REGD . NO . D. L. (N ) 04/ 0007 /2003-05 रजिस्ट्री सं. डी. एल . (एन ) 04/0007/2003-05
भारत का राजपत्र The Gazette of India
प्राधिकार से प्रकाशित
PUBLISHED BY AUTHORITY
साप्ताहिक
WEEKLY
सं. 25]
नई दिल्ली, जून 17 जून 23 , 2007 , शनिवार/ज्येष्ठ 27 - आषाढ़ 2 , 1929
No. 25]
NEW DELHI , JUNE 17 - JUNE 23 , 2007 , SATURDAY / JYAISTHA 27- ASADHA 2, 1929 इस भाग में भिन्न पृष्ठ संख्या दी जाती है जिससे कि यह पृथक संकलन के रूप में रखा जा सके Separate Paging is given to this Part in order that it may be filed as a separate compilation
भाग II-खण्ड उप-खण्ड ( ii) PART II -Section 3-Sub- section ( ii )
भारत सरकार के मंत्रालयों ( रक्षा मंत्रालय को छोड़कर ) द्वारा जारी किए गए सांविधिक आदेश और अधिसूचनाएं Statutory Orders and Notifications Issued by the Ministries of the Government of India (Other than the Ministry of Defence)
गृह मंत्रालय
नई दिल्ली , 1 मई , 2007
!! क का.आ. 1781.-लोक परिसर ( अनधिकृत कब्जेदारों की बेदखली ) अधिनियम , 1971 ( 1971 का 40 ) की धारा 3 द्वारा प्रदत्त शक्तियों का प्रयोग करते हुए केन्द्र सरकार , एतद्वारा नीचे दी गई सारणी के कालम ( 1 ) में उल्लिखित अधिकारी को, सरकार का राजपत्रित अधिकारी होने के नाते , उक्त अधिनियम के प्रयोजन हेतु सम्पदा अधिकारी नियुक्त करती है जो उक्त सारणी के कालम ( 2 ) की संबंधित प्रविष्टि में विनिर्दिष्ट लोक परिसरों के संबंध में अपने क्षेत्राधिकार की स्थानीय सीमाओं के भीतर उक्त अधिनियम के अंतर्गत अथवा उसके द्वारा सम्पदा अधिकारी को प्रदत्त शक्तियों का प्रयोग करेगा तथा सौंपे गए कर्तव्यों का निर्वहन करेगा:-
सारणी
लोक परिसरों की श्रेणियां और क्षेत्राधिकार की स्थानीय सीमाएं अधिकारी का नाम
(2)
(1)
त्रिपुरा राज्य के निम्नलिखित स्थानों पर केन्द्रीय रिजर्व पुलिस बल के परिसर अथवा उसके द्वारा या इसकी ओर से पट्टे पर लिए गए परिसर अपर पुलिस उप महानिरीक्षक , ग्रुप केन्द्र, केन्द्रीय रिजर्व पुलिस बल , अगरतला, त्रिपुरा
( i ) कंपनी मुख्यालय राताचेरा , त्रिपुरा -16.39 एकड़
(ii ) कंपनी मुख्यालय बैखोरा , त्रिपुरा-14.26 एकड़
-7.72 एकड़
(iii ) लिंबुचेरा , त्रिपुरा
( iv ) सालबागान अगरतला , त्रिपुरा -36.58 एकड़
[फा. सं. ए- II - 2/2007- प्रशा. - 1 ( टीपीएं- ओएल)-गृह मंत्रालय- पीएफ- III ]
एच. काम सुआनथंग , अवर सचिव
(3911)
2733 GI/07-1 3912
THE GAZETTE OF INDIA : JUNE 23 , 2007 /ASADHA 2 , 1929
[PART. II-SEC. 3 (ii ) ]
MINISTRY OF HOME AFFAIRS
New Delhi , the 1st May , 2007
S.O. 1781.- In exercise of the powers conferred by Section 3 of the Public Premises (Eviction of Unauthorised Occupants ) Act, 1971 (40 of 1971 ) , the Central Government hereby appoints the Officer mentioned in column ( 1 ) of the Tablebelow, being Gazetted Officer of Government , to be Estate Officer for the purpose of the said Act, who shall exercise the powers conferred , and perform the duties imposed , on Estate Officer by or under the said Act , within the local limits of his jurisdiction, in respect of public premises specified in the corresponding entry in column (2) of the said Table .
TABLE
Designation ofthe Officer
Categories ofpublic premises and local limits ofjurisdiction (1)
(2)
Additional Deputy Inspector General of Police Group Centre , Central Reserve Police Force , Agartala, Tripura.
Premises belonging to , or taken on lease , by or on behalf of, the Central Reserve Police Force at the following locations in the State ofTripura: --
(i) Coy Hqrs . Rattachera, Tripura --- 16.39 acres
( ii ) Coy Hqrs . Baikhora, Tripura ,-14.26 acres
(iii) Limbuchera, Tripura -7.72 acres
( iv) Salbagan Agartala , Tripura-36.58 acres
[F. No. A- II - 2/2007-Admn . - I (TPA-OL) -MHA - PF- IIIJ H. KAM SUANTHANG , Under Secy .
कार्मिक , लोक शिकायत तथा पेंशन मंत्रालय (कार्मिक और प्रशिक्षण विभाग )
नई दिल्ली, 8 जून , 2007
का.आ. 1782.-केन्द्रीय सरकार एतद्वारा दिल्ली विशेष पुलिस स्थापना अधिनियम , 1946 ( 1946 का अधिनियम सं. 25 ) की धारा 6के साथ पठित धारा 5 की उपधारा ( 1 ) द्वारा प्रदत्त शक्तियों का प्रयोग करते हुए आंध्र प्रदेश राज्य सरकार गृह ( एससीए ) विभाग की दिनांक 2जून, 2007 की अधिसूचना सं. जीओ एम्स सं. 115 के द्वारा दी गई सहमति से हुसैनी आलम पुलिस स्टेशन में भारतीय दंड संहिता , 1860 ( 1860 का अधिनियम सं. 45 ) की धारा 302, 307 ,120- बी और विस्फोटक पदार्थ अधिनियम , 1908 ( 1908 का अधिनियम सं. 6 ) की धारा 3 एवं 5 के अंतर्गज दर्ज अपराध सं. 100/2007 ( 18-05-2007 को हुए मक्का मस्जिद बम विस्फोट ) तथा उपर्युक्त अपराध से संबंधित अथवा संसक्त प्रयत्नों, दुष्प्रेरणों और षडयंत्रों तथा उसी संव्यवहार के अनुक्रम में किए गए तथा उन्हीं तथ्यों से उद्भूत किन्हीं अन्य अपराधों का अन्वेषण करने के लिए दिल्ली विशेष पुलिस स्थापना के सदस्यों की शक्तियों और अधिकारिता का विस्तार सम्पूर्ण आंध्र प्रदेश राज्य पर करती है।
[सं. 228/32/2007 - ए.वी.डी.- II ]
तेजा सिंह , अवर सचिव MINISTRY OF PERSONNEL , PUBLIC GRIEVANCES AND PENSIONS (Department of Personnel and Training)
New Delhi , the 8th June , 2007
S.Q. 1782. In exercise of the powers conferredby Sub - section ( 1 ) of Section 5 read with Section 6 of the Delhi Special Police Establishment Act , 1946 (Act No. 25 of 1946) , the Central Government with the consent of the State Government of Andhra Pradesh , Home (SC . A) Department vide notification No. GO Ms No. 115 dated 2nd June , 2007, hereby extends the powers and jurisdiction of the mernbers of the Delhi Special Police Establishment to the whole of the State of Andhra Pradesh for investigation of Crime No. 100/2007 (Macca Masjid Bomb Explosion occurred on 18-5-2007) under Sections 302, 307 , 120- B Indian Penal Code , 1860 (Act No. 45 of 1860) and Section 3 and 5 of Explosive Substances Act, 1908 (Act No. 6 of 1908 ) registered at Hussaini Alam Police Station and attempts , abetment and conspiracies in relation to or in connection with the said offence and any other offences committed in the course of the same transaction or arising out of the same facts .
[No. 228/32/2007 -AVD - II
TEJA SINGH , Under Secy.
3913 भारत का राजपत्र : जून 23, 2007/ आषाढ़ 2 , 1929
[भाग II-खण्ड 3 ( ii) ]
वित्त मंत्रालय
( आर्थिक कार्य विभाग )
(बैंकिंग प्रभाग)
नई दिल्ली, 18 जून , 2007
का.आ. 1783.- राष्ट्रीय आवास बैंक अधिनियम , 1987 ( 1987 का 53 ) की धारा 6 की उप- धारा ( 1 ) के खण्ड ( ड. ) द्वारा प्रदत्त शक्तियों का प्रयोग करते हुए, केन्द्रीय सरकार , एतद्द्वारा डॉ. एच. एस. आनन्द, सचिव , आवास तथा गरीबी उन्मूलन मंत्रालय , नई दिल्ली को तत्काल प्रभाव से तथा अगले आदेश तक श्री रंजीत इस्सर के स्थान पर राष्ट्रीय आवास बैंक के निदेशक मण्डल में निदेशक के पद पर नियुक्त करती है।
[फा. सं. 7/ 15/2000- बीओ-1 ] जी.बी. सिंह , उप सचिव
MINISTRY OF FINANCE
(Department of EconomicAffairs)
(BANKING DIVISION)
New Delhi , the 18th June, 2007
S.O. 1783.-In exercise of the powers conferred by clause ( e) of Sub - section ( 1 ) of Section 6 of the National Housing Bank Act , 1987 (53 of 1987) , the Central Government hereby appoints Dr. H.S. Anand , Secretary , Ministry of Housing and Poverty Alleviation, New Delhi as a Director of the Board of Directors of National Housing Bank with immediate effect and until further orders in place of Shri Ranjit Issar .
[F. No. 7/15/2000-BO- I] G.B. SINGH, Dy . Secy.
वाणिज्य और उद्योग मंत्रालय
(वाणिज्य विभाग)
नई दिल्ली, 8 जून , 2007
का.आ. 1784.- केन्द्रीय सरकार, निर्यात ( क्वालिटी नियंत्रण और निरीक्षण ) नियम , 1964 के नियम 12 के उप - नियम ( 2 ) के अनुसरण में , और निर्यात ( क्वालिटी नियंत्रण और निरीक्षण ) अधिनियम , 1963 (1963 का 22) की धारा 7 की उप- धारा ( 1 ) द्वारा प्रदत्त शक्तियों का प्रयोग करते हुए , मैसर्स राईट्स लिमिटेड, माउंट चैम्बर्स , चौथा तल , 758 , अन्ना सलाई , चैन्नई-600002 को राजपत्र में, इस अधिसूचना के प्रकाशन की तारीख से तीन वर्ष की और अवधि के लिए प्रभावी वाणिज्य मंत्रालय , भारत सरकार की अधिसूचना सं. का.आ. 3975 और का.आ. 3978 तारीख 20 दिसम्बर , 1965 के साथ उपाबद्ध अनुसूची में विनिर्दिष्ट खनिज और अयस्क समूह 1 अर्थात्लौह अयस्क और मैगनीज अयस्क ( मैंगनीज डॉयआक्साइड को छोड़कर ) , फैरोमैंगनीज जिसके अंतर्गत फैरोमैगनीज स्लेग और समूह- II अर्थात् बैराईट्स, रेड आक्साइड और फैल्डस्पार के निर्यात से पूर्व निम्नलिखित शर्तों के अधीन चैन्नई में उक्त खनिजों और अयस्कों का निरीक्षण करने के लिए एक अभिकरण के रूप में मान्यता देती है , अर्थात्:-
(i ) कि मैसर्स राईट्स लिमिटेड, चैन्नई खनिज तथा अयस्क समूह- I का निर्यात ( निरीक्षण ) नियम, 1965 खनिज तथा अयस्क समूह- II का निर्यात (निरीक्षण ) नियम , 1965 के नियम 4 के अंतर्गत निरीक्षण का प्रमाण पत्र देने के लिए उनके द्वारा अपनाई गई पद्धति की जांच करने के लिए, इस संबंध में निर्यात निरीक्षण परिषद् द्वारा नामित अधिकारियों को पर्याप्त सुविधाएं देगी;
(ii ) मैसर्स राईट्स लिमिटेड , चैन्नई इस अधिसूचना के अधीन अपने कृत्यों के अनुपालन में निदेशक ( निरीक्षण और क्वालिटी 'नियंत्रण ) , निर्यात निरीक्षण परिषद्द्वारा समय - समय पर लिखित में दिए गए निर्देशों से आबद्ध होंगे ।
[फा. सं. 5/4/2007- ईआई एंड ईपी ]
वी. के. गाबा, उप सचिव MINISTRY OF COMMERCE AND INDUSTRY
(Department of Commerce)
New Delhi , the 8th June, 2007
S.O. 1784. In exercise of the powers conferrred by sub-section ( 1 ) of Section 7 of the Export ( Quality Control and Inspection) Act , 1963 (22 of 1963 ), and in pursuance of sub -rule (2) of rule 12 of the Export (Quality Control and Inspection) Rule, 1964, the Central Government hereby recognises M/ s . RITES LTD. , Mount Chambers , 4th Floor, 758 , Anna Salai , Chennai - 600002 as an agency for a period of three years with effect from the date of publication of this notification in the Official Gazette , for inspection of Minerals and OresGroup- I , namely, Iron Ore, Managese Ore ( excluding Manganese Dioxide) , Ferromanganese including Ferromanganese slag and Group - II , namely , Barytes , Red Oxide and 3914
THE GAZETTE OF INDIA . JUNE 23 , 2007/ASADHA 2 , 1929
[ PART II- SEC . 3 (ii) ) Feldspar as specified in the Schedules annexed to the notifications of the Government of India in the Ministry of Commerce numbers S.O. 3975 and S.O. 3978 respectively both dated the 20th December , 1965 , prior to the export of the said Minerals and Ores , at Chennai , subject to the following conditions , namely :-
(i) that M/s . RITES Ltd. , Chennai shall give adequate facilities to the officers nominated by the Export Inspection Council in this behalf to examine the method of inspection followed by them in granting the certificate of inspection under rule 4 of the Export of Minerals and Ores- Group I ( Inspection ) Rules , 1965 and the export ofMinerals and Ores - Group II ( Inspection ) Rules , 1965;
(ii) that M/s . RITES Ltd. , Chennai in the performance of their function under this notification shall be bound by such directives as the Director ( Inspection and Quality Control ) , Export Inspection Council may give in writing fromtime to time.
[ F. No. 5 /4/2007 - ΕΙ & ΕΡ ] V. K GAUBA, Dy. Secy.
अल्पसंख्यक कार्य मंत्रालय
नई दिल्ली, 11 जून , 2007
विषय: मुसलमानों में कौशल और उद्यमीय विकास के लिए एक अंतर - मंत्रालयी समूह का गठन ।
का.आ. 1785.- मुसलमानों में कौशल और उद्यमीय विकास के लिए एक व्यापक कार्यक्रम की योजना बनाने और उसके कार्यान्वयन की निगरानी करने के लिए निम्न प्रकार से एक अंतर- मंत्रालयी समूह के गठन करने का निर्णय किया गया है : -
(i) प्रधानमंत्री के प्रधान सचिव
अध्यक्ष
( ii) सचिव , अल्पसंख्यक कार्य मंत्रालय
सदस्य
( iii ) सचिव , वस्त्र मंत्रालय
सदस्य
सदस्य
( iv) सचिव , लघु उद्योग एवं कृषि ग्रामीण आधारित उद्योग विभाग
सदस्य
( v ) सचिव , औद्योगिक नीति एवं संवर्द्धन विभाग
सचिव , खाद्य प्रसंस्करण उद्योग
(vi)
सदस्य
सचिव, भारी उद्योग विभाग
(vii)
सदस्य
सचिव , स्कूली शिक्षा एवं साक्षरता विभाग
सदस्य
(viii)
(ix) सचिव, उच्च शिक्षा विभाग
सदस्य
(x) सचिव, श्रम और रोजगार मंत्रालय
सदस्य
सचिव , वित्त मंत्रालय ( बैंकिंग )
(xi )
सदस्य
(xii) सचिव , स्वास्थ्य एवं परिवार कल्याण मंत्रालय
सदस्य
(xiii ) सचिव , आवास एवं शहरी गरीबी उपमशन मंत्रालय
सदस्य
संयोजक
(xiv) संयुक्त सचिव ( पीपी ) , अल्पसंख्यक कार्य मंत्रालय
2. इस अंतर- मंत्रालीय समूह के विचारार्थ विषय इस प्रकार होंगे :-
(i ) मुसलमानों में कौशल और उद्यमीय विकास के लिए एक व्यापक कार्यक्रम तैयार एवं कार्यान्वित करना । ( ii ) कौशल और उद्यमीय विकास की आवश्यकता के समाधान हेतु एक " कलस्टर दृष्टिकोण " अपनाना , जिससे भारी संख्या में स्वः रोजगार में लगी मुस्लिम जनसंख्या को लाभ हो ।
( iii ) यह सुनिश्चित करना कि इन योजनाओं की पूरकताओं एवं सहक्रिया से अभिप्रेत लाभग्राहियों को शीघ्र और सुस्पष्ट रूप से लाभ प्राप्त हो ।
(iv) योजना के कार्यान्वयन में पचायती राज संस्थानों तथा शहरी स्थानीय निकायों को शामिल करने की संभावनाओं पर विचार करना ।
( v) इस समूह के गठन की तारीख से तीन मास के भीतर इस संबंध में एक योजना प्रस्तुत करना ।
(vi ) योजना के कार्यान्वयन की निगरानी करना । 3915 [ भाग II- खण्ड 3 ( ii) ]
भारत का राजपत्र : जून 23, 2007/आषाढ़ 2, 1929
3. इस अंतर - मंत्रालयी समूह के अध्यक्ष , यदि आवश्यक हो , किसी विशिष्ठ क्षेत्र/ समस्या पर अतिरिक्त सदस्यों को सहयोजित कर सकते हैं । अल्पसंख्यक कार्य मंत्रालय , इस समूह को साचिविक सहायता प्रदान करेगा । 4.
5, यह सक्षम प्राधिकारी के अनुमोदन से जारी किया जाता है ।
[सं. 14-12/2006- पी. पी.-I ]
अमेइजिंग लुईखम , संयुक्त सचिव
MINISTRY OF MINORITY AFFAIRS
New Delhi , the 11th June, 2007
Subject: Constitution of Inter -Ministerial group for skill and entrepreneurship development amongst Muslims.
S. O. 1785. In order to plan and monitor the implementation of a comprehensive programme for skill and entrepreneurship development amongst Muslims , it has been decided to set up an Inter - Ministrerial Group as follows :-
Chairman
(i) Principal Secretary to the Prime Minister
Member
( ii) Secretary , Ministry of Minority Affairs
Member
iii) Secretary, Ministry of Textiles
(
Member
( iv) Secretary, Departmental of Small Scale Industries &Agro -Rural Based Industries .
Member
(v) Secretary, Department of Industrial Policy & Promotion
Member
(vi) Secretary, Ministry of Food Processing Industries
Member
(vii) Secretary, Department of Heavy Industries
Member
(
viii) Secretary, Department of School Education and Literacy
Member
(ix) Secretary, Department of Higher Education
Member
(x) Secretary, Ministry of Labour & Employment
Member
(
xi) Secretary, Ministry of Finance (Banking)
Member
(xii) Secretary, Ministry of Health & Family Welfare.
(xiii
) Secretary , Ministry of Housing & Urban Poverty Alleviation . Member
Convener
(xiv) Joint Secretary (PP) , Ministry of Minority Affairs
2. The terms of reference of the inter- ministerial Group shall be as follows :-
(1) To plan the implementation of comprehensive programme for skill and entrepreneurship development amongst Muslims .
(ii) To adopt a ' cluster approach ' for addressing the need for skill and entrepreneurship development that will benefit the largely self- employed Muslim population.
(iii) To ensure that the benefits form complementarities and synergy from a host of schemes accrue to the intended beneficiaries quickly and in a palpable fashion.
(iv) To consider the possibilities of seeking involvement of the Panchayati Raj Institutions and urban local bodies in the implementation of the plan.
(v) To submit a plan in this regard within three months from the date of constitution of the group .
(vi) To monitor the implementation of the plan.
problem. 3. The Chairman of the Inter - ministerial Group , if necessary , may co - opt additional members on any specific area/ 4. The Ministry of Minority Affairs will provide secretarial support to this Group.
5. This issues with the approval of the Competent Authority.
[No. 14-12/2006-PP- ]
AMEISING LUIKHAM, Jt. Secy.
