on working Capital considered for each year of the 3rd MYT Control Period.

Table 62: Interest on working capital considered by the Commission for 3rd MYT Control Period

(INRCr.)

Particulars FY 2022-23 FY 2023-24 FY 2024-25
O&M Expense for 1 month 36.16 39.40 42.35
Maintenance spares at 40% of R&M expenses for one (1) month; 1.84 2.74 3.47
Receivables equivalent to two (2) months of the expected revenue from Consumers at the prevailing tariff 401.36 423.12 449.88
Less: Power Purchase cost for one (1) month 153.29 158.40 166.71
Less: Amount held as security deposits 84.67 100.20 116.24
Net Working Capital 201.41 206.66 212.75
Rate of Interest (%) 9.00% 9.00% 9.00%
Interest on Working Capital 18.13 18.60 19.15
121 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 69 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022 ARR for the 3rd MYT Control Period Joint Electricity Regulatory Commission (JERC)

5.15. Income Tax

(cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:54)(cid:88)(cid:69)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)

The Petitioner has not made any submission in this regard.

(cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:182)(cid:86)(cid:3)(cid:68)(cid:81)(cid:68)(cid:79)(cid:92)(cid:86)(cid:76)(cid:86):

Regulation 33 of JERC MYT Regulations, 2021 stipulates the following:

(cid:179)(cid:22)3. Tax on Income

33.1 The treatment of tax on income for a Transmission Licensee shall be in accordance with the prevalent

CERC Tariff Regulations.

33.2 The Commission in its MYT Order shall provisionally approve Income Tax payable for each Year of the

Control Period, if any, based on the actual income tax paid, including cess and surcharge on the same, if any,

as per latest audited accounts available for the Distribution Licensee, subject to prudence check.

33.3 Variation between Income Tax actually paid, including cess and surcharge on the same, if any, and

approved, if any, on the income stream of the Licensed business of the Distribution Licensees shall be

reimbursed to/recovered from the Distribution Licensees, based on the documentary evidence submitted at

the time of truing up of each Year of the Control Period, subject to prudence check.

33.4 Under-recovery or over-recovery of any amount from the Consumers on account of such tax having been

passed on to them shall be adjusted every Year on the basis of income-tax assessment under the Income-Tax

Act, 1961, as certified by the statutory auditors. The Distribution Licensee may include this variation in its

truing up Petition:

Provided that tax on any income stream other than the core business shall not be a pass-through component

(cid:76)(cid:81)(cid:3)(cid:87)(cid:68)(cid:85)(cid:76)(cid:73)(cid:73)(cid:3)(cid:68)(cid:81)(cid:71)(cid:3)(cid:87)(cid:68)(cid:91)(cid:3)(cid:82)(cid:81)(cid:3)(cid:86)(cid:88)(cid:70)(cid:75)(cid:3)(cid:82)(cid:87)(cid:75)(cid:72)(cid:85)(cid:3)(cid:76)(cid:81)(cid:70)(cid:82)(cid:80)(cid:72)(cid:3)(cid:86)(cid:75)(cid:68)(cid:79)(cid:79)(cid:3)(cid:69)(cid:72)(cid:3)(cid:69)(cid:82)(cid:85)(cid:81)(cid:72)(cid:3)(cid:69)(cid:92)(cid:3)(cid:87)(cid:75)(cid:72)(cid:3)(cid:39)(cid:76)(cid:86)(cid:87)(cid:85)(cid:76)(cid:69)(cid:88)(cid:87)(cid:76)(cid:82)(cid:81)(cid:3)(cid:47)(cid:76)(cid:70)(cid:72)(cid:81)(cid:86)(cid:72)(cid:72)(cid:17)(cid:180)

Since the Petitioner has paid no Income tax in the previous years, no income tax liability is computed for the 3rd MYT Control Period and the same shall be Trued-up based on the actual income tax paid by the Petitioner.

5.16. Provision for Bad & Doubtful Debts

(cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:54)(cid:88)(cid:69)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)

The Petitioner has not proposed any provision for bad and doubtful debts during the MYT Control Period.

(cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:182)(cid:86)(cid:3)(cid:68)(cid:81)(cid:68)(cid:79)(cid:92)(cid:86)(cid:76)(cid:86)

Regulation 63 of the JERC MYT Regulation, 2021 states the following:

122 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 70 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022 ARR for the 3rd MYT Control Period Joint Electricity Regulatory Commission (JERC)

(cid:179)(cid:25)(cid:22)(cid:17)(cid:20)(cid:3) (cid:55)(cid:75)(cid:72)(cid:3) (cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:3) (cid:80)(cid:68)(cid:92)(cid:3) (cid:68)(cid:79)(cid:79)(cid:82)(cid:90)(cid:3) (cid:69)(cid:68)(cid:71)(cid:3) (cid:71)(cid:72)(cid:69)(cid:87)(cid:86)(cid:3) (cid:90)(cid:85)(cid:76)(cid:87)(cid:87)(cid:72)(cid:81)(cid:3) (cid:82)(cid:73)(cid:73)(cid:3) (cid:68)(cid:86)(cid:3) (cid:68)(cid:3) (cid:83)(cid:68)(cid:86)(cid:86)(cid:3) (cid:87)(cid:75)(cid:85)(cid:82)(cid:88)(cid:74)(cid:75)(cid:3) (cid:76)(cid:81)(cid:3) (cid:87)(cid:75)(cid:72)(cid:3) (cid:36)(cid:74)(cid:74)(cid:85)(cid:72)(cid:74)(cid:68)(cid:87)(cid:72)(cid:3) (cid:53)(cid:72)(cid:89)(cid:72)(cid:81)(cid:88)(cid:72)(cid:3)

Requirement, based on the trend of bad debts written off in the previous years, subject to prudence check:

Provided that the Commission shall true up the bad debts written off in the Aggregate Revenue Requirement,

based on the actual write off of bad debts excluding delayed payment charges waived off, if any, during the

year, subject to prudence check:

Provided also that the provision for bad and doubtful debts shall be limited to 1% of the annual Revenue

Requirement of the Distribution Licensee:

Provided further that if subsequent to the write off of a particular bad debt, revenue is realized from such bad

debt, the same shall be included as an uncontrollable item under the Non-Tariff Income of the year in which

(cid:86)(cid:88)(cid:70)(cid:75)(cid:3)(cid:85)(cid:72)(cid:89)(cid:72)(cid:81)(cid:88)(cid:72)(cid:3)(cid:76)(cid:86)(cid:3)(cid:85)(cid:72)(cid:68)(cid:79)(cid:76)(cid:86)(cid:72)(cid:71)(cid:17)(cid:180)

The Commission also has not considered any Provision for Bad & Doubtful Debts for the 3rd MYT Control Period. The same shall be accounted for as per actuals during the True-up of respective years.

5.17. Non-Tariff Income (NTI)

(cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:54)(cid:88)(cid:69)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)

The NTI proposed for each year of the 3rdMYT Control Period has been shown in the following table:

Particulars FY 2022-23 FY 2023-24 FY 2024-25
Total Non-tariff income 20.78 29.20 30.33

(cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:182)(cid:86)(cid:3)(cid:68)(cid:81)(cid:68)(cid:79)(cid:92)(cid:86)(cid:76)(cid:86):

Regulation 65 of the JERC MYT Regulations, 2021 stipulates the following:

(cid:179)(cid:25)5. Non-Tariff Income

65.1 The amount of Non-Tariff Income relating to the retail supply of electricity as approved by the

Commission shall be deducted from the Aggregate Revenue Requirement in calculating the tariff for retail

supply of electricity by the Distribution Licensee:

Provided that the Distribution Licensee shall submit full details of its forecast of Non-Tariff Income to the

Commission along with its application for determination of tariff.

65.2 The Non-Tariff Income shall inter-alia include:

(a) Income from rent of land or buildings;

(b) Income from sale of scrap;

(c) Income from statutory investments;

(d) Interest on advances to suppliers/contractors;

(e) Rental from staff quarters;

(f) Rental from contractors;

(g) Income from hire charges from contactors and others;

(h) Income from advertisements, etc.;

(i) Meter/metering equipment/service line rentals;

(j) Service charges;

(k) Consumer charges;

(l) Recovery for theft and pilferage of energy;

123 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 71 Electricity Department, Government of Goa ARR for the 3rd MYT Control Period Joint Electricity Regulatory Commission (JERC) OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022

(m) Rebate availed on account of timely payment of bills;

(n) Miscellaneous receipts;

(o) Deferred Income from grant, subsidy, etc., as per Annual Accounts;

(p) Prior period income, etc.:

Provided that the interest/dividend earned from investments made out of Return on Equity corresponding to

the Retail Supply Business of the Distribution Licensee shall not be included in Non-Tariff Income:

Provided further that any income earned by a Distribution Licensee by sale of power to other Distribution

Licensees or to Consumers as per Section 49 of the Act using the existing power purchase agreements or bulk

(cid:86)(cid:88)(cid:83)(cid:83)(cid:79)(cid:92)(cid:3)(cid:70)(cid:68)(cid:83)(cid:68)(cid:70)(cid:76)(cid:87)(cid:92)(cid:3)(cid:68)(cid:79)(cid:79)(cid:82)(cid:70)(cid:68)(cid:87)(cid:72)(cid:71)(cid:3)(cid:87)(cid:82)(cid:3)(cid:87)(cid:75)(cid:72)(cid:3)(cid:39)(cid:76)(cid:86)(cid:87)(cid:85)(cid:76)(cid:69)(cid:88)(cid:87)(cid:76)(cid:82)(cid:81)(cid:3)(cid:47)(cid:76)(cid:70)(cid:72)(cid:81)(cid:86)(cid:72)(cid:72)(cid:182)(cid:86)(cid:3)(cid:36)(cid:85)(cid:72)(cid:68)(cid:3)(cid:82)(cid:73)(cid:3)(cid:54)(cid:88)(cid:83)(cid:83)(cid:79)(cid:92)(cid:3)(cid:86)(cid:75)(cid:68)(cid:79)(cid:79)(cid:3)(cid:69)(cid:72)(cid:3)(cid:85)(cid:72)(cid:71)(cid:88)(cid:70)(cid:72)(cid:71)(cid:3)(cid:73)(cid:85)(cid:82)(cid:80)(cid:3)(cid:87)(cid:75)(cid:72)(cid:3)(cid:36)(cid:74)(cid:74)(cid:85)(cid:72)(cid:74)(cid:68)(cid:87)(cid:72)(cid:3)

Revenue Requirement of the Distribution Licensee for the purpose of determination of tariff. Such reduction

shall be carried out in accordance with Joint Electricity Regulatory Commission for the State of Goa and

Union Territories (Connectivity and Open Access in Intra-State Transmission and Distribution) Regulations,

(cid:21)(cid:19)(cid:20)(cid:26)(cid:15)(cid:3)(cid:68)(cid:86)(cid:3)(cid:68)(cid:80)(cid:72)(cid:81)(cid:71)(cid:72)(cid:71)(cid:3)(cid:73)(cid:85)(cid:82)(cid:80)(cid:3)(cid:87)(cid:76)(cid:80)(cid:72)(cid:3)(cid:87)(cid:82)(cid:3)(cid:87)(cid:76)(cid:80)(cid:72)(cid:17)(cid:180)

The Commission considers the same NTI as approved by the Commission in the True up of FY 2016-17. The same shall be Trued-up on actual basis. The NTI approved for each year of the 3rdMYT Control Period has been shown in the following table:

Particulars FY 2022-23 FY 2023-24 FY 2024-25
Non-Tariff Income 26.32 26.32 26.32

5.18. Aggregate Revenue Requirement (ARR)

(cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:54)(cid:88)(cid:69)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)

Based on the expenses as detailed above, the Petitioner submitted the net aggregate revenue requirement for each year of the 3rd MYT Control Period as shown in the following table:

S. No. Particulars FY 2022-23 FY 2023-24 FY 2024-25
1 Power Purchase Cost 1,660.44 1,732.15 1,781.47
2 Operation & Maintenance Expenses 474.02 511.43 583.49
3 Depreciation 85.51 122.24 148.77
4 Interest and Finance charges 44.90 81.69 103.43
5 Interest on Working Capital 26.14 25.91 26.04
6 Interest on Security Deposit 5.58 4.26 4.94
7 Return on Equity 85.34 122.91 150.05
8 Total Revenue Requirement 2,381.93 2,600.59 2,798.19
9 Less: Non-Tariff Income 20.78 29.20 30.33
10 Net Revenue Requirement 2,361.15 2,571.38 2,767.86

(cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:182)(cid:86)(cid:3)(cid:36)(cid:81)(cid:68)(cid:79)(cid:92)(cid:86)(cid:76)(cid:86)(cid:29)

On the basis of the detailed analysis of the cost parameters of the ARR the net revenue requirement for each year of the MYT Control Period is approved as provided in the following table:

124 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 72 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022 ARR for the 3rd MYT Control Period Joint Electricity Regulatory Commission (JERC)
Particulars FY 2022-23 FY 2023-24 FY 2024-25
Claimed by the Petitioner Approved in ARR Claimed by the Petitioner Approved in ARR Claimed by the Petitioner Approved in ARR
Power Purchase Cost 1,660.44 1,839.53 1,732.15 1,900.80 1,781.47 2,000.48
Operation & Maintenance Expenses 474.02 433.95 511.43 472.78 583.49 508.20
Depreciation 85.51 52.64 122.24 61.84 148.77 69.84
Interest and Finance charges 44.90 22.26 81.69 31.17 103.43 37.62
Interest on Working Capital 26.14 18.13 25.91 18.60 26.04 19.15
Interest on Security Deposit 5.58 3.60 4.26 4.26 4.94 4.94
Return on Equity 85.34 64.36 122.91 75.60 150.05 85.36
Total Revenue Requirement 2,381.93 2,434.47 2,600.59 2,565.05 2,798.19 2,725.59
Less: Non-Tariff Income 20.78 26.32 29.20 26.32 30.33 26.32
Net Revenue Requirement 2,361.15 2,408.15 2,571.38 2,538.73 2,767.86 2,699.27

5.19. Revenue at existing Retail Tariff

(cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:54)(cid:88)(cid:69)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)

The Revenue from sale of power at existing Tariff based on the projected sales, consumer and connected load for FY 2022-23 is tabulated below:

Sl. No. Category Sales in MU Revenue from Fixed Charges Revenue from Demand Charges Revenue from Energy Charges Total
1 Domestic
11 kV Voltage Level
Tariff HTD/Domestic 0.43 0.06 0.17 0.22
Tariff-HTTS/Temporary Supply (HT Domestic) 3.51 1.12 2.15 3.27
LT Voltage Level
Tariff LTD/Domestic and Non- Commercial 1325.53 25.15 0.00 329.27 354.42
0-100 units 508.38 6.56 76.26
101-200 units 320.26 4.43 72.06
201 to 300 units 174.32 6.92 49.68
301 to 400 units 96.92 3.32 35.37
Above 400 units 225.65 3.92 95.90
Tariff LTD/Low Income Group 1.27 0.05 - 0.05
Tariff-LT/Temporary Domestic 0.69 0.09 0.15 0.20
0-100 Units 0.69 0.05 0.15 0.20
101 to 200 Units 0.00 0.05 -
201 to 300 Units 0.00 0.00 -
301 to 400 Units 0.00 0.00 -
Above 400 Units 0.00 0.00 -
Sub-Total 1331.43 26.47 0.00 331.75 358.17
2 Commercial
33 kV & 11 kV Voltage Level
Tariff HT-Commercial 116.74 32.58 73.32 105.91
33 kV Voltage Level
Tariff HT-Commercial
11 kV Voltage Level
Tariff HT-Commercial
Tariff-HTTS/Temporary Supply (HT Commercial)
LT Voltage Level
Tariff-LTC/Commercial 436.59 14.32 209.81 224.13
0-20 KW/Commercial Consumers
1-100 Units 72.87 3.82 25.87 29.69
101-200 units 42.59 0.84 18.53 19.37
201-400 Units 50.72 0.68 24.60 25.28
Above 400 units 159.46 0.70 83.72 84.42
>20-90Kw Commercial Consumers
1-100 Units 3.52 1.11 1.25 2.36
101-200 units 3.34 0.37 1.45 1.82
201-400 Units 6.29 0.68 3.05 3.73
Above 400 units 97.80 6.10 51.35 57.45
Tariff-LT/Temporary Commercial 9.08 0.15 4.84 4.99
0-20 KW/Commercial Consumers
0-100 Units 9.08 0.15 4.84 4.99
101 - 200 Units 0.00 - 0.00
201 - 400 Units 0.00 - 0.00
Above 400 Units 0.00 - 0.00
>20-90Kw and above Commercial Consumers
0 - 100 units 0.00 - 0.00
101 - 200 units 0.00 - 0.00
201-400 units 0.00 - 0.00
Above 400 units 0.00 - 0.00
Sub-Total 562.42 47.06 287.97 335.02
3 Public Lighting
LT Voltage Level
Tariff-LTPL/Public Lighting 50 1.02 21.17 22.20
4 Agricultural Pumpsets
HT Voltage Level (33 kV & 11 kV)
HT-Agriculture
Tariff-HTAG/Agriculture (Pump Sets/Irrigation) (A) 5 0.45 1.51 1.97
Tariff-HTAG/Agriculture (Allied Activities) (B) 9 0.18 1.86 2.04
LT Voltage Level
LT-Agriculture
Tariff-LTAG/Agriculture (Pump Sets/Irrigation) (A) 17 1.05 2.59 3.64
Tariff-LTAG/Agriculture Allied (B) 1 0.07 0.17 0.24
Sub-Total 32.90 1.76 6.13 7.89
5 Small Power LT Voltage Level
LTI-Industry 81 7 31 38
0-500 Units 17 3.24 5.62 8.86
Above 500 units 64 3.76 25.43 29.18
Tariff-LTP/Mixed (Hotel Industries) 4 0.14 2.22 2.35
Sub-Total 85.38 7.13 33.27 40.40
6 Medium Supply 11kV, Large Supply 33 kV & Bulk Supply 110 kV
33 kV / 11 kV & 110 kV Voltage Level
Tariff HTI/Industrial 1483 171 845 1016.35
33 kV/11kV 1228 148.91 706.51 855.42
110kV 255 22.38 138.54 160.93
H.T.Industrial (Ferro Metallurgical/ Steel Melting/ Power Intensive) 507 27.98 279.96 307.94
H.T. MES/Defence Establishments 28 2.09 15.47 17.56
Sub-Total 2018.04 201.36 1140.48 1341.84
7 Bulk Supply
33 kV Voltage Level
Single Point Supply 5.55 1.07 0.00 2.67 3.74
Residential Complexes 0.00 0.00 0.00
Commercial Complexes 5.55 1.07 2.67 3.74
Industrial Complexes 0.00 0.00 0.00
Sub-Total 5.55 1.07 0.00 2.67 3.74
8 Other Categories
33 kV Voltage Level
Electric Vehicle Charging Station
11 kV Voltage Level
Tariff-LT Hoarding and Sign Board 0 0.04 0.16 0.21
Electric Vehicle Charging Station
Grand Total 4086.29 285.91 0.00 1823.60 2109.47
125 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 73 Electricity Department, Government of Goa ARR for the 3rd MYT Control Period Joint Electricity Regulatory Commission (JERC) OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022 126 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 74 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022 ARR for the 3rd MYT Control Period Joint Electricity Regulatory Commission (JERC)

(cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:182)(cid:86)(cid:3)(cid:68)(cid:81)(cid:68)(cid:79)(cid:92)(cid:86)(cid:76)(cid:86)

The category wise/ sub-category wise and slab-wise revenue at existing retail tariff is calculated as per the applicable tariff rates. The revenue from demand charges and the energy charges have been projected for each category/ sub-category and slab. The Commission has considered the energy sales, connected load and number of consumers approved by the Commission in the Business Plan Order dated 31st March 2022 for projecting the revenue at existing tariff. The Commission has considered suitable assumptions wherever necessary. The revenue at existing tariff as computed by the Commission for the FY 2022-23 has been shown in the following table:

Sl. No. Category Sales (MU) Revenue from fixed Charges (Rs Cr.) Revenue from energy charges (Rs Cr.) Total (Rs. Cr.)
1 DOMESTIC 1386.33 26.09 342.15 368.24
(i) LT-D Domestic 1384.58 25.98 342.00 367.98
0-100 units 544.79 7.20 81.72 88.91
101-200 units 331.54 5.25 74.60 79.84
201-300 units 175.22 6.93 49.94 56.87
301-400 units 96.50 3.11 35.22 38.33
Above 400 units 236.53 3.50 100.53 104.02
(ii) Low Income Group 1.37 0.08 - 0.08
(iii) HT-D Domestic 0.38 0.03 0.15 0.18
2 COMMERCIAL 607.53 43.18 305.26 348.43
(i) LT-C Commercial 472.52 20.08 228.11 248.19
0-100 units 77.99 3.61 27.69 31.30
101-200 units 47.80 0.97 20.79 21.76
201-400 units 60.12 3.14 29.16 32.30
Above 400 units 286.61 12.36 150.47 162.83
(ii) HT-C Commercial 135.02 23.10 77.15 100.25
3 INDUSTRIAL 2139.85 189.41 1035.85 1225.26
(i) LT-I Industrial 80.91 7.05 31.07 38.12
0-500 units 16.18 3.40 5.50 8.90
Above 500 units 64.73 3.66 25.57 29.22
(ii) Low Tension-Mixed/LT-P (Hotel Industries) 4.48 0.14 2.22 2.36
(iii) High Tension-I/HT-I 1499.12 157.91 734.68 892.58
Connected at 11/33 kV 1247.94 135.20 616.15 751.36
Connected at 110 kV 251.18 22.70 118.52 141.22
(iv) High Tension-Ferro/SM/PI/SR 555.35 24.31 267.89 292.20
4 AGRICULTURE 33.62 1.71 5.88 7.59
(i) Low Tension-AG/LT-AGP (Pump Sets/Irrigation) 17.29 1.09 2.59 3.69
(ii) Low Tension-AG/LT-AGA (Allied Activities) 0.79 0.05 0.14 0.19
(iii) High Tension-AG/HT-AGP (Pump Sets/Irrigation) 4.89 0.44 1.03 1.47
(iv) High Tension-AG/HT-AG (Allied Activities) 10.65 0.12 2.12 2.24
5 Military Engineering Services/defense Establishments 26.96 1.73 14.54 16.27
6 PUBLIC LIGHTING 29.61 0.23 12.44 12.67
7 HOARDINGS/SIGNBOARDS 0.16 0.04 0.16 0.20
8 TEMPORARY 12.10 0.00 10.19 10.19
(i) LT 9.77 0.00 8.09 8.09
LT Domestic 0.69 0.00 0.27 0.27
LT Commercial 9.08 0.00 7.81 7.81
(ii) HT 2.33 0.00 2.11 2.11
9 Single Point Supply 5.69 0.91 2.76 3.67
(i) Residential Complexes 0.00 0.00 0.00 0.00
(ii) Commercial Complexes 5.69 0.91 2.76 3.67
(iii) Industrial Complexes 0.00 0.00 0.00 0.00
TOTAL 4241.87 263.30 1729.23 1992.53
127 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 75 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022 ARR for the 3rd MYT Control Period Joint Electricity Regulatory Commission (JERC) 128 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 76 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022 ARR for the 3rd MYT Control Period Joint Electricity Regulatory Commission (JERC)

The Commission has determined revenue from sale of power at existing tariff as INR1992.53Cr. in the FY 2022- 23.