[PART II-SEC . 3 (ii ) ) THE GAZETTE OF INDIA : JUNE 23 , 2007/ASADHA 2, 1929
3916
उपभोक्ता मामले , खाद्य और सार्वजनिक वितरण मंत्रालय
( उपभोक्ता मामले विभाग )
नई दिल्ली, 24 मई, 2007
का. आ. 1786. - केन्द्रीय सरकार का विहित प्राधिकारी द्वारा उसे प्रस्तुत रिपोर्ट पर विचार करने के पश्चात् यह समाधान हो गया है कि उक्त रिपोर्ट में वर्णित मॉडल ( नीचे दी गई आकृति देखें ) बाट और माप मानक अधिनियम , 1976 ( 1976 का 60 ) तथा बाट और माप मानक (मॉडलों का अनुमोदन ) नियम , 1987 के उपबंधों के अनुरूप है और इस बात की संभावना है कि लगातार प्रयोग की अवधि में भी उक्त मॉडल यथार्थता बनाए रखेगा और विभिन्न परिस्थितियों में उपयुक्त सेवा प्रदान करता रहेगा;
अतः , अब , केन्द्रीय सरकार, उक्त अधिनियम की धारा 36 की उप - धारा ( 7 ) और ( 8 ) द्वारा प्रदत्त शक्तियों का प्रयोग करते हुए मैसर्स ई वे टकनोलॉजी , धोलेश्वर कॉम्पलेक्स, चंगोदर , सरखेज बावला हाइवे, अहमदाबाद , गुजरात द्वारा विनिर्मित उच्च यथार्थता ( यथार्थता वर्ग- II ) वाले " एस एच पी " श्रृंखला के अंकक सूचन सहित अस्वचालित तोलन उपकरण ( प्लेटफार्म प्रकार ) के मॉडल का , जिसके ब्रांड का नाम " सन " है ( जिसे इसमें इसके पश्चात् उक्त मॉडल कहा गया है ) और जिसे अनुमोदन चिह्न आई एन डी/09/ 07/202 समनुदेशित किया गया है, अनुमोदन प्रमाणपत्र जारी और प्रकाशित करती है ।
PLATFORM SCALE
FEATURES
Sare Lak
PATYCHANGE
उक्त मॉडल एक विकृत गेज प्रकार का भार सेल आधारित तोलन उपकरण है । इसकी अधिकतम क्षमता 1100 कि. ग्रा. है । और न्यूनतम क्षमता 5 कि. ग्रा. है । सत्यापन मापमान अन्तराल ( ई ) का मान 100 ग्रा. है । इसमें एक आद्येयतुलन युक्ति है जिसका शत प्रतिशत व्यवकलनात्मक धारित आद्येयतुलन प्रभाव है । प्रकाश उत्सर्जक डायोड ( एल ई डी ) प्रदर्श तोलन परिणाम उपदर्शित करता है । उपकरण 230 वोल्ट और 50 हर्ट्ज प्रत्यावर्ती धारा विद्युत प्रदाय पर कार्य करता है ।
स्टाम्मिग प्लेट के मुद्रांकन के अतिरिक्त मशीन को कपटपूर्ण व्यवहारों के लिए खोलने से रोकने के लिए सीलबंद भी किया जाएगा और मॉडल को बिक्री से पहले या बाद में उसकी सामग्री , यथार्थता , डिजाइन , सर्किट डायग्राम निष्पादन सिद्धांत आदि की शर्तों पर परिवर्तित नहीं किया जाएगा ।
और, केन्द्रीय सरकार , उक्त अधिनियम की धारा 36 की उप- धारा ( 12 ) द्वारा प्रदत्त शक्तियों का प्रयोग करते हुए , यह घोषणा करती है कि उक्त मॉडल के अनुमोदन के इस प्रमाणपत्र के अंतर्गत उसी विनिर्माता द्वारा उसी सिद्धांत , डिजाइन के अनुसार और उसी सामग्री से , जिससे उक्त अनुमोदित मॉडल का विनिर्माण किया गया है, विनिर्मित उसी श्रृंखला के वैसे ही मेक , यथार्थता और कार्यपालन के तोलन उपकरण भी होंगे जो 1 मि. ग्रा. से 50 मि. ग्रा. तक के " ई " मान के लिए 100 से 50,000 तक की रेंज में सत्यापन मापमान अंतराल ( एन ) और 100 मि. ग्रा. या उससे अधिक के " ई " मान के लिए 5000 से 50,000 तक की रेंज में सत्यापन मापमान अंतराल ( एन ) सहित 50 कि.ग्रा. से 5000 कि. ग्रा. तक की रेंज वाले हैं और " ई " मान 1 × 10 , 2× 10 * या 5 × 10 , के हैं, जो धनात्मक या ऋणात्मक पूर्णांक या शून्य के समतुल्य हैं।
[फा. सं. डब्ल्यू एम -21 ( 188 )/2004] आर. माथुरबूथम , निदेशक , विधिक माप विज्ञान [ भाग II-खण्ड 3( ii) ]
3917
भारत का राजपत्र जून 23 , 2007/आषाढ़ 2, 1929
MINISTRY OF CONSUMER AFFAIRS, FOOD AND PUBLIC DISTRIBUTION
(Department of Consumer Affairs)
New Delhi , the 24th May, 2007
S.O. 1786.-Whereas , the Central Government , after considering the report submitted to it by the prescribed authority , is satisfied that the Model described in the said report (see the figure given below) is in conformity with the provisions of the Standards of Weights and Measures Act, 1976 (60 of 1976) and the Standards of Weights and Measures (Approval of Models ) Rules , 1987 and the said Model is likely to maintain its accuracy over periods of sustained use and to render accurate service under varied conditions ;
Now, therefore, in exercise of the powers conferred by sub - sections (7 ) and (8 ) of Section 36 of the said Act, the Central Government hereby issues and publishes the certificate of approval of the Model of non- automatic weighing instrument (Platform type ) with digital indication of " SHP " series of high accuracy ( Accuracy class - II ) and with brand name " SUN " ( herein referred to as the said Model ) , manufactured by M/s . E Weigh Technolgoies , Dholeshwar Complex , Changodar, Sarkhej Bavla Highway, Ahmedabad , Gujrat and which is assigned the approval rnark IND/ 09/07/202 ;
BATT CHARGE BATYSPODE
The said Model is a strain gauge type load cell based weighing instrument with maximum capacity of 1100 kg. and minimum capacity of 5 kg . The verification scale interval (e) is 100 g . It has a tare device with a 100 per cent substractive retained tare effect. The light emitting diode (LED ) display indicates the weighing result . The instrument operates on 230Volts and 50 - Hertz alternate current power supply . In addition to sealing the stamping plate , sealing shall also be done to prevent opening of the machine for fraudulent practices and Model shall not be changed in terms of its material , accuracy , design , circuit diagram , working principle etc. before or after sale .
Further , in exercise of the powers conferred by sub- section ( 12 ) of Section 36 of the said Act, the Central Government hereby declares that this certificate of approval of the said Model shall also cover the weighing instrument of similar make and performacne of same series with maximum capacity above 50 kg . and up to 5000 kg. and with number of verification scale interval ( n) in the range of 100 to 50,000 for ' e' value of 1mg. to 50 mg. and with verification scale interval ( n) in the range of 5000 to 50,000 for ' e ' value of 100mg . or more and ' e ' value of the form 1 x 10 , 2 x 10% or 5 x 10 %, k being the positive or negative whole number or equal to zero , manufactured by the same manufacturer in accordance with the same principle , design and with the same materials with which , the said approved Model has been manufactured.
[F. No. WM- 21 ( 188 )/2004]
R. MATHURBOOTHAM, Director of Legal Metrology 3918
[PART II-SEC. 3 ( ii) ] THE GAZETTE OF INDIA : JUNE 23 , 2007/ASADHA 2 , 1929
नई दिल्ली, 24 मई , 2007
का. आ. 1787.- केन्द्रीय सरकार का , विहित प्राधिकारी द्वारा उसे प्रस्तुत रिपोर्ट पर विचार करने के पश्चात् यह समाधान हो गया है किउक्तरिपोर्ट में वर्णित मॉडल ( नीचे दी गई आकृति देखें) बाट और माप मानक अधिनियम , 1976 ( 1976 का 60 ) तथा बाट और माप मानक (मॉडलों का अनुमोदन ) नियम , 1987 के उपबंधों के अनुरूप है और इस बात की संभावना है कि लगातार प्रयोग की अवधि में भी उक्त मॉडल यथार्थता बनाए रखेगा और विभिन्न परिस्थितियों में उपयुक्त सेवा प्रदान करता रहेगा;
अतः अब , केन्द्रीय सरकार , उक्त अधिनियम की धारा 36 की उप - धारा ( 7 ) और ( 8 ) द्वारा प्रदत्त शक्तियों का प्रयोग करते हुए मैसर्स ई वे टेकनोलॉजी , धोलेश्वर कॉम्पलेक्स , चंगोदर , सरखेज बावला हाइवे, अहमदाबाद , गुजरात द्वारा विनिर्मित मध्यम यथार्थता ( यथार्थता वर्ग- III ) वाले " एस यू एन पी " श्रृंखला के अंकक सूचन सहित , अस्वचालित तोलन उपकरण ( प्लेटफार्म प्रकार) के मॉडल का, जिसके ब्रांड का नाम " सन " है ( जिसे इसमें इसके पश्चात् उक्त मॉडल कहा गया है ) और जिसे अनुमोदन चिह्न आई एन डी/09/07/203 समनुदेशित किया गया है , अनुमोदन प्रमाणपत्र जारी करती है ।
उक्त मॉडल एक विकृत गेज प्रकार का भार सेल आधारित तोलन उपकरण है । इसकी अधिकतम क्षमता 1000 कि. ग्रा. है । और न्यूनतम क्षमता 2 कि. ग्रा. है । सत्यापन मापमान अन्तराल (ई ) 100 ग्रा. है । इसमें एक आद्येयतुलन युक्ति है जिसका शत प्रतिशत व्यकलनात्मक धारित आधेयकुलन प्रभाव है । प्रकाश उत्सर्जक डायोड ( एल ई डी ) प्रदर्श तोलन परिणाम उपदर्शित करता है । उपकरण 230 वोल्ट और 50 हर्ट्ज प्रत्यावर्ती धारा विद्युत प्रदाय पर कार्य करता है ।
स्यैपिंग प्लेट के मुद्रांकन के अतिरिक्त मशीन को कपटपूर्ण व्यवहारों के लिए खोलने से रोकने के लिए सीलबंद भी किया जाएगा और मॉडल को बिक्री से पहले या बाद में उसकी सामग्री , यथार्थता , डिजाइन , सर्किट डायग्राम निष्पादन सिद्धांत आदि की शर्तों पर परिवर्तित नहीं किया जाएगा ।
और केन्द्रीय सरकार , उक्त अधिनियम की धारा 36 की उप - धारा ( 12 ) द्वारा प्रदत्त शक्तियों का प्रयोग करते हुए , यह घोषणा करती है कि उक्त मॉडल के अनुमोदन के इस प्रमाणपत्र के अंतर्गत उसी विनिर्माता द्वारा उसी सिद्धांत , डिजाइन के अनुसार और उसी सामग्री से, जिससे उक्त अनुमोदित मॉडल का विनिर्माण किया गया है, विनिर्मित उसी श्रृंखला के वैसे ही मेक , यथार्थता और कार्यपालन के तोलन उपकरण भी होंगे जो 100 मि. ग्रा. 2 ग्रा. तक के " ई " मान के लिए 100 से 10,000 तक की रेंज में सत्यापन मापमान अंतराल ( एन ) और 5 ग्राम या उससे अधिक के " ई " मान के लिए 500 से 10,000 तक की रेंज में सत्यापन मापमान अंतराल ( एन ) सहित 50 कि.ग्रा. से 5000 कि. ग्रा. तक की रेंज में हैं और " ई " मान 1 × 10 , 2 × 10 *, या 5 × 10*. के हैं, जो धनात्मक या ऋणात्मक पूर्णांक या शून्य के समतुल्य हैं।
[फा. सं. डब्ल्यू एम-21 ( 188 ) /2004 ] आर. माथुरबूथम , निदेशक, विधिक माप विज्ञान 3919
भारत का राजपत्र जून 23 , 2007/आषाढ़ 2 , 1929
[ भाग II- खण्ड 3 (ii) ]
New Delhi , the 24th May, 2007
S. O. 1787. Whereas the Central Government , after considering the report submitted to it by the prescribed authority , is satisfied that the Model described in the said report ( see the figure given below) is in conformity with the provisions ofthe Standards of Weights and Measures Act, 1976 (60 of 1976 ) and the Standards of Weights and Measures (Approval of Models ) Rules , 1987 and the said Model is likely to maintain its accuracy over periods of sustained use and to render accurate service under varied conditions ;
Now, therefore , in exercise of the powers conferred by sub - sections (7 ) and ( 8 ) of Section 36 of the said Act, the Central Government hereby issues and publishes the certificate of approval of the Model of non - automatic weighing instrument (Platform type ) with digital indication of " SUNP " series of medium accuracy ( Accuracy class III ) and with brand name " SUN " ( herein referred to as the said Model ); manufactured by M/ s . E Weigh Technolgoies , Dholeshwar Complex , Changodar , Sarkhej Bavla Highway , Ahmedabad , Gujarat and which is assigned the approval mark IND/09/07/203 ;
The said Model is a strain gauge type load cell based weighing instrument with maximum capacity of 1000 kg . and minimum capacity of 2 kg . The verification scale interval (e) is 100 g . It has a tare device with a 100 per cent substractive retained tare effect . The light emitting diode (LED) display indicates the weighing result . The instrument operates on 230Volts and 50- Hertz alternate current power supply. In addition to sealing the stamping plate sealing shall also be done to prevent opening of the machine for fraudulent practices and Model shall not be changed in terms of its material , accuracy , design , circuit diagram , working principle etc. before or after sale .
Further, in exercise of the powers conferred by sub - section ( 12) of Section 36 of the said Act , the Central Government hereby declares that this certificate of approval of the said Model shall also cover the weighing instrument of similar make and performacne of same series with maximum capacity above 50 kg . and up to 5000 kg . and with number of verification scale interval (n) in the range of 100 to 10,000 for ' e ' value between 100 mg . to 2 g and with number of verification scale interval (n) in the range of 500 to 10000 for ' e' value of 5g or more and ' e ' value of the form 1 x 10%, 2 x 10k or 5 x 10k, k being a positive or negative whole number or equal to zero , manufactured by the same manufacturer in accordance with the same principle , design and with the same materials with which , the said approved Model has been manufactured.
[F. No. WM - 21 ( 188 )/2004 ]
R. MATHURBOOTHAM, Director of Legal Metrology 2733 G1/07-2 3920
THE GAZETTE OF INDIA : JUNE 23 , 2007 /ASADHA 2, 1929
[PART II-SEC . 3 ( ii ) ]
नई दिल्ली, 24 मई , 2007
का. आ. 1788. - केन्द्रीय सरकार का , विहित प्राधिकारी द्वारा उसे प्रस्तुत रिपोर्ट पर विचार करने के पश्चात् यह समाधान हो गया है कि उक्त रिपोर्ट में वर्णित मॉडल ( नीचे दी गई आकृति देखें ) बाट और माप मानक अधिनियम , 1976 ( 1976 का 60 ) तथा बाट और माप मानक (मॉडलों का अनुमोदन ) नियम , 1987 के उपबंधों के अनुरूप है और इस बात की संभावना है कि लगातार प्रयोग की अवधि में भी उक्त मॉडल यथार्थता बनाए रखेगा और विभिन्न परिस्थितियों में उपयुक्त सेवा प्रदान करता रहेगा;
अतः अब केन्द्रीय सरकार , उक्त अधिनियम की धारा 36 की उप- धारा ( 7 ) और उप- धारा ( 8 ) द्वारा प्रदत्त शक्तियों का प्रयोग करते हुए मैसर्स ई वे टेकनोलॉजी , धोलेश्वर कॉम्पलेक्स , चंगोदर, सरखेज बावला हाइवे , अहमदाबाद , गुजरात द्वारा विनिर्मित मध्यम यथार्थता ( यथार्थता वर्ग- III ) वाले " एस यूएन टी " श्रृंखला के अंकक सूचन सहित , अस्वचालित तोलन उपकरण ( टेबल टाप प्रकार ) के मॉडल का, जिसके ब्रांड का नाम " सान " है ( जिसे इसमें इसके पश्चात् उक्त मॉडल कहा गया है ) और जिसे अनुमोदन चिह्न आई एन डी/09/07/ 204 समनुदेशित किया गया है , अनुमोदन प्रमाणपत्र जारी करती है ।
उक्त मॉडल एक विकृत गेज प्रकार का भार सेल आधारित तोलन उपकरण है। इसकी अधिकतम क्षमता 30 कि.ग्रा. है । और न्यूनतम क्षमता 100 ग्रा. है । सत्यापन मापमान अन्तराल ( ई ) 5 ग्रा. है । इसमें एक आद्येयतुलन युक्ति है जिसका शत प्रतिशत व्यवकलनात्मक धारित आधेयतुलन प्रभाव है । प्रकाश उत्सर्जक डायोड ( एल ई डी ) प्रदर्श तोलन परिणाम उपदर्शित करता है । उपकरण 230 वोल्ट और 50 हर्ट्ज प्रत्यावर्ती धारा विद्युत प्रदाय पर कार्य करता है ।
स्वम्पिंग प्लेटके मुद्रांकन के अतिरिक्त मशीन को कपटपूर्ण व्यवहारों के लिए खोलने से रोकने के लिए सीलबंद भी किया जाएगा और मॉडल को बिक्री से पहले या बाद में उसकी सामग्री , यथार्थता , डिजाइन , सर्किट डायग्राम निष्पादन सिद्धांत आदि की शर्तों पर परिवर्तित नहीं किया जाएगा ।
और केन्द्रीय सरकार उक्त अधिनियम की धारा 36 की उप - धारा ( 12 ) द्वारा प्रदत्त शक्तियों का प्रयोग करते हुए यह घोषणा करती है कि उक्त मॉडल के अनुमोदन के इस प्रमाण- पत्र के अंतर्गत उसी विनिर्माता द्वारा उसी सिद्धांत , डिजाइन के अनुसार और उसी सामग्री से जिससे उक्त अनुमोदित मॉडल का विनिर्माण किया गया है , विनिर्मित उसी श्रृंखला के वैसे ही मेक, यथार्थता और कार्यपालन के तोलन उपकरण भी होंगे जो 100 मि.ग्रा. से 2 ग्रा. तक के " ई " मान के लिए 100 से 10,000 तक की रेंज में सत्यापन मापमान अंतराल ( एन ) और 5 ग्रा. या उससे अधिक के " ई " मान के लिए 500 से 10,000 तक की रेंज में सत्यापन मापमान अंतराल ( एन ) सहित 50 कि.ग्रा. तक अधिकतम क्षमता वाले हैं और " ई " मान 1 × 10* , 2 × 10 * या 5 × 10 * , के हैं, जो धनात्मक या ऋणात्मक पूर्णांक या शून्य के समतुल्य हैं।
[फा. सं. डब्ल्यू एम-21 ( 188 )/2004] आर. माथुरबूथम , निदेशक , विधिक माप विज्ञान 3921 भारत का राजपत्र : जून 23, 2007/आषाढ़ 2, 1929
[ भाग II- खण्ड 3 ( ii) ]
New Delhi , the 24th May , 2007
S. O. 1788. Whereas the Central Government , after considering the report submitted to it by the prescribed authority, is satisfied that the Model described in the said report ( see the figure given below ) is in conformity with the provisions of the Standards of Weights and Measures Act, 1976 (60 of 1976) and the Standards of Weights and Measures (Approval of Models ) Rules , 1987 and the said Model is likely to maintain its accuracy over periods of sustained use and to render accurate service under varied conditions;
Now, therefore, in exercise of the powers conferred by sub- sections (7 ) and (8 ) of Section 36 of the said Act, the Central Government hereby issues and publishes the certificate of approval of the Model of non - automatic weighing instrument (Table Top type ) with digital indication of " SUNT" series of medium accuracy (Accuracy class III ) and with brand name " SUN" (hereinafter referred to as the said Model ) , manufactured by M/s . E Weigh Technologies , Dholeshwar Complex, Changodar , Sarkhej Bavla Highway , Ahmedabad and which is assigned the approval mark IND/09/07/204;
The said Model is a strain gauge type load cell based weighing instrument with maximum capacity of 30 Kg. and minimum capacity of 100 kg . The verification scale interval (e) is 5 g. It has a tare device with a 100 per cent subtractive retained tare effect . The light emitting diode (LED) display indicates the weighing result. the instrument operates on 230 Volts and 50- Hertz alternate current power supply. In addition to sealing the stamping plate , sealing shall also be done to prevent the opening of the machine for fraudulent practices and Model shall not be changed in terms of its material , accuracy , design , circuit diagram, working principle etc. before or after sale.
Further , in exercise of the powers conferred by sub - section ( 12) of Section 36 of the said Act, the Central Government hereby declares that this certificate of approval of the said Model shall also cover the weighing instruments of similar make and performance of same series with maximum capacity upto 50 kg . and with the number of verification scale interval (n) in the range of 100 to 10,000 for ' e ' value between 100 mg . to 2 g . and with number of verification scale interval ( n) in the range of 500 to 10,000 for ' e ' value of 5g . or more and ' e ' value of the form 1× 10%, 2×10% or 5× 10k , k being a positive or negative whole number or equal to zero , manufactured by the same manufacturer in accordance with the same principle, design and with the same materials with which , the said approved Model has been manufactured.
[F. No. WM- 21 ( 188 )/2004]
R. MATHURBOOTHAM, Director of Legal Metrology 3922
THE GAZETTE OF INDIA : JUNE 23 , 2007 /ASADHA 2, 1929
[PART II SEC . 3 ( ii ) ]
नई दिल्ली , 30 मई , 2007
का. आ. 1789. - केन्द्रीय सरकार का , विहित प्राधिकारी द्वारा उसे प्रस्तुत रिपोर्ट पर विचार करने के पश्चात् यह समाधान हो गया है कि उक्त रिपोर्ट में वर्णित मॉडल ( नीचे दी गई आकृति देखें ) बाट और माप मानक अधिनियम , 1976 ( 1976 का 60 ) तथा बाट और माप मानक (मॉडलों का अनुमोदन ) नियम , 1987 के उपबंधों के अनुरूप है और इस बात की संभावना है कि लगातार प्रयोग की अवधि में भी उक्त मॉडल यथार्थता बनाए राखेगा और विभिन्न परिस्थितियों में उपयुक्त सेवा प्रदान करता रहेगा;
अतः अब , केन्द्रीय सरकार , उक्त अधिनियम की धारा 36 की उप - धारा ( 7 ) और ( 8 ) द्वारा प्रदत्त शक्तियों का प्रयोग करते हुए मैसर्स स्मार्ट डिस्पेंसर्स प्रा. लि. , ई-187 , जी. आई.डी.सी. , इलैक्ट्रोनिक्स एस्टेट, सेक्टर -26 , गान्धीनगर-382028 , गुजरात द्वारा निर्मित " एम एच ओ " श्रृंखला के अंकक सूचन सहित डिस्पैंसिग पम्प ( आयल मिक्स टाइप ) के माडल का , जिसके ब्रांड का नाम " स्मार्ट " है ( जिसे इसमें इसके पश्चात् उक्त मॉडल कहां गया है ) और जिसे अनुमोदन चिह्न आई एन डी/ 09/ 07/273 समनुदेशित किया गया है , अनुमोदन प्रमाणपत्र जारी और प्रकाशित करती है ।
स्टाम्पिंग प्लेट के मुद्रांकन के अतिरिक्त मशीन को कपटपूर्ण व्यवहारों के लिए खोलने से रोकने के लिए सीलबंद भी किया जाएगा और मॉडल को बेचने से पहले या बाद में उसकी सामग्री , यथार्थता , डिजाइन , सर्किट डायग्राम , निष्पादन सिद्धांत आदि की शर्तों पर परिवर्तन/परिवर्धन नहीं किया जाएगा ।
उक्त मॉडल एक आटोमेटिक आयल मिक्स डिस्पैसिग पम्प है जिसमें एक , दो और मल्टीपल होस के साथ पिस्ट्न लगे हैं जो पेट्रोलियम उत्पादोंको मापने के लिये लिनियर मोशन को रोटरी मोशन में परिवर्तित करते हैं । लिक्विड क्रिस्टल डिस्पले ( एल सी डी ) प्रदर्श तोलन परिणाम उपदर्शित करता है । इसका प्रवाह दर 40 एल पी एम से 80 एल पी एम है । इसकी अधिकायत आयत प्रदर्श क्षमता 999.99 लीटर है और न्यूनतम प्रभाग 10 मि. लीटर है । आयत और मूल्य के लिये प्रिसेट डिवाईस है । उक्त माडल में 7 डिजिट का नान - रिवर्सिबल इलैक्ट्रों मैकेनिकल टोटेलाइजर लगा है ।
[फा. सं. डब्ल्यूएम-21 ( 207 )/2005 ] आर. माथुरबूथम , निदेशक , विधिक माप विज्ञान 3923 [ भाग II- खण्ड 3( ii) ]
भारत का राजपत्र जून 23, 2007/आषाढ़ 2 , 1929
New Delhi , the 30th May, 2007
S. O. 1789. Whereas the Central Government , after considering the report submitted to it by the prescribed authority, is satisfied that the Model described in the said report (see the figure given below) is in conformity with the provisions of the Standards of Weights and Measures Act , 1976 (60 of 1976) and the Standards of Weights and Measures (Approval of Models ) Rules , 1987 and the said Model is likely to maintain its accuracy over periods of sustained use and to render accurate service under varied conditions;
Now, therefore, in exercise of the powers conferred by Sub - sections (7) and ( 8 ) of Section 36 of the said Act, the Central Government hereby issues and publishes the certificate of approval of the Model of Dispensing Pump (oil mix type) of digital indication with brand name " SMART " of " MHO " series (hereinafter referred to as the said model ) , manufactured by M/s . Smart Dispensers Pvt . Ltd. , E- 187 , G.I.D.C. , Electronics Estate, Sector- 26 , Gandhinagar- 382028 , Gujarat and which is assigned the approval mark IND/09/07/273 ;
In addition to sealing the stamping plate sealing shall also be done to prevent opening of the machine for fraudulent practices and Model shall not be changed in terms of its material , accuracy , design, circuit diagram , working principle etc. before or after sale .
The said Model is an Automatic Oil Mix Dispensing Pump with single , double and multiple hose consisting pistons converting linear motion in to rotary motion to measure the petroleum products . The indications of the measurement are display on Liquid Crystal Diode (LCD ) display . Its flow rate is 40 lmp to 80 Imp . Its maximum value indicating capacity is 999.99 litres and smallest division is 10 ml . It has a preset device for measurement by volume and price. The said model consists of 7 digits non -reversible electro - mechanical totalizer .
[F. No. WM-21 (207 )/2005 )
R. MATHURBOOTHAM , Director of Legal Metrology 3924
THE GAZETTE OF INDIA : JUNE 23 , 2007 /ASADHA 2 , 1929
[PART II-SEC . 3 ( ii) ]
नई दिल्ली , 1 जून , 2007
का. आ. 1790.- केन्द्रीय सरकार का, विहित प्राधिकारी द्वारा उसे प्रस्तुत रिपोर्ट पर विचार करने के पश्चात् यह समाधान हो गया है कि उक्त रिपोर्ट में वर्णित मॉडल ( नीचे दी गई आकृति देखें ) बाट और माप मानक अधिनियम , 1976 ( 1976 का 60 ) तथा बाट और माप मानक (मॉडलों का अनुमोदन ) नियम, 1987 के उपबंधों के अनुरूप है और इस बात की संभावना है कि लगातार प्रयोग की अवधि में भी उक्त मॉडल यथार्थता बनाए रखेगा और विभिन्न परिस्थितियों में उपयुक्त सेवा प्रदान करता रहेगा ;
अतः , अब, केन्द्रीय सरकार , उक्त अधिनियम की धारा 36 की उप - धारा ( 7 ) और ( 8 ) द्वारा प्रदत्त शक्तियों का प्रयोग करते हुए मैसर्स आर.सी. एडवर्ड्स एण्ड कं. प्रा. लि. 16 , अर्थर बंदर रोड , कोलाबा , मुंबई-400 005 द्वारा विनिर्मित " एफ टी-66 " श्रृंखला के अंकक सूचन सहित टैक्सी/आटो किराया मीटर के मॉडल का , जिसके ब्रांड का नाम " ई डी सी ओ " है ( जिसे इसमें इसके पश्चात् उक्त मॉडल कहा गया है ) और जिसे अनुमोदन चिह्न आई एन डी/09/07/265 समनुदेशित किया गया है , अनुमोदन प्रमाणपत्र जारी और प्रकाशित करती है ।
EDCO MODEL :FT
RC.EDWARDS & CO (P) LTD
FARE
उक्त मॉडल अंकक सूचन सहित टैक्सी किराया मीटर है जो समय और दूरी नापने का उपकरण है । यह यात्रा के किसी भी क्षण यात्री द्वारा संदेय प्रभार को निरंतर जोड़ता रहता है और उपदर्शित करता रहता है । यात्रा के दौरान कतिपय विनिर्दिष्ट चाल से ऊपर और विनिर्दिष्ट चाल के नीचे चली गई दूरी के किराए को देय करने का फंक्शन है । प्रकाश उत्सर्जक डायोड ( एल ई डी ) मीटर की रीडिंग उपदर्शित करता है । " के " घटक 1400 पल्स/कि.मी. है ।
स्टॉपिंग प्लेट के मुद्रांकन के अतिरिक्त मशीन को कपटपूर्ण व्यवहारों के लिए खोलने से रोकने के लिए सीलबंद भी किया जाएगा और मॉडल को बिक्री से पहले या बाद में उसकी सामग्री , यथार्थता , डिजाइन , सर्किट डायग्राम निष्पादन सिद्धांत आदि की शर्तों पर परिवर्तित नहीं किया जाएगा ।
[फा. सं. डब्ल्यूएम-21 ( 112 )/2007 ] आर. माथुरबूथम , निदेशक , विधिक माप विज्ञान 3925 [ भाग II- खण्ड 3 (ii ) ]
भारत का राजपत्र : जून 23, 2007/आषाढ़ 2, 1929
New Delhi , the 1st June , 2007
S. O. 1790.-Whereas the Central Government , after considering the report submitted to it by the prescribed authority , is satisfied that the model described in the said report ( see the figure given below) is in conformity with the provisions of the Standards of Weights and Measures Act , 1976 ( 60 of 1976) and the Standards of Weights and Measures (Approval of Models ) Rules , 1987 and the said Model is likely to maintain its accuracy over periods of sustained use and to render accurate service under varied conditions;
Now, therefore , in exercise of the powers conferred by sub- sections (7 ) and (8 ) of Section 36 of the said Act, the Central Government hereby issues and publishes the certificate of approval of the model of a Taxi/Auto Fare Meter with digital indication of ' FT - 66 ' series with brand name " EDCO " (herein referred to as the said model ) , manufactured by M/s . R.C. Edwards & Co. Pvt . Ltd. , 16, Aurthur Bunder Road, Colaba , Mumbai -400 005 and which is assigned the approval mark IND/09/07/265;
The said model is a Taxi/Auto Fare Meter with digital indication incorporated with a distance and time measuring device . It totalizes continuously and indicates the fare at any moment of the journey, the charges payable by the passenger . The fare to pay is a function of the distance travelled above a certain specified speed and the time elapsed below a specified speed during the journey. The reading of the meter is indicated by Light Emitting Diode (LED). The ' k' factor of the instrument is 1400 pulses per kilometer .
In addition to sealing the stamping plate sealing shall also be done to prevent opening of the machine for fraudulent practices and model shall not be changed in terms of its material , accuracy , design , circuit diagram , working principle etc. before or after sale .
[F. No. WM-21 ( 112)/2007]
R. MATHURBOOTHAM , Director of Legal Metrology 3926
THE GAZETTE OF INDIA : JUNE 23 , 2007 /ASADHA 2 , 1929
[PART II SEC . 3 ( ii ) ]
नई दिल्ली, 1 जून , 2007
का. आ. 1791.- केन्द्रीय सरकार का , विहित प्राधिकारी द्वारा उसे प्रस्तुत रिपोर्ट पर विचार करने के पश्चात् यह समाधान हो गया है कि उक्त रिपोर्ट में वर्णित मॉडल ( नीचे दी गई आकृति देखें ) बाट और माप मानक अधिनियम , 1976 ( 1976 का 60 ) तथा बाट और माप मानक (मॉडलों का अनुमोदन ) नियम, 1987 के उपबंधों के अनुरूप है और इस बात की संभावना है कि लगातार प्रयोग की अवधि में भी उक्त मॉडल यथार्थता बनाए रखेगा और विभिन्न परिस्थितियों में उपयुक्त सेवा प्रदान करता रहेगा;
अतः अब , केन्द्रीय सरकार, उक्त अधिनियम की धारा 36 की उप- धारा ( 7 ) और ( 8 ) द्वारा प्रदत्त शक्तियों का प्रयोग करते हुए मैसर्स इटैलीजेंट माइक्रो सिस्टम प्रा. लि. , शेड नं. बी 70/ 1 ए पोरैयुर विलेज , ओसुदी वेली , विल्लैनुर कम्युन , पाण्डीचेरी -605110 द्वारा विनिर्मित यथार्थता वर्ग एक्स ( 1 ) वाले " आईएनएम - पीडब्ल्यूए सीएफआईएलएल " श्रृंखला के आटोमेटिक ग्रेविमैट्रिक फिलिंग इंसट्रूमेंट ( एल पी जी कैरोसेल ) के मॉडल का , जिसके ब्रांड का नाम " प्रो - वेद्य- ऑटो " है ( जिसे इसमें इसके पश्चात् उक्त मॉडल कहा गया है ) और जिसे अनुमोदन चिह्न आई एन डी/09/07 /275 समनुदेशित किया गया है , अनुमोदन प्रमाणपत्र जारी और प्रकाशित करती है ।
01
उक्त मॉडल एक विकृत गेज प्रकार का भार सेल आधारित आटोमेटिक ग्रेविमैट्रिक फिलिंग इंसट्रूमेंट ( एल पी जी कैरौसेल ) है । इसकी अधिकतम क्षमता 100 कि. ग्रा. और सत्यापन मापमान अन्तराल 50 ग्रा. है । कैरौसेल 24 वेइंग सैल वाले है जो सिलेण्डरों में एल पी जी भरने के लिए सरकुलर रोटेटिंग सिस्टम में बनाए गए हैं । इसकी अधिकतम भरने की दर 120 सिलेण्डर प्रति घण्टा प्रति फिलिंग स्टेशन है । लिक्विड क्रिस्टल डायोड ( एल सी डी ) प्रदर्श तोलन परिणाम उपदर्शित करता है । उपकरण 230 वोल्ट , 50 हर्ट्ज प्रत्यावर्ती धारा विद्युत प्रदाय पर कार्य करता है । स्टाम्पिंग प्लेट के मुद्रांकन के अतिरिक्त मशीन को कपटपूर्ण व्यवहारों के लिए खोलने से रोकने के लिए सीलबंद भी किया जाएगा और मॉडल को बिक्री से पहले या बाद में उसकी सामग्री , यथार्थता , डिजाइन , सर्किट डायग्राम निष्पादन सिद्धांत आदि की शर्तों पर परिवर्तित/ परिवर्धित नहीं किया जाएगा ।
और केन्द्रीय सरकार, उक्त अधिनियम की धारा 36 की उप- धारा ( 12 ) द्वारा प्रदत्त शक्तियों का प्रयोग करते हुए , यह घोषणा करती है कि उक्त मॉडल के अनुमोदन के इस प्रमाणपत्र के अंतर्गत उसी विनिर्माता द्वारा उसी सिद्धांत , डिजाइन के अनुसार और उसी सामग्री से, जिससे अनुमोदित मॉडल का निर्माण किया गया है , विनिर्मित उसी श्रृंखला के वैसे ही मेक, यथार्थता और कार्यपालन के तोलन उपकरण भी होंगे 1 कि. ग्रा. से 100 कि. ग्रा. तक की रेंज में हैं ।
[फा. सं. डब्ल्यू एम-21 ( 57 ) /2006] आर. माथुरबूथम , निदेशक , विधिक माप विज्ञान 3927 [भाग II- खण्ड 3 ( ii ) ]
भारत का राजपत्र : जून 23, 2007/आषाढ़ 2, 1929
New Delhi , the 1st June , 2007
S. O. 1791. Whereas the Central Government, after considering the report submitted to it by the prescribed authority , is satisfied that the Model described in the said report (see the figure given below) is in conformity with the provisions ofthe Standards of Weights and Measures Act , 1976 (60 of 1976) and the Standards of Weights and Measures (Approval of Models ) Rules , 1987 and the said Model is likely to maintain its accuracy over periods of sustained use and to render accurate service under varied conditions ;
Now, therefore , in exercise of the powers conferred by sub - sections ( 7) and (8) of Section 36 of the said Act, the Central Government hereby issues and publishes the certificate of approval of the Model of Automatic Gravimetric Filling Instrument (LPG Carousal ) of accuracy class -X( 1 ) of " INM- PWA - CFILL " series with brand name "PRO-WEIGH - AUTO " (herein referred to as the said Model ) , manufactured by M/s . Intelligent Micro System Pvt . Ltd. , Shed No. B , 70/1 , Poraiyur Village , Osudu Veli , Villianur Commune , Pondicherry- 605 110 and which is assigned the approval mark IND/09/07 /275;
The said Model (see the figure given below ) is a load cell based Automatic Gravimetric Filling Instrument (LPG Carousal) with a maximum capacity of 100 kg with scale division of 50g. There are 24 filling heads with automatic filling heads mounted on the rotating table of the Carousal . It fills LPG in cylinders with a maximum frequency of 120 cylinders per hour per filling station. The Liquid Crystal Display (LCD) indicates the weighing result. The instrument operates on 230 Volts and 50- Hertz alternate current power supply. In addition to sealing the stamping plate , sealing shall also be done to prevent the opening of the machine for fraudulent practices and Model shall not be changed in terms of its material , accuracy , design , circuit diagram, working principle etc. before or after sale .
Further, in exercise of the powers conferred by sub- section ( 12) of Section 36 of the said Act, the Central Government hereby declares that this certificate of approval of the said Model shall also cover the weighing instrument of similar make and performance of same series with capacity in the range 1 kg to 100 kg manufactured by the same manufacturer in accordance with the same principle , design, accuracy and with the same materials with which , the said approved Model has been manufactured.
[F. No. WM-21 ( 57 )/2006]
R. MATHURBOOTHAM, Director of Legal Metrology 2733 G1/07--3 3928
[PART II-SEC. 3 (ii )] THE GAZETTY OF INDIA : JUNE 23 , 2007/ASADHA 2 , 1929
भारतीय मानक ब्यूरो
नईदिल्ली, 11 जून , 2007
का.आ. 1792.- भारतीय मानक ब्यूर ( प्रमाणन ) विनियम, 1988 के विनियम ( 5 ) के उपविनियम ( 6 ) के अनुसार में भारतीय मानक ब्यूरो एतद्वारा अधिसूचित करता है कि जिन लाइसेसों के विवरण नीचे अनुसूची में दिये गये हैं उन लाइसेसों को उनके आगे दर्शायी गई तारीख से रद्द कर दिया गया है :--
अनुसूची
लाइसेंसधारी का नाम व पता
रद्द करने की तिथि क्रम संख्या लाइसेंस संख्या
लाइसेंस के अंतर्गत वस्तु/प्रक्रम सम्बद्ध भारतीय मानक का शीर्षक
23-04-07 8178384
1
बत्ती उपकरणों की विशिष्टि भाग 5 विशेष अपेक्षायें खंड । सामान्य उपयोग के लिए बत्ती उपकरण
शिंकोलाईट प्राईवेट लिमिटेड, गली नं. 8 , शम्भुनाथ कैम्पस, फ्रैंडस औद्योगिक क्षेत्र , जीटी रोड, शाहदरा , दिल्ली-110032
[सं. सीएमडी/ 13: 13 ]
ए. के. तलवार , उपमहानिदेशक ( मुहर )
BUREAU OF INDIAN STANDARDS New Delhi , the 11th June , 2007
SO . 1792.- In pursuance of sub- regulation (6) of the regulation 5 of the Bureau of Indian Standard (Certification) Regulations 1988 , of the Bureau of Indian Standards , hereby notifies that licences particulars of which are givenbelow have been cancelled with effect from the date indicated against each:
SCHEDULE
Date ofCancellation Name & Address of the Licencees
S. No. LicenceNo.
Article/Process with relevant Indian Standards covered by the licence cancelleci
23-04-2007 1 8178384
Luminaries part 5 Particular requirements , sec . 1 general purpose luminaries
Shinkolite Pvt. Ltd. , Gali No. 8 , Shambhunath Campus, Friends Industrial Area G.T. Road , Shahdara , Delhi- 110032 .
[No. CMD/13 : 13 ]
A. K. TALWAR , Dy. Director General (Marks )
नई दिल्ली, 11 जून , 200%"
का.आ. 1793.- भारतीय मानक ब्यूरो ( प्रमाणन ) विनियम , 1988 के विनियम ( 4 ) के उपविनियम ( 5 ) के अनुसार में भारतीय मानक ब्यूरो एतद्वारा अधिसूचित करता है कि जिन लाइसेंसों के विवरण नीचे अनुसूची में दिये गये हैं वे स्वीकृत कर दिए गए हैं : ---
अनुसूची
भाग अनु. वर्ष लाइसेंस संख्या
भा.मा. संख्या
भारतीय मानक का शीर्षक
स्वीकृत करने की तिथिवर्ष/माह
लाइसेंसधारी का नाम
व पता
क्रम संख्या
418
बिजली'के बल्ब
1978 04-04-07
1. 8806286
एच. आर. इलैक्ट्रीकल
इंडस्ट्रीज ,
कार्यालय : 4794,
दिल्ली-110006
डिप्टी गंज , सदर बाजार फैक्ट्री: प्लॉट नं. 3 ,
खसरा नं. 30/18 ,
लिबासपुर , मेन रोड,
समयपुर, औद्योगिक क्षेत्र ,
दिल्ली-42
3929 भारत का राजपत्र : जून 23 , 2007/आषाढ़ 2, 1929
[ भाग II- खण्ड 3 (ii) ]
वर्ष
अनु.
लाइसेंस संख्या
क्रम सं.
मा.मा. संख्या
भारतीय मानक का शीर्षक
लाइसेंसधारी का नाम
व पता
स्वीकृत करने की तिथिवर्ष/माह
1967
2312
11-04-07
2. 8808290
नोदक टाइप एसी सवातन पंखखे
मैसर्स एम्पायर फैंट्रानिक्स इंडिया प्राइवेट लिमिटेड बी-407, प्रथम एवंम द्वितीय तल , मंगोलपुरी औद्योगिक क्षेत्र , फेस 2 , नईदिल्ली-110083
1992
3
302 12
20-04-07
3. 8810883
मैसर्स एकता इलैक्ट्रीकल 57 , जी ब्लाक , डी एस आई डीसी, मंगोलपुरी दिल्ली-110083
घरेलू और सामान बिजली के साधित्रों कीसुरक्षा बिशिष्टि भाग 2विशेष अपेक्षाएँ खंड 3 बिजली की इस्तरी
1979
374
4. 8810984
19-04-07
बिजली के छत टाइप पंखे और रेगुलेटर
मैसर्सश्याम इलैक्ट्रीकल एप्लाइसेंस टी-4/71 , मंगोलपुरी औद्योगिक क्षेत्र , फेस 1 , नईदिल्ली-110083
1986
1
3
7809
23-04-07
5. 8811279
शुभम इंडस्ट्रीज, बीसी290 , मंगोलपुरी औद्योगिक क्षेत्र , फेस 2 , नईदिल्ली-110034
विद्युत प्रयोजनों के लिए दाव संवेदी आसंजक (प्लास्टीकृत पोलीविनायल क्लोराइड टेप, गैर- थर्मोस्टेटिक आसंतक)
1991
366
बिजली की इस्तरी
25-04-07
8812079
6.
मैसर्स भसीन टर्निंग एंडपंचिग वर्क्स 2892, कूचा नीलकंठ , दरियागंज नईदिल्ली-110002
1993
2082
24-04-07
8812180
7.
स्टेशनरी स्टोरेज टाईप पानी के हीटर
मैसर्स थर्मोकिंग
ए-24, नारायणा
औद्योगिक क्षेत्र , फेस-1 ,
नईदिल्ली-110028
[सं. सीएमडी/ 13 : 11 ]
ए. के. तलवार, उपमहानिदेशक (मुहर)
New Delhi , the 11th June, 2007
S.O. 1793. In pursuance of sub-regulation (5) of regulation 4 of the Bureau of Indian Standards (Certification) Regulation 1988, of the Bureau of Indian Standards hereby notifies the grant of licences of which are given in the following Schedule :
3930
THE GAZETTE OF INDIA : JUNE 23 , 2007 /ASADHA 2 , 1929
[PART II-SEC . 3 ( ii) ]
SCHEDULE
S. No.
Title of the Standard IS No. Part . Sec. Year Grant Date
Licence No
Name & Address of the Party
12
3
4
6
7
5
9
8
418
1978 1. 8806286 04-04-2007
Tungsten filament General Service Electric Lamps
H.R. Electrical Industries , Off. 4794, Dipti Gunj , Sadar Bazar , Delhi - 110006. Factory: Plot No. 3 , Khasra No. 30/18 , Libaspur , Main Road , Samaypur , Industrial Area , New Delhi - 110042.
2312
1967 2. 8808290 11-04-2007
Propeller Type ac ventilating fans
M/ s . Empire Fentranics , (India) Pvt . Ltd. , B-407 , First & Second Floor ,Mangol Puri Industrial Area, Phase 2, New Delhi - 110083 .
302
2
3 3. 8810883 20-04-2007
1992
Electric Iron-Safety Requirments
M/ s. Ekta Electricals 57, G-Block, DSIDC , Mangol Puri , NewDelhi - 110083 .
374
1979 4. 8810984 19-04-2007
Electric ceiling type fans& Regulator
M/ s . Shyam Electrical Appliances , T-4/71 , Mangol Puri , Industrial Area, Phase- I , New Delhi- 110083 .
3
1
1986 5. 881 279 23-04-2007
7809
Pressure sensitive Adhesive insulating Tape
Shubham Industries , BC 290 , Mangol Puri , Industrial Area , Phase 2, NewDelhi - 110034.
7809 3
1 1991 6. 8812079 25-04-2007
Pressure sensitive Adhesive insulating Tape
M/s . Bhasin Turning & Punching Works , 2892 , Kucha Neelkanth , DaryaGanj , NewDelhi - 110002 .
1993 7. 8812180 24-04-2007
2082
Stationary Storage Type Electric Water Heaters
M/s . Thermoking , A-24 , Naraina Industrial Area , Phase- 1 NewDelhi - 110028 .
[No. CMD/ 13: 11 ]
A. K. TALWAR, Dy. Director General (Marks) [भाग II-खण्ड 3 ( ii) ]
3931
भारत का राजपत्र : जून 23 , 2007/आषाढ़ 2 , 1929
नईदिल्ली, 14 जून , 2007
का.आ. 1794.- भारतीय मानक ब्यूरो नियम 1987 के नियम 7 के उप - नियम ( 1 ) के खंड (ख ) के अनुसरण में भारतीय मानक ब्यूरो एतद्वारा अधिसूचित करता है कि जिन भारतीय मानकों के विवरण नीचे अनुसूची में दिए गए हैं वे स्थापित हो गये हैं :
क्रम संख्या स्थापित भारतीय मानक ( कों) की संख्या , वर्ष और शीर्षक
(2)
(1)
1. आई एस 1656:2007 दुग्ध-अनाज आधारित अनुपूरक आहार - विशिष्टि ( चौथा पुनरीक्षण ) 2 आई एस 11536:2007 प्रसंस्कृत-अनाज आधारित अनुपूरक आहार - विशिष्टि ( दूसरा पुनरीक्षण ) 3. आई एस 14433 :2007 शिशु दुग्ध के वैकल्पिक आहार - विशिष्टि( पहला पुनरीक्षण) 4. आई एस 15757:2007 अनुसरित फार्मूला- अनुपूरक आहार - विशिष्टि
अनुसूची
स्थापित तिथि नये भारतीय मानक द्वारा अतिक्रमित भारतीय मानक अथवा ( मानकों) , यदि कोई हो, की संख्या और वर्ष
(4) (3).