5.20. Standalone Revenue Gap/ Surplus for FY 2022-23

(cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:54)(cid:88)(cid:69)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)

Based on the ARR and the revenue from retail tariff projected by the Petitioner, the Petitioner has submitted a standalone revenue gap of INR 251.69 Cr for the FY 2022-23.

(cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:182)(cid:86)(cid:3)(cid:68)(cid:81)(cid:68)(cid:79)(cid:92)(cid:86)(cid:76)(cid:86)

Based on the approved ARR and existing retail tariff, the following Revenue Gap/Surplus is arrived at for the FY 2021-22:

Table 69: Standalone Revenue Gap/ (Surplus) at existing tariff approved by Commission for FY

2022-23 (In INR Cr)

S. No Particulars 3HWLWLRQHUV¶6XEPLVVLRQ Now Approved
1 Net Revenue Requirement 2,361.15 2,408.15
2 Revenue from Retail Sales at Existing Tariff 2,109.47 1,992.53
Net Gap /(Surplus) 251.69 415.62

The standalone gap at existing retail tariff is INR415.62 Cr. for FY 2022-23. This estimated gap

is considered while determining the retail tariff for FY 2022-23, as discussed in the subsequent

Chapter.

129 OFFICIAL GAZETTE — GOVT. OF GOA Tariff Principles and Design Joint Electricity Regulatory Commission (JERC) SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022

6. Chapter 6: Tariff Principles and

Design

6.1. Overall Approach

The Commission while designing retail tariffs for the FY 2022-23 has kept in view the principles of determination of tariff as set out in the Electricity Act, 2003 (EA 2003), Tariff Policy, 2016 and the JERC MYT Regulations, 2021.

The provision of supply of electricity to all the people is an essential driver for development, and also influences social and economic change. In this Tariff Order, the Commission has continued with its endeavor to meet the objectives of the EA 2003, as set out in its Preamble, including the protection of the interest of consumers, the supply of electricity to all areas and the rationalisation of tariffs. The EA, 2003 also mandates the Commission to strikea fine balance between the interests of various stakeholders including Utilities and consumers. The Commission has also taken into conside(cid:85)(cid:68)(cid:87)(cid:76)(cid:82)(cid:81)(cid:3) (cid:87)(cid:75)(cid:72)(cid:3) (cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3) (cid:86)(cid:88)(cid:69)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:86)(cid:3) (cid:68)(cid:86)(cid:3) (cid:90)(cid:72)(cid:79)(cid:79)(cid:3) (cid:68)(cid:86)(cid:3) (cid:87)(cid:75)(cid:72)(cid:3) (cid:83)(cid:88)(cid:69)(cid:79)(cid:76)(cid:70)(cid:3) (cid:85)(cid:72)(cid:86)(cid:83)(cid:82)(cid:81)(cid:86)(cid:72)(cid:86)(cid:3) (cid:76)(cid:81)(cid:3) these proceedings.

6.2. Applicable Regulations

Regulation 20 of the JERC MYT Regulations, 2021 states the following:

(cid:179)20. Annual determination of tariff

20.1 The Commission shall determine the tariff of a Generating Company, Transmission Licensee and

Distribution Licensee covered under a Multi Year Tariff framework for each Year during the Control Period,

in accordance with timelines specified in Regulation 18, having regard to the following:

a) The approved forecast of Aggregate Revenue Requirement and Expected Revenue from Tariff and Charges

of the Generating Company, Transmission Licensee and Distribution Licensee for such Financial Year,

including modifications approved at the time of Mid-term Review, if any; and

b) Approved gains and losses, including the incentive available, to be passed through in tariff, following the

truing up of previous Year.(cid:180)

Further, Regulation 68 of the JERC MYT Regulations, 2021 states the following:

(cid:179)68. Determination of Tariff

68.1 The Commission may categorize Consumers on the basis of their load factor, power factor, voltage, total

consumption of electricity during any specified period or the time at which the supply is required or the

geographical position of any area, the nature of supply and the purpose for which the supply is required and

any other factor as considered appropriate by the Commission.

68.2 The Commission shall endeavour to determine cost of supply for each category/ sub-category of

Consumers.

68.3 The Commission shall endeavour to reduce gradually the cross-subsidy between Consumer categories

withrespect to the cost of supply in accordance with the provisions of the Act.

68.4 The tariff proposal by Licensee and the tariff determination by the Commission shall be based on the

following principles:

(a) The tariff for all categories shall preferably be two part, consisting of fixed and variable charges.

(b) The fixed charges in tariff shall progressively reflect actual fixed cost incurred by Distribution Licensee;

130 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 78 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA Tariff Principles and Design Joint Electricity Regulatory Commission (JERC) SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022

(c) The overall retail supply tariff for different Consumer categories shall progressively reflect the cost of

supply for respective categories of Consumers;

(d) The tariff for residential Consumers shall be set considering the affordability of tariff for various class of

Consumers;

(e) The tariff shall be set in such a manner that it may not present a tariff shock to any category of

(cid:38)(cid:82)(cid:81)(cid:86)(cid:88)(cid:80)(cid:72)(cid:85)(cid:86)(cid:17)(cid:180)

6.3. Standalone and Consolidated Revenue Gap/ Surplus at

existing tariff

(cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:54)(cid:88)(cid:69)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)

The Petitioner has proposed a standalone revenue gap at existing tarifffor FY 2022-23 as shown in the table below:

Particulars FY 2022-23
Net Revenue Requirement 2,361.15
Revenue from Retail Sales at Existing Tariff 2,109.47
Standalone Gap /(Surplus) for the year 251.69

The Petitioner has further submitted that the Council of Ministers in the meeting held on 25th August 2021 resolved to keep the Tariff Order for FY 2021-22 in abeyance for the period from 1st April, 2021 till 31st March, 2022 (12 months) except for levy of Tariff of Rs.3.50/Unit as per Tariff Order for FY 2021-22 to Consumer (cid:38)(cid:68)(cid:87)(cid:72)(cid:74)(cid:82)(cid:85)(cid:92)(cid:3)(cid:179)(cid:40)(cid:79)(cid:72)(cid:70)(cid:87)(cid:85)(cid:76)(cid:70)(cid:3)(cid:57)(cid:72)(cid:75)(cid:76)(cid:70)(cid:79)(cid:72)(cid:3)(cid:38)(cid:75)(cid:68)(cid:85)(cid:74)(cid:76)(cid:81)(cid:74)(cid:3)(cid:54)(cid:87)(cid:68)(cid:87)(cid:76)(cid:82)(cid:81)(cid:180)(cid:3)(cid:68)(cid:81)(cid:71)(cid:3)(cid:76)(cid:80)(cid:83)(cid:79)(cid:72)(cid:80)(cid:72)(cid:81)(cid:87)(cid:68)(cid:87)(cid:76)(cid:82)(cid:81)(cid:3)(cid:82)(cid:73)(cid:3)(cid:78)(cid:57)(cid:36)(cid:75)(cid:3)(cid:69)(cid:68)(cid:86)(cid:72)(cid:71)(cid:3)(cid:87)(cid:68)(cid:85)(cid:76)(cid:73)(cid:73)(cid:3)(cid:73)(cid:82)(cid:85)(cid:3)(cid:43)(cid:55)(cid:18)(cid:40)(cid:43)(cid:55)(cid:3)(cid:38)(cid:68)(cid:87)(cid:72)(cid:74)(cid:82)(cid:85)(cid:76)(cid:72)(cid:86)(cid:3) and to grant of subsidy to all categories of Consumers to nullify the impact of hike in Tariff Order for FY 2021- 22 issued vide Petition No: 39/2020 by the Commission. The Petitioner has estimated a reduction of INR 108.44 Cr. from the projected revenue in FY 2022-23 as follows:

Particulars FY 2022-23
Net ARR 2,361.15
Revenue from Existing Tariff 2,109.47
Revenue Gap for the Year (at existing tariff) 251.69
Opening Balance of Gap 0.00
Total Cumulative Gap for years 251.69
Less: Budgetary Support commitment provided -
Balance Gap to be recovered 0.00
Proposed Gap Recovery 251.69
Proposed Tariff Reduction from last year -108.44
Budgetary Support required from Government of Goa to meet balance Revenue Gap 360.13

(cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:182)(cid:86)(cid:3)(cid:68)(cid:81)(cid:68)(cid:79)(cid:92)(cid:86)(cid:76)(cid:86)

The Commission takes a stern view of the fact that the tariff schedule prescribed by the Commission in the Tariff Order dated 30.03.2021 has not been implemented by the Petitioner. The Commission directs the Petitioner to implement the Tariff Schedule as approved in this Order from 1st April 2022.

The Commission in the True-up of FY 2016-17 approved the revenue gap/surplus as nil in the Tariff Order dated 30.03.2021. Further, the Commission has not approved any revenue gap for the FY 2017-18 to FY 2020- 21 due to non(cid:177)availability of audited annual accounts and for FY 2021-22 due to unreliable data. The131 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 79 Electricity Department, Government of Goa Tariff Principles and Design Joint Electricity Regulatory Commission (JERC) OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022 Commission has determined the tariff for FY 2022-23 as part of this Order. Therefore, the Commission approves the standalone revenue gap for FY 2022-23 as follows:

Table 72: Standalone Revenue Gap/ (Surplus) at existing tariff approved by Commission for FY

2022-23 (In INR Cr)

S. No Particulars Now Approved
1 Net Revenue Requirement 2,408.15
2 Revenue from Retail Sales at Existing Tariff 1,992.53
Net Gap /(Surplus) 415.62

The Commission has computed a standalone revenue gap of INR 415.62 Cr in the FY 2022-23 at

the existing tariff.

6.4. Treatment of the Revenue Gap/ Surplus and Tariff

Design

The revenue gap of INR 415.62Cr. typically signifies that the revenue from the existing tariff is not commensurate with the costs incurred by the Petitioner. However, it is observed that due to unavailability of audited annual accounts for FY 2017-18, FY 2018-19, FY 2019-20 and FY 2020-21, it is difficult to ascertain the accuracy of the data in respect of capital expenditure, capitalisation, power purchase, energy sales etc. during this period thereby leading to unreliable estimates of ARR parameters for FY 2022-23. Further, the Commission also does not have verified figures for revenue from sale of power during this period. Therefore, the Commission does not have an accurate picture of standalone revenue gap at existing tariff for FY 2022-23.

The Commission has accordingly dealt with this issue in the following section.

6.4.1. Tariff Design

(cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:54)(cid:88)(cid:69)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)

The Petitioner has submitted that the Council of Ministers in the meeting held on 25th August 2021 resolved to keep the Tariff Order for FY 2021-22 in abeyance for the period from 1st April, 2021 till 31st March, 2022 (12 months) except for levy of Tariff of Rs.3.50/Unit as per Tariff Order for FY 2021-22 to Consumer Category (cid:179)(cid:40)(cid:79)(cid:72)(cid:70)(cid:87)(cid:85)(cid:76)(cid:70)(cid:3) (cid:57)(cid:72)(cid:75)(cid:76)(cid:70)(cid:79)(cid:72)(cid:3) (cid:38)(cid:75)(cid:68)(cid:85)(cid:74)(cid:76)(cid:81)(cid:74)(cid:3) (cid:54)(cid:87)(cid:68)(cid:87)(cid:76)(cid:82)(cid:81)(cid:180)(cid:3) (cid:68)(cid:81)(cid:71)(cid:3) (cid:76)(cid:80)(cid:83)(cid:79)(cid:72)(cid:80)(cid:72)(cid:81)(cid:87)(cid:68)(cid:87)(cid:76)(cid:82)(cid:81)(cid:3) (cid:82)(cid:73)(cid:3) (cid:78)(cid:57)(cid:36)(cid:75)(cid:3) (cid:69)(cid:68)(cid:86)(cid:72)(cid:71)(cid:3) (cid:87)(cid:68)(cid:85)(cid:76)(cid:73)(cid:73)(cid:3) (cid:73)(cid:82)(cid:85)(cid:3) (cid:43)(cid:55)(cid:18)(cid:40)(cid:43)(cid:55)(cid:3) (cid:38)(cid:68)(cid:87)(cid:72)(cid:74)(cid:82)(cid:85)(cid:76)(cid:72)(cid:86)(cid:3) (cid:68)(cid:81)(cid:71)(cid:3) (cid:87)(cid:82)(cid:3) grant of subsidy to all categories of Consumers to nullify the impact of hike in Tariff Order for FY 2021-22 issued vide Petition No: 39/2020 by the Commission. The Petitioner has proposed the tariff schedule as follows:

Table 73:Tariff Schedule proposed by the Petitioner for FY 2022-23

S. No. Category Proposed Tariff for FY 2022-23
Fixed Charges Energy Charges (INR/kWh)
Units Rate
1 Domestic
A Low Tension-D/LT-D
0-100 units Single Phase INR 25/Con/Month Three Phase INR 60/Con/Month Rs/kWh 1.40
101-200 units Rs/kWh 2.10
201 to 300 units Rs/kWh 2.65
301 to 400 units Rs/kWh 3.45
Above 400 units Rs/kWh 4.00
B Low Tension-LIG/LT-LIG
All Units INR 40/Con/Month Rs/kWh -
C High Tension-D/HT-D
All Units INR 100/kVA/Month Rs/kVAh 3.45
2 A Commercial Low Tension-C/LT-C
0-100 units For consumers with Load upto 20 kW INR 50/Con/Month For consumers with Load more than 20 kW and upto 90 kW INR 55/kW/Month Rs/kWh 3.40
101-200 units Rs/kWh 4.10
201 units- 400 units Rs/kWh 4.60
Above 400 units Rs/kWh 5.00
B High Tension-C/HT-C
All Units INR 250/kVA/month Rs/kVAh 5.50
3 Industrial
A Low Tension-I/LT-I
0-500 units INR 35/HP/Month Rs/kWh 3.30
Above 500 units INR 35/HP/Month Rs/kWh 3.80
B Low Tension-Mixed/LT-P (Hotel Industries)
All Units INR 40/kW/Month Rs/kWh 4.70
C High Tension-I/HT-I
Connected at 11/33 kV INR 250/kVA/Month Rs/kVAh 4.50
Connected at 110 kV INR 250/kVA/Month Rs/kVAh 4.40
D High Tension- Ferro/SM/ PI/ SR
All Units INR 250/kVA/Month Rs/kVAh 4.50
4 Agricultural
A Low Tension-AG/LT-AGP (Pump Sets/Irrigation)
All Units INR 15/HP/Month Rs/kWh 1.40
B Low Tension-AG/LT-AGA (Allied Activities)
All Units INR 20/HP/Month Rs/kWh 1.70
C High Tension-AG/HT-AGP (Pump Sets/Irrigation)
All Units INR 35/kVA/Month Rs/kVAh 1.50
D High Tension-AG/HT-AG (Allied Activities)
All Units INR 60/kVA/Month Rs/kVAh 1.90
5 Military Engineering Services/ defense Establishments
All Units INR 175/kVA/Month Rs/kVAh 5.00
6 Public Lighting
All Units INR 50/kW/Month Rs/kWh 4.10
7 Hoardings/Signboards
All Units INR 60/kVA/Month Rs/kWh 9.90
8 Temporary Supply
A LT Temporary Domestic Tariff shall be Fixed/ Demand charges (if any) plus energy charges (for relevant slab, if any) under corresponding permanent supply category plus 50% of both. For multi activity pursuit, applicable Tariff for temporary connection shall be with reference to that of commercial category for permanent supply.
B LT Temporary Commercial
C HT Temporary
9 Single Point Supply
A Residential Complexes INR 100 per kVA per month or part thereof Rs/kVAh 3.45
B Commercial Complexes INR 200 per kVA per month or part thereof Rs/kVAh 4.60
C Industrial Complexes INR 200 per kVA per month or part thereof Rs/kVAh 4.20
10 Electric Vehicle Charging Station
All Units - Rs/kWh 3.50
132 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 80 Electricity Department, Government of Goa Tariff Principles and Design Joint Electricity Regulatory Commission (JERC) OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022 133 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 81 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA Tariff Principles and Design Joint Electricity Regulatory Commission (JERC) SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022

(cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:182)(cid:86)(cid:3)(cid:68)(cid:81)(cid:68)(cid:79)(cid:92)(cid:86)(cid:76)(cid:86)

The Commission has determined the retail tariff for the FY 2022-23 in accordance with the principles stated in the Electricity Act, 2003 Tariff Policy, 2016, and the JERC MYT Regulations, 2021. The Tariff design in general is guided by the following principles:

1. Cost reflective: The tariffs determined should efficiently reflect the cost of supply for each consumer category.

2. Progressive tariffs: Ensuring progressivity among tariffs by having telescopic tariff slabs which encourages efficient consumption and at the same time allows intra-category cross-subsidy by way of charging higher tariff for higher consumption to subsidise the lower consumption consumers

3. (cid:53)(cid:72)(cid:89)(cid:72)(cid:81)(cid:88)(cid:72)(cid:3)(cid:81)(cid:72)(cid:88)(cid:87)(cid:85)(cid:68)(cid:79)(cid:76)(cid:87)(cid:92)(cid:29)(cid:3)(cid:55)(cid:75)(cid:72)(cid:85)(cid:72)(cid:3)(cid:86)(cid:75)(cid:82)(cid:88)(cid:79)(cid:71)(cid:3)(cid:69)(cid:72)(cid:3)(cid:81)(cid:82)(cid:3)(cid:76)(cid:80)(cid:83)(cid:68)(cid:70)(cid:87)(cid:3)(cid:82)(cid:81)(cid:3)(cid:87)(cid:75)(cid:72)(cid:3)(cid:88)(cid:87)(cid:76)(cid:79)(cid:76)(cid:87)(cid:92)(cid:182)(cid:86)(cid:3)(cid:92)(cid:72)(cid:68)(cid:85)(cid:79)(cid:92)(cid:3)(cid:85)(cid:72)(cid:89)(cid:72)(cid:81)(cid:88)(cid:72)(cid:3)(cid:71)(cid:88)(cid:72)(cid:3)(cid:87)(cid:82)(cid:3)(cid:85)(cid:68)(cid:87)(cid:76)(cid:82)(cid:81)(cid:68)(cid:79)(cid:76)(cid:93)(cid:68)(cid:87)(cid:76)(cid:82)(cid:81)(cid:3) of tariffs i.e. the overall status quo should be maintained.

4. Affordability: Assessing affordability of electricity for Domestic and Commercial consumers for defining slab ranges and setting tariffs

5. Revenue stability: Tariff should ensure adequate fixed cost recovery for utilities from fixed/demand charges

6. Avoiding tariff shocks: Tariff shocks should be avoided and stakeholders should be able to predict the future trends in tariffs

7. Demand management and grid stability: Demand management and grid stability should be ensured with demand-based tariffs

8. Simplified tariff structure: Tariff structure should be simplified to make it easily administrable by the utility and easy to understand for the consumer.

9. Smart tariff design: Tariff rate design should take into consideration trends in electric power such as small-scale renewable generation by consumers, energy efficiency, electric vehicle charging, etc.

While all the above parameters contribute significantly to developing a sustainable tariff framework, there are certain parameters namely Cost of Supply and Tariff Affordability which are of importance and constitute the building blocks in achieving the overall objective. The context and the approach for these parameters have been discussed as follows:

Cost of Supply

a) Context Due to electricity being a crucial utility item for all consumers, over the period of time, various socio- (cid:72)(cid:70)(cid:82)(cid:81)(cid:82)(cid:80)(cid:76)(cid:70)(cid:3)(cid:76)(cid:86)(cid:86)(cid:88)(cid:72)(cid:86)(cid:3)(cid:75)(cid:68)(cid:89)(cid:72)(cid:3)(cid:69)(cid:72)(cid:72)(cid:81)(cid:3)(cid:73)(cid:68)(cid:70)(cid:87)(cid:82)(cid:85)(cid:72)(cid:71)(cid:3)(cid:76)(cid:81)(cid:3)(cid:87)(cid:82)(cid:3)(cid:71)(cid:72)(cid:87)(cid:72)(cid:85)(cid:80)(cid:76)(cid:81)(cid:72)(cid:3)(cid:87)(cid:75)(cid:72)(cid:3)(cid:72)(cid:81)(cid:71)(cid:3)(cid:88)(cid:86)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:87)(cid:68)(cid:85)(cid:76)(cid:73)(cid:73)(cid:86)(cid:17)(cid:3)(cid:55)(cid:75)(cid:76)(cid:86)(cid:3)(cid:75)(cid:68)(cid:86)(cid:3)(cid:88)(cid:81)(cid:73)(cid:82)(cid:85)(cid:87)(cid:88)(cid:81)(cid:68)(cid:87)(cid:72)(cid:79)(cid:92)(cid:3)(cid:79)(cid:72)(cid:71)(cid:3)(cid:87)(cid:82)(cid:3)(cid:86)(cid:72)(cid:89)(cid:72)(cid:85)(cid:72)(cid:3) imbalance between the tariffs levied vis-a-vis the cost of supply of the electricity, causing distress to the Distribution Licensee. For example, in order to ensure that tariffs are kept in check for domestic consumers,134 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 82 Electricity Department, Government of Goa Tariff Principles and Design Joint Electricity Regulatory Commission (JERC) OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022 while still allowing cost recovery for Distribution Licensees, cross subsidy has been built in between categories. The tariffs so determined, are skewed, with tariff for industrial and commercial consumers being higher and for other categories being lower than their respective costs of supply. The implications of this imbalance in tariffs is twofold (cid:177) uncompetitive industries owing to higher input costs and inability of Distribution Licensees to recover sufficient tariffs from domestic consumers, resulting in financial distress.