3 जुलाई, 2007
3जुलाई, 2007
3 जुलाई, 2007
3 जुलाई, 2007 इस भारतीय मानक की प्रतियां भारतीय मानक ब्यूरो , मानक भवन , 9 , बहादुर शाह जफर मार्ग , नई दिल्ली-110002 , क्षेत्रीय कार्यालयों नई दिल्ली, कोलकाता , चण्डीगढ़ , चैन्नई , मुम्बई तथा शाखा कार्यालयों अहमदाबाद , बंगलौर , भोपाल, भुवनेश्वर , कोयम्बतूर, गुवाहाटी, हैदराबाद, जयपुर , कानपुर , नागपुर , पटना, पूणे तथा तिरूवनन्तापुरम में बिक्री हेतु उपलब्ध हैं ।
[संदर्भ: एफएडी/जी-128 ] श्रीमती मधुलिका प्रकाश , वैज्ञानिक एफ एवं प्रमुख (खाद्य एवं कृषि)
NewDelhi , the 14th June , 2007
S.O. 1794. -In pursuance of clause (b) of sub- rule ( 1 ) ofRules (1 ) of rules 7 of the Bureau of Indian Standards Rules , 1987, the Bureau of Indian Standards hereby notifies that the Indian Standards, particulars of which are given in the Schedule hereto annexed have been established on the date indicated against each :
S. No.
No. & Year of the Indian Standards Established
(2)
(1)
1.
IS 1656: 2007 Milk-cereal based complementary foods Specification (Fourth Revision)
2
IS 11536: 2007 Processed- cereal based complementary foods-Specification (SecondRevision)
3.
IS 14433:2007 Infant milk substitutes -Specification (FirstRevision)
4.
IS 15757 :2007 Follow -up formula- Complementary foods Specification
SCHEDULE
Date of Established No. & year of Indian Standards, ifany, Superseded by the New Indian Standard
(4)
(3)
3 July, 2007
3.July, 2007
3 July, 2007
3 July, 2007 Copy of this Standard is available for sale with the Bureau of Indian Standards , Manak Bhavan , 9, Bahadur Shah Jafar Marg, New Delhi - 110002 and Regional Office: New Delhi , Kolkata, Chandigarh , Chennai , Mumbai and also Branch Offices: Ahmedabad, Bangalore , Bhopal , Bhubaneshwar , Coimbatore , Guwahati, Hyderabad, Jaipur, Kanpur , Nagpur , Patna, Pune, Thiruvananthapuram.
[Ref. FAD/G- 128]
Mrs. MADHULIKA PRAKASH, Scientist F & Head (Food & Agri . ) 3932
[PART II-SEC. 3 (ii) ] THE GAZETTE OF INDIA : JUNE 23 , 2007/ASADHA 2, 1929
नईदिल्ली, 13 जून , 2007
का.आ. 1795.-अधिसूचना संख्या का.आ. 681 ( अ ) दिनांक 31 जुलाई, 1995 के अधिक्रमण में भारतीय मानक ब्यूरो नियम 1987 , केनियम 9 के उपनियम ( 1 ) के अनुसरण में भारतीय मानक ब्यूरो नीचे अनुसूची में दिए गए विभिन्न प्रबन्ध पद्धति प्रमाणन सम्बन्धी मानक मुहर के डिजाइन तत्काल प्रभाव से अधिसूचित करता है :-
अनुसूची
भारतीय मानक की संख्या क्रम सं.
प्रबन्ध पद्धति की किस्म
मानक मुहर का डिजाइन
आईएस/आईएसओ
गुणता प्रबन्ध पद्धति
IS/ISO 9001
भारतीय मानकब्यूरो
9001: 2000
QMS
BUREAU OF INDIAN STANDARDS
2
पर्यावरण प्रबन्ध पद्धति
IS/ISO 14001
भारतीय मानक ब्यूरो
आईएस/आईएसओ 14001
AS
EMS
BUREAU OF INDIAN STANDARDS
आईएस 18001 3.
IS 18001
भारतीय मानक ब्यूरो
व्यवसायिक स्वास्थ्य एवं सुरक्षा प्रबन्ध पद्धति
A
OHSMS
BUREAU OF INDIAN STANDARDS
4.
आईएस 15000 IS 15000
भारतीय मानकब्यूरो
हजर्ड विश्लेषण एवं सघन नियंत्रण पद्धति
A
HACCP
BUREAU OF INDIAN STANDARDS
आईएस/आईएसओ 5.
खाद्य सुरक्षा प्रबन्ध पद्धति
IS/ISO 22000
भारतीय मानक ब्यूरो
22000
A
FSMS
BUREAU OF INDIAN STANDARDS 3933
भारत का राजपत्र : जून 23, 2007/आषाढ़ 2, 1929
[ भाग II- खण्ड 3 ( ii ) ]
क्रम सं. मानक मुहर का डिजाइन
6
IS15700
भारतीय मानक ब्यूरो
SOMS BUREAU OF INDIAN STANDARDS
7.
IS/ISO 27001
भारतीय मानक ब्यूरो
A
ISMS BUREAU OF INDIAN STANDARDS
भारतीय मानक की संख्या प्रबन्ध पद्धति की किस्म
आईएस 15700 सेवा गुणता प्रबंध पद्धति
आईएस/आईएसओ सूचना सुरक्षा प्रबंध पद्धति
27001
[संदर्भ: सीएमडी-1/13 :9 ]
ए. के. तलवार, उप- महानिदेशक (मुहर)
New Delhi , the 13th June, 2007
S.O. 1795. In supersession of Notification No. S.O. 681 (E) dated 31 July, 1995 and in pursuance of sub-rule ( 1 ) of Rule 9 of the Bureau of Indian Standards Rules 1987 , the Bureau of Indian Standards hereby notifies the Standard Mark(s ) for different Management Systems Certifications in accordance with the relevant Indian Standards as given in the schedule below with immediate effect :-
Design of the Standard Mark
Sl . No.
1.
IS/ISO 9001 भारतीय मानक ब्यूरो
AQ
QMS BURSAU OF INDIAN STANDARDS
2.
IS/ISO 14001 भारतीय मानक ब्यूरो
ENIS BUREAU OF INDIAN STANDARDS
3.
IS18001 भारतीय मानक ब्यूरो
AS
OHSMS BUREAU OF INDIAN STANDARDS
SCHEDULE
Type ofManagement System
No. of the Indian Standards
IS/ISO 9001 QualityManagement System
IS/ISO 14001 Environmental Management System
IS18001 Occupational Health & Safety Management System 3934
THE GAZETTE OF INDIA : JUNE 23 , 2007/ASADHA 2 , 1929
[PART II-SEC. 3 ( ii) ] Sl. No. Design of the Standard Mark
Type ofManagement System
No. of the Indian Standards 4.
IS 15000
IS 15000
भारतीय मानक ब्यूरो
Hazard Analysis & Critical Control Point
AS
BUREAU OF INDIAN STANDARDS
HACCP
5.
IS/ISO 22000 IS/ISO 22000
भारतीय मानक ब्यूरो
Food Safety Management System
A
FSMS
BUREAU OF INDIAN STANDARDS
6:
IS 15700
IS 15700
भारतीय मानक ब्यूरो
ServiceQuality Management System
AQ
SOMS
BUREAU OF INDIAN STANDARDS
7.
IS/ISO 27001 IS/ISO 27001
भारतीय मानक ब्यूरो
Information Security Management System
A
BUREAL OF INDIAN STANDARDS
ISMS
[No. CMD- I/ 13 : 9 ]
A. K. TALWAR, Dy . Director General (Marks )
नई दिल्ली, 14 जून , 2007
का.आ. 1796.-भारतीय मानक ब्यूरो ( प्रमाणन ) विनियम , 1988 के नियम (4 ) के उप - नियम (5 ) को अनुसरण में भारतीय मानक ब्यूरो एतद्वारा अधिसूचित करता है कि जिन लाइसेंसों के विवरण नीचे अनुसूची में दिये गये हैं वे स्वीकृत कर दिए गए हैं : --
अनुसूची
लाइसेंस सं. चालूतिथि
लाइसेंसधारी का नाम व पता
क्रम सं
भारतीय मानक का शीर्षक व संबंधित भारतीय मानक मई 2007
01. 8815085
01-05-2007
मैसर्स महाराजा केबल्स
14255 : 1995
जी-1/391 , फेज -1
एरियल बन्च्ड केबल्स
भिवाडी औद्योगिक क्षेत्र , भिवाडी
जिला-अलवर-301 019
(राजस्थान)
भारत का राजपत्र : जून 23 , 2007/ आषाढ़ 2 , 1929
[भाग II- खण्ड 3 ( ii ) ]
3935
लाइसेंसधारी का नाम व पता
लाइसेंस सं. चालूतिथि क्रम सं
मई 2007
16-05-2007 8821080
02.
मैसर्स सलूजा मिनरल्स प्रा.लि. ए-24-ए , औद्योगिक क्षेत्र बहरोड, जिला-अलवर-301 701 (राजस्थान)
01-05-2007 8815489
03.
मैसर्स बी.एन. सन्स जी-7 , आकेडा औद्योगिक क्षेत्र रोड नं. 18 , वि.औ. क्षेत्र जयपुर-302 013 (राजस्थान)
01-05-2007 8815186
04.
मैसर्स निरकोन पोलीमर्स प्रा.लि. जी-692/693 , औद्योगिक क्षेत्र सीतापुरा विस्तार , टौंक रोड. जयपुर-302 023 (राजस्थान)
01-05-2007 05. 8815287
मैसर्स निरकोन पोलीमर्स प्रा.लि. जी-692/693 , औद्योगिक क्षेत्र सीतापुरा विस्तार , टौंक रोड जयपुर-302 023 (राजस्थान)
26-04-2007 8813182
06.
मैसर्स श्री साई ज्वैलर्स आजाद मैदान के पास आबूरोड, जिला-सिरोही 307 026 (राजस्थान)
01-05-2007 07.
8814891
8818697
09-05-2007 08.
11-05-2007 8819602
09.
मैसर्स डिवाईन ओरनामेन्ट्स प्रा. लि. 10, गणपति दर्शन गोविन्दमार्ग , त्रिमूर्ति सर्किल जयपुर-302 004 (राजस्थान) 2733 GI/07-4
भारतीय मानक का शीर्षक व संबंधित भारतीय मानक
8112 : 1989 43ग्रेड ओपीसी
7098 ( भाग 1 ) : 1988 एक्सएलपीई इन्सुलेटेड पीवीसी केबल्स
4985 : 2000 यूपीवीसी पाईप्स
13592: 1992 यूपीवीसी पाईप्स फॉर एस डब्ल्यूआर
1417 : 1999 स्वर्णाभूषणों की हॉसलमार्किंग 14494 : 1998 इलास्टोमर इन्सुलेटेड फ्लैक्सिबल केबल
मैसर्स के ई आई इण्डस्ट्रीज लिमिटेड एस-920 , फेज -3 , रीको औद्योगिक क्षेत्र भिवाडी, जिला-अलवर-301 019 (राजस्थान) 3975 : 1999 मोइल्ड स्टील वायर्स
मैसर्स बजरंग वायर प्रोडक्ट्स ( इण्डिया ) प्रा. लि. , यूनिट-2 प्लॉट नं. 15-28 , आकेडा डूंगर (औद्योगिक पार्क ) जयपुर-302 013 (राजस्थान) 1417 : 1999 स्वर्णाभूषणों की हॉलमार्किंग 3936
THE GAZETTE OF INDIA : JUNE 23 , 2007/ASADHA 2, 1929
[PART II-SEC . 3 ( ii) ] लाइसेंस सं.
लाइसेंसधारी का नाम व पता
चालूतिथि
क्रम सं
भारतीय मानक का शीर्षक व संबंधित भारतीय मानक मई 2007
10. 8824894
24-05-2007
12786: 1989
लैटरल्स
मैसर्स वैंकटेश इरीगेशन सिस्टम्स प्रा. लि. जी- 1-28 , रीको एचएमटी औद्योगिक क्षेत्र ब्यावर रोड, अजमेर (राजस्थान)
11. 8825694
24-05-2007
2112: 2003 रजत आभूषणों की हॉलमार्किंग
मैसर्स गणपति ज्वैलर्स मेन बाजार , लाला जी चौक हनुमानगढ टाउन हनुमानगढ-335 513 (राजस्थान)
24-05-2007
12. 8825593
1417: 1999 स्वर्णाभूषणों की हॉलमार्किंग
मैसर्स गणपति ज्वैलर्स मेन बाजार , लाला जी चौक हनुमानगढ टाउन हनुमानगढ -335 513 (राजस्थान)
13. 8825290
24-05-2007
2112: 2003 रजत आभूषणों की हॉलमार्किंग
मैसर्स आर सी ज्वैलर्स 3. ओल्ड ग्रेन मार्केट सांगरिया जिला-हनुमानगढ-335 063 (राजस्थान)
14. 8825189
24-05-2007
1417: 1999 स्वर्णाभूषणों की हॉलमार्किंग
मैसर्स आर सी ज्वैलर्स 3. ओल्ड ग्रेन मार्केट सांगरिया जिला- हनुमानगढ-335063 (राजस्थान)
15. 8825391
24-05-2007
1417: 1999 स्वर्णाभूषणों की हॉलमार्किंग
मैसर्स जे.के. मौसूण ज्वैलर्स एण्ड सन्स पीएनबी बैंक के पास , स्टेशन रोड रतनगढ , जिला-चूरू-331 022 (राजस्थान)
16. 8825492
24-05-2007
2112 : 2003
रजत आभूषणों की हॉलमार्किंग
मैसर्स जे.के. मौसूण ज्वैलर्स एण्ड सन्स पीएनबी बैंक के पास , स्टेशन रोड रतनगढ, जिला- चूरू-331 022 (राजस्थान)
17. 8825795
25-05-2007
2508: 1984 एलडीपीई फिल्म
मैसर्स सिनर्जी पैट्रो प्रोडक्ट्स प्रा.लि. बी/481, सैमटेल रोड भिवाडी, जिला-अलवर-301 019 (राजस्थान)
[सं. सी एम डी- I/ 13 : 11 ]
ए. के. तलवार , उप महानिदेशक ( मुहर )
New Delhi , the 14th June, 2007
S.O. 1796.-In pursuance of sub- regulation (5) of regulation 4 of the Bureau of Indian Standards , Certification Regulation, 1988 , the Bureau of Indian Standards , hereby notifies the grant of licence particulars of which are given in the following schedules .
3937
भारत का राजपत्र : जून 23 , 2007/आषाढ़ 2, 1929
[ भाग II- खण्डः 3 ( ii ) ]
Sl . No.
OperativeDate SCHEDULE
the Licensee
Name and Address of
Licence No. (CM/L )
3
2
1
May 2007
01-05-2007 8815085
Article/Process Covered by the licences and the relevant IS :Designation
5
4
14255: 1995
Maharaja Cables
01.
16-05-2007 8821080
02.
01-05-2007 03. 8815489
01-05-2007 8815186
04.
01-05-2007 8815287
05.
26-04-2007 8813182
06.
01-05-2007 8814891
07.
09-05-2007 8818697
08.
11-05-2007 8819602
09.
24-05-2007 8824894
10.
24-05-2007 8825694
11.
Aerial Bunched Cables
G-1/391, Phase- 1 Bhiwadi Industrial Area Bhiwadi, Distt . Alwar-301 019 Rajasthan
8112: 1989 43Grade OPC
Saluja Minerals Private Limited A24 A, Industrial Area Behror, Distt. Alwar- 301 701 Rajasthan
7098 (Part 1): 1988 XLPE Insulated PVC Cables
B.N. Sons G-7, Akeda Industrial Area Road No. 18 , VKI Area Jaipur-302013 Rajasthan
4985:2000 UPVCPipes
NirconPolymers Pvt . Ltd. G-692/693 , Industrial Area Sitapura Extn . Tonk Road Jaipur - 302 023 Rajasthan
13592: 1992
UPVC Pipes for SWR
Nircon Polymers Pvt. Ltd. G-692/693 , IndustrialArea Sitapura Extn . Tonk Road Jaipur- 302 023 Rajasthan
1417: 1999 Hallmarking ofGold Jewellery
Shree Sai Jewellers Near Azad Maidan Abu Road, Distt. Sirohi - 307 026 Rajasthan
14494: 1998 Elastomer Insulated Flexible Cable
KEI Industries Limited SP-920 , Phase- III RIICO Industrial Area Bhiwadi, Distt. Alwar - 301 019 Rajasthan
3975: 1999 Mild Steel Wires
BajrangWire Products ( 1 ) Pvt . Ltd. Unit- II Polt No. 15-28 , Akera Dungar (Industrial Park) Jaipur - 302 013 Rajasthan
1417:1999 Hallmarking ofGold Jewellery
Divine Ornaments Pvt . Ltd. 10, Ganpati Darshan GovindMarg. Trimurti Circle Jaipur- 302004 Rajasthan
12786: 1989
Irrigation Equipment Polyethylene Pipes for IrrigationLaterals
Vanktesh Irrigation Systems Pvt . Ltd. G-1-28 , RIICO HMT Industrial Area Beawar Road, Ajmer Rajasthan
2112: 2003 Hallmarking of Silver Jewellery
Ganpati Jewellers MainBazar , Lala Ji Chauk Hanumangarh Town Hanumangarh- 335513 Rajasthan 3938
THE GAZETTE OF INDIA : JUNE 23, 2007/ASADHA 2 , 1929
1
3
2
24-05-2007
12. 8825593
[PART II -SEC . 3 ( ii) ]
5
4
Ganpati Jewellers
1417: 1999 Hallmarking ofGold Jewellery
Main Bazar, Lala Ji Chauk
Hanumangarh Town
Hanumangarh -335513
Rajasthan
24-05-2007
13. 8825290
2112: 2003 Hallmarking of Silver Jewellery
RC Jewellers
3. Old Grain Market
Sangaria
Hanumangarh-335063
Rajasthan
24-05-2007
14. 8825189
1417: 1999 Hallmarking ofGold Jewellery
RC Jewellers
3. Old Grain Market
Sangaria
Hanumangarh-335063
Rajasthan
24-05-2007
15. 8825891
24-05-2007
16. 8825492
25-05-2007
17. 8825795
1417: 1999 Hallmarking ofGold Jewellery
JK Mosun Jewellers & Sons Near PNB Bank , Station Road Ratangarh, Distt. Churu- 331 022 Rajasthan
2112: 2003 Hallmarking of Silver Jewellery
JK Mosun Jewellers & Sons Near PNB Bank , Station Road Ratangarh, Distt . Churu - 331 022 Rajasthan
2508-1984 LDPE Films
Synergy Petro Products Pvt . Ltd. , B/431 , Samtal Road , Bhiwadi , Distt. Alwar -301 019 Rajasthan
[No. CMD- 1/13 : 11 ] A. K. TALWAR , Dy . Director General (Marks )
नईदिल्ली, 14 जून , 2007
का.आ. 1797.- भारतीय मानक ब्यूरो ( प्रमाणन ) विनियम, 1988 के नियम 5 के उपनियम ( 6 ) के अनुसरण में भारतीय मानक ब्यूरो एतद्वारा अधिसूचित करता है कि निम्न विवरण वाले लाइसेंसों को उनके आगे दर्शायी गई तारीख से रद्द कर दिया गया है :--
लाइसेंसधारी का नाम व पता लाइसेंस सं.
क्रम सं
मई 2007
01. 8475592
मैसर्स श्री श्याम एण्टरप्राईजेज ए-405 , बी-1 , रोड नं. 9 एफ वि.औ. क्षेत्र , जयपुर -302 013 (राजस्थान)
अनुसूची
रद्द करने की तिथि
लाइसेन्स के अंतर्गत वस्तु/ प्रक्रम से संबंधित भारतीय मानक का शीर्षक व संबंधित भा. मा.
26-04-2007 14104 : 1994
डीपवैल हैण्डपम्प कम्पोनेन्ट्स- नाइट्राईल रबर
[सं. सी एम डी- I/ 13 : 13 ]
ए. के. तलवार , उप महानिदेशक ( मुहर ) 3939 भारत का राजपत्र : जून 23, 2007/आषाढ़2 ,1929
[ भाग II- खण्ड 3 ( ii) ]
New Delhi , the 14th June , 2007
S.O. 1797.-In pursuance of sub - regulation (6) of regulation 5 of the Bureau of Indian Standards ( Certification) Regulation, 1988 , the Bureau of Indian Standards , hereby notifies that the licence( s ) particulars of which is/are given below 、 has/have been Cancelled with effect from the date indicated .
SCHEDULE
Date of Cancellation SI . No.
Name and Address of the Licensee
Licence No. (CM/ L )
Article/Process with relevant Indian Standards covered by the licence cancelled
May2007
26-04-2007
14104:1994
8475592
01 .
Shree Shyam Enterprises
Deepwell Hand Pump Components -Nitrile Rubber
A-405 B - 1 , Road No. 9F V.K.I. AREA Jaipur- 302013 Rajasthan
[No. CMD- I/ 13 : 13 ]
A. K. TALWAR, Dy. Director General (Marks) पेट्रोलियम और प्राकृतिक गैस मंत्रालय नई दिल्ली , 21 जून 2007
अतः अब , केन्द्रीय सरकार , उक्त अधिनियम की धारा 6 की उपधारा ( 1 ) द्वारा प्रदत्त शक्तियों का प्रयोग करते हुए यह घोषणा करती हैकि इस अधिसूचना से संलग्न अनुसूची में विनिर्दिष्ट भूमि में पाइपलाइन बिछाने के लिए उपयोग के अधिकार का अर्जन किया जाता है;
और केन्द्रीय सरकार उक्त अधिनियम की धारा 6 की उपधारा (4) द्वारा प्रदत्त शक्तियों का प्रयोग करते हुए , यह निदेश देती है कि उक्त भूमि में उपयोग का अधिकार इस घोषणा के प्रकाशन की तारीख को केन्द्रीय सरकार में निहित होने की बजाए , सभी विल्लंगमों से मुक्त, भारत पेट्रोलियम कारपोरेशन लिमिटेड में निहित होगा।
अनूसूची
तहसील
सवाई
राज्य: राजस्थान
जिला: सवाई माधोपुर
माधोपुर:
क्षेत्रफल हेक्टेयर में
सर्वे नंबर
ग्राम का नाम
क्र.