The issue is more pronounced for rural supply where tariffs are highly subsidized, actual cost of supply is higher and revenue recovery is poor.

It is thus essential that tariffs reflect the true cost to service a category of consumer. As a crucial first step towards cost-reflective tariffs, it is important for Distribution Licensees to determine the costs of supply (which cascade from generation to transmission and finally to distribution and retail supply of power) that should be prudently recovered from each consumer category. These costs should correspond to the actual costs being caused/contributed by each consumer category towards total cost incurred by the Distribution Licensee. By determining consumer category wise costs of supply, the Distribution Licensee would be in a better position to allocate costs where relevant and determine how tariffs can be levied fairly on each category.

b) Approach:

The overall approach that can be followed for accurately determining the Cost of Supply has been discussed as follows.

Presently, the most commonly used approach for determining the cost of supply of electricity for tariff determination is the Average Cost of Supply (ACoS) method. The ACoS is computed by dividing the Annual Revenue Requirement (ARR) determined by the Commission for recovery through tariffs by the total energy sales for the y(cid:72)(cid:68)(cid:85)(cid:17)(cid:3)(cid:43)(cid:82)(cid:90)(cid:72)(cid:89)(cid:72)(cid:85)(cid:15)(cid:3)(cid:87)(cid:75)(cid:76)(cid:86)(cid:3) (cid:80)(cid:72)(cid:87)(cid:75)(cid:82)(cid:71)(cid:82)(cid:79)(cid:82)(cid:74)(cid:92)(cid:3)(cid:71)(cid:82)(cid:72)(cid:86)(cid:81)(cid:182)(cid:87)(cid:3)(cid:76)(cid:81)(cid:71)(cid:76)(cid:70)(cid:68)(cid:87)(cid:72)(cid:3)(cid:87)(cid:75)(cid:72)(cid:3)(cid:70)(cid:82)(cid:86)(cid:87)(cid:86)(cid:3)(cid:76)(cid:81)(cid:70)(cid:88)(cid:85)(cid:85)(cid:72)(cid:71)(cid:3)(cid:69)(cid:92)(cid:3)(cid:70)(cid:82)(cid:81)(cid:86)(cid:88)(cid:80)(cid:72)(cid:85)(cid:86)(cid:3)(cid:68)(cid:87)(cid:3)(cid:71)(cid:76)(cid:73)(cid:73)(cid:72)(cid:85)(cid:72)(cid:81)(cid:87)(cid:3) (cid:89)(cid:82)(cid:79)(cid:87)(cid:68)(cid:74)(cid:72)(cid:3)(cid:79)(cid:72)(cid:89)(cid:72)(cid:79)(cid:86)(cid:3)(cid:88)(cid:86)(cid:76)(cid:81)(cid:74)(cid:3)(cid:71)(cid:76)(cid:73)(cid:73)(cid:72)(cid:85)(cid:72)(cid:81)(cid:87)(cid:3)(cid:68)(cid:86)(cid:86)(cid:72)(cid:87)(cid:86)(cid:3)(cid:82)(cid:73)(cid:3)(cid:87)(cid:75)(cid:72)(cid:3)(cid:81)(cid:72)(cid:87)(cid:90)(cid:82)(cid:85)(cid:78)(cid:17)(cid:3)(cid:55)(cid:75)(cid:72)(cid:85)(cid:72)(cid:73)(cid:82)(cid:85)(cid:72)(cid:15)(cid:3)(cid:76)(cid:87)(cid:3)(cid:71)(cid:82)(cid:72)(cid:86)(cid:81)(cid:182)(cid:87)(cid:3)(cid:75)(cid:72)(cid:79)(cid:83)(cid:3)(cid:76)(cid:81)(cid:3)(cid:71)(cid:72)(cid:87)(cid:72)(cid:85)(cid:80)(cid:76)(cid:81)(cid:76)(cid:81)(cid:74)(cid:3)(cid:68)(cid:70)(cid:70)(cid:88)(cid:85)(cid:68)(cid:87)(cid:72)(cid:3)(cid:87)(cid:68)(cid:85)(cid:76)(cid:73)(cid:73)(cid:86)(cid:3) for particular consumers, eventually resulting in insufficient cost coverage.

As a next logical step, the Voltage wise cost of supply (VCoS) method provides a better reflection of cost to supply to consumers at different voltage levels.

VCoS uses three parameters for allocating various costs to voltage levels (cid:177) energy input at each voltage level, energy sales and asset allocation to voltage levels. The losses segregated voltage wise (as percentage of input energy) are to be allocated to different voltage levels based on energy input to each voltage level (as explained in subsequent sections). Subsequently, the cost elements such as power procurement costs, employee expenses, administrative and general expenses and income tax can be allocated to each voltage levels based on total sales at each voltage level. The cost elements, which are dependent on assets such as depreciation, interest costs, return allowed to utility etc. are allocated in ratio of assets allocated to each voltage level. The sum of all the cost components at each voltage level is the cost to supply the particular voltage (EHT/HT/LT).

The Commission is of the opinion that while VCoS differentiates cost allocation based on voltage levels, it does not factor in consumer category level differentiation. For instance, at the same LT level, cost of supplying electricity to a Commercial consumer may be different from that of a domestic consumer. Thus, it believes that the most progressive way forward for the Distribution Licensee is to accurately determine the cost of supply is to attempt to determine Cost of Supply for various consumer categories and also voltage level. The Commission notes that States like Andhra Pradesh and Telangana have determined Category wise Cost of Supply albeit with several assumptions and the Distribution Licensee must also attempt to determine the same.

The Commission is of the opinion that for determination of the Category wise Cost of Supply, the embedded cost methodology is an appropriate starting point.

The Commission strongly believes that determination of Category wise Cost of Supply is essential to ensure cost reflectivity in tariffs fixed for different categories. However, the Commission feels that to carry out this135 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 83 Electricity Department, Government of Goa Tariff Principles and Design Joint Electricity Regulatory Commission (JERC) OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022 exercise a lot of field level information would be required such as Category wise co-incident and non- co- incident demand, Voltage wise value of assets (Voltage wise asset ratio), Voltage wise losses, Category wise break-up of costs related to Metering, Billing and Collection etc. which cur(cid:85)(cid:72)(cid:81)(cid:87)(cid:79)(cid:92)(cid:3) (cid:87)(cid:75)(cid:72)(cid:3) (cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:3) (cid:71)(cid:82)(cid:72)(cid:86)(cid:81)(cid:182)(cid:87)(cid:3) maintain. Therefore, in absence of the same, the Commission is unable to determine the Category wise Cost of Supply in this Order but directs the Petitioner to start maintaining this data and submit the same in the tariff proceedings of next year. In absence of the requisite data for determination of voltage-wise/category-wise cost of supply as mentioned above, the Commission as part of this Tariff Order has determined the tariff according to the Average Cost of Supply (ACoS).

Tariff Affordability

a) Context The Commission understands that the consumer base of Distribution Licensee is varied and covers a wide spectrum of socio-economic backgrounds, specially the domestic category consumers. It is also aware that most low-income households spend a substantial share of their income on utility services such as electricity, heating and water. However, any envisaged tariff reforms are often objected to avoid further burdening of these consumers. But to improve the quality of service of electricity, the Distribution Licensee has to undertake significant capital expenditure which eventually deteriorates the affordability of tariffs. Thus, to tackle this problem and in the spirit of economic wellbeing of all consumer classes, the concept of cross- subsidies has been built into the current tariff structure.

However, the Commission believes that a more scientific and logical approach can be adopted to identify the right categories of consumers and the right cross-subsidy/subsidy requirement that will benefit the end consumers at the same time. Hence, the Commission believes that there is a strong need to develop a scientific methodology to assess the social impact of electricity tariffs.

The overall approach that can be followed for determining the tariff affordability has been discussed as follows.

b) Approach

On reviewing methodologies adopted for social impact assessment of electricity tariffs, the Commission found that Tariff Affordability Ratio (TAR) is a reliable parameter to measure affordability of electricity in households.

TAR is defined by obtaining the burden incurred by a household for electricity as compared to the overall household expenditure. The rationale behind this concept is that the electricity is basic utility and is unavoidab(cid:79)(cid:72)(cid:3)(cid:76)(cid:81)(cid:3)(cid:87)(cid:82)(cid:71)(cid:68)(cid:92)(cid:182)(cid:86)(cid:3)(cid:86)(cid:70)(cid:72)(cid:81)(cid:68)(cid:85)(cid:76)(cid:82)(cid:15)(cid:3) (cid:75)(cid:82)(cid:90)(cid:72)(cid:89)(cid:72)(cid:85)(cid:15)(cid:3)(cid:87)(cid:75)(cid:76)(cid:86)(cid:3)(cid:71)(cid:82)(cid:72)(cid:86)(cid:3)(cid:81)(cid:82)(cid:87)(cid:3)(cid:72)(cid:81)(cid:86)(cid:88)(cid:85)(cid:72)(cid:3)(cid:87)(cid:75)(cid:68)(cid:87)(cid:3)(cid:87)(cid:75)(cid:72)(cid:3)(cid:72)(cid:91)(cid:83)(cid:72)(cid:81)(cid:71)(cid:76)(cid:87)(cid:88)(cid:85)(cid:72)(cid:3)(cid:79)(cid:72)(cid:89)(cid:72)(cid:79)(cid:3) (cid:76)(cid:86)(cid:3)(cid:76)(cid:81)(cid:3)(cid:79)(cid:76)(cid:81)(cid:72)(cid:3)(cid:90)(cid:76)(cid:87)(cid:75)(cid:3)(cid:87)(cid:75)(cid:72)(cid:3) overall household expenditure. Hence, this concept helps to understand the affordability level of electricity on households with different economic levels.

The electricity expenditure can be determined initially for domestic consumers by computing the average consumption levels across each slab and the household expenditure can be estimated from national surveys of household expenditure across economic levels conducted by organizations like NSSO. Thereafter the distribution of consumers of the Distribution Licensee across tariff slabs can be mapped across the established economic levels to develop the final affordability ratio matrix for the Distribution Licensee(cid:182)(cid:86)(cid:3) domestic consumer base.

Following the identification of the current ratio of Tariff Affordability, the Commission in consultation with the stakeholders will develop benchmarks for acceptable affordability levels by studying trends across countries with a demography and energy scenario similar to that of India and propose appropriate tariffs. The final output shall help understand the Commission to modify tariffs in cases where there is more room for tariff increase or a need to correct tariffs. The exercise would also help the Commission in setting tariff slabs as per the paying capacity of the consumers which would be beneficial especially for Domestic category consumers. Additionally, this shall also help the Government to formulate better schemes to effectively channelize its intended benefits.

136 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 84 Electricity Department, Government of Goa Tariff Principles and Design Joint Electricity Regulatory Commission (JERC) OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022

The Commission in these tariff proceedings is not carrying out this exercise due to unavailability of accurate data. The Petitioner is directed to ensure the sanctity of the data maintained pertaining to various categories.

Based on the discussions above, the Commission is continuing with its existing approach of determination of tariff for various consumer categories based on the Average Cost of Supply (ACoS) and reduction of Cross Subsidy amongst various consumer categories, ensuring consumer tariffs progressively moving towards the cost.

Cross Subsidy

As per Section 61 (g) of the Electricity Act 2003

(cid:179)(cid:11)(cid:74)(cid:12)(cid:3) (cid:87)(cid:75)(cid:68)(cid:87)(cid:3) (cid:87)(cid:75)(cid:72)(cid:3) tariff progressively reflects the cost of supply of electricity and also, reduces and

eliminates cross-subsidies within the period to be specified by the Appropriate Commission;(cid:180)

For reduction of cross subsidies, the Tariff Policy 2016 in Section 8.3 stipulates as below:

(cid:179)(cid:41)(cid:82)(cid:85)(cid:3) (cid:68)(cid:70)(cid:75)(cid:76)(cid:72)(cid:89)(cid:76)(cid:81)(cid:74)(cid:3) (cid:87)(cid:75)(cid:72)(cid:3) (cid:82)(cid:69)(cid:77)(cid:72)(cid:70)(cid:87)(cid:76)(cid:89)(cid:72)(cid:3) (cid:87)(cid:75)(cid:68)(cid:87)(cid:3) (cid:87)(cid:75)(cid:72)(cid:3) (cid:87)(cid:68)(cid:85)(cid:76)(cid:73)(cid:73)(cid:3) (cid:83)(cid:85)(cid:82)(cid:74)(cid:85)(cid:72)(cid:86)(cid:86)(cid:76)(cid:89)(cid:72)(cid:79)(cid:92)(cid:3) (cid:85)(cid:72)(cid:73)(cid:79)(cid:72)(cid:70)(cid:87)(cid:86)(cid:3) (cid:87)(cid:75)(cid:72)(cid:3) (cid:70)(cid:82)(cid:86)(cid:87)(cid:3) (cid:82)(cid:73)(cid:3) (cid:86)(cid:88)(cid:83)(cid:83)(cid:79)(cid:92)(cid:3) (cid:82)(cid:73)(cid:3) (cid:72)(cid:79)(cid:72)(cid:70)(cid:87)(cid:85)(cid:76)(cid:70)(cid:76)(cid:87)(cid:92)(cid:15)(cid:3) (cid:87)(cid:75)(cid:72)(cid:3)

Appropriate Commission would notify a roadmap such that tariffs are brought within ±20% of the

average cost of supply. The road map would also have intermediate milestones, based on the approach

(cid:82)(cid:73)(cid:3)(cid:68)(cid:3)(cid:74)(cid:85)(cid:68)(cid:71)(cid:88)(cid:68)(cid:79)(cid:3)(cid:85)(cid:72)(cid:71)(cid:88)(cid:70)(cid:87)(cid:76)(cid:82)(cid:81)(cid:3)(cid:76)(cid:81)(cid:3)(cid:70)(cid:85)(cid:82)(cid:86)(cid:86)(cid:3)(cid:86)(cid:88)(cid:69)(cid:86)(cid:76)(cid:71)(cid:92)(cid:17)(cid:180)

In order to achieve the objectives of the Tariff Policy 2016 of bringing down the cross subsidy levels amongst various consumer categories within ±20% of the average cost of supply, the Commission has tried to rationalize the tariff applicable to various consumer categories.

The limit of cross subsidy, as envisaged in the Tariff Policy 2016, can(cid:182)t be achieved by rationalizing the tariff in a single year, as this may lead to tariff shock to the cross subsidized consumers. In this Tariff Order, the Commission has continued its approach of rationalization of the tariff for various consumer categories and reducing the cross subsidy.

Accordingly, in this Tariff Order, the Commission has designed tariff for various consumer categories considering the Average Cost of supply in line with the provisions of the Tariff Policy, 2016. While designing the tariff for FY 2022-23, the Commission has reduced the cross-subsidy levels with an endeavored to bring the same within range specified in Tariff Policy 2016. To achieve this objective, the Commission has increased the tariff levels for cross-subsidized categories by higher than the average hike and either reduced/maintained the tariff levels or increased tariff at lower than average tariff hike for cross-subsidizing categories.

6.4.2. Approved Final Tariff Schedule

The existing retail tariff and tariff now approved by the Commission for each consumer category has been shown in the table below:

Category Existing Tariff Approved Tariff
Fixed Charges Energy Charges Fixed Charges Energy Charges
1 Domestic
A Low Tension-D/LT-D
0-100 units Single Phase INR 25/Con/Month Three Phase INR 65/Con/Month 1.50 INR/kWh INR 20/kW/Month 1.60 Rs/kWh
101-200 units 2.25 INR/kWh INR 20/kW/Month 2.35 Rs/kWh
201 to 300 units 2.85 INR/kWh INR 20/kW/Month 2.95 Rs/kWh
301 to 400 units 3.65 INR/kWh INR 20/kW/Month 3.90 Rs/kWh
Above 400 units 4.25 INR/kWh INR 20/kW/Month 4.50 Rs/kWh
B Low Tension-LIG/LT-LIG INR 50/Con/Month - INR 20/kW/Month -
C High Tension-D/HT-D
All Units INR 110/kVA/Month 3.65 INR/kVAh INR 110/kVA/Month 4.60 Rs/kVAh
2 Commercial
A Low Tension-C/LT-C
0-100 units For consumers with Load upto 20 kW INR 50/Con/Month For consumers with Load more than 20 kW and upto 90 kW INR 60/kW/Month 3.55 INR/kWh For consumers with Load upto 20 kW INR 40/kW/Month For consumers with Load more than 20 kW and upto 90 kW INR 60/kW/Month 3.55 INR/kWh
101-200 units 4.35 INR/kWh 4.35 INR/kWh
201 units- 400 units 4.85 INR/kWh 4.85 INR/kWh
Above 400 units 5.25 INR/kWh 5.25 INR/kWh
B High Tension-C/HT-C
All Units INR 250/kVA/month 5.50 INR/kVAh INR 250/kVA/month 5.25 INR/kVAh
3 Industrial
A Low Tension-I/LT-I
0-500 units INR 40/HP/Month 3.40 INR/kWh INR 40/HP/Month 3.40 INR/kWh
Above 500 units INR 40/HP/Month 3.95 INR/kWh INR 40/HP/Month 3.95 INR/kWh
B Low Tension-Mixed/LT-P (Hotel Industries)
All Units INR 50/kW/Month 4.95 INR/kWh INR 50/kW/Month 5.25 INR/kWh
C High Tension-I/HT-I
Connected at 11/33 kV INR 250/kVA/Month 4.80 INR/kVAh INR 250/kVA/Month 4.80 INR/kVAh
Connected at 110 kV INR 250/kVA/Month 4.70 INR/kVAh INR 250/kVA/Month 4.70 INR/kVAh
D High Tension- Ferro/SM/ PI/ SR
All Units INR 250/kVA/Month 4.80 INR/kVAh INR 250/kVA/Month 4.80 INR/kVAh
4 Agricultural
A Low Tension-AG/LT-AGP (Pump Sets/Irrigation)
All Units INR 18/HP/Month 1.50 INR/kWh INR 18/HP/Month 1.50 INR/kWh
B Low Tension-AG/LT-AGA (Allied Activities)
All Units INR 25/HP/Month 1.75 INR/kWh INR 25/HP/Month 1.75 INR/kWh
C High Tension-AG/HT-AGP (Pump Sets/Irrigation)
All Units INR 40/kVA/Month 1.60 INR/kVAh INR 40/kVA/Month 1.60 INR/kVAh
D High Tension-AG/HT-AG (Allied Activities)
All Units INR 70/kVA/Month 1.95 INR/kVAh INR 70/kVA/Month 1.95 INR/kVAh
5 Military Engineering Services/defense Establishments
All Units INR 200/kVA/Month 5.20 INR/kVAh INR 200/kVA/Month 4.90INR/kVAh
6 Public Lighting
All Units INR 70/kW/Month 4.20 INR/kWh INR 70/kW/Month 5.65 INR/kWh
7 Hoardings/Signboards
All Units INR 70/kVA/Month 10.00 INR/kWh INR 70/kVA/Month 10.00 INR/kWh
8 Temporary Supply
A LT Temporary Domestic Tariff shall be Fixed/Demand charges(if Tariff shall be Fixed/ Demand charges (if Tariff shall be Fixed/Demand charges Tariff shall be Fixed/ Demand charges
B LT Temporary Commercial any) plus energy charges (for relevant slab, if any) under corresponding permanent supply category plus 50% of both. For multi activity pursuit, applicable Tariff for temporary connection shall be with reference to that of commercial category for permanent supply. (if any) plus energy charges (for relevant slab, if any) under corresponding permanent supply category plus 50% of both. For multi activity pursuit, applicable Tariff for temporary connection shall be with reference to that of commercial category for permanent supply.
C HT Temporary
9 Single Point Supply
A Residential Complexes INR 110 per kVA per month or part thereof 3.55 INR/kVAh INR 110 per kVA per month or part thereof 3.55 INR/kVAh
B Commercial Complexes INR 220 per kVA per month or part thereof 4.80 INR/kVAh INR 220 per kVA per month or part thereof 4.80 INR/kVAh
C Industrial Complexes INR 220 per kVA per month or part thereof 4.40 INR/kVAh INR 220 per kVA per month or part thereof 4.40 INR/kVAh
10 Electric Vehicle Charging Station - 3.50 INR/kWh - 3.50* INR/kVAh
137 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 85 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA Tariff Principles and Design Joint Electricity Regulatory Commission (JERC) SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022 138 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 86 Electricity Department, Government of Goa Tariff Principles and Design Joint Electricity Regulatory Commission (JERC) OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022

*This tariff is applicable only for supply at HT. In case of LT supply, tariff will be INR 0.20/kVAh higher than the above

tariff.

6.4.3. Revenue from Approved Retail Tariff for FY 2022-23

Based on the retail tariff approved above, the Revenue from approved tariff is shown in the following table. The Commission has not estimated any revenue for Electric Vehicle Charging Station, Residential Complexes and Industrial Complexes categories as no sales have been booked under the respective categories. the Commission as of now approves the k factor for the category as shown in the table, however, directs the Petitioner to submit the requisite data for energy sales, no. of consumers and connected load in case any consumers are identified under these categories. Accordingly, the revenue from approved retail tariff is determined as follows:

S. No. Category Sales (MUs) Fixed Charges (INR Cr.) Energy charges (INR Cr.) Total Charges (INR. Cr.) ABR (INR./unit) K Factor
1 Domestic 1386.33 36.93 361.03 397.96 2.87 0.60
(i) LT-D Domestic 1384.58 36.89 360.84 397.74 2.87 0.60
0-100 units 544.79 11.80 87.17 98.96 1.82 0.38
101-200 units 331.54 9.07 77.91 86.98 2.62 0.55
201-300 units 175.22 6.17 51.69 57.86 3.30 0.69
301-400 units 96.50 3.48 37.64 41.12 4.26 0.89
Above 400 units 236.53 6.38 106.44 112.82 4.77 1.00
(ii) Low Income Group 1.37 0.00 - 0.00 0.02 0.00
(iii) HT-D Domestic 0.38 0.03 0.18 0.22 5.75 1.21
2 Commercial 607.53 44.89 301.75 346.64 5.71 1.20
(i) LT-C Commercial 472.52 21.79 228.11 249.90 5.29 1.11
0-100 units 77.99 4.59 27.69 32.28 4.14 0.87
101-200 units 47.80 1.69 20.79 22.49 4.70 0.99
201-400 units 60.12 3.14 29.16 32.30 5.37 1.13
Above 400 units 286.61 12.36 150.47 162.83 5.68 1.19
(ii) HT-C Commercial 135.02 23.10 73.64 96.74 7.17 1.50
3 Industrial 2139.85 189.41 1035.98 1225.39 5.73 1.20
(i) LT-I Industrial 80.91 7.05 31.07 38.12 4.71 0.99
0-500 units 16.18 3.40 5.50 8.90 5.50 1.15
Above 500 units 64.73 3.66 25.57 29.22 4.51 0.95
(ii) Low Tension- Mixed/LT-P (Hotel Industries) 4.48 0.14 2.35 2.49 5.56 1.17
(iii) High Tension- I/HT-I 1499.12 157.91 734.68 892.58 5.95 1.25
Connected at 11/33 kV 1247.94 135.20 616.15 751.36 6.02 1.26
Connected at 110 kV 251.18 22.70 118.52 141.22 5.62 1.18
(iv) High Tension- Ferro/SM/PI/SR 555.35 24.31 267.89 292.20 5.26 1.10
4 Agriculture 33.62 1.71 5.88 7.59 2.26 -
(i) Low Tension- AG/LT-AGP (Pump Sets/Irrigation) 17.29 1.09 2.59 3.69 2.13 -
(ii) Low Tension- AG/LT-AGA (Allied Activities) 0.79 0.05 0.14 0.19 2.42 -
(iii) High Tension- AG/HT-AGP (Pump Sets/Irrigation) 4.89 0.44 1.03 1.47 3.01 -
(iv) High Tension- AG/HT-AG (Allied Activities) 10.65 0.12 2.12 2.24 2.11 -
5 Military Engineering Services/ defense Establishments 26.96 1.73 13.70 15.43 5.72 1.20
6 Public Lighting 29.61 0.23 16.73 16.96 5.73 1.20
7 Hoardings/Signb oards 0.16 0.04 0.16 0.20 12.48 2.62
8 Temporary 12.10 0.00 10.18 10.18 8.41 1.50*
(i) LT 9.77 0.00 8.07 8.07 8.26 1.50*
LT Domestic 0.69 0.00 0.30 0.30 4.31
LT Commercial 9.08 0.00 7.77 7.77 8.56
(ii) HT 2.33 0.00 2.11 2.11 9.04
5.69 0.91 2.76 3.67 6.44
9 Single Point Supply 0.00 0.00 0.00 0.00 1.35
(i) Residential Complexes 5.69 0.91 2.76 3.67 6.44 0.00
(ii) Commercial Complexes 0.00 0.00 0.00 0.00 1.35
(iii) Industrial Complexes 0.00 0.00 0.00 0.00 0.00
10 Electric Vehicle Charging Station - - - - - 0.74
TOTAL 4241.87 275.84 1748.18 2024.02 4.77 1.00
139 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 87 Electricity Department, Government of Goa Tariff Principles and Design Joint Electricity Regulatory Commission (JERC) OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022 140 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 88 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA Tariff Principles and Design Joint Electricity Regulatory Commission (JERC) SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022

The Commission approves revenue from approved Retail Tariff of INR2024.02 Cr. for the FY

2021-22

The average increase in the retail tariff now approved by the Commission vis-à-vis the prevailing tariff is 1.58%.

The table below provides the category wise Average Cost of Supply (ACoS), existing Average Billing Rate (ABR), Approved ABR and category wise increase in tariff approved by Commission.

Table 76: Tariff increase approved by Commission

Increase

Category ACoS

ABR at

Approved

Tariff

Cross Subsidy

level at

approved tariff

ABR at

Existing

Tariff

(%)

(Rs/kwh)

Cross Subsidy

level at

existing tariff

(%)

Domestic 5.68 2.66 2.87 8.07% 46.8% 50.6%
Commercial 5.68 5.74 5.71 -0.52% 101.0% 100.5%
Industrial 5.68 5.68 5.68 0.00% 100.0% 100.0%
Agriculture 5.68 2.26 2.26 0.00% 39.8% 39.8%
Military Engineering Services 5.68 6.03 5.72 -5.16% 106.3% 100.8%
Public Lighting 5.68 4.28 5.73 33.90% 75.3% 100.9%
Hoardings/ Signboards 5.68 12.48 12.48 0.00% 219.9% 219.9%
Temporary 5.68 8.42 8.41 -0.18% 148.4% 148.1%
Single Point Supply 5.68 6.44 6.44 0.00% 113.5% 113.5%
Total 5.68 4.70 4.77 1.58% 82.7% 84.0%

It can be observed in the above table thatthe Commission has increased the tariff levels for cross-subsidized categories by higher than the average hike and has reduced/maintained the tariff levels at lower than average tariff hike for cross-subsidizing categories.

6.4.4. Revenue Gap/ (Surplus) at Approved Tariff

The Govt. of Goa vide its letter No. 1/14/2021-FIN (BUD)/300 dated 29thDecember 2021has conveyed its consent for providing the required budgetary support to meet the revenue gap for the year as may be approved by the Commission. Moreover, no gap is carried forward from previous years to FY 2022-23 as the Govt. of Goa had provided an upfront budgetary support for the entire gap in FY 2021-22.

In view of above the Commission approves the revenue gap as follows:

S. No. Particulars FY 2022-23
1 Net Revenue Requirement 2,408.15
2 Revenue from Retail Sales at Existing Tariff 1,992.53
3 Revenue from Retail Sales at Approved Tariff 2,024.02
4 Revenue Gap/ (Surplus) at Existing Tariff 415.62
5 Revenue Gap/ (Surplus) at Approved Tariff 384.13
6 Gap/(Surplus) for the previous year -
7 Total Gap/ (Surplus) 384.13
8 Budgetary support from Govt. of Goa 384.13
9 Final Gap/ (Surplus) for FY 2022-23 -
141 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 89 Electricity Department, Government of Goa Tariff Principles and Design Joint Electricity Regulatory Commission (JERC) OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022

The Govt. of Goa has given an upfront commitment to bridge the revenue gap by way of

budgetary support, in line with the practice followed in previous years.

6.4.5. Government Budgetary Support

The Commission has approved an overall revenue gap of INR 384.13 Cr at approved tariff in FY 2022-23. The Govt. of Goavide its letter No. 1/14/2021-FIN (BUD)/300 dated 29thDecember 2021 has given an upfront commitment to bridge the revenue gap by way of budgetary support for any revenue gap that may arise.

It is observed that the Govt. of Goa has been providing budgetary assistance to the Petitioner during the past (cid:73)(cid:72)(cid:90)(cid:3)(cid:92)(cid:72)(cid:68)(cid:85)(cid:86)(cid:17)(cid:3)(cid:55)(cid:75)(cid:72)(cid:3)(cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:3)(cid:76)(cid:81)(cid:3)(cid:87)(cid:75)(cid:76)(cid:86)(cid:3)(cid:80)(cid:68)(cid:87)(cid:87)(cid:72)(cid:85)(cid:3)(cid:90)(cid:82)(cid:88)(cid:79)(cid:71)(cid:3)(cid:79)(cid:76)(cid:78)(cid:72)(cid:3)(cid:87)(cid:82)(cid:3)(cid:83)(cid:82)(cid:76)(cid:81)(cid:87)(cid:3)(cid:82)(cid:88)(cid:87)(cid:3)(cid:87)(cid:75)(cid:72)(cid:3)(cid:82)(cid:89)(cid:72)(cid:85)(cid:3)(cid:85)(cid:72)(cid:79)(cid:76)(cid:68)(cid:81)(cid:70)(cid:72)(cid:3)(cid:82)(cid:73)(cid:3)(cid:87)(cid:75)(cid:72)(cid:3)(cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:3)(cid:82)(cid:81)(cid:3)(cid:42)(cid:82)(cid:89)(cid:87)(cid:17)(cid:182)(cid:86)(cid:3) budgetary support. The Petitioner should prepare itself of the repercussions in case the Govt. withdraws the budgetary support in the future.

The ABR without the Government Budgetary support has been calculated considering the per unit gap of INR 0.91/kWh (difference between ACoS and ABR at Approved Tariff with Govt. Budgetary Support). However, the Commission would like to highlight that in case this gap had to be entirely fulfilled by revenue from consumers then it would have demanded an additional average tariff increase of 18.98%.

6.4.6. Highlights of the Tariff Structure

The highlights of the tariff structure approved by the Commission for FY 2022-23 are as follows:

1. The Govt. of Goa vide its letter No. 1/14/2021-FIN (BUD)/300 dated 29th December 2021 has conveyed its consent for providing the required budgetary support to meet the revenue gap for the year as may be approved by the Commission. The Commission acknowledges theletter of assurance from the Government of Goa towards meeting any prospective revenue gap for FY 2022-23.

2. The Petitioner has proposed a reduction in average tariff rate thereby estimating a reduction of INR 108.44 Cr. from the projected revenue in FY 2022-23.

3. The Commission has approved an average tariff hike of 1.58% to further reduce the reliance of the Petitioner on budgetary support from the Govt. of Goa. The Commission has also introduced fixed charges based on connected load for all Domestic and Commercial slabs.

4. The Commission has increased the tariff levels for cross-subsidized categories by higher than the average hike and has reduced/maintained the tariff levels at lower than average tariff hike for cross- subsidizing categories.

142 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 90 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA Open Access Charges Joint Electricity Regulatory Commission (JERC) SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022

7. Chapter 7: Open Access Charges for

the FY 2022-23

7.1. Wheeling Charges

7.1.1. Allocation Matrix - Allocation of ARR into Wheeling and

Retail Supply of Electricity

(cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:54)(cid:88)(cid:69)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81):

The Petitioner has submitted the bifurcation of all expenses of FY 2022-23 between the functions of wheeling business (wire business) and retail supply business based on the Regulation 49 of the JERC MYT Regulations, 2021. The summary of the allocation statement and the segregation of ARR into wheeling and retail supply business for FY 2022-23 is given in the table below:

Sl. No. Particulars Distribution Wires Business Retail Supply Business FY 2022-23 (INR Cr.)
% % Distribution Wire business Retail Supply Business Total
1 Cost of Power Purchase from Own Generating Stations
2 Cost of Power Purchase from other Generating Stations 0% 100% 0.00 1,439.07 1,439.07
3 Inter State Transmission Charges 0% 100% 0.00 221.36 221.36
4 Intra State Transmission Charges
5 SLDC Fees & Charges
6 O&M Expenses (Gross) 223.39 250.64 474.02
a) R&M Expenses 90% 10% 55.75 6.19 61.94
b) Employee Cost 40% 60% 153.60 230.40 384.01
c) A&G Expenses 50% 50% 14.04 14.04 28.07
7 Depreciation 90% 10% 76.96 8.55 85.51
8 Interest and Finance Charges 90% 10% 40.41 4.49 44.90
9 Interest on Working Capital 10% 90% 2.61 23.52 26.14
10 Prior Period Expenses
Interest on Consumer Security Deposit 10% 90% 0.56 5.03 5.58
11 Extraordinary Items
12 Bad and Doubtful Debts 0% 100%
13 Other Debts and Write-offs
14 Statutory Levies and Taxes, if any
15 Less: Expenses Capitalised
a) Interest Charges Capitalized
b) R&M Expenses Capitalized
c) A&G Expenses Capitalized d) Employee Cost Capitalized
Sub Total (a+b+c+d)
Sub Total Expenditure (1 to 14-15) 343.93 1952.66 2,296.59
16 Return on Equity 90% 10% 76.56 8.78 85.34
17 Less: Non-Tariff and other Income 10% 90% 2.08 18.70 20.78
18 Less: Any Grant/ Subventions, other subsidy provided by the Government
19 Annual Revenue Requirement 418.41 1942.74 2,361.15
20 Energy Sales 4086.29
21 Average Cost of Supply (Rs./kWh) 5.78
143 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 91 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA Open Access Charges Joint Electricity Regulatory Commission (JERC) SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022

The Petitioner has further submitted that it has computed the wheeling charges based on the following methodology:

a) O&M Expenses consisting of Employee, A&G and R&M expenses are allocated to each voltage level based on number of consumers.

b) All expenses other than the O&M expenses are allocated to each voltage level based on voltage wise asset allocation.

c) The resultant cost at HT/EHT voltage level derived after performing the above steps is then divided between LT and HT/EHT voltage level on the basis of input energy at respective voltage levels, since the HT/EHT network is used by consumers of both HT/EHT and LT voltage levels.

Accordingly, the computation of Wheeling charges as submitted by the Petition has been shown in the following table:

Category O&M expenses (INR Cr.) Other Expenses (INR Cr.) Total Expenses (INR Cr.) Sales (MU) Wheeling Charges (INR/kWh)
Low Tension (LT) Level 223.00 117.01 417.68 1927.36 1.76
High Tension (HT)/ Extra High Tension (EHT)Level 0.39 78.01 0.73 2158.94 0.36
Total 223.39 195.02 418.41 4086.29 1.02

(cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:182)(cid:86)(cid:3)(cid:68)(cid:81)(cid:68)(cid:79)(cid:92)(cid:86)(cid:76)(cid:86):

The allocation between wheeling and retail supply business for the FY 2022-23as per the ARR approved in this Order is provided in the table below:

Particulars Allocation (%) FY 2021-22
Wires Business (%) Retail Supply Business (%) Wires Business (Rs Cr) Retail Supply Business (Rs Cr) Total ARR (Rs Cr)
Power purchase expenses inclusive of Inter-State Transmission expenses 0% 100% 0.00 1839.53 1839.53
Employee costs 40% 60% 137.82 206.74 344.56
Administration and General Expenses 50% 50% 17.03 17.03 34.06
Repair and Maintenance Expenses 90% 10% 49.80 5.53 55.33
Depreciation 90% 10% 47.38 5.26 52.64
Interest on Loan 90% 10% 20.03 2.23 22.26
Interest on Working Capital 10% 90% 1.81 16.31 18.13
Interest on consumer security deposit 10% 90% 0.36 3.24 3.60
Return on Equity 90% 10% 57.74 6.62 64.36
Bad & Doubtful Debt written off 0% 100% 0.00 0.00 0.00
Income Tax 90% 10% 0.00 0.00 0.00
Total Revenue Requirement 331.97 2102.49 2434.47
Less: Non-Tariff Income 10% 90% 2.63 23.69 26.32
Net Revenue Requirement 329.34 2078.81 2408.15
144 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 92 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA Open Access Charges Joint Electricity Regulatory Commission (JERC) SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022

To determine the wheeling charges, the wheeling costs are allocated on the basis of voltage levels. The wheeling charges are levied for the distribution network utilized by the Open Access consumers and primarily comprises of O&M Expenses and other costs as provided in the table above.

The methodology adopted for allocating the derived wheeling costs at respective voltage levels has been elaborated as follows:

(cid:120) O&M Expenses consisting of Employee, A&G and R&M expenses are allocated to each voltage level on the basis of number of consumers

(cid:120) All expenses other than the O&M expenses are allocated to each voltage level on the basis of voltage wise asset allocation. The Petitioner in this regard was directed to submit the voltage wise asset allocation but has failed to submit the desired information and in the absence of such information, the Commission has assumed the voltage wise asset allocation.

(cid:120) The resultant cost at HT/EHT voltage level derived after performing the above steps is then divided between LT and HT/EHT voltage level on the basis of input energy at respective voltage levels, since the HT/EHT network is used by consumers of both HT/EHT and LT voltage levels.

(cid:120) The energy input has been determined assuming the cumulative loss level of HT/EHT voltage as 3.64%, which is the same as approved in the MYT Order for FY 2021-22. The Petitioner in this regard has failed to submit the voltage wise losses. The resultant losses have been loaded to the LT voltage level in order to maintain the overall Intra-State T&D loss at 10.25% as approved in the Business Plan Order dated 31.03.2022.

Category No. of Consumers Asset Allocation (%) Sales (MU) Cumulative Voltage wise Losses (%)
Low Tension (LT) Level 720,039 60.00% 2,001.31 16.65%
High Tension (HT)/ Extra High Tension (EHT) Level 1,366 40.00% 2,240.55 3.64%
Total 721,405 100.00% 4,241.87 10.25%
145 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 93 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA Open Access Charges Joint Electricity Regulatory Commission (JERC) SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022

Accordingly, the Commission approves the Wheeling Charges as shown in the table below:

Category O&M (INR Cr) Others (INR Cr) Total (INR Cr) Sales (MU)
Low Tension (LT) Level 204.46 100.15 304.61 2,001.31
High Tension (HT)/ Extra High Tension(EHT) Level 0.19 24.54 24.73 2,240.55
Total 204.65 124.69 329.34 4,241.87
Category O&M (INR Cr) Others (INR Cr) Total (INR Cr) Sales (MU) Wheeling Charges (INR/kWh)
Low Tension (LT) Level 204.46 100.15 304.61 2,001.31 1.52
High Tension (HT)/ Extra High Tension (EHT) Level 0.19 24.54 24.73 2,240.55 0.11
Total 204.65 124.69 329.34 4,241.87

The Commission approves wheeling charge of INR 1.52/kWh at LT voltage level and INR

0.11/kWh at HT/EHT voltage level

7.2. Additional Surcharge

(cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:86)(cid:88)(cid:69)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:29)

The Petitioner has computed the additional surcharge based on the methodology followed by the Commission in the Tariff Order for FY 2021-22. The additional surcharge determined by the Petitioner for FY 2022-23 has been provided in the table as follows:

Particulars FY 2022-23
Total Power Purchase cost approved 1,615.79
Fixed Cost component in Power Purchase Cost (excluding Transmission Charges) 422.80
Energy Sales (MU) 4,086.29
Additional Surcharge (INR/kWh) 1.03

(cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:182)(cid:86)(cid:3)(cid:68)(cid:81)(cid:68)(cid:79)(cid:92)(cid:86)(cid:76)(cid:86)(cid:29)

The Commission has notified the Joint Electricity Regulatory Commission for the State of Goa and Union Territories (Connectivity and Open Access in Intra-State Transmission and Distribution) Regulations, 2017.

Regulation 4.5 (1) of the said Regulations states the following:

(cid:179)An Open Access Consumer, receiving supply of electricity from a person other than theDistribution Licensee

of his area of supply, shall pay to the Distribution Licensee an additionalsurcharge in addition to wheeling

146 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 94 Electricity Department, Government of Goa Open Access Charges Joint Electricity Regulatory Commission (JERC) OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022

charges and cross-subsidy surcharge, to meet the fixed cost ofsuch Distribution Licensee arising out of his

obligation to supply as provided under sub-section (4)of Section 42 of the Ac(cid:87)(cid:180)

Regulation 4.5 (2) of the said Regulations stipulates:

This additional surcharge shall become applicable only if the obligation of the Licensee interms of power

purchase commitments has been and continues to be stranded or there is anunavoidable obligation and

incidence to bear fixed costs by the Licensee consequent to such acontract. However, the fixed costs related to

network assets would be recovered through wheeling charges.

Further, Regulation 5.2 (1) (b) states the following:

The quantum of drawal of electricity by a partial Open AccessConsumerfrom theDistribution Licensee during

(cid:68)(cid:81)(cid:92)(cid:3)(cid:55)(cid:76)(cid:80)(cid:72)(cid:3)(cid:37)(cid:79)(cid:82)(cid:70)(cid:78)(cid:3)(cid:82)(cid:73)(cid:3)(cid:68)(cid:3)(cid:39)(cid:68)(cid:92)(cid:3)(cid:86)(cid:75)(cid:82)(cid:88)(cid:79)(cid:71)(cid:3)(cid:81)(cid:82)(cid:87)(cid:3)(cid:72)(cid:91)(cid:70)(cid:72)(cid:72)(cid:71)(cid:3)(cid:87)(cid:75)(cid:72)(cid:179)(cid:36)(cid:71)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:69)(cid:79)(cid:72)(cid:3)(cid:39)(cid:85)(cid:68)(cid:90)(cid:79)(cid:3)(cid:82)(cid:73)(cid:3)(cid:40)(cid:79)(cid:72)(cid:70)(cid:87)(cid:85)(cid:76)(cid:70)(cid:76)(cid:87)(cid:92)(cid:3)(cid:69)(cid:92)(cid:3)(cid:87)(cid:75)(cid:72)(cid:3)(cid:50)(cid:83)(cid:72)(cid:81)(cid:3)(cid:36)(cid:70)(cid:70)(cid:72)(cid:86)(cid:86)(cid:38)(cid:82)(cid:81)(cid:86)(cid:88)(cid:80)(cid:72)(cid:85)(cid:180)(cid:3)

which is the differenceof Contract Demand and maximum quantum of Open Access for which approval

hasbeen granted by the Nodal Agency.

[Illustration: If an Open AccessConsumer with a Contract Demand of 10 MW has beengiven an approval for a

maximum Open Access quantum of 6MW for a period of 3Months, the Admissible Drawl of Electricity from

the Distribution Licensee during anyTime Block shall be 4 MW for any Da(cid:92)(cid:3)(cid:71)(cid:88)(cid:85)(cid:76)(cid:81)(cid:74)(cid:3)(cid:68)(cid:3)(cid:83)(cid:72)(cid:85)(cid:76)(cid:82)(cid:71)(cid:3)(cid:82)(cid:73)(cid:3)(cid:22)(cid:3)(cid:48)(cid:82)(cid:81)(cid:87)(cid:75)(cid:86)(cid:17)(cid:64)(cid:180)

Therefore, in accordance with the above Regulations, the Commission has determined the Additional Surcharge as per the following:

Particulars 2022-23
Total Power Purchase cost approved 1,839.53
Fixed Cost component in Power Purchase Cost (excluding Transmission Charges) 427.56
Energy Sales (MU) 4,241.87
Additional Surcharge (INR/kWh) 1.01

Earlier, a consumer availing Open Access was required to pay fixed charges on contracted load even when the load was drawn partially from the Distribution Licensee. In addition, the consumer was also required to pay wheeling charges, additional surcharge and the cross-subsidy surcharge. As per the (cid:81)(cid:72)(cid:90)(cid:3) (cid:179)Open Access Regulations, 2017(cid:180), a consumer may choose to pay fixed charges on reduced demand after adjusting for demand drawn through Open Access in accordance with the regulation.