सं
का.आ. 1798. - केन्द्रीय सरकार ने पेट्रोलियम और खनिज पाइपलाइन ( भूमि में उपयोग के अधिकार का अर्जन ) अधिनियम , 1962 ( 1962 का 50 ) ( जिसे इसमें इसके पश्चात् उक्त अधिनियम कहा गया है ) की धारा 3 की उपधारा ( 1 ) के अधीन जारी की गई भारत सरकार के पेट्रोलियम और प्राकृतिक गैस मंत्रालय की अधिसूचना संख्या का.आ. 4925 तारीख 19 दिसम्बर, 2006 जो भारत के राजपत्र तारीख 23 दिसम्बर , 2006 में प्रकाशित की गई थी, द्वारा उस अधिसूचना से संलग्न अनुसूची में विनिर्दिष्ट भूमि में मध्य प्रदेश राज्य में मांगल्या ( इंदौर ) संस्थापन से हरियाणा राज्य में पियाला तथा दिल्ली राष्ट्रीय राजधानी क्षेत्र में बिजवासन तक पेट्रोलियम उत्पादों के परिवहन के लिये मुंबई- मांगल्या पाइपलाइन विस्तार परियोजना के माध्यम से भारत पेट्रोलियम कॉरपोरेशन लिमिटेड द्वारा एक विस्तार पाइपलाइन बिछाने के प्रयोजन के लिए उपयोग के अधिकार का अर्जन के अपने आशय की घोषणा की थी;
4
3
2
1
0.0100
3898
1. कुस्तला
और उक्त राजपत्र अधिसूचना की प्रतियां जनता को तारीख 19फरवरी , 2007 को उपलब्ध करा दी गई थीं;
0.1546
3894
0.3006
3891
0.1314 और सक्षम प्राधिकारी ने, उक्त अधिनियम की धारा 6 की उपधारा ( 1 ) के अधीन , केन्द्रीय सरकार को अपनी रिपोर्ट दे दी है;
3888
0.1512
4251
0.0100
4972
0.1584
4960
0.0216
4932
और केन्द्रीय सरकार ने , उक्त रिपोर्ट पर विचार करने के पश्चात्, और यह समाधान हो जाने पर कि उक्त भूमि पाइपलाइन बिछाने के लिये अपेक्षित है , उसमें उपयोग के अधिकार का अर्जन करने का विनिश्चय किया है;
3940
THE GAZETTE OF INDIA: JUNE 23 , 2007/ASADHA 2 , 1929
1
2
3
4
0.0108
4932/5470
1. कुस्तला
4262
0.0828
00846
4260
4258
0.0234
3887
0.0360
4006
0.0090
3897
0.0539
3904
0.0.628
3902
00161
4243
0.0562
131
0.0600 2. फूसोदा
3. चकेरी
259
0.0366
751
0.0500 4. नीमली कलां
115
0.1293 [फा. सं. आर-31015/78 /2004- ओ जार- II
ए. गोस्वामी , अवर सचिव MINISTRY OF PETROLEUM AND NATURAL GAS New Delhi , the 21st June , 2007
S.O. 1798.-Whereas by a notification of the Government of India in the Ministry of Petroleum and Natural Gas number S.O. 4925 , dated the 19th December , 2006, issued under sub - section ( 1 ) of Section 3 of the Petroleum and Minerals Pipelines ( Acquisition of Right of User in Land) Act , 1962 ( 50 of 1962) ( hereinafter referredto as the said Act ) published in the Gazette of India dated the 23rd December , 2006, the Central Government declared its intention to acquire the right of user in the land, specified in the Schedule appended to that notification for the purpose of laying an extension pipeline for transportation ofpetroleum products through Mumbai - Manglya Pipeline Extension Project from Manglya ( Indore ) terminal in the State ofMadhya Pradesh to Piyala in the State of Haryana and Bijwasan in the NCT of Delhi by Bharat Petroleum Corporation Limited;
And whereas the copies of the said Gazette notification were made available to the public on the 19thFebruary , 2007.
And whereas the competent authority has , under sub- section ( 1 ) of Section 6 of the said Act , submitted report to the Central Government ;
And whereas the Central Government , after considering the said report and on being satisfied that the said land is required for laying the pipeline , has decided to acquire the right of user therein;
[PART II-SEC . 3 ( ii) ] Now , therefore , in exercise of the powers conferred by sub - section ( 1) of Section 6 of the said Act, the Central Government hereby declares that the right of user in the land, specified in the Schedule , appended to this notifi- cation is hereby acquired for laying the pipeline ; And further, in exercise of the powers conferred by sub - section ( 4) of Section 6 of the said Act, the Central Government directs that the right of user in the said land forlaying the pipeline shall, instead of vesting in the Central Covernment, vest on the date of the publication of this declaration , in Bharat Petroleum Corporation Limited, free from all encumbrances .
SCHEDULE
Tehsil: Sawai Madhopur District : Sawai Madhopur State : Rajasthan
Area in Hectare S.No. Name of Village Survey No.
1 2
4
3
1. Kushtala
3898
0.0100
0.1546
3894
3891
0.3006
3888
0.1314
4251
0.1512
4972
0.0100
4960
0.1584
4932
0.0216
4932/5470
0.0108
4262
0.0828
4260
0.0846
4258
0.0234
3887
0.0360
0.0090
4006
3897
0.0539
00628
3904
3902
0.0161
4243
0.0562 2. Phusoda
131
0.0600
0.0366 3. Chakeri
259
751
0.0500 4. Nimli Kalan
115
0.1293
[F. No. R- 31015/78 /2004- OR - II ] A. GOSWAMI , Under Secy .
3941 [ भाग II- खण्ड 3( ii) ]
भारत का राजपत्र : जून 23 , 2007/आषाढ़ 2, 1929
4
1
2
3
नईदिल्ली, 21 जून 2007
0.0060
61
60
0.0060
चंगेरी
1.
0.0070
59
0.0050
57
0.1368
34
0.1008
35
0.0500
36
0.0150
39
278
0.1512
63
0.3000
[फा. सं. आर. - 31015/77/2004-ओ आर- II ]
ए. गोस्वामी , अवर सचिव
New Delhi , the 21st June , 2007 का.आ. 1799.- केन्द्रीय सरकार ने पेट्रोलियम और खनिज पाइपलाइन ( भूमि में उपयोग के अधिकार का अर्जन ) अधिनियम , 1962 ( 1962 का 50 ) ( जिसे इसमें इसके पश्चात् उक्त अधिनियम कहा गया है ) की धारा 3 की उपधारा ( 1 ) के अधीन जारी की गई भारत सरकार के पेट्रोलियम और प्राकृतिक गैस मंत्रालय की अधि- सूचना संख्या का.आ. 4001 तारीख 9 अक्तूबर , 2006 जो भारत के राजपत्र तारीख 14 अक्तूबर , 2006 में प्रकाशित की गई थी , द्वारा उस अधिसूचना से संलग्न अनुसूची में विनिर्दिष्ट भूमि में मध्य प्रदेश राज्य में मांगल्या ( इंदौर ) संस्थापन से हरियाणा राज्य में पियाला तथा दिल्ली राष्ट्रीय राजधानी क्षेत्र में बिजवासन तक पेट्रोलियम उत्पादों के परिवहन के लिये मुंबई - मांग्लया पाइपलाइन विस्तार परियोजना के माध्यम से भारत पेट्रोलियम कारपोरेशन लिमिटेड द्वारा एक विस्तार पाइपलाइन बिछाने के प्रयोजन के लिए उपयोग के अधिकार का अर्जन के अपने आशय की घोषणा की थी;
और उक्त राजपत्र अधिसूचना की प्रतियां जनता को तारीख 13 फरवरी , 2007 को उपलब्ध करा दी गई थीं;
और सक्षम प्राधिकारी ने , उक्त अधिनियम की धारा 6 की उपधारा ( 1 ) अधीन , केन्द्रीय सरकार को अपनी रिपोर्ट दे दी है ;
और केन्द्रीय सरकार ने , उक्त रिपोर्ट पर विचार करने के पश्चात्, और यह समाधान हो जाने पर कि उक्त भूमि पाइपलाइन बिछाने के लिये अपेक्षित है , उसमें उपयोग के अधिकार का अर्जन करने का विनिश्चय किया है ;
S. O. 1799.- Whereas by notification of the Government of India in the Ministry of Petroleum and Natural Gas number S. O. 4001, dated 9th October, 2006, issued under sub - Section ( 1 ) ofSection 3 ofthe Petroleum and Minerals Pipelines ( Acquisition of Right of User in Land) Act , 1962 (50 of 1962) (hereinafter referred to as the said Act) published in the Gazette of India dated the 14th October , 2006 , the Central Government declared its intention to acquire the right of user in the land , specified in the Schedule appended to that notification for the purpose of laying an extension pipeline for transportation ofpetroleum products through Mumbai -Manglya Pipeline Extension Project from Manglya ( Indore) terminal in the State of Madhya Pradesh , to Piyala in the State of Haryana and Bijwasan in the NCT of Delhi by Bharat Petroleum CorporationLimited.
अतः अब , केन्द्रीय सरकार, उक्त अधिनियम की धारा 6 की उपधारा ( 1 ) द्वारा प्रदत्त शक्तियों का प्रयोग करते हुए घोषणा करती है कि इस अधिसूचना से संलग्न अनुसूची में विनिर्दिष्ट भूमि में पाइपलाइन बिछाने के लिए उपयोग के अधिकार का अर्जन किया जाता है ;
And whereas the copies of the said Gazette notification were made available to the public on the 13thFebruary, 2007;
And whereas the competent authority has , under sub - section ( 1 ) of Section 6 of the said Act , submitted report to the Central Government ;
और केन्द्रीय सरकार उक्त अधिनियम की धारा 6 की उपधारा (4) द्वारा प्रदत्त शक्तियों का प्रयोग करते हुए , यह निवेश देती है कि उक्त भूमि में उपयोग का अधिकार इस घोषणा के प्रकाशन की तारीख को केन्द्रीय सरकार में निहित होने की बजाए , सभी विल्लंगमों से मुक्त, भारत पेट्रोलियम कॉरपोरेशन लिमिटेड में निहित होगा ।
अनूसूची
And whereas the Central Government , after considering the said report and on being satisfied that the said land is required for laying the pipeline , has decided to acquire the right of user therein;
तहसील : झालरापाटन
जिला: झालावाड़
राज्य : राजस्थान
ग्राम का नाम सर्वे नंबर
क्षेत्रफल हेक्टेयर में
क्र. सं
Now, therefore , in exercise of the powers conferred by sub - section ( 1 ) of Section 6 of the said Act , the Central Government hereby declares that the right of user in the land , specified in the Schedule , appended to this notification , is hereby acquired for laying the pipeline ;
1
2
3
4
1. चंगेरी
69
0.0468
0.1080
71
72
0.0576
62
0.0560
And further, in exercise of the powers conferred by sub- section ( 4) of Section 6 of the said Act, the Central Government hereby directs that the right of user in the said land for laying the pipeline shall , instead of vesting in the Central Government, vest on the date of the publication of thisdeclaration, in Bharat Petroleum Corporation Limited, free from all encumbrances .
3942
[PART II-SEC . 3 (ii ) ) THE GAZETTE OF INDIA: JUNE 23 , 2007/ASADHA 2, 1929
SCHEDULE
Rajasthan
Tehsil: Jhalarapatan District : Jhalawar State:
Are in hectare
S. Name ofVillage Survey No.
No.
अतः अब , केन्द्रीय सरकार , उक्त अधिनियम की धारा 6 की उपधारा ( 1 ) द्वारा प्रदत्त शक्तियों का प्रयोग करते हुए यह घोषणा करती है कि इस अधिसूचना से संलग्न अनुसूची में विनिर्दिष्ट भूमि में पाइपलाइन बिछाने के लिए उपयोग के अधिकार का अर्जन किया जाता है;
4
3
1
1.
68
0.0468
Changeri
0.1080
71
0.0576
72
0.0560
62
और केन्द्रीय सरकार उक्त अधिनियम की धारा 6 की उपधारा ( 4 ) द्वारा प्रदत्त शक्तियों का प्रयोग करते हुए, यह निर्देश देती है कि उक्त भूमि में उपयोग का अधिकार इस घोषणा के प्रकाशन की तारीख को केन्द्रीय सरकार में निहित होने की बजाए, सभी विल्लंगमों से मुक्त, भारत पेट्रोलियम कारपोरेशन लिमिटेड में निहित होगा । 61
0.0060
अनुसूची
60
0.0060
राज्य : राजस्थान
तहसील : झालरापाटन
0.0070
59
जिला : झालावाड़
57
0.0050
ग्राम का नाम सर्वे नंबर
क्षेत्रफल हेक्टेयर में
क्र.
0.1368
34
सं
0.1008
35
4
2
3
1
0.0500
36
69
1.
0.4980
सेमलीपटड़िया
0.0150
39
0.1780
2.
79
गोविन्दपुरा
278
0.1512
0.3000
63
[फा. सं. आर -31015/77/2004-ओ आर--II ]
ए. गोस्वामी , अवर सचिव [F. No. R- 31015 /77/2004- OR - II]
New Delhi , the 21st June , 2007 A. GOSWAMI . Under Secy.
नई दिल्ली , 21 जून , 2007
का.आ. 1800. - केन्द्रीय सरकार ने पेट्रोलियम और खनिज
S. O. 1800.- Whereas by notification of the Government of India in the Ministry of Petroleum and Natural Gas number S. O. 4002 , dated 9th October , 2006 , issued under sub- Section ( 1 ) of section 3 of the Petroleum and Minerals Pipelines (Acquisition of Right of User in Land) Act , 1962 (50 of 1962 ) (hereinafter referred to as the said Act) published in the Gazette of India dated the 14th October , 2006 , the Central Government declared its intention to acquire the right of user in the land , specified in the Schedule appended to that notification for the purpose of laying an extension pipeline for transportion ofpetroleum products through Mumbai - Manglya Pipeline Extension Project from Manglya (Indore ) termminal in the State ofMadhya Pradesh , to Piyala in the State of Haryana and Bijwasan in the NCT of Delhi by Bharat Petroleum Corporation Limited.
पाइपलाइन ( भूमि में उपयोग के अधिकार का अर्जन ) अधिनियम, 1962 ( 1962का 50 ) (जिसे इसके पश्चात् उक्त अधिनियम कहा गया है ) की धारा 3 की उपधारा ( 1 ) के अधीन जारी की गई भारत सरकार के पेट्रोलियम और प्राकृतिक गैस मंत्रालय की अधिसूचना संख्या का. आ. 4002 तारीख 9 अक्तूबर , 2006 जो भारत के राजपत्र तारीख 14 अक्तूबर , 2006 में प्रकाशित की गई थी, द्वारा उस अधि-- सूचना से संलग्न अनूसूची में विनिर्दिष्ट भूमि में मध्य प्रदेश राज्य में मांगल्या ( इंदौर ) संस्थापन से हरियाणा राज्य में पियाला तथा दिल्ली राष्ट्रीय राजधानी क्षेत्र में बिजवासन तक पेट्रोलियम उत्पादों के परिवहन के लिये मुबई - मांग्लया पाइपलाइन विस्तार परियोजना के माध्यम से भारत पेट्रोलियम कारपोरेशन लिमिटेड द्वारा एक विस्तार पाइपलाइन बिछाने के प्रयोजन के लिए उपयोग के अधिकार का अर्जन के अपने आशय की घोषणा की थी;
And whereas the copies of the said Gazette notification were made available to the public on the 13th February, 2007;
और उक्त राजपत्र अधिसूचना की प्रतियां जनता को तारीख 13फरवरी , 2007 को उपलब्ध करा दी गई थीं;
And whereas the competent authority has , under sub- section ( 1 ) of section 6 of the said Act , submitted report to the Central Government ;
और सक्षम प्राधिकारी ने , उक्त अधिनियम की धारा 6 की उपधारा ( 1 ) के अधीन , केन्द्रीय सरकार को अपनी रिपोर्ट दे दी है;
And whereas the Central Government , after considering the said report and on being satisfied that the said land is required for laying the pipeline , has decided to acquire the right of user therein;
और केन्द्रीय सरकार ने, उक्त रिपोर्ट पर विचार करने के पश्चात्, और यह समाधान हो जाने पर कि उक्त भूमि पाइपलाइन बिछाने के लिये अपेक्षित है , उसमें उपयोग के अधिकार का अर्जन करने का विनिश्चय किया है ;
Now, therefore , in exercise of the powers conferred by sub - section ( 1 ) of section 6 of the said Act , the Central [भाग II-- खण्ड 3 ( ii) ]
भारत का राजपत्र : जून 23 , 2007/आषाढ़ 2 , 1929
Government hereby declares that the right of user in the land , specified in the Schedule ; appended to this notification, is hereby acquired for laying the pipeline;
And further, in exercise of the powers conferred by sub - section (4) of section 6 of the said Act , the Central Government hereby directs that the right of user in the said land for laying the pipeline shall , instead of vesting in the Central Government, vest on the date of the publication of this declaration , in Bharat Petroleum Corporation Limited, free from all encumbrances .
SCHEDULE
Tehsil: Jhalarapatan District : Jhalawar State : Rajasthan
Are in hectare
Survey No.
S. Name ofVillage No.
4 1
2
3
0.4980
69
1. Semlipadia
2.
0.1780
79
Govindpura
[F. No. R-31015/77/2004- OR- II] A. GOSWAMI , Under Secy.
नई दिल्ली, 21 जून , 2007
का.आ. 1801. - केन्द्रीय सरकार ने पेट्रोलियम और खनिज पाइपलाइन ( भूमि में उपयोग के अधिकार का अर्जन ) अधिनियम , 1962 ( 1962 का 50 ) की धारा 6 की उपधारा ( 1 ) ( जिसे इसके पश्चात् उक्त अधिनियम कहा गया है ) की धारा 3 की उपधारा ( 1 ) के अधीन जारी की गई भारत सरकार पेट्रोलियम और प्राकृतिक गैस मंत्रालय की अधिसूचना संख्टः का.आ. 4006 तारीख 11 अक्तूबर , 2006 जो भारत के राजपत्र तारीख 14 अक्तूबर, 2006 में प्रकाशित की गई थी, द्वारा उस अधिसूचना से संलग्न अनुसूची में विनिर्दिष्ट भूमि में मध्य प्रदेश राज्य में मांगल्या ( इंदौर ) संस्थापन से हरियाणा राज्य में पियाला तथा दिल्ली राष्ट्रीय राजधानी क्षेत्र में बिजवासन तक पेट्रोलियम उत्पादों के परिवहन के लिये मुंबई- मांग्लया पाइपलाइन विस्तार परियोजना के माध्यम से भारत पेट्रोलियम कारपोरेशन लिमिटेड द्वारा एक विस्तार पाइपलाइन बिछाने के प्रयोजन के लिए उपयोग के अधिकार का अर्जन के अपने आशय की घोषणा की थी;
और उक्त राजपत्र अधिसूचना की प्रतियां जनता को तारीख 5 फरवरी , 2007 को उपलब्ध करा दी गई थीं;
और सक्षम प्राधिकारी ने, उक्त अधिनियम की धारा 6 की उपधारा ( 1 ) के अधीन, केन्द्रीय सरकार को अपनी रिपोर्ट दे दी है ;
और केन्द्रीय सरकार ने , उक्त रिपोर्ट पर विचार करने के पश्चात्, और यह समाधान हो जाने पर कि उक्त भूमि पाइपलाइन बिछाने के लिये अपेक्षित है , इसमें उपयोग के अधिकार का अर्जन करने का विनिश्चय किया है;
अतः अब, केन्द्रीय सरकार , उक्त अधिनियम की धारा 6 की उपधारा ( 1 ) द्वारा प्रदत्त शक्तियों का प्रयोग करते हुए यह घोषणा करती है कि इस अधिसूचना से संलग्न अनुसूची में विनिर्दिष्ट भूमि में पाइपलाइन बिछाने के उपयोग के अधिकार का अर्जन किया जाता है;
2733 GI/07-5
3943 और केन्द्रीय सरकार उक्त अधिनियम की धारा 6 की उपधारा (4 ) द्वारा प्रदत्त शक्तियों का प्रयोग करते हुए, यह निर्देश देती है कि उक्त भूमि में उपयोग का अधिकार इस घोषणा के प्रकाशन की तारीख को केन्द्रीय सरकार में निहित होने की बजाए, सभी विल्लंगमों से मुक्त, भारत पेट्रोलियम कारपोरेशन लिमिटेड में निहित होगा ।
अनूसूची
राज्य : उत्तर प्रदेश
जिला : मथुरा
तहसील : मथुरा
क्षेत्रफल हेक्टेयर में
सर्वे नंबर
क्र. सं. ग्राम का नाम
4
3
2
1
0.0196
136
1. ओल
0.1870
137
0.0990
144/2
0.0300
146
0.2152
149
0.0150
237
0.0150
239
0.0138 2.
64
खेड़िया
0.0458
91
0.0080
0.0994
150
0.0082
98
3. तारसी
0.0506
1262
महोली
4.
0.0582
1348
0.0200
289
5. जैत
0.0250
668
0.1260
1079
0.2520
1264
0.0090
1272
[फा. स. आर. - 31015/3/2005-ओ आर- II ]
ए. गोस्वामी , अवर सचिव New Delhi , 21st June , 2007
S. O. 1801. Whereas by notification of the Government of India in the Ministry of Petroleum and Natural Gas number S. O. 4005 , dated 11th October , 2006, issued under sub - section ( 1 ) of section 3 of the Petroleum and Minerals Pipelines ( Acquisition of Right of User in Land) Act , 1962 (50 of 1962 ) (hereinafter referred to as the said Act) published in the Gazette of India dated the 14th October , 2006, the Central Government declared its intention to acquire the right of user in the land , specified in the Schedule appended to that notification for the purpose of laying an extension pipeline for transportation ofpetroleum product through Mumbai - Manglya Pipeline Extension Project from Manglya ( Indore ) terminal in the State of Madhya Pradesh , to Piyala in the State of Haryana 3944
[PART II -SEC . 3 ( ii ) ] THE GAZETTE OF INDIA : JUNE 23 , 2007/ ASADHA 2 , 1929
नई दिल्ली, 21 जून , 2007
and Bijwasan in the NCT of Delhi by Bharat Petroleum Corporation Limited .