The Commission approves an Additional Surcharge of INR1.01/kWh for FY 2022-23.

The Commission directs the Petitioner to submit quarterly details of the power stranded on account of consumers opting for open access along with the Additional Surcharge recovered from these consumers. The Commission will analyse the information and change the applicable Additional Surcharge, if required.

7.3. Cross-Subsidy Surcharge

(cid:51)(cid:72)(cid:87)(cid:76)(cid:87)(cid:76)(cid:82)(cid:81)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:86)(cid:88)(cid:69)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:29)

The Petitioner has adopted the same methodology for computation of Cross-Subsidy Surcharge as approved by the Commission in the Tariff Order for FY 2021-22. The cross-subsidy surcharge determined by the Petitioner for FY 2022-23 has been provided in the table as follows:

Category VCoS (INR/kWh) ABR (INR/kWh) Cross- Subsidy (INR/kWh)
Low Tension (LT) Level 7.20 3.19 -
High Tension (HT)/ Extra High Tension(EHT) Level 4.31 6.42 2.12
147 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 95 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA Open Access Charges Joint Electricity Regulatory Commission (JERC) SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022

(cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:182)(cid:86)(cid:3)(cid:68)(cid:81)(cid:68)(cid:79)(cid:92)(cid:86)(cid:76)(cid:86)(cid:29)

The Commission in this Order has calculated the cross-subsidy surcharge with respect to voltage wise cost of supply. The following approach has been adopted to determine the voltage wise cost of supply:

(cid:120) Voltage Wise losses are assumed for HT/EHT voltage level. The remaining losses are adjusted in the LT voltage level in order to maintain the Intra-State T&D losses at 10.25%, as approved in the ARR for FY 2022-23. Voltage wise losses assumed at each level have been shown in the table below:

Category Voltage Level Loss (%) Cumulative Losses upto that voltage level (%)
Low Tension (LT) Level 13.50% 16.65%
High Tension (HT)/ Extra High Tension (EHT) Level 3.64% 3.64%
Total 10.25% 10.25%

Using these losses, the energy input at each voltage level is determined based on the energy sales. The following table shows the energy input at each voltage level

Category Energy Sales (MU) Cumulative Losses (%) Energy Input (MU)
Low Tension (LT) Level 2,001.31 16.65% 2,401.12
High Tension (HT)/ Extra High Tension (EHT) Level 2,240.55 3.64% 2,325.19
Total 4,241.87 10.25% 4,726.31

Now the overall ARR approved for FY 2022-23 is divided into variable and fixed ARR with variable ARR comprising of variable component of the power purchase cost and fixed ARR comprising of all the other costs.

The fixed component comprising of fixed cost of power purchase, O&M etc. is further allocated to each voltage category as per the following principles:

(cid:120) The fixed cost of power purchase is assigned to each voltage level on the basis of energy input at respective voltage levels.

(cid:120) The O&M expenses are allocated to each voltage level on the basis of the number of consumers. The resultant cost allocated to HT/EHT level is then further allocated between HT/EHT and LT level on the basis of input energy, as the HT/EHT network is utilized by both LT and HT/EHT network consumers.

(cid:120) The remaining fixed costs are allocated on the basis of voltage wise asset allocation assumed earlier and further allocated to respective voltage levels on the basis of input energy.

Category Energy Input (MU) Voltage wise Asset Allocation (%) Number of Consumers
Low Tension (LT) Level 2,401.12 60.00% 720,039
Fuel and Power Purchase Adjustment Mechanism High Tension (HT)/ Extra High Tension(EHT) Level 2,325.19 40.00% Joint Electricity Regulatory Commission (JERC) 1,366
Total 4,726.31 Energy Input Voltage wise 100.00% 721,405 Number of
148 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 96 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA Open Access Charges Joint Electricity Regulatory Commission (JERC) SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022

The Variable component of the Power purchase cost is allocated on the basis of energy input. The Voltage wise

2,325.19 40.00% 1,366 High Tension (HT)/ Extra High Tension(EHT) Level

cost of supply (VCoS) is then determined on the basis of energy sales of respective categories. Accordingly, the

4,726.31 100.00% 721,405 Total

VCoS is determined as shown in the table below:

The Variable component of the Power purchase cost is allocated on the basis of energy input. The Voltage wise Table 90: Voltage Wise Cost of Supply (VCoS) cost of supply (VCoS) is then determined on the basis of energy sales of respective categories. Accordingly, the

VCoS is determined as shown in the table below: Category Allocated Fixed Cost Table 90: Voltage Wise Cost of Supply (VCoS) (INR Cr) Allocated Variable Cost (INR Cr) Total Cost (INR Cr) Energy Sales (MU) VCoS (INR/kwh)
Low Tension (LT) Level Allocated 873.82 Allocated 602.44 1,476.25 Total Cost Energy 2,001.31 7.38 VCoS
Category High Tension (HT)/ Extra High Tension(EHT) Low Tension (LT) Level Level High Tension (HT)/ Fixed Cost (INR Cr) 348.51 87382 Variable Cost (INR Cr) 583.38 60244 (INR Cr) 931.89 1,47625 Sales (MU) 2,240.55 2,00131 (INR/kwh) 4.16 738
Extra High Tension(EHT) Total 1,222.33 34851 1,185.82 58338 2,408.15 93189 4,241.87 2,24055 416

This, VCoS is then used to determine the Cross-Subsidy Surcharge at each voltage level.

Table 91: Cross-Subsidy Surcharge approved by Commission (INR/kWh)

Table 91: Cross-Subsidy Surcharge approved by Commission (INR/kWh) Category Category VCoS VCoS (INR/kWh) ABR ABR (INR/kWh) Cross- Subsidy Cross- Subsidy (INR/kWh)
Low Tension (LT) Level (INR/kWh) 7.38 (INR/kWh) 3.58 (INR/kWh) -
Low Tension (LT) Level High Tension (HT)/ Extra High Tension (HT)/ Extra High Tension(EHT) Level High Tension(EHT) Level 738 4.16 416 358 5.83 583 - 1.67 167

The Commission approves nil Cross-Subsidy Surcharge at LT Voltage level and INR 1.67/kWh at The Commission approves nil Cross-Subsidy Surcharge at LT Voltage level and INR 1.67/kWhat

HT/EHT Voltage level, in FY 2022-23.

HT/EHT Voltage level, in FY 2022-23.

149 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 97 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA Fuel and Power Purchase Adjustment Mechanism Joint Electricity Regulatory Commission (JERC) SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022

8. Chapter 8: Fuel and Power Purchase

Adjustment Mechanism

The State of Goa and Union Territories of Andaman & Nicobar Islands, Lakshadweep Island, Chandigarh, Daman & Diu, Dadra & Nagar Haveli and Puducherry receive power from the Central Generating Stations, State Ge(cid:81)(cid:72)(cid:85)(cid:68)(cid:87)(cid:76)(cid:81)(cid:74)(cid:3)(cid:54)(cid:87)(cid:68)(cid:87)(cid:76)(cid:82)(cid:81)(cid:86)(cid:15)(cid:3)(cid:44)(cid:81)(cid:71)(cid:72)(cid:83)(cid:72)(cid:81)(cid:71)(cid:72)(cid:81)(cid:87)(cid:3)(cid:51)(cid:82)(cid:90)(cid:72)(cid:85)(cid:3)(cid:51)(cid:85)(cid:82)(cid:71)(cid:88)(cid:70)(cid:72)(cid:85)(cid:182)(cid:86)(cid:3)(cid:11)(cid:44)(cid:51)(cid:51)(cid:182)(cid:86)(cid:12)(cid:3)(cid:87)(cid:75)(cid:85)(cid:82)(cid:88)(cid:74)(cid:75)(cid:3)(cid:87)(cid:75)(cid:72)(cid:3)(cid:79)(cid:82)(cid:81)(cid:74)-term power purchase agreements and short-term purchases (cid:177) through exchange, bilateral purchases etc. The distribution licensees procure power from various available sources and supply power to the consumers at retail tariffs determined by the Commission. Power purchase cost accounts for more than 80% of the Annual Revenue Requirements (ARR) of the distribution licensees and includes the cost paid for procurement of power, transmission charges, Deviation Settlement Mechanism (DSM) charges, State Load Despatch Center (SLDC)/ Regional Load Despatch Center (RLDC) charges and is netted off with revenue earned from the sale of surplus power.

The cost of the long-term power being procured by the distribution licensees is fixed by the Central Electricity Regulatory Commission (CERC) for plants supplying power to more than one State/UT (for example NTPC, (cid:49)(cid:43)(cid:51)(cid:38)(cid:3)(cid:72)(cid:87)(cid:70)(cid:17)(cid:12)(cid:3)(cid:68)(cid:81)(cid:71)(cid:3)(cid:69)(cid:92)(cid:3)(cid:87)(cid:75)(cid:72)(cid:3)(cid:45)(cid:40)(cid:53)(cid:38)(cid:3)(cid:73)(cid:82)(cid:85)(cid:3)(cid:83)(cid:79)(cid:68)(cid:81)(cid:87)(cid:86)(cid:3)(cid:79)(cid:82)(cid:70)(cid:68)(cid:87)(cid:72)(cid:71)(cid:3)(cid:90)(cid:76)(cid:87)(cid:75)(cid:76)(cid:81)(cid:3)(cid:87)(cid:75)(cid:72)(cid:3)(cid:85)(cid:72)(cid:74)(cid:76)(cid:82)(cid:81)(cid:3)(cid:11)(cid:73)(cid:82)(cid:85)(cid:3)(cid:44)(cid:51)(cid:51)(cid:182)(cid:86)(cid:15)(cid:3)(cid:79)(cid:76)(cid:70)(cid:72)(cid:81)(cid:86)(cid:72)(cid:72)(cid:86)(cid:3)(cid:82)(cid:90)(cid:81)(cid:3)(cid:74)(cid:72)(cid:81)eration and other State generating sources). Charges for the Over-drawal/Under-drawal from the Grid and the Inter-State Transmission charges, RLDC charges are fixed by the CERC, while Intra-State Transmission charges and SLDC charges are fixed by the JERC. Short term purchase/ sale of power is done through traders, bilateral contracts, banking and power exchanges at market-determined prices.

While determining retail tariff for any year, the Commission first determines the ARR based on the projection of various cost elements including power purchase cost. Power purchase cost of the distribution licensee is derived from the power purchase quantum and per unit power purchase cost. Quantum of power purchase depends upon the energy sales to the retail consumer and distribution losses, out of which energy sales is not under the control of the distribution licensee. There is also variation in actual per unit power purchase cost vis- a-vis projected per unit power purchase cost due to change in fuel cost, change in power purchase mix i.e. thermal /hydel/renewable mix, long term/short term power mix etc. This makes power purchase cost uncontrollable in nature.

The Commission undertakes the truing up exercise for the variation in the cost and revenue once the audited accounts of the distribution licensee are available. For example, True-up of FY 2016-17 will be undertaken by the Commission once the audited accounts of FY 2016-17 are available. If the audited accounts for FY 2016-17 are prepared timely, the impact of true-up of various cost and revenue items is allowed in the tariff of FY 2018- 19, along with the carrying cost for 2 years. As the power purchase cost is the major cost element of the ARR of the distribution licensee, adjustment due to change in power purchase cost at regular intervals is important in order to avoid the burden of carrying cost on the additional power purchase cost incurred during the year.

8.1. Legal Provisions

The relevant provisions of the Electricity Act, Regulations, Policy document and the ATE judgments, which enable the Commission to devise, adopt and implement a power purchase/ fuel price adjustment mechanism are as follows:-

(a) Electricity Act, 2003- Section 62 (4)

(cid:179)(cid:49)(cid:82)(cid:3)(cid:87)(cid:68)(cid:85)(cid:76)(cid:73)(cid:73)(cid:3)(cid:82)(cid:85)(cid:3)(cid:83)(cid:68)(cid:85)(cid:87)(cid:3)(cid:82)(cid:73)(cid:3)(cid:68)(cid:81)(cid:92)(cid:3)(cid:87)(cid:68)(cid:85)(cid:76)(cid:73)(cid:73)(cid:3)(cid:80)(cid:68)(cid:92)(cid:3)(cid:82)(cid:85)(cid:71)(cid:76)(cid:81)(cid:68)(cid:85)(cid:76)(cid:79)(cid:92)(cid:3)(cid:69)(cid:72)(cid:3)(cid:68)(cid:80)(cid:72)(cid:81)(cid:71)(cid:72)(cid:71)(cid:3)(cid:80)(cid:82)(cid:85)(cid:72)(cid:3)(cid:73)(cid:85)(cid:72)(cid:84)(cid:88)(cid:72)(cid:81)(cid:87)(cid:79)(cid:92)(cid:3)(cid:87)(cid:75)an once in any financial

year, except in respect of any changes expressly permitted under the terms of any fuel surcharge

(cid:73)(cid:82)(cid:85)(cid:80)(cid:88)(cid:79)(cid:68)(cid:3)(cid:68)(cid:86)(cid:3)(cid:80)(cid:68)(cid:92)(cid:3)(cid:69)(cid:72)(cid:3)(cid:86)(cid:83)(cid:72)(cid:70)(cid:76)(cid:73)(cid:76)(cid:72)(cid:71)(cid:17)(cid:180)

(b) Tariff Policy, 2016, clause 5.11 (cid:177) sub-clause (h-4)

150 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 98 Electricity Department, Government of Goa Fuel and Power Purchase Adjustment Mechanism Joint Electricity Regulatory Commission (JERC) OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022

(cid:179)(cid:56)(cid:81)(cid:70)(cid:82)(cid:81)(cid:87)(cid:85)(cid:82)(cid:79)(cid:79)(cid:68)(cid:69)(cid:79)(cid:72)(cid:3)(cid:70)(cid:82)(cid:86)(cid:87)(cid:86)(cid:3)(cid:86)(cid:75)(cid:82)(cid:88)(cid:79)(cid:71)(cid:3)(cid:69)(cid:72)(cid:3)(cid:85)(cid:72)(cid:70)(cid:82)(cid:89)(cid:72)(cid:85)(cid:72)(cid:71)(cid:3)(cid:86)(cid:83)(cid:72)(cid:72)(cid:71)(cid:76)(cid:79)(cid:92)(cid:3)(cid:87)o ensure that future consumers are not burdened

with past costs. Uncontrollable costs would include (but not limited to) fuel costs, costs on account of

inflation, taxes and cess, variations in power purchase unit costs including on account of adverse

natu(cid:85)(cid:68)(cid:79)(cid:3)(cid:72)(cid:89)(cid:72)(cid:81)(cid:87)(cid:86)(cid:17)(cid:180)

(c) Tariff Policy, 2016, clause 8.2(cid:177) sub-clause 8.2.1-(1) (cid:179)(cid:27)(cid:17)(cid:21)(cid:3)(cid:41)(cid:85)(cid:68)(cid:80)(cid:72)(cid:90)(cid:82)(cid:85)(cid:78)(cid:3)(cid:73)(cid:82)(cid:85)(cid:3)(cid:85)(cid:72)(cid:89)(cid:72)(cid:81)(cid:88)(cid:72)(cid:3)(cid:85)(cid:72)(cid:84)(cid:88)(cid:76)(cid:85)(cid:72)(cid:80)(cid:72)(cid:81)(cid:87)(cid:86)(cid:3)(cid:68)(cid:81)(cid:71)(cid:3)(cid:70)(cid:82)(cid:86)(cid:87)(cid:86) Actual level of retail sales should be grossed up by normative level of T&D losses as indicated in MYT trajectory for allowing power purchase cost subject to justifiable power purchase mix variation (for example, more energy may be purchased from thermal generation in the event of poor rainfall) and (cid:73)(cid:88)(cid:72)(cid:79)(cid:3)(cid:86)(cid:88)(cid:85)(cid:70)(cid:75)(cid:68)(cid:85)(cid:74)(cid:72)(cid:3)(cid:68)(cid:71)(cid:77)(cid:88)(cid:86)(cid:87)(cid:80)(cid:72)(cid:81)(cid:87)(cid:3)(cid:68)(cid:86)(cid:3)(cid:83)(cid:72)(cid:85)(cid:3)(cid:85)(cid:72)(cid:74)(cid:88)(cid:79)(cid:68)(cid:87)(cid:76)(cid:82)(cid:81)(cid:86)(cid:3)(cid:82)(cid:73)(cid:3)(cid:87)(cid:75)(cid:72)(cid:3)(cid:54)(cid:40)(cid:53)(cid:38)(cid:17)(cid:180)

(d) (cid:43)(cid:82)(cid:81)(cid:182)(cid:69)(cid:79)(cid:72)(cid:3)(cid:36)(cid:55)(cid:40)(cid:3)(cid:77)(cid:88)(cid:71)(cid:74)(cid:72)(cid:80)(cid:72)(cid:81)(cid:87)(cid:3)(cid:76)(cid:81)(cid:3)(cid:50)(cid:51)(cid:20)(cid:3)(cid:82)(cid:73)(cid:3)(cid:21)(cid:19)(cid:20)1 dated 11 November 2011

(cid:55)(cid:75)(cid:72)(cid:3)(cid:43)(cid:82)(cid:81)(cid:182)(cid:69)(cid:79)(cid:72)(cid:3)(cid:36)(cid:55)(cid:40)(cid:3)(cid:71)(cid:76)(cid:85)(cid:72)(cid:70)(cid:87)(cid:72)(cid:71)(cid:3)(cid:87)(cid:75)(cid:72)(cid:3)(cid:54)(cid:40)(cid:53)(cid:38)(cid:86)(cid:3)(cid:87)(cid:82)(cid:3)(cid:71)(cid:72)(cid:89)(cid:72)(cid:79)(cid:82)(cid:83)(cid:3)(cid:68)(cid:3)(cid:83)(cid:82)(cid:90)(cid:72)(cid:85)(cid:3)(cid:83)(cid:88)(cid:85)(cid:70)(cid:75)(cid:68)(cid:86)(cid:72)(cid:3)(cid:70)(cid:82)(cid:86)(cid:87)(cid:3)(cid:68)(cid:71)(cid:77)(cid:88)(cid:86)(cid:87)(cid:80)(cid:72)(cid:81)(cid:87)(cid:3)(cid:80)(cid:72)(cid:70)(cid:75)(cid:68)(cid:81)(cid:76)(cid:86)(cid:80)(cid:3) (cid:90)(cid:76)(cid:87)(cid:75)(cid:76)(cid:81)(cid:3) six months of the date of the Order. The relevant excerpt of the Order is shown as follows: (cid:179)(cid:11)(cid:89)(cid:76)(cid:12)(cid:41)(cid:88)(cid:72)(cid:79) and Power Purchase cost is a major expense of the distribution Company which is uncontrollable. Every State Commission must have in place a mechanism for Fuel and Power Purchase cost in terms of Section 62 (4) of the Act. The Fuel and Power Purchase cost adjustment should (cid:83)(cid:85)(cid:72)(cid:73)(cid:72)(cid:85)(cid:68)(cid:69)(cid:79)(cid:92)(cid:3)(cid:69)(cid:72)(cid:3)(cid:82)(cid:81)(cid:3)(cid:80)(cid:82)(cid:81)(cid:87)(cid:75)(cid:79)(cid:92)(cid:3)(cid:69)(cid:68)(cid:86)(cid:76)(cid:86)(cid:3)(cid:82)(cid:81)(cid:3)(cid:87)(cid:75)(cid:72)(cid:3)(cid:79)(cid:76)(cid:81)(cid:72)(cid:86)(cid:3)(cid:82)(cid:73)(cid:3)(cid:87)(cid:75)(cid:72)(cid:3)(cid:38)(cid:72)(cid:81)(cid:87)(cid:85)(cid:68)(cid:79)(cid:3)(cid:38)(cid:82)(cid:80)(cid:80)(cid:76)(cid:86)(cid:86)(cid:76)(cid:82)(cid:81)(cid:182)(cid:86)(cid:3)(cid:53)(cid:72)(cid:74)(cid:88)(cid:79)(cid:68)(cid:87)(cid:76)(cid:82)(cid:81)(cid:86)(cid:3)(cid:73)(cid:82)(cid:85)(cid:3)(cid:87)(cid:75)(cid:72)(cid:3)(cid:74)(cid:72)(cid:81)(cid:72)(cid:85)(cid:68)(cid:87)(cid:76)(cid:81)(cid:74)(cid:3) companies but in no case exceeding a quarter. Any State Commission which does not already have such formula/mechanism in place must within 6 months of the date of this Order must put in place (cid:86)(cid:88)(cid:70)(cid:75)(cid:3)(cid:73)(cid:82)(cid:85)(cid:80)(cid:88)(cid:79)(cid:68)(cid:18)(cid:80)(cid:72)(cid:70)(cid:75)(cid:68)(cid:81)(cid:76)(cid:86)(cid:80)(cid:17)(cid:180)

8.2. Formula

The following mechanism shall be followed for calculation and adjusting variations on account of Fuel and Power Purchase Cost in the end consumer tariff, which shall come into force w.e.f. 1st April 2020 (i.e. Power Purchased by the Licensee from 1st April 2020 onwards).

1. Periodicity for recovery (Cycle)

The licensee shall compute the fuel and power procurement cost variations on a quarterly basis. The adjustment shall be made in the consumers bills starting after a month following the end of the quarter on the units billed in the months following the quarter.

For example, FPPCA for the quarter April-June shall be done in the month of July and shall be reflected in the consumer bills raised in the months of August, September and October on the units billed for the months of July, August and September respectively.

2. Chargeability

FPPCA charges shall be levied on all consumer categories excluding Below Poverty Line (BPL) and Agriculture category consumers on per unit basis on monthly/ bi-monthly consumption depending on the billing cycle.