And whereas the copies of the said Gazette notification were made available to the public on 5thFebruary, 2007 ;
And whereas the competent authority has , under sub - section ( 1 ) of Section 6 of the said Act , submitted report to the Central Government ;
And whereas the Central Government , after considering the said report and on being satisfied that the said land is required for laying the pipepline , has decided to acquired the right of user therein;
Now, therefore, in exercise of powers conferred by sub - section ( 1 ) of Section 6 of the said Act , the Central Government hereby declares that the right of user in the land, specified in the Schedule ; appended to this notification , is hereby acquired for laying the pipeline;
का.आ. 1802.-केन्द्रीय सरकार ने पेट्रोलियम और खनिज पाइपलाइन ( भूमि में उपयोग के अधिकार का अर्जन ) अधिनियम, 1962 ( 1962 का 50 ) की धारा 6 की उपधारा ( 1 ) ( जिसे इसमें इसके पश्चात् उक्त अधिनियम कहा गया है ) की धारा 3 की उपधारा ( 1) के अधीन जारी की गई भारत सरकार के पेट्रोलियम और प्राकृतिक गैस मंत्रालय की अधिसूचना संख्या का.आ. 4005 तारीख 1 अक्तूबर , 2006 जो भारत के राजपत्र तारीख 14 अक्तूबर , 2006 में प्रकाशित की गई थी, द्वारा उस अधिसूचना से संलग्न अनुसूची में विनिर्दिष्ट भूमि में मध्य प्रदेश राज्य में मांगल्या ( इंदौर ) संस्थापन से हरियाणा राज्य में पियाला तथा दिल्ली राष्ट्रीय राजधानी क्षेत्र में बिजवासन तक पेट्रोलियम उत्पादकों के परिवहन के लिये मुंबई- मांग्लया पाइपलाइन विस्तार परियोजना के माध्यम से भारत पेट्रोलियम कॉरपोरेशन लिमिटेड द्वारा एक विस्तार पाइपलाइन बिछाने के प्रयोजन के लिए उपयोग के अधिकार का अर्जन केअपने आशय की घोषणा की थी;
और उक्त राजपत्र अधिसूचना की प्रतियां जनता को तारीख 5 फरवरी , 2007 को उपलब्ध करा दी गई थीं ;
और सक्षम प्राधिकारी ने , उक्त अधिनियम की धारा 6 की उपधारा ( 1 ) के अधीन , केन्द्रीय सरकार को अपनी रिपोर्ट दे दी है;
And further, in exercise of the powers conferredby sub - section ( 4) of Section 6 of the said Act , the Central Government hereby directs that the right of user in the said land for laying the pipeline shall , instead of vesting in theCentral Government , vest on the date of the publication of this declaration , in Bharat Petroleum Corporation Limited , free from all encumbrances .
SCHEDULE
Mathura State : Uttar Pradesh Tehsil : Mathura Distt .
और केन्द्रीय सरकार ने , उक्त रिपोर्ट पर विचार करने के पश्चात्, और यह समाधान हो जाने पर कि उक्त भूमि पाइपलाइन बिछाने के लिये अपेक्षित है, उसमें उपयोग के अधिकार का अर्जन करने का विनिश्चय किया है ;
Area in hectare
S. No. Name ofVillage Survey No.
1
2
3
4
1.
AOL
136
0.0196
137
0.1870
अतः अब, केन्द्रीय सरकार , उक्त अधिनियम की धारा 6 की उपधारा ( 1 ) द्वारा प्रदत्त शक्तियों का प्रयोग करते हुए घोषणा करती है कि इस अधिसूचना से संलग्न अनुसूची में विनिर्दिष्ट भूमि में पाइपलाइन बिछाने के उपयोग के अधिकार का अर्जन किया जाता है; 144/2
0.0990
146
0.0300
149
0.2152
237
0.0150
239
0.0150
और केन्द्रीय सरकार उक्त अधिनियम की धारा 6 की उपधारा (4 ) द्वारा प्रदत्त शक्तियों का प्रयोग करते हुए , यह निर्देश देती है कि उक्त भूमि में उपयोग का अधिकार इस घोषणा के प्रकाशन की तारीख को केन्द्रीय सरकार में निहित होने की बजाए , सभी विल्लंगमों से मुक्त, भारत पेट्रोलियम कारपोरेशन लिमिटेड में निहित होगा । 2.
64
Khedia
0.0138
91
0.0458
राज्य : उत्तर प्रदेश
0.0080 तहसील: मथुरा
अनूसूची जिला : मथुरा
150
0.0994
क्षेत्रफल हेक्टेयर में
क्र. ग्राम का नाम सर्वे नंबर
3. Tarsi
98
0.0082
4
1
3
2
0.0506
4.
1262
Maholi
0.0028
319
1. अरहेरा
1348
0.0582
379
0.2610
0.0200
5. Jait
289
383
0.0900 668
0.0250
0.0252
2. गणेषरा
39
0.1260
1079
0.2520
1264
50
0.01506 1272
0.0090
0.0448
3. मघेरा
146
336
0.1000 [F. No. R- 31015/3/2005 -OR- II]
0.2440
340
A. GOSWAMI , Under Secy .
3945 भारत का राजपत्र : जून 23, 2007/आषाढ़ 2, 1929
[ भाग II-खण्ड 3 ( ii) ]
4
3
4
1 2
2
1
3
0.1980
627
0.2520
भैंसा (जारी )
169
4. मासूम नगर
0.1152
637
0.0100
223
0.0586
638
0.0150
724
5. वाटी
0.2160
645
0.0230
1381
0.0064
23
9. धानाषमसाबाद
0.0040
1387
0.0174
27
0.0516
116
6. धनगाँव
0.0080
18
0.0060
132
0.2282
185
0.0862
149
0.0330
3
0.0185 10.
194
इकदन्ता
0.1495
0.0198
9
196
0.0570
0.0288
11
197
0.0320
0.1345 260
19
0.1308
262
0.1118
11.
367
बमूरी मुहाल गर्वी
0.0144
453
0.0090
403
0.0221
454
0.0090
405
0.0140
0.3492
437
434
7 छड़गाँव
0.1886
0.0252 560
440
0.2050
561
0.0490
बरारी
213
12.
0.0828
562
0.0094
675
0.1080
563
0.0136
677
0.0315
640
0.0684
684
0.0028
642
0.0390
689
0.0152
652
0.0515
171
धानातेजा
13.
0.1500
4
8. भैंसा
0.0200
182
0.1230
5
0.0403
183
0.0150
9
0.0178
185
0.1296
3
0.0068
188
0.1170
32
0.0418
207
0.2456
61
0.0068
442
63
0.1774
0.0540
448
0.2250
70
0.0092
449
0.2328
72
0.0250
483
0.1980
135
0.0060
535
0.2132
144
0.2185
259
0.0014
212
14. महीउद्दीनपुर
0.3906
274
0.0878
216
0.510
305
0.0864
227
0.0180
486
0.3636
228
0.1026
507
0.0396
510
0.0280
15. पिलुआ सादिकपुर 29
0.0030
512
0.0036
65
0.1488
0.0082 522
70
0.0644
76
0.0936
551
0.0130
122
0.0240
600
0.2440
509
0.0138
601
0.1090
528
0.0954
622
0.0032
574
0.0323
604
0.0680
0.0684
586
605
606
0.0648
68
0.0372
16. अडूकी
0.1044
608
0.0196
70 3946
[PART II-SEC . 3 ( ii) ) THE GAZETTE OF INDIA : JUNE 23 , 2007/ASADHA 2, 1929
2
4
1
3
131
0.0332
16. अडूकी
Central Government , vest on the date of the publication of thisdeclaration in Bharat Petroleum Corporation Limited, free from all encumbrances .
0.0590
172
SCHEDULE
173
0.0410
Tehsil : Mathura District: Mathura State : Uttar Pradesh
0.0214
175
Area in Hectare
S.No.
Survey No.
नौगॉब
0.2340
17.
80
Name of Village
0.4860
194
205
0.0420
4
3
2
1
742
0.0180
0.0028
1. Arahera
319
0.2610
0.0394
379
18.
219
सतोहा असगरपुर
0.0900
383
628
0.1360
0.0580
1044
0.0252
2.
39
Ganeshra
0.0720
1046
0.1506
50
0.0448
146
3. Maghera
[फा. सं. आर. - 31015/3/2005-ओ आर- II ]
0.1000
336
ए. गोस्वामी , अवर सचिव
0.2440
340
NewDelhi , the 21st June , 2007
0.2520
4. Masum Nagar 169
0.0100
223
0.0150
724
Vaati
5.
0.0230
1381
1387
0.0040
0.0516
116
6. Dhangaon
0.0060
132
0.0862
149
0.0185
194
196
0.0198
0.0288
197
0.0320
260
0.1308
262
0.0144
453
0.0221
454
S.O. 1802.- Whereas , by a notification of the Government of India in the Ministry of Petroleum and Natural Gas , S.O. No. 4006 dated 11th October , 2006 , issued under sub - section 3 of the Petroleum and Minerals Pipeline (Acquisition of Right of User in Land ) Act , 1962 ( 50 of 1962) (hereinafter referred to as the said Act ) published in the Gazette of India dated 14th October , 2006, the Central Government declared its intention to acquire the right of user in land , specified in Schedule appended to that notification for the purpose of laying a pipeline for transportation of petroleum product through Mumbai- Manglya Pipeline Extension Project from Manglya ( Indore) terminal in the State of Madhya Pradesh, to Piyala in the State of Haryana and Bij wasan in the NCT of Delhi by Bharat Petroleum Corporation Limited;
0.3492
437
7. Chadgaon
560
0.1886
0.2050
561
And, whereas , the copies of the said Gazette notification were made available to the public on 5thFebruary, 2007;
0.0828
562
0.1080
563
0.0315
640
0.0028
642
And, whereas , the competent authority has , under sub- section ( 1 ) of Section 6 of the said Act , submitted report to the Central Government ;
0.0152
652
0.1500
8.
4
Bhainsa
0.1230
5
0.0150
9
And , whereas , the Central Government after considering the said report and on being satisfied that said land is required for laying the pipeline , has decided to acquire the right of user therein;
0.1296
30
0.1170
-32
0.2456
61
0.1774
63
0.2250
70
Now, therefore , in exercise of powers conferred by sub- section ( 1 ) of Section 6 of the said Act , the Central Government hereby declares that the right of user in the land, specified in Schedule , appended to this notification , ishereby acquired for laying pipeline ;
0.2328
72
0.1980
135
144
0.2132
0.2185
259
And further, in exercise of the powers conferred by sub- section (4) of Section 6 of the said Act , the Central Government hereby directs that the right of user in the said land for laying the pipeline shall, instead of vesting in the 3947 [ भाग II- खण्ड 3 ( ii ) ]
भारत का राजपत्र जून 23 , 2007/आषाढ़ 2 , 1929
4
2
3
4
1
3
1
2
0.0280
0.3906
274
15.
8. Bhainsa
Pilua Sadikpur 29
0.0036
65
0.0510
305
0.0082
70
0.0180
486
0.0644
76
0.1026
507
0.0130
122
0.0396
510
0.2440
509
512
0.0030
0.1090
528
0.1488
522
0.0032
574
0.0936
551
0.0680
586
0.0240
600
0.0372 601
68
Aduki
0.0138 16.
0.0954
0.0196 602
70
0.0323
0.0332 604
131
0.0684
0.0590 605
172
606
0.0648
0.0410
173
0.1044
608
0.0214
175
0.1980
627
0.2340
80
17. Naugaon
0.1152
637
0.4860
194
0.0586
638
0.0420
205
645
0.2160
0.0180
742
9.
23
Dhana
0.0394
219
0.0064 18. Satoha
27
0.0174
Shamsabad
0.1360
628
Asgarpur
0.0080
18
0.0580
1044
0.2282
195
1046
0.0720
0.0330
Ekdanta
3
10.
[F. No. R. -31015/3/2005 -OR - II]
0.1495
9
A. GOSWAMI , Under Secy.
11
0.0570
0.1345
19
नई दिल्ली, 21 जून 2007
11.
0.1118
Bamuri Muhal 367
Garvi
403
0.0090
405
0.0090
434
0.0140
0.0252
440
12. Barari
213
0.0490
675
0.0094
0.0136
677
684
0.0684
0.0390
689
13.
171
0.0515
Dhana Teja
182
0.0200
183
0.0403
0.0178
185
0.0068
188
का.आ. 1803. केन्द्रीय सरकार ने पेट्रोलियम और खनिज पाइपलाइन ( भूमि में उपयोग के अधिकार का अर्जन ) अधिनियम , 1962 ( 1962 का 50 ) ( जिसे इसमें इसके पश्चात् उक्त अधिनियम कहा गया है ) की धारा 3 की उपधारा ( 1 ) के अधीन जारी की गई भारत सरकार के पेट्रोलियम और प्राकृतिक गैस मंत्रालय की अधिसूचना संख्या का.आ. 397 तारीख 08 फरवरी , 2007 जो भारत के राजपत्र तारीख 10 फरवरी , 2007 में प्रकाशित की गई थी , द्वारा उस अधिसूचना से संलग्न अनूसूची में विनिर्दिष्ट भूमि में मध्य प्रदेश राज्य में मांगल्या ( इंदौर ) संस्थापन से हरियाणा राज्य में पियाला तथा दिल्ली राष्ट्रीय राजधानी क्षेत्र में बिजवासन तक पेट्रोलियम उत्पादों के परिवहन के लिये मुंबई- मांगल्या पाइपलाइन विस्तार परियोजना के माध्यम से भारत पेट्रोलियम कारपोरेशन लिमिटेड द्वारा एक विस्तार पाइपलाइन बिछाने के प्रयोजन के लिए उपयोग के अधिकार का अर्जन के अपने आशय की घोषणा की थी;
0.0418
207
0.0068
442
0.0540
448
और उक्त राजपत्र अधिसूचना की प्रतियां जनता को तारीख 5 अप्रैल, 2007 को उपलब्ध करा दी गई थीं;
0.0092
449
483
0.0250
और सक्षम प्राधिकारी ने, उक्त अधिनियम की धारा 6 की उपधारा ( 1 ) के अधीन , केन्द्रीय सरकार को अपनी रिपोर्ट दे दी है ;
0.0060
535
0.0014
14. Muhiuddinpur 212
0.0878
216
0.0864
227
0.3636
228
और केन्द्रीय सरकार ने , उक्त रिपोर्ट पर विचार करने के पश्चात्, और यह समाधान हो जाने पर कि उक्त भूमि पाइपलाइन बिछाने के लिये अपेक्षित है , उसमें उपयोग के अधिकार का अर्जन करने का विनिश्चय किया है ;
3948
THE GAZETTE OF INDIA: JUNE 23 , 2007/ASADHA 2, 1929
अतः अब, केन्द्रीय सरकार , उक्त अधिनियम की धारा 6 की उपधारा ( 1 ) द्वारा प्रदत्त शक्तियों का प्रयोग करते हुए , यह घोषणा करती है कि इस अधिसूचना से संलग्न अनुसूची में विनिर्दिष्ट भूमि में पाइपलाइन बिछाने के लिए उपयोग के अधिकार का अर्जन किया जाता है;
और केन्द्रीय सरकार उक्त अधिनियम की धारा 6 की उपधारा (4 ) द्वारा प्रदत्त शक्तियों का प्रयोग करते हुए , यह निर्देश देती है कि उक्त भूमि में उपयोग का अधिकार इस घोषणा के प्रकाशन की तारीख को केन्द्रीय सरकार में निहित होने की बजाए, सभी विल्लंगमों से मुक्त, भारत पेट्रोलियम कारपोरेशन लिमिटेड में निहित होगा।
अनूसूची
राज्य :
तहसील:
मध्य प्रदेश तराना
जिला : उज्जैन
सर्वे नंबर
क्षेत्रफल हेक्टेयर में क्र. सं. ग्राम का नाम
4 1
2
3
1.
0.0540 बिजल
50/332(शासकीय )
2.
0.0324 भडसिम्बा
379(शासकीय रास्ता)
0.0720
400
0.2016
51
3. नौगांवा
0.0216
260
4. बिसनश्खेडा
0.1440
281
0.1440
280
0.0720 नांदेड
5.
0.0720
1078 985
0.0540
792
6. कढाई
0.0720
104
7. चिकली
0.0630
571
0.0540 8.
259
खोकरिया
[फा. सं. आर. -31015/67/2004-ओ आर- II ]
2.
ए. गोस्वामी , अवर सचिव New Delhi , the 21st June, 2007
S.O. 1803. Whereas by notification of the Government of India in the Ministry of Petroleum and Natural Gas , No. S.O. 397 dated the 8th February , 2007 , issued under Sub- section ( 1 ) of Section 3 of the Petroleum and Minerals Pipeline (Acquisition of Right of User in Land) Act, 1962 (50 of 1962) (hereinafter referred to as the said Act) published in the Gazette of India dated the 10th February, 2007 , the Central Government declared its intention to acquire the right of user in the land, specified in the Schedule appended to that notification for the purpose of laying an extention pipeline for transportation ofpetroleum product through Mumbai - Manglya Pipeline Extension Project from Manglya (Indore ) terminal in the
[PART II-SEC . 3( ii) ]
State ofMadhya Pradesh , to Piyala in the State of Haryana and Bijwasan in the NCT of Delhi by Bharat Petroleum Corporation Limited;
And whereas the copies of the said Gazette notification were made available to the public on the 5thApril , 2007;
And whereas the competent authority has , under sub - section ( 1 ) of Section 6 of the said Act , submitted report to the Central Government;
And whereas the Central Government after considering the said report and on being satisfied that the said land is required for laying the pipeline , has decided to acquire the right of user therein;
Now, therefore , in exercise of the powers conferred by sub - section ( 1 ) of Section 6 of the said Act , the Central Government hereby declares that the right of user in the land, specified in the Schedule , appended to this notification, is hereby acquired for laying the pipeline ;
And further , in exercise of the powers conferred by sub-section (4) of the Section 6 of the said Act , the Central Government hereby directs that the right of user in the said land for laying the pipeline shall , instead of vasting in the Central Government , vest on the date of the publication of thisdeclaration in Bharat Petroleum Corporation Limited, free from all encumbrances .
SCHEDULE
Tehsil: Tarana
District: Ujjain
State: Madhya Pradesh
Area in Hectare
S.No.
SurveyNo.
Name of Village
4
3
1 2
0.0540
1.
50/332 ( Govt . Land)
Binjal
0.0324 Bhadsimba 379 (Govt . Rasta)
0.0720 400
0.2016 51
3. Naugawa
0.0216
4. Bisankheda
0.1440
0.1440 260 281 280
Nanded
5.
0.0720 0.0720 1078 985
0.0540
6. Kadai
792
0.0720 Chikli
7.
0.0630 104 571
0.0540 259
8. Khokariya
[F. No.R. - 31015/ 67/2004 - OR - II ) A. GOSWAMI , Under Secy .
3949 [भाग II-खण्ड 3 (ii) ]
भारत का राजपत्र जून 23 , 2007/आषाढ़ 2, 1929
2
4
3
1
नई दिल्ली, 21 जून 2007
0.0600
655,655/1
0.2160
650
0.0600
398
0.0800
623
576
0.0316
0.1900
477
0.0800
485
[फा. सं. आर. - 31015/88/2004- ओ आर- II ]
ए. गोस्वामी, अवर सचिव
New Delhi , the 21st June , 2007 का.आ. 1804. - केन्द्रीय सरकार ने पेट्रोलियम और खनिज पाइपलाइन ( भूमि में उपयोग के अधिकार का अर्जन ) अधिनियम , 1962 ( 1962 का 50 ) ( जिसे इसमें इसके पश्चात् उक्त अधिनियम कहा गया है ) की धारा 3 की उपधारा ( 1 ) के अधीन जारी की गई भारत सरकार के पेट्रोलियम और प्राकृतिक गैस मंत्रालय की अधिसूचना संख्याका. आ. 14 तारीख 3 जनवरी , 2007 जो भारत के राजपत्र तारीख 6 जनवरी , 2007 में प्रकाशित की गई थी , द्वारा उस अधिसूचना से संलग्न अनुसूची में विनिर्दिष्ट भूमि में मध्य प्रदेश राज्य मेंमांग्ल्या ( इंदौर ) संस्थापन से हरियाणा राज्य में पियाला तथा दिल्ली राष्ट्रीय राजधानी क्षेत्र में बिजवासन तक पेट्रोलियम उत्पादकों के परिवहन के लिये मुंबई- मांग्लया पाइपलाइन विस्तार परियोजना के माध्यम से भारत पेट्रोलियम कारपोरेशन लिमिटेड द्वारा एक विस्तार पाइपलाइन बिछाने के प्रयोजन के लिए उपयोग के अधिकार का अर्जन के अपने आशय की घोषणा की थी;
और उक्त राजपत्र अधिसूचना की प्रतियां जनता को तारीख 1 मार्च , 2007 को उपलब्ध करा दी गई थीं;
और सक्षम प्राधिकारी ने , उक्त अधिनियम की धारा 6 की उपधारा ( 1 ) के अधीन , केन्द्रीय सरकार को अपनी रिपोर्ट दे दी है ;
और केन्द्रीय सरकार न , उक्त रिपोर्ट पर विचार करने के पश्चात्, और यह समाधान हो जाने पर कि उक्त भूमि पाइपलाइन बिछाने के लिये अपेक्षित है , उसमें उपयोग के अधिकार का अर्जन करने का विनिश्चय किया है ;
S.O. 1804. Whereas by a notification of the Government of India in the Ministry of Petroleum and Natural Gas , No. S.O. 14 dated the 3rd January , 2007 , issued under Sub- section ( 1 ) of Section 3 of the Petroleum and Minerals Pipeline (Acquisition of Right of User Land) Act, 1962 (50 of 1962) (hereinafter referred to as the said Act) published in the Gazette of India dated the 6th January , 2007, the Central Government declared its intention to acquire the right of user in the land , specified in the Scheduled appended to that notification for the purpose of laying an extension pipeline for transportation of petroleum products through Mumbai -Manglya Pipeline Extension Project from Manglya ( Indore ) terminal in the State of Madhya Pradesh , to Piyala in the State of Haryana and Bijwasan in the NCT of Delhi by Bharat Petroleum Corporation Limited;
And whereas the copies of the said Gazette notification were made available to the public on the 1stMarch , 2007;
अतः अब , केन्द्रीय सरकार, उक्त अधिनियम की धारा 6 की उप- धारा ( 1 ) द्वारा प्रदत्त शक्तियों का प्रयोग करते हुए , यह घोषणा करती है कि इस अधिसूचना से संलग्न अनुसूची में विनिर्दिष्ट भूमि में पाइपलाइन बिछाने के लिए उपयोग के अधिकार, का अर्जन किया जाता है;
And whereas the competent authority has , under sub- section ( 1 ) of Section 6 of the said Act, submitted report to the Central Government;
और केन्द्रीय सरकार उक्त अधिनियम की धारा 6 की उप- धारा ( 4 ) द्वारा प्रदत्त शक्तियों का प्रयोग करते हुए , यह निदेश देती है कि उक्त भूमि में उपयोग का अधिकार इस घोषणा के प्रकाशन की तारीख को केन्द्रीय सरकार में निहित होने की बजाए, सभी विल्लंगमों से मुक्त, भारत पेट्रोलियम कारपोरेशन लिमिटेड में निहित होगा।
And whereas the Central Government after considering the said report and on being satisfied that said land is required for laying the pipeline , has decided to acquire the right of user therein;
अनूसूची
तहसील:
जिला:
राज्य: राजस्थान
मलारना डूंगर
सवाईमाधोपुर
Now, therefore, in exercise of the powers conferred by sub - section ( 1 ) of Section 6 of the said Act, the Central Government hereby declares that the right of user in the land , specified in the Schedule , appended to this notification, is hereby acquired for laying the pipeline;
क्षेत्रफल हेक्टेयर में
क्र. सं. ग्राम का नाम सर्वेनंबर
4
1
2
3
1. पीलवा नदी
653
0.0550
0.0170
651/1,2
478
0.0450
0.0060
587
And further , in exercise of the powers conferred by sub- section (4) of Section 6 of the said Act, the Central Government directs that the right of user in the said land for laying the pipeline shall , instead of vesting in the Central Government, vest on the date of the publication of this declaration in Bharat Petroleum Corporation Limited, free from all encumbrances .