3. Formula

The FPPCA formula shall contain the following three components:

1. Power Purchase Cost adjustments which shall contain the following elements:

(cid:135) (cid:57)(cid:68)(cid:85)(cid:76)(cid:68)(cid:87)(cid:76)(cid:82)(cid:81)(cid:3) (cid:76)(cid:81)(cid:3) (cid:87)(cid:75)(cid:72)(cid:3) (cid:51)(cid:82)(cid:90)(cid:72)(cid:85)(cid:3) (cid:51)(cid:88)(cid:85)(cid:70)(cid:75)(cid:68)(cid:86)(cid:72)(cid:71)(cid:3) (cid:73)(cid:85)(cid:82)(cid:80)(cid:3) (cid:79)(cid:82)(cid:81)(cid:74)(cid:3) (cid:87)(cid:72)(cid:85)(cid:80)(cid:18)(cid:3) (cid:73)(cid:76)(cid:85)(cid:80)(cid:3) (cid:86)(cid:82)(cid:88)(cid:85)(cid:70)(cid:72)(cid:86)(cid:3) (cid:89)(cid:76)(cid:93)(cid:17)(cid:3) (cid:38)(cid:42)(cid:54)(cid:15)(cid:3) (cid:44)(cid:51)(cid:51)(cid:182)(cid:86)(cid:15)(cid:3) (cid:54)(cid:87)(cid:68)(cid:87)(cid:72)(cid:15)(cid:3) (cid:50)(cid:90)(cid:81)(cid:3) generation etc. This may consist of fixed cost, variable costs, arrears, other charges but excluding any kind of penalties151 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 99 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA Fuel and Power Purchase Adjustment Mechanism Joint Electricity Regulatory Commission (JERC) SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022 (cid:135) Variation in Short term power purchase cost through IEX, Bilateral etc. (shall be allowed upto a certain ceiling rate as may be fixed in the Tariff Order by the Commission).

(cid:135) Variation on account of Deviation Settlement Mechanism (cid:177) shall be allowed, but the incentive/penalty shall be excluded

2. Transmission cost adjustments which shall contain the following elements:

(cid:135) Variation on account of Central Transmission Charges including arrears/ revisions. (cid:135) Variation on account of State Transmission charges including arrears/revisions

3. Other Charges which shall contain all the other elements not forming part of the above two components for example:

(cid:135) Any adjustments /reversals due to over recovery of charges (cid:135) Any adjustments due to under recovery of charges in case the Commission decides to limit the FPPCA charges in previous quarters to avoid tariff shock or other reasons

(cid:135) Any other adjustments on account of factors not envisaged at the time of tariff fixation

4. Less any revenue from Additional Surcharge collected from Open Access consumer towards the stranded power purchase cost.

Based on the components as defined above, the new FPPCA formula can be represented as follows:

+ +

=.

(cid:4666)(cid:2172)(cid:2183)(cid:2185)(cid:2202)

+ (cid:2176)(cid:2183)(cid:2185)(cid:2202) (cid:2171)(cid:2183)(cid:2185)(cid:2202) (cid:3398) (cid:2157)(cid:2175)(cid:2183)(cid:2185)(cid:2202)(cid:4667) (cid:1499) (cid:2778)(cid:2777)

(cid:2165)(cid:2170)(cid:2174)

Where:

(cid:3440) (cid:4678)

(cid:4679) (cid:3398) (cid:2174)(cid:2183)(cid:2198)(cid:2198) (cid:2162)(cid:2172)(cid:2172)(cid:2159)(cid:2157) (cid:3436)

(cid:2177)(cid:2196)(cid:2191)(cid:2202)

(cid:4666)(cid:2778) (cid:3398) (cid:2176)(cid:2168)(cid:2183)(cid:2198)(cid:2198)(cid:4667) (cid:2172)(cid:2172)(cid:2165)(cid:2183)(cid:2185)(cid:2202) (cid:3398) (cid:2172)(cid:2175)(cid:2171)(cid:2183)(cid:2185)(cid:2202)(cid:4671) (cid:1499) (cid:4666)(cid:2778) (cid:3398) (cid:2160)(cid:2168)(cid:2183)(cid:2198)(cid:2198)(cid:4667)(cid:4669) (cid:3398) (cid:2182)(cid:2183)(cid:2185)(cid:2202)

(cid:120)

(

(cid:4668)(cid:4670)(cid:2172)(cid:2172)(cid:2171)(cid:2183)(cid:2185)(cid:2202) (cid:1499) . ): Actual Power purchase cost inclusive of fixed cost, variable costs, arrears, and other charges excluding any kind of penalties incurred in the quarter. This shall include: (cid:1842)(cid:1853)(cid:1855)(cid:1872) (cid:1861)(cid:1866) (cid:1835)(cid:1840)(cid:1844) (cid:1829)(cid:1870)

o Cost of procurement from sources outside the State,

o Cost of procurement from sources within the State,

o Cost of DSM excluding any penal charges,

o Cost of procurement from the Bilateral/ exchange etc.

o Less: Revenue from sale of surplus power/ DSM

(cid:120)

(

. ): Actual Transmission cost inclusive of any kind of arrears, other charges etc. and excluding any kind of penalties incurred in the quarter. This shall include: (cid:1846)(cid:1853)(cid:1855)(cid:1872) (cid:1861)(cid:1866) (cid:1835)(cid:1840)(cid:1844) (cid:1829)(cid:1870)

o Inter-State transmission cost (PGCIL charges),

o Intra-State transmission cost

(cid:120)

(

. ): Adjustments from the previous FPPCA quarter on account of over/ under recovery and any other incidental costs not accounted for at the time of retail tariff fixation (cid:1841)(cid:1853)(cid:1855)(cid:1872) (cid:1835)(cid:1840)(cid:1844) (cid:1829)(cid:1870)

(cid:120)

(cid:1861)(cid:1866) (

. ): Revenue from Additional Surcharge collected from Open Access consumer towards the stranded power purchase cost (cid:1827)(cid:1845)(cid:1853)(cid:1855)(cid:1872) (cid:1835)(cid:1840)(cid:1844) (cid:1829)(cid:1870)

(cid:120)

(cid:1861)(cid:1866) ( ): Quantum of power purchased in the quarter from sources outside State/ Union

(cid:1861)(cid:1866) (cid:1839)(cid:1847)

(cid:120)

Territory (cid:1842)(cid:1842)(cid:1841)(cid:1853)(cid:1855)(cid:1872) ( %): Approved Inter- State transmission losses for the year in consideration as provided in the relevant Tariff Order (cid:1846)(cid:1838)(cid:1853)(cid:1868)(cid:1868) (cid:1861)(cid:1866)152 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 100 Electricity Department, Government of Goa Fuel and Power Purchase Adjustment Mechanism Joint Electricity Regulatory Commission (JERC) OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022 (cid:120)

( ): Quantum of power purchased in the quarter from sources within State/Union

Territory, Bilateral/ Exchange and Over-drawal under the DSM (cid:1842)(cid:1842)(cid:1835)(cid:1853)(cid:1855)(cid:1872) (cid:1861)(cid:1866) (cid:1839)(cid:1847)

(cid:120)

( ): Actual quantum of sale of surplus power/ under-drawal under the DSM in the

(cid:1861)(cid:1866) (cid:1839)(cid:1847)

(cid:120)

quarter (cid:1842)(cid:1845)(cid:1841)(cid:1853)(cid:1855)(cid:1872) ( %): Approved T&D losses for the year in consideration as provided in the relevant Tariff

(cid:1861)(cid:1866)

(cid:120)

Order (cid:1830)(cid:1838)(cid:1853)(cid:1868)(cid:1868) ( ): Actual energy sales for agriculture and BPL category consumers in the quarter

(cid:1852)(cid:1853)(cid:1855)(cid:1872) (cid:1861)(cid:1866) (cid:1839)(cid:1847)

+

10

( ) =

1

1

(cid:1835)(cid:1840)(cid:1844)

+ (cid:4666)(cid:1842)(cid:1853)(cid:1868)(cid:1868) (cid:1846)(cid:1853)(cid:1868)(cid:1868) (cid:4667) (cid:1499)

(cid:1844)(cid:1853)(cid:1868)(cid:1868)

(cid:4678)

(cid:4679)

(cid:4666)

(cid:1873)(cid:1866)(cid:1861)(cid:1872)

(cid:3398) (cid:1846)(cid:1838)(cid:1853)(cid:1868)(cid:1868)(cid:4667) (cid:1842)(cid:1842)(cid:1835)(cid:1853)(cid:1868)(cid:1868) (cid:3398) (cid:1842)(cid:1845)(cid:1841)(cid:1853)(cid:1868)(cid:1868)(cid:4671) (cid:1499) (cid:4666) (cid:3398) (cid:1830)(cid:1838)(cid:1853)(cid:1868)(cid:1868)(cid:4667)(cid:4669) (cid:3398) (cid:1852)(cid:1853)(cid:1868)(cid:1868) (cid:120)

(

(cid:4668)(cid:4670)(cid:1842)(cid:1842)(cid:1841)(cid:1853)(cid:1868)(cid:1868) (cid:1499) . ): Total power purchase cost approved in the Tariff Order for a quarter inclusive of

fixed costs, variable costs etc. and containing the following elements: (cid:1842)(cid:1853)(cid:1868)(cid:1868) (cid:1861)(cid:1866) (cid:1835)(cid:1840)(cid:1844) (cid:1829)(cid:1870)

o Cost of procurement from sources outside the State,

o Cost of procurement from sources within the State,

o Cost of procurement from the Bilateral/ exchange etc.

o Less: Revenue from sale of surplus power

(cid:120)

(

. ): Total transmission charges approved in the Tariff Order for a quarter consisting of

the following elements: (cid:1846)(cid:1853)(cid:1868)(cid:1868) (cid:1835)(cid:1840)(cid:1844)

(cid:1861)(cid:1866) (cid:1829)(cid:1870)

o Inter-State transmission charges (PGCIL charges),

o Intra-State transmission charges

(cid:120)

( ): Quantum of power to be procured from sources outside State/ Union Territory in a

(cid:1839)(cid:1847)

(cid:120)

quarter as approved in the Tariff Order (cid:1842)(cid:1842)(cid:1841)(cid:1853)(cid:1868)(cid:1868) (

(cid:1861)(cid:1866) %): Approved Inter- State transmission losses for the year in consideration as provided in

the relevant Tariff Order (cid:1846)(cid:1838)(cid:1853)(cid:1868)(cid:1868) (cid:1861)(cid:1866)

(cid:120)

( ): Quantum of power to be procured from sources within the State, bilateral/ exchange

(cid:1839)(cid:1847)

(cid:120)

in a quarter as approved in the Tariff Order (cid:1842)(cid:1842)(cid:1835)(cid:1853)(cid:1868)(cid:1868) (

(cid:1861)(cid:1866) %): Approved T&D losses for the year in consideration as provided in the Tariff Order

(cid:120)

): Quantum of sale of surplus power approved in the Tariff Order for a quarter (cid:1830)(cid:1838)(cid:1853)(cid:1868)(cid:1868)

( (cid:1861)(cid:1866)

(cid:120)

(

(cid:1861)(cid:1866)

): Sales for agriculture and BPL category consumers for a quarter as approved in the (cid:1839)(cid:1847)

(cid:1842)(cid:1845)(cid:1841)(cid:1853)(cid:1868)(cid:1868) relevant Tariff Order (cid:1852)(cid:1853)(cid:1868)(cid:1868) (cid:1861)(cid:1866) (cid:1839)(cid:1847)

4. Other Terms and conditions

1. For the purpose of the Fuel and Power Purchase Cost Adjustment, the Commission suggests that all the bills admitted and credits, if any, received by the distribution licensee during the period in consideration, irrespective of the period to which they pertain, may be considered.

2. The FPPCA charges determined as per the formula above may be recovered from the consumers of all categories based on their billed units excluding the BPL and the agriculture category consumers.

3. The FPPCA charges for a quarter shall be limited to +10% of the ABR for a consumer category. The distribution licensee shall be allowed to collect the FPPCA without obtaining approval from the153 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 101 Electricity Department, Government of Goa Fuel and Power Purchase Adjustment Mechanism Joint Electricity Regulatory Commission (JERC) OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022 Commission. However, the distribution licensee shall be required to submit the FPPCA calculation to

the Commission at least one week before levying the same on the consumers.

4. The per unit FPPCA so worked out is charged differentially as per the approved retail tariff of the

consumers. The determination of differential per unit FPPCA is mentioned below:

(cid:120) Step 1: Determination of Value of K

)

(

(cid:1835)(cid:1840)(cid:1844)

)

(

(cid:1873)(cid:1866)(cid:1861)(cid:1872)

(cid:1827)(cid:1868)(cid:1868)(cid:1870)(cid:1867)(cid:1874)(cid:1857)(cid:1856) (cid:1844)(cid:1857)(cid:1872)(cid:1853)(cid:1861)(cid:1864) (cid:1846)(cid:1853)(cid:1870)(cid:1861)(cid:1858)(cid:1858) (cid:1858)(cid:1867)(cid:1870) (cid:1853) (cid:1855)(cid:1853)(cid:1872)(cid:1857)(cid:1859)(cid:1867)(cid:1870)(cid:1877) (cid:1867)(cid:1870) (cid:1871)(cid:1873)(cid:1854) (cid:1855)(cid:1853)(cid:1872)(cid:1857)(cid:1859)(cid:1867)(cid:1870)(cid:1877) (cid:1835)(cid:1840)(cid:1844)

(cid:1873)(cid:1866)(cid:1861)(cid:1872)

(cid:1849)(cid:1857)(cid:1861)(cid:1859)(cid:1860)(cid:1872)(cid:1857)(cid:1856) (cid:1827)(cid:1874)(cid:1857)(cid:1870)(cid:1853)(cid:1859)(cid:1857) (cid:1844)(cid:1857)(cid:1872)(cid:1853)(cid:1861)(cid:1864)

(cid:4666)(cid:1849)(cid:1827)(cid:1844)(cid:1846)(cid:4667)

(cid:1846)(cid:1853)(cid:1870)(cid:1861)(cid:1858)(cid:1858) The value of K for different consumer category or sub-category for the year in consideration is

considered as approved in this Tariff Order.

(cid:120) Step 2: Determination of proportionate FPPCA (INR /unit) consumer category/sub-category wise

=

(cid:1835)(cid:1840)(cid:1844)

(cid:1832)(cid:1842)(cid:1842)(cid:1829)(cid:1827) (cid:3436) (cid:3440) (cid:1827)(cid:1874)(cid:1857)(cid:1870)(cid:1853)(cid:1859)(cid:1857) (cid:1832)(cid:1842)(cid:1842)(cid:1829)(cid:1827) (cid:1499) (cid:1837) (cid:1858)(cid:1867)(cid:1870) (cid:1872)(cid:1860)(cid:1853)(cid:1872) (cid:1855)(cid:1867)(cid:1866)(cid:1871)(cid:1873)(cid:1865)(cid:1857)(cid:1870) (cid:1855)(cid:1853)(cid:1872)(cid:1857)(cid:1859)(cid:1867)(cid:1870)(cid:1877) (cid:1867)(cid:1870) (cid:1871)(cid:1873)(cid:1854) (cid:3398) (cid:1855)(cid:1853)(cid:1872)(cid:1857)(cid:1859)(cid:1867)(cid:1870)(cid:1877) (cid:1847)(cid:1866)(cid:1861)(cid:1872)

5. The Petitioner shall compute the fuel and power procurement cost variations, and adjustments shall be made in the consumer bills based on the FPPCA formula as approved by the Commission in this

Order.

For the purpose of calculation, the approved per unit cost of power purchase (Rapproved) shall be taken as INR 5.24/kWh for the FY 2022-23.

Table 92:Rapproved determined by Commission for FY 2022-23

Particulars Amount
Total Power Purchase Cost (INR Cr ), Papp 1,613.38
Transmission Charges (INR Cr), Tapp 226.15
Power Purchase Quantum from CGS Stations at Ex-Bus Periphery (NTPC, NPCIL) (MU), PPOapp 3,814.68
Approved Weighted Average Inter-State Transmission Loss (%), TLapp 4.05%
Power Purchase Quantum from sources within State/ Open Market (Own Gen and Open Market) (MU), PPIapp 290.33
Quantum of Sale of Surplus Power (MU), PSOapp -
Approved Intra-State T&D Loss (%), DLapp 10.25%
Energy Sales for LIG/BPL and Agriculture consumer category (MU), Zapp(MU) 34.99
Rapp (INR/kWh) 5.24
154 OFFICIAL GAZETTE — GOVT. OF GOA Directives Joint Electricity Regulatory Commission (JERC) SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022

9. Chapter 9: Directives

Over the years, the Commission has issued various directives to the Petitioner for necessary

action at its end. It has been observed that the Petitioner is not fully complying with many of

the directives issued by the Commission. In order to strengthen the effective monitoring and

ensure timely implementation of all the directives in true spirit, the Commission hereby

directs that the Petitioner shall now submit:

(cid:120) The detailed action plan for compliance of all the directives within 1 month of the

issuance of this Order.

(cid:120) The quarterly progress report as per the detailed action plan for all the directives

issued in the subsequent sections within 10 days of the end of each quarter of the

calendar year.

9.1. Directives continued in this Order

While examining the compliance note and supporting documents submitted by the Petitioner in the present Petition, it is observed that some of the directives issued in the previous Tariff Orders have not been fully complied with by the Petitioner.

The Commission is of the view that substantial time has already been given to the utility for compliance with these directions. Thus, the Commission hereby directs the utility to comply with the directions mentioned below in the given timeframe, failing which the Commission shall be constrained to initiate appropriate action under the Electricity Act, 2003 and Regulations made there under.

9.1.1. Annual Statement of Accounts

Originally Issued in Tariff Order dated 27th June 2012
&RPPLVVLRQ¶V/DWHVW'LUHFWLYHLQ7DULII2UGer dated 30th March 2021 As reiterated last year, the Commission has taken a serious note of this issue. The Petitioner has failed to comply with the directive every year since the issuance of Tariff Order dated 27th June 2012. The Petitioner is directed to submit the audited annual accounts for FY 2017-18, FY 2018-19, FY 2019-20 and FY 2020-21 by November 2021 so that the appropriate base year values for 3rd MYT Control Period can be considered.
3HWLWLRQHU¶V5HVSRQVHLQWKH3UHVHQW7DULII3HWLWLRQ ‡7KHCAG audit process for Financial Accounts of FY 2017-18 is under process. ‡7KH)LQDQFLDO$FFRXQWVRI)<-19 and FY 2019-20 are submitted to CAG and is due for Audit. ‡)LQDQFLDO$FFRXQWVIRU)<-21 are under progress and the same will be completed by 31stDecember 2021. Upon completion, the same will be submitted to CAG for audit purposes.
&RPPLVVLRQ¶V5HVSRQVH As reiterated last year, the Commission has taken a serious note of this issue. The Petitioner has failed to comply with the directive every year since the issuance of Tariff Order dated 27th June 2012. The Petitioner is directed to submit the audited annual accounts for FY 2017-18, FY 2018-19, FY 2019-20, FY 2020-21 and FY 2021-22 by November 2022along with Tariff petition for FY 2023-24.

9.1.2. Preparation of Fixed Asset Register

Originally Issued in Tariff Order dated 27th June 2012

155 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 103 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA Directives Joint Electricity Regulatory Commission (JERC) SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022
&RPPLVVLRQ¶VLatest Directive in Tariff Order dated 30th March 2021 The Commission reiterates that the information with regards to type, nature and value of assets depreciated upto 90% in the relevant year has not been provided, the purpose for which FAR is prepared. The Petitioner is directed to submit the information upto FY 2020-21 in the next tariff petition.
3HWLWLRQHU¶V5HVSRQVHLQWKH3UHVHQW7DULII3HWLWLRQ Collection of Information for the Assets for FY 2020-21 is under progress and the same shall be submitted on 31stDecember 2021.
&RPPLVVLRQ¶V5HVSRQVH The Petitioner is directed to submit the information up to FY 2021-22 in the next tariff petition, along with the audited annual accounts as sought in the preceding directive. The Petitioner is to also ensure that the FAR reports contain the details of the assets which have completed 90% of their but are still included in the FAR.

9.1.3. Energy Audit Reports

Originally Issued in Tariff Order dated 27th June 2012
&RPPLVVLRQ¶VLatest Directive in Tariff Order dated 30th March 2021 The Commission reiterates that it has noted with serious concern that the Petitioner is yet to submit the Energy Audit Reports for previous years despite repeated directions. The Commission directs the Petitioner to expedite the process and complete the Energy Audit of the State on priority.
3HWLWLRQHU¶V5HVSRQVHLQWKH3UHVHQW7DULII3HWLWLRQ ‡'HSDUWPHQWKDVVWDUWHGSURFHVVRIHQHUJy audit. However, at this point of time because of 100% DT metering is not done and we are unable to ascertain the losses of feeder-wise. ‡+RZHYHURQWKHEURDGHUOHYHOZHDUHDEOHWRPHDVXUHORVVHVEDVHGRQWKH3RZHUGHOLYHUHGGXULQJWKH$SULO 2019 to March 2020 and respective energy recorded billed in May 2019 to April 2020 at each Feeder level, Sub-Division level and Division level are listed out the attached along with the Petition. ‡7KH SURSRVDO IRU WKH SURFXUHPHQW RI QRQ-ZRUNLQJ &7¶V 37¶V DQG PHWHrs was kept on hold due to financial constraint resulted from the recent Pandemic but it is now being processed and all non-working CTs, PTs, and meters shall be installed by May 2022. Further after installation of above required equipments, Energy Audit will be conducted by September 2022.
&RPPLVVLRQ¶V5HVSRQVH The Commission has noted with serious concern that the Petitioner has not submitted the Energy Audit Reports for previous years despite repeated directions. The Commission directs the Petitioner to expedite the process and complete the Energy Audit of the State on priority, and positively submit the same along with Tariff Petition for FY 2023-24.

9.1.4. Employee Cost / Manpower study

Originally Issued in Tariff Order dated 27th June 2012
&RPPLVVLRQ¶VLatest Directive in Tariff Order dated 30th March 2021 The Commission is yet to receive the Manpower Study report from the Petitioner. The Commission directs the Petitioner to submit the same along with the next quarterly progress report without further delay.
3HWLWLRQHU¶V5HVSRQVHLQWKH3UHVHQW7DULII3HWLWLRQ Manpower Analysis has been done at all the divisional level. The Details of the same was submitted in the 1st quarter directives. However, in this regard, some clarifications were sought by the Commission and the ED- Goa has prepared a detailed Manpower Analysis, which is attached with the Petition.
&RPPLVVLRQ¶V5HVSRQVH
156 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 104 Electricity Department, Government of Goa Directives Joint Electricity Regulatory Commission (JERC) OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022

The Commission is yet to receive the Manpower Study report from the Petitioner. The Commission directs the

Petitioner to submit the same within one month of the issuance of this Order.

9.1.5. Interest on Consumer Security Deposit

Originally Issued in Tariff Order dated 31st March 2013
&RPPLVVLRQ¶VLatest Directive in Tariff Order dated 30th March 2021 The Commission acknowledges the efforts made by the Petitioner. The Commission directs the Petitioner to ensure payment of interest on security deposit upto FY 2020-21as per the provisions of Supply Code, 2018.
3HWLWLRQHU¶V5HVSRQVHLQWKH3UHVHQW7DULII3HWLWLRQ PD\PHQWWRZDUGVFRQVXPHU¶VVHFXULW\GHSRVLWIRU)<-21 is in the process of disbursement and the same shall be completed by March 2022 along with the arrears if any.
&RPPLVVLRQ¶V5HVSRQVH The Commission reiterates that the Petitioner is directed to ensure payment of interest on security deposit upto FY 2021-22as per the provisions of Supply Code, 2018.

9.1.6. Sub-Divisions as Strategic Business Units

Originally Issued in Tariff Order dated 06th April 2015
&RPPLVVLRQ¶VLatest Directive in Tariff Order dated 30th March 2021 The Commission is yet to receive the compiled data for Strategic Business Unit for Sub-Division of Division ± VII Curchorem and Division XIV Verna. The Petitioner is directed to submit the same within one month of the issuance of this Order. )XUWKHU DQ RYHUDOO VWUDWHJLF SODQ WR LPSOHPHQW WKH VDPH LQ WKH HQWLUH DUHD DOO VXEGLYLVLRQV RI 3HWLWLRQHU¶V serving area.
3HWLWLRQHU¶VResponse in the Present Tariff Petition Collection of Data for Strategic Business Unit for Sub-Division of Division 6 is completed. The same is being VXEPLWWHG WR WKH +RQ¶EOH &RPPLVVLRQ DORQJ ZLWK WKLV 7DULII SHWLWLRQ LQ WKH Annexure-5. The Collection of data for Sub-Division of 4 & 17 are under progress.
&RPPLVVLRQ¶V5HVSRQVH The Commission is yet to receive the compiled data as stated by the Petitioner. The Petitioner is directed to submit the same within one month of the issuance of this Order.

9.1.7. Installation of Pre-Paid Meters

Originally Issued in Tariff Order dated 06th April 2015
&RPPLVVLRQ¶V/DWHVW'LUHFWLYHLQ7DULII2UGHUGDWHGWK0DUFK The Commission directs the Petitioner to expedite the process and submit an updated status with the next quarterly progress report.
3HWLWLRQHU¶V5HVSRQVHLQWKH3UHVHQW7DULII3HWLWLRQ Administrative approval from the Government has been obtained for installation of 7 Lakhs Prepaid SMART meters on Totax mode. The project will be tendered after the receipt of the standard bidding document from REC as the project is proposed to be funded under the Revamped Distribution Sector Scheme.
&RPPLVVLRQ¶V5HVSRQVH The Commission directs the Petitioner to expedite the process and submit an updated status with the next
157 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 105 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA Directives Joint Electricity Regulatory Commission (JERC) SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022

quarterly progress report.

9.1.8. Unbundling of Electricity Department

Originally Issued in Tariff Order dated 06th April 2015
&RPPLVVLRQ¶V/DWHVW'LUHFWLYHLQ7DULII2UGHUGDWHG30th March 2021 The Commission reiterates that the Petitioner should submit the proposal to the State Govt. at the earliest and provide a status on the same along with the next quarterly progress report.
3HWLWLRQHU¶V5HVSRQVHLQWKH3UHVHQW7DULII3HWLWLRQ The Matter has been discussed with the Government of Goa and the Government decision is to continue as Department.
&RPPLVVLRQ¶V5HVSRQVH The Commission directs the Petitioner to submit the documentary evidence for the decision of the Govt. of Goa to the Commission within one month of the issuance of this Order.

9.1.9. Renewable Purchase Obligation

Originally Issued in Tariff Order dated 06th April 2015
&RPPLVVLRQ¶VLatest Directive in Tariff Order dated 30th March 2021 The Commission reiterates its directive to the Petitioner that it must continue its efforts towards fulfilment of RPO and ensure yearly obligation is fulfilled.
3HWLWLRQHU¶V5HVSRQVHLQWKH3UHVHQW7DULII3HWLWLRQ EDG submits that it has fulfilled 50% of the total RPO Obligation for FY 2021-22 and is making continuous efforts to fulfil the RPO Target for FY 2021-22.
&RPPLVVLRQ¶V5HVSRQVH The Commission appreciates the efforts undertaken by the Petitioner towards fulfillment of RPO. The 3HWLWLRQHU LV HPSKDVL]LQJ RQ SURFXULQJ PRUH SK\VLFDO SRZHU WKDQ SXUFKDVH 5(&¶V LQ DFFRUGDQFH ZLWK WKH Commissions directions. The Petitioner is directed to continue its efforts towards fulfillment of RPO and ensure yearly compliance are achieved.

9.1.10. Billing and Collection Efficiency

Originally Issued in Tariff Order dated 06th April 2015
&RPPLVVLRQ¶V/DWHVW'LUHFWLYHLQTariff Order dated 30th March 2021 The Commission directs the Petitioner to submit a detailed status report along with the next quarterly progress report.
3HWLWLRQHU¶V5HVSRQVHLQWKH3UHVHQW7DULII3HWLWLRQ The Report on OTS scheme is already submitted.
&RPPLVVLRQ¶V5HVSRQVH The Commission is yet to receive the report from the Petitioner. The Commission directs the Petitioner to submit the same within one month of the issuance of this Order.
158 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 106 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA Directives Joint Electricity Regulatory Commission (JERC) SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022

9.1.11. Determination of Category wise/ Voltage wise Cost of supply

Issued in Tariff Order dated 20th May 2019
&RPPLVVLRQ¶VDirective in Tariff Order dated 30th March 2021 The Petitioner is directed to expedite the process of energy audit and submit the requisite data and the proposal along with the next tariff petition.
3HWLWLRQHU¶V5HVSRQVHLQWKH3UHVHQW7DULII3HWLWLRQ GIS Mapping for 11kV/33kV assets are under progress. It shall be completed once the energy audit and the same is expected to be completed by November 2022.
&RPPLVVLRQ¶V5HVSRQVH The Petitioner is directed to submit voltage-wise and category-wise details of assets, O&M expenses and fixed asset cost allocation for the last 3 years along with the Tariff Petition for FY 2023-24.

9.1.12. Submission of Petition for True up of FY 2016-17, FY 2017-18,

FY 2018-19 and FY 2019-20 and APR of FY 2020-21

Issued in Tariff Order dated 20th May 2019
&RPPLVVLRQ¶VDirective in Tariff Order dated 30th March 2021 As reiterated last year, the Commission has taken a serious note of this issue. The Petitioner is directed to submit the audited annual accounts for FY 2017-18, FY 2018-19, FY 2019-20 and FY 2020-21 by 30th November 2021 so that the appropriate base year values for 3rd MYT Control Period can be considered.
3HWLWLRQHU¶V5HVSRQVHLQWKH3UHVHQW7DULII3HWLWLRQ The CAG audit process for Financial Accounts of FY 2017-18 is under process. x The Financial Accounts of FY 2018-19 and FY 2019-20 are submitted to CAG and is due for Audit. x Financial Accounts for FY 2020-21 are under progress and the same will be completed by 31st December x 2021. Further completion the same will be submitted to CAG for audit purposes. The True-up petition for FY 2017-18, FY 2018-19 and FY 2019-20 will be submitted separately once the x accounts are audited by CAG.
&RPPLVVLRQ¶V5HVSRQVH The progress shown by the Petitioner is not satisfactory. As reiterated last year, the Commission has taken a serious note of this issue. The Petitioner is directed to submit the audited annual accounts for FY 2017-18, FY 2018-19, FY 2019-20, FY 2020-21 and FY 2021-22 by 30th November 2022.

9.1.13. Collection of data based on consumer type

Issued in Tariff Order dated 20th May 2019
&RPPLVVLRQ¶VDirective in Tariff Order dated 30th March 2021 The Petitioner is directed to submit the requisite information along with the next quarterly progress report.
3HWLWLRQHU¶V5HVSRQVHLQWKH3UHVHQW7DULII3HWLWLRQ
The requisite data has been collected from all the sub-division and division level. The sub division/division personnel has performed physical survey for identification of Hotel Industries, Govt./Private educational institutions, Govt./Private hospitals etc category of consumers and respective details were flagged and updated in SAP database. Accordingly, the requisite details are summarised and submitted along with the Tariff Petition for FY 2022-23.
&RPPLVVLRQ¶V5HVSRQVH The Commission is yet to receive the requisite details from the Petitioner. The Commission directs the Petitioner to submit the same within one month of the issuance of this Order.
159 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 107 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA Directives Joint Electricity Regulatory Commission (JERC) SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022

9.1.14. kVAh based tariff for LT-Industrial and LT-Commercial

categories

Issued in Tariff Order dated 30th March 2021
&RPPLVVLRQ¶VDirective in Tariff Order dated 30th March 2021 The Commission is considering the introduction of kVAh based tariff for LT-Industrial and LT-Commercial categories. Accordingly, the Petitioner is hereby directed to submit a compliance report indicating its readiness for implementation of kVAh billing for LT-Industrial and LT-Commercial categories with the next tariff petition.
3HWLWLRQHU¶V5HVSRQVHLQWKH3UHVHQW7DULII3HWLWLRQ ED-Goa is in the process of installing smart meters and the Proof of Concept (PoC) for the Smart Meter has also been carried out successfully. The kVAh based billing will be carried out for LT Commercial and LT Industrial after installation of the Smart Meters..
&RPPLVVLRQ¶V5HVSRQVH The Petitioner is directed to ensure kVAh reading for all LT-Industrial and LT-commercial meters at the earliest so that kVAh based billing can be introduced for them too as has been done for HT consumers and submit the requisite information along with the Tariff Petition for FY 2023-24.
160 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 108 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA Tariff Schedule Joint Electricity Regulatory Commission (JERC) SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022

10. Chapter 10: Tariff Schedule

10.1. Tariff Schedule

Category Approved Tariff
Fixed Charges Energy Charges
1 Domestic
A Low Tension-D/LT-D
0-100 units INR 20/kW/Month 1.60 Rs/kWh
101-200 units INR 20/kW/Month 2.35 Rs/kWh
201 to 300 units INR 20/kW/Month 2.95 Rs/kWh
301 to 400 units INR 20/kW/Month 3.90 Rs/kWh
Above 400 units INR 20/kW/Month 4.50 Rs/kWh
B Low Tension-LIG/LT-LIG INR 20/kW/Month -
C High Tension-D/HT-D
All Units INR 110/kVA/Month 4.60 Rs/kVAh
2 Commercial
A Low Tension-C/LT-C
0-100 units For consumers with Load upto 20 kW INR 40/kW/Month For consumers with Load more than 20 kW and upto 90 kW INR 60/kW/Month 3.55 INR/kWh
101-200 units 4.35 INR/kWh
201 units- 400 units 4.85 INR/kWh
Above 400 units 5.25 INR/kWh
B High Tension-C/HT-C
All Units INR 250/kVA/month 5.25 INR/kVAh
3 Industrial
A Low Tension-I/LT-I
0-500 units INR 40/HP/Month 3.40 INR/kWh
Above 500 units INR 40/HP/Month 3.95 INR/kWh
B Low Tension-Mixed/LT-P (Hotel Industries)
All Units INR 50/kW/Month 5.25 INR/kWh
C High Tension-I/HT-I
Connected at 11/33 kV INR 250/kVA/Month 4.80 INR/kVAh
Connected at 110 kV INR 250/kVA/Month 4.70 INR/kVAh
D High Tension- Ferro/SM/ PI/ SR
All Units INR 250/kVA/Month 4.80 INR/kVAh
4 Agricultural
A Low Tension-AG/LT-AGP (Pump Sets/Irrigation)
All Units INR 18/HP/Month 1.50 INR/kWh
B Low Tension-AG/LT-AGA (Allied Activities)
All Units INR 25/HP/Month 1.75 INR/kWh
C High Tension-AG/HT-AGP (Pump Sets/Irrigation)
All Units INR 40/kVA/Month 1.60 INR/kVAh
D High Tension-AG/HT-AG (Allied Activities)
All Units INR 70/kVA/Month 1.95 INR/kVAh
5 Military Engineering Services/defense
Establishments
All Units INR 200/kVA/Month 4.90INR/kVAh
6 Public Lighting
All Units INR 70/kW/Month 5.65 INR/kWh
7 Hoardings/Signboards
All Units INR 70/kVA/Month 10.00 INR/kWh
8 Temporary Supply
A LT Temporary Domestic Tariff shall be Fixed/ Demand charges (if any) plus energy charges (for relevant slab, if any) under corresponding permanent supply category plus 50% of both. For multi activity pursuit, applicable Tariff for temporary connection shall be with reference to that of commercial category for permanent supply.
B LT Temporary Commercial
C HT Temporary
9 Single Point Supply
A Residential Complexes INR 110 per kVA per month or part thereof 3.55 INR/kVAh
B Commercial Complexes INR 220 per kVA per month or part thereof 4.80 INR/kVAh
C Industrial Complexes INR 220 per kVA per month or part thereof 4.40 INR/kVAh
10 Electric Vehicle Charging Station - 3.50* INR/kVAh
161 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 109 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA Tariff Schedule Joint Electricity Regulatory Commission (JERC) SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022

tariff.

10.2. Applicability

Low Tension Category - Applicable to Power Supply of Voltages at 230V and 440V Voltages when the Sanctioned Load is below 100 KVA/90 KW / 120 HP and power is supplied at single/ three phase.

High Tension/ Extra High Tension Category - Applicable to Power Supply of Voltages at 11KV/ 33KV/ 110KV and above i.e. High/Extra High Voltages when the Contracted Demand is above 100 KVA/ 90 KW / 120 HP and power is supplied at three phase.

Category Applicability Point of Supply/Notes
1. LT Domestic This schedule shall apply to private residential houses, government residential quarters, Government schools and related facilities, charitable institutions, religious institutions etc. for consumption of energy using normal domestic appliances. Professionals such as Doctors, Engineers, Lawyers, CAs, Journalists and Consultants practicing from their residence irrespective of location provided that such use shall not exceed 25% of the area of the premises or as specified in the rules/regulations of their respective State or Union Territory. a. For the premises or flats which are closed or locked for a continuous period of more than three months and having sanctioned / connected load more than 10 kW, the monthly minimum charges would be Rs1000/-.
2. HT Domestic This schedule shall apply to individual residential consumers of Bungalows, Villas, Cottages, etc. using normal domestic appliances and whose contract demand falls within the threshold limit of HT category.
3. Low Income Group/Life Line consumers This schedule shall apply to consumers of Low Income Group who have a sanctioned load of up to 0.25 kW and who consume up to 50 units per month only. The applicability of the Low Income Group category will be assessed at the end of each month and in case the consumption exceeds 50 units per month, the entire consumption would be billed at the rate of LTD-/Domestic for that particular month.
4. Commercial ± LT and HT This tariff is applicable to any activity not specifically covered in any other consumer categories, or although covered in another activity, the use is made for a commercial category. It would include electricity used in all non- residential, non-industrial premises and/or commercial premises for commercial consumption meant foroperating various appliances. It would include the following categories but not limited to: Houses with rent back facilities x Government hospitals x Professionals not covered in domestic x category. Commercial Complexes and Business x premises, including Shopping malls/show rooms, offices / shops; Combined lighting and power services x for Entertainment including film studios, cinemas and theatres, including multiplexes, Race Course, Meeting/Town Halls, Clubs, all types of Guest houses; Offices including Government Offices, x Commercial Establishments; Marriage Halls (including halls x attached to religious places), Hotels /Restaurants (without boarding facilities), Ice-cream parlours, Bakeries, Coffee Shops, private hospitals, private messes, Internet / Cyber Cafes, Mobile Towers, Microwave Towers, Satellite Antennas used for telecommunication activity, Telephone Booths, Fax / Xerox Shops, X-ray installations, bars and cold drink houses, Tailoring Shops, Computer Training Schools, Typing Institutes, Photo Laboratories, Photo Studios, Laundries, Beauty Parlours and Saloons, dry cleaners etc Automobile and any other type of x repair centers, Retail Gas Filling stations, Petrol Pumps and Service Cold Storages which are solely attached to Agriculture and its allied activities shall be charged tariff of Agriculture Allied activities. All other cold storages which are partly or not attached with Agriculture and Allied activities shall be charged commercial tariff.
Stations including Garages, Tyre Vulcanizing units, Battery Charging Units, Tyre vulcanizing centresetc; Banks, Telephone Exchanges, TV x Station, Micro Wave Stations, All India Radio (AIR) Stations, ATM Centresetc; For common facilities, like Water x Pumping / Street Lighting / Lifts / Fire Fighting Pumps / Premises (Security) Lighting, etc. in Commercial Complexes; Sports Clubs, Health Clubs, x Gymnasium, Swimming Pools; Research and Development units x situated outside Industrial premises; Airports, Railways, Railway Stations, x Bus stands of KTC etc; Educational institutions excluding x Government Schools and related facilities
5. LT Industrial This tariff shall apply to industrial units engaged in industrial activities, manufacturing process etc. It would include the following categories but not limited to: Flour Mills, wet grinding, Dal Mills, x Rice Mills, Poha Mills, Masala Mills, Saw Mills, Power looms including other allied activities like Warping, Doubling, Twisting, etc. Ice Factories, Ice Cream x Manufacturing units/ Plants, Dairy Testing Process, Milk Dairies, Milk Processing/ Chilling Plants (Dairy) etc; Engineering workshops, Engineering x Goods Manufacturing units, Printing Presses, Transformer repairing Workshops, Tyre retreading units, Motive Power Loads etc; Mining, Quarry and Stone Crushing x units etc; Garment Manufacturing units, x LPG/ CNG Bottling plants etc; x Sewage Water Treatment Plants/ x Common Effluent Treatment Plants owned, operated and managed by Industrial Associations and situated within industrial area. Pumping of water for public water x supply, Sewage Treatment Plants, activities related with public water Supply Schemes and Sewage Pumping Stations. Use of electricity / power supply for x activities/ facilities exclusively meant The above mentioned tariff is based on the supply being given through a single delivery and metering point and at a single voltage.
for employees of the industry within the premises of the Industry. IT Industry, IT parks etc. x
6. LT Mixed ± Hotel Industries This schedule shall apply to Hotels/ restaurants with lodging and boarding facilities. Hotel Industry consumers intending to avail the facility of this tariff should produce a certificate from the Tourism Department stating that the intending applicant is registered under Goa Registration of Tourist Trade Act, 1982 and in the Hotel business on a regular basis. On receipt of the certificate, such tariff shall be made effective from the date of original validity of the certificate. In case of failure to produce the certificate, the same shall be considered under Commercial category.
7. HT Industrial This schedule shall apply to consumers taking electricity supply for Industrial purpose. It shall also include the following categories: Bulk Supply of power at 11 KV, 33 kV x /110 KV and above for industries, factories and other industrial purposes. Bulk supply of power at 11 KV and x above for educational institutions owned or aided by Government, non- industrial establishments, Industrial units engaged in Ice x Manufacturing Units; Hotels with lodging and boarding x facilities etc Use of electricity / power supply by an x establishment such as IT Industries, IT Parks, IT Units Pumping of water, public water x supply, public water treatment plant, activities related with Supply Schemes and Sewage Treatment Plants, Sewage Pumping Stations etc
8. HT Ferro Metallurgical /Steel Rolling/Steel Melting/Power Intensive This schedule shall apply to supply of power having a Contract Demand from 100 KVA up to 1000 KVA at 11 KV and above 1000 KVA at 33 KV for Steel rolling industry and Metal Alloy, Steel Melting, Ferro Alloy, and Ferro metallurgical industries where melting is involved using electric power.
9. LT and HT Agriculture Pump sets This schedule shall apply to establishments for Irrigation pumping, De-watering and Lift Irrigation for cultivation of food crops such as cereals, pulses, vegetables and fruits etc and Cane crusher and/or fodder cutter for self-use for Agricultural purposes. This tariff shall be applicable from the date of production of a certificate from the Directorate of Animal Husbandry or Agriculture Department of Government of Goa to the effect that the consumer carried on the said activity on regular basis. In case of
10. LT and HT Agriculture Allied Activities This schedule shall apply to establishments for other allied activities related to Agriculture and shall include but not limited to: Poultry farms, Livestock farms, x Combination of livestock farms with dairy, Piggery etc Horticulture, Green Houses, x Plantations, all types of nurseries etc. Fish farms including ornamental fish x farms, prawn farms, other aqua farms etc Tissue culture, Mushroom activities, x Aquaculture, Floriculture, Fisheries, Sericulture, Floricultural nurseries, hatcheries etc Any other agricultural activity not x falling under HT-Agriculture (A) shall be covered under this category failure to produce the certificate, the same shall be considered under Commercial category. Cold Storages which are solely attached to Agriculture and its allied activities shall be charged tariff of Agriculture allied activities. All other cold storages which are partly or not attached with Agriculture and Allied activities shall be charged Commercial Tariff.
11. MES/Defense Establishments This schedule shall apply to supply of power for defense installation establishments, having mixed load with predominantly lighting or non-industrial load of more than 50% of connected load.
12. LT Public Lighting This schedule shall apply to public lighting systems. It would include the following categories but not limited to: Market Places, Roads, Pathways and x Parking Lighting belonging to local authorities such as Municipality/ Panchayats/ Government; Lighting in Public Gardens; x Traffic Signals and Traffic Islands; x State Transport Bus Shelters; x Public Sanitary Conveniences; and x Public Water Fountains and such x other Public Places open for general public free of charge. Street lighting in the colony of a x factory which is situated separately from the main factory. This shall also be applicable to public x lighting of Government/ Semi Government Establishments but shall not be applicable in case of private establishments
13. LT Hoardings/ Sign Boards This schedule shall apply to lighting advertisements, hoardings and displays at departmental stores, malls, multiplexes, theatres, clubs, hotels, bus shelters, Railway Stations etc. and shall be separately metered and charged at the tariff applicable for "Hoardings / Sign Board" category. However use of electricity for displays for the purpose of indicating /
displaying the name and other details of the shop, on commercial premises itself, shall be covered under the prevailing tariff for such shops or commercial premises.
14. Temporary Supply This schedule shall apply to usage of electricity for all temporary purposes. i. The temporary connection shall be released through a proper meter ii. The Temporary Tariff is applicable for a temporary period of supply for a period of maximum one (1) year at a time, which may be further extended, as per the provisions of Supply Code Regulations as notified by JERC.
15. HT SPS Single Point Supply This schedule shall apply to a group of consumers who desire to take a HT connection at single point for consumption of energy within a Residential Complex ± Group Housing Societies, Residential Housing Colonies, Cooperative Group Housing Societies, Township Areas; Commercial Complexes, including Malls; Industrial Complexes, including IT Parks, Bio-Parks or other entities classified as industries by the Government of Goa. In case of a dispute on whether the complex can be classified as an industrial complex, a certificate from Industries Department, Government of Goa will be required. The following shall be the different combinations for SPS in a defined area: i. All LT consumer mix area ii. All HT consumer mix area iii. HT+LT consumer mix area a. The General Conditions, Miscellaneous and General Charges would also be applicable for all SPS categories. b. Based on technical and administrative feasibility, the ED- Goa may consider providing SPS power supply at HV/ EHV level to a complex at a mutually agreed injection point. c. The SPS arrangement would be applicable for the application received from a Residential complex / Association of Persons (AOP) / Developer of the complex or any other such similar person. d. The SPS arrangement would be considered by ED-Goa only if the minimum sanctioned cumulative contracted demand of the complex (group of consumers) is 1.15 MVA/ 1 MW. e. The complete cost of erection and O&M for the sub-transmission and distribution infrastructure within such complex would need to be borne by the said SPS applicant. f. The SPS applicant would be required to develop and maintain an efficient, coordinated and quality sub-transmission and distribution system in its area of electricity supply. Further, the applicant would be responsible to
comply with Standards of Performance and Supply Code Regulation as laid down under JERC Regulations and guidelines of Goa Electricity Department, if any. The network within the complex will need to be certified by the Chief Electrical Inspector. g. For Residential Complexes, SPS application shall be entertained for groups of LT consumers only. The loads of common amenities for such group may include pumps for pumping water supply, lifts and lighting of common area. However, the consumption of energy for common services shall be separately metered with meters installed by the consumer and tested and sealed by licensee. The consumption of such energy over and above 10% of the total consumption of energy shall be billed at LT Commercial Tariff. The user shall inform the details of every non-domestic activity within the residential complex, such as commercial complex, industrial activity, and recreation club, along with the connected load to the licensee at the time of seeking the connection or at the time of enhancement in contract demand, and shall seek a separate connection for the same in case the common load is more than 10%. h. Individual Domestic HT consumers in a residential complex that opt for SPS shall need to apply separately under HT Domestic category. i. The SPS applicant shall not charge tariff to the downstream consumers higher than stipulated. j. The applicant shall be obliged to pay the total tariff (total billed amount) due to ED-Goa, as measured at HT end of SPS. However, to cover energy transformation losses and other O&M expenses, such applicant would be eligible to get rebates from ED-Goa on full bill payment, within the due time: i. 5% on the overall billed amount in all cases of LT and HT consumers ii. Any other loss would be to the account of the applicant. k. For CC and IC applicant, any LT / HT Consumer in the area should
have minimum 80% pre-dominant load of their appropriate category i.e. mix load is allowed only upto 20%. For e.g. If a HT/ LT Industry Consumer has Factory, Residential Colony for its workers and also some Commercial facilities for his staff and the total of Residential and Commercial load is say around 30%, then separate Individual SPD connection may be taken for each such group as per activity. l. The implementation of SPS arrangement should be in accordance with the Electricity Act, 2003 and APTEL judgement dated 11th July 2011 in appeal no. 155 and 156 of 2010 in this regard.
16. Electric Vehicle Charging Stations This tariff schedule shall apply to consumers that have set up Public Charging Stations (PCS) in accordance with the technical norms/ standards/specifications laid down by the Ministry of Power, GoI and Central Electricity Authority (CEA) from time to time. The tariff for domestic consumption shall be applicable for domestic charging (LT/HT)
162 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 110 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA Tariff Schedule Joint Electricity Regulatory Commission (JERC) SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022 163 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 111 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA Tariff Schedule Joint Electricity Regulatory Commission (JERC) SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022 164 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 112 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA Tariff Schedule Joint Electricity Regulatory Commission (JERC) SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022 165 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 113 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA Tariff Schedule Joint Electricity Regulatory Commission (JERC) SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022 166 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 114 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA Tariff Schedule Joint Electricity Regulatory Commission (JERC) SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022 167 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 115 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA Tariff Schedule Joint Electricity Regulatory Commission (JERC) SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022 168 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 116 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA Tariff Schedule Joint Electricity Regulatory Commission (JERC) SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022