3950
THE GAZETTE OF INDIA JUNE 23 , 2007 /ASADHA 2 , 1929
[PART II-SEC. 3( ii) ] SCHEDULE
Tehsil:
District:
State:
Malarna Dungar Sawai Madhopur Rajasthan
S. No.
Area inHectare
SurveyNo.
Name of Village
सचिव (आवास ) , आवास एवं शहरी गरीबी उपशमन मंत्रालय को उक्त नियमों के नियम 11 के खण्ड ( v ) से ( ix ) में विनिर्दिष्ट शास्तियों में से किसी को अधिरोपित करने तथा पूर्वोक्त समूह ( ख ) एवं समूह ( ग ) पदों/कर्मचारियों के संबंध में उक्त नियमों के अधीन मुद्रण निदेशक को प्रदत्त अपीलीय प्राधिकारी की शक्तियों का प्रयोग करने के लिए अनुशासनिक प्राधिकारी नियुक्त करते हैं। 1
2
3
4
1. PilwaNadi 653
0.0550
[फा. सं. सी -31011 /2/2003 - एवी ) जी. गणेशन , अवर सचिव
09170
651/ 1,2
MINISTRY OF URBAN DEVELOPMENT 478
0.0450
New Delhi , the 22nd June , 2007
587
0.0060
655,655/1
0.0600
650
0.2160
398
0.0600
623
0.0800
576
0.0316
477
0.1900
485
0.0800
[F. No. R. -31015/88 /2004- OR- III A. GOSWAMI, Under Secy .
S.O. 1805.- Whereas the Director of Printing in the Directorate of Printing , New Delhi has been conferred under the Central Civil Services ( Classification , Control and Appeal ) Rules , 1965 , (hereinafter referred to as the said Rules ) with the powers of Disciplinary Authority and Appellate Authority in respect of certain categories of General Central Services Group ' B ' and Group ' C ' employees working in the Directorate of Printing , the Government of India Presses and the Branches under the control ofDirectorate of Printing ( hereinafter referred to as theDirectorate);
शहरी विकास मंत्रालय नई दिल्ली, 22 जून , 2007
And whereas , the post of Director of Printing has fallen vacant on 1st August , 2003 consequent on the retirement on superannuation of the then incumbent and is likely to continue to be so vacant for some time more;
का.आ. 1805.-मुद्रण निदेशालय , नई दिल्ली में मुद्रण निदेशक को केन्द्रीय सिविल सेवा ( वर्गीकरण , नियंत्रण एवं अपील ) नियमावली , 1965 ( जिसे इसमें इसके पश्चात् उक्त नियम कहा गया है ) के अधीन मुद्रण निदेशालय ( जिसे इसमें इसके पश्चात् निदेशालय कहा गयाहै। ) के नियंत्रणाधीन मुद्रण निदेशालय , भारत सरकार के मुद्रणालयों तथा शाखाओं में कार्यरत सामान्य केन्द्रीय सेवा समूह ( ख ) तथा समूह ( ग ) कर्मचारियों के कतिपय प्रवर्ग के संबंध में अनुशासनिक प्राधिकारी और अपील प्राधिकारी की शक्तियां प्रदत्त की गई है;
और मुद्रणा निदेशक का पद, पदधारी को अधिर्षिता पर सेवा निवृत्ति के परिणामस्वरूप 1 अगस्त, 2003 की रिक्त हुआ है और कुछ और अधिक समय के लिए रिक्त रहने की संभावना है;
And whereas , there was urgent need to make an arrangement to provide for carrying out the disciplinary and appellate functions , hitherto performed by the said Director of Printing and Shri P. K. Pradhan , Joint Secretary in the Ministry of Urban Development was appointed as Disciplinary Authority vide notification No. C- 31011/2/2003- AV/Ptg . dated 22-1-04 to impose any of the penalties specified in clauses ( v) to ( ix ) of rule 11 of the said Rules as well as to exercise all the appellate powers conferred on the Director of Printing under the said Rules in respect of the aforesaid Group ' B ' and Group ' C ' posts ;
And whereas , Shri P.K. Pradhan, Joint Secretary has since been relieved of his duties in the Ministry of Urban Development consequent on completion of his tenure vide Office Order No. A. - 22012/ 2/ 2005 - Admn . - I dated 27-4-06.
And, therefore, there is again an urgent need to make an arrangement for ensuring the smooth performance of the aforesaid Disciplinary and Appellate function hitherto exercised by the said Director of Printing in the Directorate.
और उक्त मुद्रण निदेशक द्वारा अब तक निर्वाह किए गए अनुशासनिक तथा अपील संबंधी कृत्यों के लिए एक व्यवस्था किए जाने की अत्यंत आवश्यकता थी तथा श्री पी. के. प्रधान , संयुक्त सचिव, शहरी विकास मंत्रालय को दिनांक 22-1-04की अधिसूचना सं. सी -31011/2/2003 -ए वी/मु द्वारा उक्त नियमों के नियम 11 के खण्ड ( v) से ( ix ) में विनिर्दिष्ट शास्तियों में से किसी के अधिरोपित करने तथा पूर्वोक्त समूह ( ख ) तथा समूह ( ग ) पदों के संबंध में उक्त नियमों के अधीन मुद्रण निदेशक को प्रदत्त सभी अपीलीय शक्तियोंका प्रयोग करने के लिए अनुशासनिक प्राधिकारी नियुक्त किया गया;
और श्री पी. के. प्रधान, संयुक्त सचिव को उनकी पदावधि पूर्ण होने के परिणामस्वरूप शहरी विकास मंत्रालय से दिनांक 27-4-06 के कार्यालय आदेश सं ए. - 22012 /2/2005 - प्रशा.-! द्वारा कार्यभार से मुक्तकिया गया;
तथा, अतैव , निदेशालय में उक्त मुद्रण निदेशक द्वारा अब तक प्रयोग किए जा रहे पूर्वोक्त अनुशासनिक तथा अपीलीय कृत्यों के निर्विघ्न निष्पादन को सुनिश्चित करने के लिए एक व्यवस्था करने की पुनः अत्यन्त आवश्यकता है ;
Now, therefore , in pursuance of clause (b ) of sub- rule ( 2) of rule 12 of said Rules , the President hereby appoints Shri S. K. Singh , Joint Secretary ( Housing) in the Ministry of Housing and Urban Poverty Alleviation as Disciplinary Authority to impose any of the penalties specified in clauses ( v) to ( ix) of rule 11 of the said Rules as well as to exercise the powers of the Appellate Authority conferred on the Director of Printing under the said Rules inrespect of the aforesaid Group ' B ' and Group ' C ' posts/ employees .
अतः , अब , राष्ट्रपति उक्त नियमों के नियम 12 के उप -नियम (2 ) के खण्ड ( ख ) के अनुसरण में श्री एस . के. सिंह , संयुक्त
[F. No. C - 31011 /2/2003 -AV] G. GANESAN , Under Secy.
3951 [भाग II- खण्ड 3( ii) ]
भारत का राजपत्र : जून 23 , 2007/आषाढ़ 2 , 1929
श्रम और रोजगार मंत्रालय नई दिल्ली, 24 मई , 2007
"Whether the action of Management ofManganese Ore [ India] Ltd. , Nagpur in dismissing Shri Mandelal Dharma, Security Guard of Chikla Mine from service w.e.f. 11/06/1988 is justified? If not, to what relief is the workman entitled?"
का.आ. 1806. औद्योगिक विवाद अधिनियम, 1947 (1947 का 14 ) की धारा 17 के अनुसरण में, केन्द्रीय सरकार मैंगनीज ओर (इंडिया) लिमिटेड के प्रबंधतंत्र के संबद्ध नियोजकों और उनके कर्मकारों के बीच , अनुबंध में निर्दिष्ट औद्योगिक विवाद में केन्द्रीय सरकार औद्योगिक अधिकरण/श्रम न्यायालय , नागपुर के पंचाट ( संदर्भ संख्या सी जी आई टी/एनजीपी/59/2003 ) को प्रकाशित करती है, जो केन्द्रीय सरकार को 24-5-2007 को प्राप्त हुआ था ।
[सं. एल-27012/4/90- आई आर ( एम ) ]
एन. एस. बोरा , डेस्क अधिकारी
MINISTRY OF LABOUR AND EMPLOYMENT
New Delhi , the 24thMay, 2007
2.The dispute came up for hearing before the Tribunal on 14-12-2006 on which both the parties were absent . However, the counsel for the respondent was present and for the petitioner nobody had appeared nor he himself was present. It seems that initially the dispute was referredto CGIT, Jabalpur and consequent upon the establishment on this Tribunal , Nagpur that has been transferred to it . The perusal of record indicates that after the transfer to this court the petitioner did not attend it. A notice was issued to him still he did not attend and right from 23-8-2005 there is no representation on behalf of the petitioner in the present dispute . He himself also did not attend it . It was pending for filing the affidavit of the workman i.e. for adducing the evidence to prove the perversity of findings, but as indicated above the petitioner has not taken any steps of filing the evidence/affidavit . Hence, it was again fixed for arguments on the point of perversity and quantum of punishment .
S.O.1806 . In pursuance of Section 17 of the Industrial Disputes Act, 1947 ( 14 of 1947) , the Central Government hereby publishes the award (Ref. No. CGIT/ NGP/ 59/ 2003 ) of the Central Government Industrial Tribunal -cum - Labour Court, Nagpur now as shown in the Annexure in the Industrial Dispute between the employers in relation to the management of Manganese Ore ( India) Ltd. , and their workman , which was received by the Central Government on 24-5-2007.
[No. L-27012/4/90- IR (M)] N.S. BORA , Desk Officer
ANNEXURE
3. The record also indicates that at Jabalpur before CGITmy learned predecessor had given finding about the validity of enquiry on 13-6-1996. He has concluded that the enquiry was proper, legal and the case was fixed for adducing evidence and argument on the point of perversity offindings of the enquiry officer and about the content of punishment . But no further steps are taken since then.
BEFORE SHRI A. N. YADAV, PRESIDING OFFICER , CENTRAL GOVERNMENT INDUSTRIAL TRIBUNAL CUM - LABOUR COURT, NAGPUR
Date: 8-5-2007
Case No. CGIT/NGP/ 59/2003
4. On 14-12-2006 both the parties were expected to submit their arguments on the point of perversity of the finding and on the quantum of the punishment . The same stage on which the case was fixed before CGIT, Jabalpur in the year 1996. Since the petitioner was not taking any interest it was seized for Award .
Patitioner/ : Shri Mandelal Dharma , Through the Secretary General , Rashtriya Manganese Party No. 1 Mazdoor Sangh, Bansi Villa Compound , Katol Road, Nagpur.
Versus
Respondent/ : CM- cum- MD, Manganese Ore (India ) Ltd. , PartyNo. 2 3, Mount Road Extension , Sadar, Nagpur.
AWARD
Datet: 8th May 2007
5. I have gone through the record it shows that the petitioner was watchman in MOIL. At the time of checking itwas found that the locks of the room where the explosives werekept and were under the control of the petitioner were stolen. The lock was broken and the explosive worth more than Rs . 11,000 were stolen . It was a seer negligence on the part of the petitioner and the management after conducting enquiry has issued the order of dismissal . The findings of the enquiry officer are based on the evidence. The evidence was recorded in a questions and answers form at some time . The findings of the enquiry officer are reasoned . He has considered all the evidence in detail and there is nothing to show a perversity in it. Hence I hold that the findings are not perverse .
6. Similarly the allegations were of a serious nature regarding the theft of explosive having a considerable price at that time. The management considering the gravity of offence as well as giving opportunity to the petitioner 1. The Central Government after satisfying the existence of disputes between The Secretary General , Rashtriya Manganese Mazdoor Sangh , Bansi Villa Compound, Katol Road , Nagpur Party No.1 and CM- cum- MD,Manganese Ore [ India ) Ltd. , 3, Mount Road Extension, Sadar, Nagpur Party No. 2 referred the same for adjudication to this Tribunal vide its Letter No. L- 27012/4/90- IR(Mine) Dt. 19-3-1991 under clause (d) of sub-section ( 1 ) and sub- section (2A) of Section 10 of Industrial Disputes Act , 1947 (14 of 1947) with the following schedule.
2733 G1/07-6 [PART II-SEC . 3( ii ) ] THE GAZETTE OF INDIA : JUNE 23 , 2007 /ASADHA 2 , 1929
3952
AWARD
passed an order of dismissal . The quantum of punishment is also proper and cannot be said was disproportionate to the misconduct . Hence , I do not find it necessary to interfere in the order of the management consequently the order ofdismissal from the service is proper and correct . In the result I answer the dispute in negative. Its stands as dismissed.
Hence this Award .
Dated 8-5-2007 A. N. YADAV, Pesiding Officer
नई दिल्ली, 24 मई , 2007
The Government of India vide their No. L - 29012/17 / 2001- IR(M) dated 2nd June , 2001 , the Ministry of Labour , Government of India referred the following matter for the adjudication of this Tribunal and the same was received on 27th June , 2001. The notice of the reference was given to the parties who appeared through their representatives . The workman filed his Claim Petition and the Management opposed the claim through their Written Statement . The workman filed rejoinder as well as the affidavit supporting his claim . The Management has filed the affidavit of Shri M.S Pathania their General Manager besides that of R.S. Bhardwaj , who , however was not examined as a witness . TheManagement also placed on record the photo copy of the inquiry proceedings . The workman had the opportunity to cross - examine the witness of the Management and the Management cross - examined the workman to their satisfaction .
का.आ. 1807.औद्योगिक विवाद अधिनियम , 1947 ( 1947 का 14) की धारा 17 के अनुसरण में , केन्द्रीय सरकार जनरल इंडस्ट्रीज कापर्पोरेशन लिमिटेड के प्रबंधतंत्र के संबद्ध नियोजकों और उनके कर्मकारों के बीच , अनुबंध में निर्दिष्ट औद्योगिक विवाद में केन्द्रीय सरकार औद्योगिक अधिकरण/ श्रम नयायालय II , चंडीगढ़ के पंचाट (संदर्भ संख्या आई. डी. सं. 621/2005 ) को प्रकाशित करती है, जो केन्द्रीय सरकार को 24-5-2007 को प्राप्त हुआ था ।
[सं. एल -29012/ 17/2001- आई आर ( एम ) ]
एन. एस. बोरा , डेस्क अधिकारी F
New Delhi, the 24th May, 2007
S.O.1807 .-In pursuancemance of Section 17 of the Industrial Disputes Act, 1947 ( 14 of 1947) , the Central Government hereby publishes the award (Ref. No. I. D. No. 621/2005) of Chandigarh nowt he Central Government Industrial Tribunal - cum - Labour Court, as shown in the Annexure in the Industrial Dispute between the employers inrelation to the management of Gen. Ind . Corpn . Ltd. , and theirworkman, which was received by the Central Government on 24-5-2007 .
[No. L- 29012/17/2001 - IR (M) ]
Stated in brief the claim of the workman , as is made out by him in his statement of claim filed on 9th August , 2000 , is that he had joined the services with the Management as semi - skilled worker in compliance to the order dated 17th September, 1991. He remained in their service till 31st March , 1998 when his services were terminated in violation of provisions of law and principles of natural justice for the reason of his Trade Union Activities . The Domestic Inquiry held against him was farce and the report made was biased and partial . Even otherwise nothing could be proved against the workman beyond any doubt. That the punishment awarded to the workman was harsh and disproportionate to the mis- conduct alleged against him . Even otherwise the workman was not provided with fair opportunity to defend himself. The order of dismissal , therefore , was bad in law is required to be quashed.
N.S. BORA , Desk Officer
ANNEXURE
CENTRAL GOVERNMENT INDUSTRIAL TRIBUNAL-CUM- LABOUR COURT- IL,
CHANDIGARH
SHRI KULDIP SINGH
PRESIDING OFFICER
Case No. I.D. No. 621/2005
Registered on 24-8-2005
Date ofDecision 16-3-2007
Roop Lal Sto Shri Sukh Ram Village Dehlag ,
Petitioner
PO Bhater Nichla, District Bilaspur
Versus
TheManaging Director,
General Industries Corporation Ltd.
.Respondent
Shimla, Himachal Pradesh
APPEARANCE
For theWorkman :
Shri J. C. Bhardwaj , AR
According to the workman , the Management failed toproduce any conclusive proof to show that the vehicles were owned by him . They could also not prove the factum of instigation of the workers to go on strike . The Management failed in its duty to produce as witnesses the private parties which according to them were benefited by the act ofthe workman . The charge of failure of the workman to attend the Shimla Office was also bad since before issuing directions to the workman , to go to Shimla , it was required of the Management to have fixed the wages of the workman and provided him the allowances . The inquiry was also bad for the reason that both the Inquiry Officer and the Presenting Officer were the employees of the Management , thus under their influence . Moreover, they failedto prescribe procedure , to be followed, in the inquiry. They further failed in their duty to provide the copies of the documents , sought to be produced , against the workman besides did not provide the list of witnesses . The Inquiry Officer based the report only on the testimony of the witness who was the Manager of the Management . The Management also failed in their duty to provide Shri V. KGupta, AR
FortheManagement:
3953
भारत का राजपत्र : जून 23, 2007/आषाढ़ 2 , 1929
[ भाग II- खण्ड 3 ( ii ) ]
opportunity to the workman for properly defending his case . The Management further failed in not recording the minutes of the personal hearing . They rejected the review petition without giving any findings . They also did not consider the past record of the workman which was blameless . The workman in the end has prayed for quashing the finding of the domestic inquiry and the punishment awarded to him . He has claimed that right from the date of his termination of his services he has remained without work. He has also prayed for the exercise of power under Section - 11 -A. of the Act .
served upon him the notice for unauthorized absence from duties . He denied that a fair and proper inquiry was held against him . He claimed that the Inquiry Officer was biased against him as he was posted in that Branch. Moreover , he proved the charges without any evidence rather against the statement of the witnesses . Neither the procedure for inquiry was settled nor the workman was provided with the documents . It is also claimed by the workman that the Management was biased against him , therefore , they had fixed hisHeadQuarter at Shimla, whereas the inquirywas ordered to be held at Delog district, Bilaspur at a distance of 200 kms . The Management also did not give him the subsistence allowance , a mandatory requirement . Thus the finding of the inquiry was bad . Denying that he had a blemished service record he claimed that he had never been issued a warning regarding any misconduct earlier , rather his work was appreciated a number of times and he was charge sheeted only for having taken part in legitimate Trade Union Activities . The punishment was also disproportionate and harsh to the misconduct alleged. He prayed for allowing him to lead the evidence , afresh so as to prove his innocence.
The workman appeared as a witness and proved his affidavitW - 1 . In cross examination he admitted that he was charge sheeted, the Management had produced the witnesses and so was done by him . He had engaged Shri J.C. Bhardwaj , as his representative in the inquiry; that he had been provided with the copy of the statements . He was placed under suspension and by the same order his HeadQuarter was shifted to Shimla. However , he was not relieved from Bilaspur for Shimla . He admitted that he had received the copies of the documents , such as , Memorandum dated 3rd December , 1996 , letter dated 30thMay, 1996, agreement dated 7th June, 1996, another letter dated 12th October, 1996, the list of witnesses placed onrecord and all the documents attached with the affidavit ofShri R.S. Bhardwaj, He also admitted to have filed the reply a copy of which is on record . He admitted to have received the copies of the Annexure A, B, C besides that of letter dated 5th November , 1996 , documents no.78 to 117. He claimed that he had pointed out to the Management that he has not received the copies of some documents . He, however , did not show what were these documents , the copies ofwhich he had not received.
The Management has opposed the claim of the workman stating that the workman had indulge in gross misconduct during the course of his employment as he remained unauthorisedly absent from duty. He neglected his duty and ran his own business . He incited the workers oftheManagement by provoking them to indulge in illegal activities and thus caused financial loss to the Management. For those misconducts he was placed under suspension and was charge sheeted . As a result of his incitement the workers went on strike causing huge loss to the Management . A domestic inquiry was conducted against him in a fair and proper manner by observing the principles of natural justice. In the inquiry the workman was found guilty of having committed the misconduct , therefore , he was dismissed from service and the action taken against him was legal and justified. Denying that the allegation of the workman that he did not own two vehicles , in his name, it is stated by the Management that the workman himself admitted duringthe inquiry that he owns the vehicles . The Inquiry Officer was fair in conducting the inquiry whereas the workmandid not attend the inquiry proceedings despite notices . He was represented by Shri K.C Bhardwaj , his representative, who had taken full care of him , during the inquiry . Claiming that the finding of the inquiry was based on evidence, it is stated by them that though the venue of the inquiry was fixed at Shimla , the Head Quarter of the workman, but the workman remained at his native place anddid not report at the Head Quarter at Shimla . Regarding theallegation of denial of fair opportunity to him it is stated by theManagement that the workman had full opportunity and that the review petition had been rejected since it did not have any merit . Otherwise also the record of the workman was blemished . They further stated that the punishment awarded to the workman was proportionateto the gravity of misconduct . The Management in the end has prayed for permission to lead the evidence in case the Tribunal comes to the conclusion that the domestic inquiry was not based on the facts . They have prayed for dismissal ofthe Claim Petition .
The workman filed a long rejoinder , without adding anything substantial to the claim made by him in the Claim Statement. He denied that he had ever admitted being the owner of any vehicle or that he had running any business and was neglecting his duty. The Management also never
The Management produced Shri M.S. Pathania as their witness besides Shri Ram Saroop Bhardwaj . By his statement Mr. Pathania proved his affidavit , Exhibit M - 1 and the documents Exhibits M- 2 to M- 14 . In cross examination he admitted that at the time the workman was dismissed fromthe service a reference was pending in this Court and no approval , to terminate the services of the workman, was taken by the Management from this Court . He denied the knowledge that the workman was issued a month'snotice before the termination of his services . He admitted that the place of inquiry was Shimla, because of [PART II -SEC . 3 (ii) ] THE GAZETTE OF INDIA : JUNE 23 , 2007/ASADHA 2, 1929
3954
fair andproper , it cannot interfere with the factual position. In that circumstances it can only examine whether the punishment awarded was proportionate to the misconduct alleged.
Headquarter and that the workman was not paid the subsistence allowance during the period of his suspension. He claimed that two certificates showing him as owner of the vehicles are on record. He denied that the workman's union had made a complaint of corruption against him but admitted that the workman was a General Secretary ofthe Union . He denied that the workman was victimized for his Trade Union activities .
The other witness Ram Saroop also proved his affidavit M - 15 and the documents M - 16 to M - 22 . He admitted that he was subordinate to Managing Director butdenied that the finding given by him were not based on the evidence or that the report was based upon the dictations of Mr. Pathania or that he had given the report under pressure.
Ihaveconsidered the rival contentions of the parties and have also gone through the record.