10.3. General Terms and Conditions

1) The tariffs are exclusive of electricity duty and taxes levied by the Government or other competent authority from time to time which are payable by the consumers in addition to the charges levied as per the tariffs.

2) Unless otherwise agreed to, these tariffs for power supply are applicable for supply at one point only.

3) Unless specifically stated to the contrary the figures of energy charges relate to rupee per unit (kWh) charge for energy consumed and fixed charge relates to a month.

4) If the energy supplied for a specific purpose under a particular tariff is used for a different purpose not contemplated in the contract for supply and / or for which a higher tariff is applicable, it shall be deemed as unauthorized use of electricity and shall be assessed under the provisions of section 126 of the Electricity Act, 2003 and Supply Code Regulation notified by the JERC.

5) Fixed charges, wherever applicable, will be charged on pro-rata basis from the date of release of connection. These shall be double in case bi-monthly billing is carried out and shall be proportionately calculated as per the number of days of billing, Similarly slabs of energy consumption shall also be considered accordingly in case of bi-monthly or periodic billing.

6) The consumption for factory lighting/pump house lighting shall be billed as per respective main tariff category. A separate energy meter for recording energy consumed towards factory lighting for new installation need not be provided. For the existing installations, till the factory lighting meter's mains are shifted to main meter, the total energy consumption shall be arrived at by adding the energy consumption of the main energy meter and the factory lighting meter.

169 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 117 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA Tariff Schedule Joint Electricity Regulatory Commission (JERC) SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022

7) The conditions, definitions etc. shall be applicable as per the Electricity Act 2003 and various JERC Regulations, such as Standards of Performance, Supply Code, Conditions of Supply, Distribution Code etc., issued from time to time.

8) Billing of Demand in excess of Contracted Demand

The billing shall be on the maximum demand recorded during the month or 85% of contracted demand whichever is higher. If in any month, the recorded maximum demand of the consumer exceeds its contracted demand, that portion of the demand in excess of the contracted demand shall be billed at double the normal rate. Similarly, energy consumption corresponding to excess demand shall also be billed at double the normal energy rate.

The definition of the maximum demand would be in accordance with the provisions of the Supply Code Regulations notified by JERC. If such over-drawal is more than 20% of the contracted demand then the connection shall be disconnected immediately.

Explanation:

Assuming the contract demand as 100 kVA, maximum demand at 120 kVA and total energy consumption as 12000 units, then the consumption corresponding to the contract demand will be 10,000 units (12000 X 100/ 120) and consumption corresponding to the excess demand will be 2000 units. This excess demand of 20 kVA and excess consumption of 2000 units will be billed at twice the respective normal rate.

9) The adjustment because of Fuel and Power Purchase Cost variation shall be calculated in accordance with the FPPCA formula separately notified by the Commission under the Regulation. Such charges shall be recovered / refunded in accordance with the terms and conditions specified in the FPPCA formula.

10) (cid:55)(cid:75)(cid:72)(cid:3)(cid:89)(cid:68)(cid:79)(cid:88)(cid:72)(cid:86)(cid:3)(cid:82)(cid:73)(cid:3)(cid:87)(cid:75)(cid:72)(cid:3)(cid:181)(cid:46)(cid:182)(cid:3)(cid:73)(cid:68)(cid:70)(cid:87)(cid:82)(cid:85)(cid:3)(cid:68)(cid:83)(cid:83)(cid:79)(cid:76)(cid:70)(cid:68)(cid:69)(cid:79)(cid:72)(cid:3)(cid:73)(cid:82)(cid:85)(cid:3)(cid:87)(cid:75)(cid:72)(cid:3)(cid:71)(cid:76)(cid:73)(cid:73)(cid:72)(cid:85)(cid:72)(cid:81)(cid:87)(cid:3)(cid:70)(cid:82)(cid:81)(cid:86)(cid:88)(cid:80)(cid:72)(cid:85)(cid:3)(cid:70)(cid:68)(cid:87)(cid:72)(cid:74)(cid:82)(cid:85)(cid:76)(cid:72)(cid:86)(cid:3)(cid:73)(cid:82)(cid:85)(cid:3)(cid:88)(cid:86)(cid:72)(cid:3)(cid:76)(cid:81)(cid:3)(cid:87)(cid:75)(cid:72)(cid:3)(cid:41)(cid:51)(cid:51)(cid:38)(cid:36)(cid:3)(cid:73)(cid:82)(cid:85)(cid:80)(cid:88)(cid:79)(cid:68)(cid:3) shall be as specified in Chapter 9 of this Tariff Order.

11) For staff quarters, rest/guest houses, street lighting in the colony of a factory which is situated separately from the main factory and for distribution lines, service lines, etc. permitted to be owned and maintained by the HT consumer owning the factory, there shall be a separate connection and such energy consumed shall be charged under Single Point Supply.

12) Advance Payment Rebate: If payment is made in advance well before commencement of the consumption period for which the bill is prepared, a rebate @ 1% per month shall be given on the amount (excluding security deposit, taxes and duties) which remains with the licensee at the end of the month. Such rebate, after adjusting any amount payable to the licensee, shall be credited to the account of the consumer.

If payment is made in advance along with prior declaration of premises to be closed for a certain period of time, a rebate of 1% per month shall be given on the amount (excluding security deposit, taxes and duties) which remains with the licensee at the end of the month. Such rebate, after adjusting any amount payable to the licensee, shall be credited to the account of the consumer.

13) Prompt Payment Rebate: If payment is made at least 7 days in advance of the due date of payment a rebate for prompt payment @ 0.25 % of the bill amount (excluding taxes and duties) shall be given in case of cash payment and . Those consumers having arrears shall not be entitled for such rebate and the amount paid will first be used to set off past liabilities.

Provided that in case the payment is made by cheque, the prompt payment discount will be applicable only if the payment by cheque is made 3 days prior to date of availing the prompt payment discount i.e. before 10 days from the due date of payment.

14) Delayed Payment Charges (DPC): In case the electricity bills are not paid within the due date mentioned on the bill, delayed payment charges of 1.5% (computed on a daily basis on the outstanding bill from the due date till the date of payment) shall be levied on the bill amount. However, if a consumer makes part payment of a bill (in exceptional circumstances, with prior approval of the Chief Electrical Engineer), within the due date, then the delayed payment charges shall be applicable only on the amount which was not paid within the due date.

170 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 118 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA Tariff Schedule Joint Electricity Regulatory Commission (JERC) SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022

Such surcharge shall be rounded off to the nearest multiple of one rupee. Amount less than 50 paise shall be ignored and amount of 50 paise or more shall be rounded off to the next rupee.

If the consumer fails to pay the energy bill presented to him by the due date the department shall have the right to disconnect the supply as per provision of the Electricity Act 2003 and Supply Code Regulations notified by JERC as amended from time to time.

In case of non-realization of payment through Cheque, a penalty of 5% of the cheque amount in addition to the Delayed Payment Charges (DPC) will be levied on the consumers

15) Time of Day Tariff (ToD ):

i. Under the Time of Day (ToD) Tariff, electricity consumption and maximum demand in respect of HT/EHT consumers for different periods of the day, i.e. normal period, peak load period and off peak load period, shall be recorded by installing a ToD meter.

ii. The maximum demand and consumption recorded in different periods shall be billed at the following rates on the tariff applicable to the consumer.

Time of use Demand Charges Energy Charges
Normal period (7:00 a.m. to 6:00 p.m) Normal Rate Normal rate of energy charges
Evening peak load period (6:00 p.m to 11.00 p.m) Normal Rate 120% of normal rate of energy charges
Off-peak load period (11:00 p.m to 7:00 a.m) Normal Rate 90% of normal rate of energy charges

iii. Applicability and Terms and Conditions of TOD tariff:

a) TOD tariff is mandatory for HT/EHT consumers and shall be optional for LT industrial and commercial consumers

b) The facility of aforesaid TOD tariff shall not be available to HT/EHT consumers having captive power plants and/or availing supply from sources other than ED-Goa through wheeling of power.

c) The HT/EHT industrial consumers who have installed standby generating plants shall also be eligible for the aforesaid TOD tariff

d) In the event of applicability of TOD tariff to a consumer, all other terms and conditions of the applicable tariff shall continue to apply.

10.4. Schedule of Miscellaneous Charges

Description Approved Charges
Monthly Meter Rental Charges(as per provisions of Supply Code Regulations notified by JERC)
Single Phase LT meter INR 15/month
Three Phase LT meter INR 25/month
Three Phase LT meter with CTs INR75/month
LT Meter with MD Indicator INR 30/month
LT Tri-YHFWRUPHWHUZLWK&7¶V INR75/month
Tri-vector Meter INR 1200/month
Bi- directional meter INR 1,500/month
Temporary Supply Shall be twice as applicable in above meter types
Changing or moving a Meter board Actual Cost + 15%
Note: a. For all domestic and other LT loads less than 50 kW loads in Urban and Rural areas - Static single phase / three phase meters b. )RU/7 FRQWUDFWHGORDG•.: +7(+7FRQVXPHU± Static, 3 Phase Tri-vector meters with MDI (MD Display)
Reconnection Charges(as per provisions of Supply Code Regulations notified by JERC)
LT Services ± At Cut outs
Single Phase x INR 25/-
Three Phase x INR 50/-
LT Services ± At Overhead Mains
Single Phase x INR 30/-
Three Phase x INR 50/-
LT Services ± At Underground Mains
Single Phase x INR 75/-
Three Phase x INR 125/-
HT Services INR 200/-
Note: If the same consumer seeks reconnection within 12 months from the date of reconnection or disconnection, 50% will be added to above charges
Re-Rating of Installations
Lighting Installation INR 50/-
Motive Power Installation INR 100/-
High Tension INR 500/-
Testing Fee for Various Metering Equipments (as per provisions of Supply Code Regulations notified by JERC)
Single phase LT INR 25/energy meter
Poly Phase LT without CT INR 50/energy meter
L.T. meter with CTs/Demand or Special Type Meters INR 150/energy meter
H.T and E.H.T. metering equipment INR 10,000/- at site
Transformer Oil INR 200/- per sample
LT Current Transformer at Lab INR50/- per sample
3 ± Ø Phase Tri-vector Meter Industrial LT Consumer INR 1000/- for laboratory testing
3 ± Ø Phase Tri-vector Meter 11 KV and 33kV HT Consumer INR 5,000/- at site
Three Phase Tri-Vector Meter 110 KV EHT Consumers INR 1,000/-at site
Combined CTPT Unit for 11kV and 33kV Consumer INR 2,500/-
110KV CT / PT Unit INR 10,000/-
Single Phase CT INR 150/ unit
Three Phase TT Block INR 500/unit
Distribution Transformer Testing (HT con.) INR 6,000
Power Transformer Testing ( EHT consumer) INR 20,000
Service Connection Charges(as per provisions of Supply Code Regulations notified by JERC)
6LQJOH3KDVHȜ INR 250
7KUHH3KDVHȜ
Up to 5 HP INR 500
5 HP to 20 HP INR 800
Above 20 HP INR 1,200
HT (First 500 KVA) INR 10,000
HT (Beyond 500 KVA) INR 20,000
HT Additional Load INR500/- for every addition of 100 KVA
([WUD/HQJWKIRUȜ EH\RQGPHWHUV INR 50 /meter
([WUD/HQJWKIRUȜIRUDJULFXOWXUDOFRQVXPHUV EH\RQGPHWHUV INR 25 /meter
([WUD/HQJWKIRUȜ EH\RQGPHWHUV INR 100 /meter
Extra /HQJWKIRUȜIRUDJULFXOWXUDOFRQVXPHUV EH\RQGPHWHUV INR 50 /meter
Underground Service Cable Actual Charges + 15%
Shunt Capacitor- 20 kW to 50 kW INR 2,000
Shunt Capacitor- above 50 kW INR 5,000
7HVWLQJ&RQVXPHU¶VLQVWDOODWLRQ as per provisions of Supply Code Regulations notified by JERC)
For first test of the new installation on or off an extension to an existing installation if the installation is found to be defective. NIL
For Subsequent test of the new installation or of an existing installation if the installation is found to be defective
Single phase LT ‡ INR 100/-
Three phase ‡ INR 200/-
MS/BS loads upto70kW ‡ INR 4,000 + GST
LS/BS/RT (loads Above 70kW) ‡ INR 8,000 + GST
Shunt Capacitor- 20 kW to 50 kW ‡ INR 1,000 + GST
Shunt Capacitor- above 50 kW ‡ INR 4,000 + GST
Changing the Meter or its position in the same premises at the request of the consumer when no additional material is required(as per provisions of Supply Code Regulations notified by JERC)
Single phase INR 100/-
3-phase without C.Ts INR 200/-
L.T. meter with C.T.s INR 500/-
H.T and E.H.T. metering equipment INR 8,000 + GST
Re-sealing charges irrespective of the number of seals involved against each item below and where seals found to have been broken by the consumer
Meter cupboard / Meter Cubical / Box INR 50/-
Where cut-out is independently sealed INR 50/-
Meter cover or Meter Terminal cover INR 50/-
Meter cover of Meter Terminal cover (3 phase). INR 50/-
Maximum demand Indicator or C.T.s chamber INR 50/-
Service Charges
General Supply
Single Phase ‡ INR 10/-
Three phase below 70kW ‡ INR 20/-
Three phase above 70kW ‡ INR 50/-
Industrial/bulk/ agriculture /Street Lightning Supply
‡ Upto70kW INR 25/-
‡ Above 70kW INR 50/-
Replacement of broken glass
Replacement of broken glass of meter cupboard (When there is default on Consumer Side) INR 50/-
Replacement of broken Glass of single phase meter if the consumer has broken or tamper and with meter. INR 50/-
Replacement of broken Glass of three phase meter if the consumer has broken or tamper and with meter INR 50/-
Supply of duplicate copies of electricity bills
Domestic Consumers INR 5 per bill
Non Domestic consumers INR10 per bill
LT Industrial upto 20kW and AP Consumer INR 5 per bill
H.T Industrial and Bulk supply consumer INR10 per bill
Stand by Meter
HT INR10,000/-
EHT INR20,000/-
Check Meter
HT INR10,000/-
EHT INR20,000/-
Load Enhancement Actual Cost + 15% Supervision Charges
System Strengthening charges or capacity building charges, Actual Cost + 15% Supervision Charges
Advance for Temporary Connections (Except for Prepaid meters)
‡6LQJOHSKDVH/7 INR 2,000/-
‡7KUHHSKDVH INR 5,000/-
‡+7 INR 20,000/-
‡(+7 INR 20,000/-
Note : this shall be adjusted in bills
Non-Refundable Registration-cum-processing fees As per Supply Code Regulations notified by JERC
Underground service cable
1 Phase through underground service cable Rs.100/meter
Extra Length 1 phase for Agriculture consumer(beyond 300 meters) through underground service cable Rs.25/meter
3 Phase through underground service cable Rs.300/meter
Extra Length for 3Phase for Agriculture consumers (beyond 300meters) through underground service cable Rs.100/meter
At location where overhead network exist and consumer desires to avail power through Underground service cable Actual charges+15%
171 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 119 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA Tariff Schedule Joint Electricity Regulatory Commission (JERC) SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022 172 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 120 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA Tariff Schedule Joint Electricity Regulatory Commission (JERC) SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022 173 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 121 Electricity Department, Government of Goa OFFICIAL GAZETTE — GOVT. OF GOA Tariff Schedule Joint Electricity Regulatory Commission (JERC) SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022 174 Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 122 Electricity Department, Government of Goa Tariff Schedule Joint Electricity Regulatory Commission (JERC) OFFICIAL GAZETTE — GOVT. OF GOA SERIES I No. 3 (EXTRAORDINARY No. 2) 27TH APRIL, 2022

In case of bonafide agricultural pumping loads, the department shall provide overhead service lines at a free of cost upto 300 meters from the nearest distribution point i.e. existing rural transformer sub-station or from a service line already laid for supply to any other consumer, provided the latter has sufficient current carrying capacity. Any length in excess of the specified length shall be payable at a fixed cost of INR 25 / metre for single phase and INR.50/ meter for Three phase as approved under Schedule of General and Miscellaneous Charges Annexures Joint Electricity Regulatory Commission (JERC)

Annexures

Annexure 1: List of Stakeholders

The following is the list of the participants in Public Hearings conducted on 24.1.2022through video conferencing:

Table 97: List of participants in Public Hearing

S. No. Name of Person (Mr/Ms) Organization/ Address
1 Martin Rodrigues Secretary, Raia Civic and Consumer Forum.
2 Mr. Gerard DMello Goa Chamber of Commerce & Industry
3 Mr. Sanjay Y. Amonkar Goa Chamber of Commerce & Industry
4 Mr. Joseph D'Souza Goa Chamber of Commerce & Industry
5 Mr. M. Durairaj Goa Chamber of Commerce & Industry

www.goaprintingpress.gov.in

Order on ARR for FY 2022-23 to FY 2024-25 and Retail Tariff for the FY 2022-23 123 Electricity Department, Government of Goa

Printed and Published by the Director, Printing & Stationery, Government Printing Press, Mahatma Gandhi Road, Panaji-Goa 403 001.

PRICE – Rs. 121.00

PRINTED AT THE GOVERNMENT PRINTING PRESS, PANAJI-GOA—34/150—4/2022.

175
Cite this issue. Goa Gazette, Government of Goa, 27 April 2022. Indian Gazettes, https://egazette.servantsofknowledge.in/details/in.goa.egaz.2223-3.SI/2223-3-SI-EOG-2/. Archive identifier in.goa.egaz.2223-3.SI/2223-3-SI-EOG-2.