The claim of the workman is that (i ) the charges are not proved against him , therefore, the punishment awarded to him is bad in law, (ii ) that no procedure was set by the Inquiry Officer during the course of the inquiry , ( iii) that thedocuments were not provided to the workman ; ( iv) that the report was based upon testimony of a person who was prejudicial to the workman; (v) that the workman was not provided with subsistence allowance during the course of the inquiry; (vi ) that no minutes of the personal hearing were recorded; and (vii ) that the punishment awarded to the workman was disproportionate to the misconduct alleged against him.
In order to see whether the inquiry was fair and proper, it can see whether the procedure required to be followed was followed by the inquiry officer , the Disciplinary Authority and the Appellate Authority. It is by now settled that the Disciplinary Authority and the InquiryOfficer can devise the procedure to be followed in the inquiry . The only rider as their powers is that the procedure so adopted should be reasonable and in consonance with the principles of natural justice . In the case of Kharda and Co. Ltd. Vs. its workmen reported as (1963) 2 LLJ 452, their Lordship of the Supreme Court have held that the requirements of natural justice is that the inquiries should be held with scruplus regard for the requirements of rules of natural justice as questions of bonafide or malafide of employer are the issues . In the case ofMeenglass T. Estate Vs. its workmen reported as 1963 (2LLJ 392), their Lordships gave the requirements ofnatural justice broadly and according to that ( i) the inquiry must be held by a person who is not biased in favour or against theparties , (ii ) and a delinquent employee should be given ofopportunity of the hearing of the evidence , in support ofthe charge and to cross- examine the witnesses produced against him and aiso be allowed to the evidence rebut against him , by examining witnesses including himself if he or she has any relevant matter . Hon'ble High Court of Guwahati, in the case reported as 1981 LAB.I.C 557 held that the principles of natural justice in its journey through the centuries, has shed much of its glories and is now crystallized into four principles of justice namely ( 1 ) opportunity to both the contested parties to be heard , (2) hearing before an impartial Tribunal so that no man can be ajudge in his own cause ; (3 ) decision made in full faith, and (iv) an orderly course of procedure . Hon'ble High Court ofKarnataka in the case of G.R. Venkateshwara Reddy Vs. Karnataka State Road Transport Corporation reported as (1995) I LLJ 1011 , has laid down the following requirement of reasonable procedure subject to any special provision relating to procedure in the relevant rules , regulations , standing orders or a statute;
(a) the employees should be informed of exact charges which he is called upon to meet . He should be given an opportunity to explain any material relied on by the Management to prove the charges , (c) the evidence of the Management witnesses should be recorded in the presence of the delinquent employee and he should be given an opportunity to cross - examine such witnesses ; the delinquent employee shall either be furnished with copies of the documents relied on by the Management or bepermitted to have adequate inspection of the documents relied on by the Management; the delinquent employee should be given the opportunity to produce relevant Before adverting towards the allegations , made by the workman , against the report of the inquiry made against him and the punishment awarded, it has to be understood as to what is the scope of proceeding before this Tribunal . Hon'ble Supreme Court has circumscribed the powers of even High Court with regard to the matter in which a domestic inquiry is held before a workman is punished by theemployer. Inthe case reported as 1999 ( 1 ) SCT 642, their Lordship, in para 15 of their judgement held that " the High Court appears to have over looked the settled position that in departmental proceedings , the Disciplinary Authority isthe sole judge of facts and in case an appeal is presented to the Appellate Authority, the Appellate Authority has also the same powers and jurisdiction to reappreciate the evidence and to come to the conclusions on facts , being the sole fact finding authorities . Once finding of the facts based on appreciation of evidence are recorded, the High Cours inWrit Jurisdiction , may not normally interfere with those factual findings unless it finds that the recorded findings were perverse and/are legally untenable . The adequacy or inadequacy of the evidence is not permitted to be canvassed before the High Court. " The position of the Tribunal is not better than that of the High Court in a case of domestic inquiry. The Tribunal can only examine whether the inquiry so held was fair and proper or not . If theTribunal comes to the conclusion that the inquiry was 3955
भारत का राजपत्र : जून 23 , 2007/आषाढ़ 2 , 1929
[भाग II- खण्ड 3 ( ii ) ]
evidence documentary and oral , which includes the right to examine self and other witnesses and to call for relevant and material documents in the custody of the employer; (e) whenever the inquiry authority is different from Disciplinary Authority, the delinquent employee shall be furnished with a copy of the inquiry report and he permitted to make a presentation to the Disciplinary Authority against the finding recorded in the inquiry report . Keeping all these principles in mind I approach to examine the grievance of the workman as made out by him though his pleadings . In my opinion his own statement is sufficient to answer the grievances raised by him.
it was held. No doubt he meakly alleged that the inquiry officer had relied upon the statement of the single witness the Manager , who was having prejudice against him . The workman has however not produced any evidence to show that the witness was prejudiced against him and why. He didnot even put a question to that witness during inquiry to show what enmity he was harbouring against the workman. Therefore , I am of the opinion that the allegation made against the witness is without any reason and substance and is afterthought. After going through the record I do not find any justification with the workman to claim that the Management has failed to prove the charges against him; that he was not provided with documents and that the inquiry was based upon the statement of a person who was prejudiced against him .
In his statement recorded on 9th August, 2004 he admitted that he was charge sheeted by the Management and an inquiry was held against him. He further claimed to haveplaced on record the copies of the inquiry proceedings and stated that the Management had produced witnesses against him and he has also produced his witnesses in the inquiry. He further stated that he had engaged Shri J.C Bhardwaj as his representative in the inquiry. He further admitted that he had the knowledge of his having been placed under suspension and that his Head Quarter was shifted to Shimla . In the same breath he stated that he had not been relieved from Dilog in Bilaspur District . He further admitted that he was provided with the copies of the documents such as the agreements dated 7th June, 1996 , list of witnesses , memorandum dated 3rd Dec., 1996. He also admitted that the copy of the reply placed on record wasthe replymade by him . It is only in the end he made the grievance that the copies of some documents had not been provided to him . He did not name the documents the copies ofwhich were not provided to him , before this Tribunal nor earlier. The next allegation made is vague and after thought .
The next claim made by the workman is that since he was not paid the subsistence allowance , therefore , the inquiry made against him and the punishment awarded thereupon is bad in law. This claim the workman has not made even in his statement of claim and is raised only in the arguments . No matter which is not raised in the pleadings cannot be looked into with providing opportunity to other side to admit or deny the same. The next claim is that the Management had awarded him the punishment even when the Industrial Dispute was pending and, therefore , they violated the provisions of Section 33 (2- B ) of the Act . This plea the workman has raised without bringing on record any evidence to show as to what reference was pending and whether any reference they related to the workman andthe proceedings before this Tribunal . During the course of arguments he submitted that the Management has admitted that I.D. No.77/1996 was pending in the Court whenthe services of the workman were terminated . Mere this admission of the Management is not sufficient . The workman is further required to show that there was pendency of proceedings before the Labour Tribunal , in respect of the Industrial Dispute , between the parties . I find no evidence on record to show as to between what parties the Industrial Dispute was pending in the shape of I.D. No.77/ 1996 so as to get any relief on this count the workman was required to prove that the dispute referred by I.D. No.77/ 1996 related to the parties to the present reference and, therefore , the Management changed the service conditions of the workman during the pendency of thatdispute and so violated the provisions of the Act.
After going through the inquiry proceedings , the copies ofwhich are placed on record I am of the opinion that the Management had conducted the inquiry against the workman in a fair and proper manner. The workman got full opportunity to defend himself and in that process he was assisted by his representative . Moreover, the allegations against the workman have been proved , much onthe basis of the documents against which the workman has failed to produce any evidence . Thus he has no reason to claim that the vehicles bearing No. H.P- 24-537 and I find that the workman himself has admitted that the Management had followed the procedure during the course of the inquiry as he was informed of the exact charges , which he was called upon to meet. He claims to have replied the charges . He admitted that the Management had produced the witnesses against him and he had cross examinedthem. He further stated that he had produced his witnesses also and during the inquiry he was represented by Shri J.C. Bhardwaj , his representative . He did not raise any grievance that at any stage of the inquiry , the Management had not followed the procedure or they had violated the principles of natural justice by not following the procedure laid down by Hon'ble Supreme Court of India and the High Courts of the country. There was , therefore , no violation of natural justice by the Management during the inquiry. The delinquent employee was given fairopportunity to adequately represent his case by cross examining the witnesses of the Management and by producing his own evidence and documents . The inquiry was held by an unbiased person and the decision was takenin good faith , without malice or as the workman has not raised a finger against the inquiry officer or the manner [PART II-SEC . 3 (ii ) ] 3956
THE GAZETTE OF INDIA : JUNE 23 , 2007/ ASADHA 2 , 1929
Government hereby publishes the award (Ref. I.D. No. 02/03 ) ofthe Central Government Industrial Tribunal , cum- Labour Court , Udaipur as shown in the Annexure in the Industrial Dispute between the employers in relation to the management of Hindustan Zinc Ltd. , and their workman, which was received by the Central Government on 24-5-2007.
[No.1-29012/50/2002- IR (M) ]
N.S. BORA , Desk Officer
अनुबन्ध
HP-24-337 were not registered in his name . The Management had levelled three charges against the workman, that he had engaged himself in a private business and ignored the work of the Management he remained absent from duty on different dates without advancing any reasonable explanation ; and that he had incited the workers to proceed on strike much against the interest of the Management . On facts the Inquiry Officer found the charges proved and as is noted above , the Tribunal cannot interfere in the findings of the facts as the workman has failed to showthat the findings are perverse and untenable inview of the evidence brought on record . The authorities relied upon by him , in my opinion also do not help him in the circumstances of the case .
न्यायालय औद्योगिक विवाद अधिकरण एवं श्रम न्यायालय , उदयपुर ( राज. ) पीठासीन अधिकारी श्री हरसुखराम पुनिया, आर. एच. जे. एस.
प्रकरण सं. 02/03 श्रम वाद
श्री पूरणसिंह पिता उदय सिंह रावत , जाति राजपूत , निवासी बी-27 , प्रेमनगर , जावर माईन्स, जिला उदयपुर
-प्रार्थी
विरुद्ध
1. श्री डारेक्टर , हिन्दुस्तान जिंक लि. , जावर माईन्स
2. श्री चेयरमेन , हिन्दुस्तान जिंक लि. ,
स्वरूप सागर के सामने उदयपुर
-विपक्षीगण
उपस्थित:
श्रीसी. पी. शर्मा
प्रार्थी की ओर से:
श्री बी. एल. गुप्ता
विपक्षी की ओर से
पंचाट
Now the next question which falls for consideration iswhether the punishment awarded commensurates with the misconduct alleged against the workman . As stated earlier, there were three charges , against the workman , that he ignored the working of the Management that he indulge in side business and, therefore , he ignored the working with the Management ; and that he incited the workers to go on strike against the Management without any justified cause. The Inquiry Officer found the charges proved and inview of that the punishment awarded was not disproportionate as no employer would keep an employee who is dishonest in his working and gives preference to hisside business and at the top of that who unauthorizedly instigate the co - workers to go on strike much against the interest of the Management. Thus I find that the workman has failed to show that the Management was unjust in terminating his services on 31st March , 1998 , therefore, their action was illegal . The authorities referred to by him inmy opinion do not help him in facts and circumstances ofthe case . He is , therefore , not entitled to any relief . The award is passed against him . Let the copy of this award be sent to the appropriate Government for necessary action and file be consigned to records after due completion.
दिनांक 30-3-2007 KULDIP SINGH, Presiding Officer
नई दिल्ली, 24 मई , 2007
भारत सरकार के श्रम मंत्रालय न्यूदिल्ली के आदेश संख्या एल -29012/50/2002 [ आई आर ( एम ) ] दिनांक4-3-2003 के द्वारा निम्नांकित विवाद इस न्यायालय को अधिनिर्णय हेतु प्रेषित किया गया :
"Whether the action of Management of Hindustan Zinc Ltd. in retiring Shri Pooran Singh from services w.e.f. 30-6-2001 justified ? If not, to what relief is the workman is entitled?"
का.आ. 1808. औद्योगिक विवाद अधिनियम , 1947 (1947 का 14) की धारा 17 के अनुसरण में, केन्द्रीय सरकार हिन्दुस्तान जिंक लिमिटेड के प्रबंधतंत्र के संबद्ध नियोजकों और उनके कर्मकारों के बीच, अनुबंध में निर्दिष्ट औद्योगिक विवाद में केन्द्रीय सरकार औद्योगिक अधिकरण/ श्रम न्यायालय , उदयपुर के पंचाट ( संदर्भ संख्या आईडी स. 02/03 ) को प्रकाशित करती है , जो केन्द्रीय सरकार को 24-5-2007 को प्राप्त हुआ था ।
[सं. एल-29012/50/2002- आई आर ( एम )
एन. एस. बौरा , डेस्क अधिकारी
उक्त आशय का प्रसंग प्राप्त होने पर न्यायालय द्वारा दिनांक 4-4-2003 को नियमित श्रम वाद संख्या 02/03 दर्ज रजिस्टर किया जाकर पक्षकारान को नोटिस जारी किए गए । जिस पर प्रार्थी की ओर से क्लेम व विपक्षी की ओर से जवाब पेश किया गया । New Delhi , the 24th May, 2007
प्रार्थी की ओर से प्रस्तुत क्लेम के तथ्य संक्षेप में इस प्रकार है कि विपक्षी के अधीन प्रार्थी की नियुक्ति जावर माईन्स इकाइ में दिनांक 7-6-66 को अस्थायी श्रमिक के पद पर की गई । भर्ती के SO.1808 . In pursuance of Section 17 of the Industrial Disputes Act , 1947 ( 14 of 1947 ), the Central 3957 [भाग II- खण्ड 3 ( ii ) ]
भारत का राजपत्र : जून 23, 2007/ आषाढ़ 2, 1929
प्रार्थी को दिनांक 30-6-2001 को अपराह्न को सेवामुक्ति सुपरएन्यूएशन की आयु प्राप्त करने पर दिया गया। प्रार्थी द्वारा सेवानिवृति के सम्बन्ध में प्रस्तुत आपत्ति नियमानुसार मेन्टेनेबल नहीं होने तथा सेवानिवृत्ति की आयु में परिवर्तन करने की प्रथा एवं व्यवस्था नहीं होने से उचित रूप सेस्वीकार किया गया तथा प्रार्थी को 30-6-2001 को सेवानिवृत्ति कर दिया गया। प्रार्थी ने 1966 में भर्ती के समय आयु 25 वर्ष बताई इस आधार पर उसे नियुक्त किया गया । अतः प्रार्थी का क्लेम सव्यय निरस्त किए जाने की प्रार्थना की।
प्रार्थी ने अपने क्लेम के समर्थन में स्वयं का शपथ पत्र प्रस्तुत किया जिस पर विपक्षी प्रतिनिधि ने जिरह की। विपक्षी की ओर से कोई साक्ष्य पेश नहीं हुई । दोनों पक्षों ने संबंधित दस्तावेज को प्रर्दिशत कराया।
मैने दोनों पक्षों के प्रतिनिधि की बहस सुनी । पत्रावली का अवलोकनदिया।
समय प्रार्थी से उसकी जन्म तिथि नहीं मांगी गई न किसी प्रकार की कोई मैडिकल जांच कराई गई । फरवरी , 1968 में प्रार्थी को हैल्पर के स्थाई पद पर नियुक्त किया और उससे जन्म तिथि मांगी जिस पर प्रार्थी ने देहरादून ( घर ) से मंगाकर प्रमाण पत्र पेश करने को कहा । जन्म तिथि प्रमाण पत्र नहीं होने से कम्पनी के डाक्टर ने भर्ती के समय मेरी उम्र अन्दाज से 25 वर्ष लिख दी । मैंने इस पर आपत्ति की कि मेरी उम्र इस समय 19 वर्ष है। प्रार्थी देहरादून गया व स्कूल का ट्रांसफर सर्टिफिकेट लाकर कम्पनी में जमा कराया । उसमें इस प्रार्थी की जन्म तिथि 1-3-49 दर्ज है । इसके बाद जब - जब भी जहां-जहां भी कम्पनी में आवश्यकता हुई प्रार्थी ने उसकी जन्म तिथि 1-3-49 ही बताई। सन् 1969 में प्रोविडेन्ट फण्ड के फार्म भरे उसमें भी उसने 1--3-49 जन्म तिथि दर्ज कराई। भवन निर्माण हेतु लोन लिया उसमें भी उसमें भी ये ही तिथि अंकित की। परन्तु सन् 1996 में जब पेंशन फार्म भरे गए तब प्रबन्धक द्वारा मेरी जन्म तिथि 7--6-41 लिखी तब प्रार्थी प्रबन्धक से मिला उसने यह बताया कि प्रार्थी की जन्म तिथि 1-3-49 है और प्रोविडेन्ट फार्म में 7-6-41 गलत दर्ज है , इसके बावजूद भी जन्म तिथि में कोई सुधार नहीं किया । फिर प्रार्थी ने इसके सुधार हेतु 17-8-97 को एक पत्र दिया जिसे विपक्षी ने अस्वीकृत कर दिया। प्रार्थी ने डुप्लीकेट टी. सी निकलवा कर भी पेश की परन्तु उसकी जन्म तिथि में कोई सुधार नहीं किया। आदेश दिनांक 1-4-2001 द्वारा प्रार्थी को दिनांक 30-6-2001 को अपराह्न को सेवानिवृत्त करने का आदेश पारित कर दिया व उसे 30-6-01 को सेवानिवृत्त कर दिया। इस आधार पर प्रार्थी जून , 2001 में किसी भी रूप में सेवानिवृत्त नहीं हुआ। इसलिए प्रार्थना की है कि प्रबन्धक द्वारा श्रमिक को दिनांक 30-6-2001 को सेवानिवृत्त करना अनुचित एवं अवैध घोषित किया जाए। साथ ही दिनांक 30-6-2001 से निरन्तरता के साथ समस्त लाभ सहित सेवा में लिया जाने का आदेश दिया जावे।
इस प्रकरण में मुख्यमुद्दा जेन्म तिथि व सेवानिवृत्ति तिथि का है। प्रार्थी ने अपनी जन्म तिथि 1-3-49 बताई है , जिसके आधार पर यह बताया गया है कि उसके स्कूल प्रमाण पत्र में जन्म तिथि 1-3-49 दर्ज है । उसने अलग- अलग दस्तावेजों में उक्त जन्म तिथि दर्ज की है । विपक्षी संस्थान इस जन्म तिथि को सही नहीं मान रहा है । विपक्षी संस्थान का यह तर्क है कि प्रार्थी ने सर्वप्रथम दिनांक 7-6-1966 को अस्थाई रूप से श्रमिक के पद पर कार्य प्रारम्भ किया था । फरवरी , 1968 में उसे हैल्पर के पद पर नियुक्ति दी थी, उस वक्त उसकी उम्र के बारे में डॉक्टरी मुआयना करवाया गया था । डाक्टरी प्रमाण पत्र के अनुसार उसकी उम्र 25 वर्ष थी । जिस दस्तावेज पर प्रार्थी के दस्तखत हैं। प्रार्थी ने अपने डिक्लेरेशन में अपनी उम्र 25 वर्ष बताई हैं प्रार्थी ने कई वर्षों तक अपनी जन्म तिथि प्रमाण पत्र कार्यालय में प्रस्तुत नहीं कर उसे जानबूझ कर छिपाया और वर्षों बाद उसे प्रस्तुत किया । प्रमाण पत्र में दर्ज जन्म तिथि 1-3-49 को सही मानें तो प्रार्थी उस दिन नौकरी पाने की उम्र तक नहीं पहुंचा था। ऐसी स्थिति में प्रार्थी की उम्र वर्ष 1968 में 25 वर्ष थी ।
मैंने दोनों पक्षों द्वारा प्रस्तुत उक्त तकों पर गौर किया । पत्रावली पर उपलब्ध मौलिख एवं दस्तावेजी साक्ष्य का पूर्णरूपेण अवलोकन किया। प्रार्थी पूर्णसिंह द्वारा प्रस्तुत शपथ पत्र पर विपक्षी प्रतिनिधि ने जिरह की है , उस जिरह में प्रार्थी ने यह स्वीकार किया है कि प्रदर्श एम-1 डिक्लेरेशन उसने दिनांक 24-1-68 की विपक्षी कम्पनी में दिया था , जिस पर एसे बी उसके हस्ताक्षर हैं। उसी रोज उसका मैडिकल हुआ था जो डॉक्टर दशौरा ने किया था , उस प्रमाण पत्र प्रदर्श एम-2 पर भी उसके अंगूठा निशानी है। प्रार्थी ने अपनी जिरह में इस बात को भी स्वीकार किया है कि प्रदर्श एम-2 व प्रदर्श एम -5 पर उसकी उम्र 25 वर्ष लिखी हुई है , उसने अधिक उम्र लिख देने के विरुद्ध सिविल कोर्ट में कोई दावा पेश नहीं किया। विपक्षी ने जो जवाब प्रस्तुत किया है , उसमें वर्णित मुख्य बिन्दुओं की पुष्टि प्रार्थी की जिरह से हो जाती है। ऐसी स्थिति में प्रार्थी द्वारा प्रस्तुत जन्म तिथि प्रमाण पत्र सहीं नहीं माना जा सकता है ।
वर्ष 1963 में प्रार्थी ने जो डिक्लेरेशन पेश किया था और फिर प्रार्थी का डाक्टरी मुआयना हुआ , उसमें प्रार्थी की उम्र 25 वर्ष बताई विपक्षीगण ने अपने जबाव में ये आपत्तियां ली हैं कि प्रार्थी की जन्म तिथि 1-3-49 सही नहीं है और न ही हो सकती है । प्रार्थी ने 1968 में डी.ए.वी. स्कूल की अंकतालिका प्रस्तुत नहीं की। प्रार्थी सेवा निवृत्ति के पश्चात् हिन्दुस्तान जिंक लि. के कान्ट्रक्टर अरावली कन्स्क्ट्रशन कं. में सुपरवाइजर के पद पर कार्यरत है । स्थाई आदेश की धारा 5 ( ग ) के अन्तर्गत रेकार्ड जन्म तिथि में परिवर्तन अनुज्ञेय नहीं है । प्रार्थी ने सेवा में स्थायीकरण के 21 वर्ष पश्चात् उक्त स्कूल प्रमाण पत्र प्रस्तुत किया जो प्रार्थी के क्लेम को संदेहास्पद बनाता है । प्रार्थी न्यायालय के समक्ष स्वच्छ हाथों से नहीं आया है । पैरावाइज उत्तर में विपक्षीगण ने यह अंकित किया है कि दिनांक 7-6-66 को अस्थाई श्रमिक के रूप में भर्ती के समय कोई मैडिकल जांच नहीं की गई थी। प्रार्थी ने जो स्कूल प्रमाणपत्र, पेश किया वह जायज नहीं है तथा नियमानुसार प्रस्तुत नहीं किया गया है। प्रोविडेन्ट फार्म के नोमिनेशन में प्रार्थी द्वारा अपनी घोषित जन्म तिथि में परिवर्तन करने से प्रार्थी की अभिलेख में अंकित जन्म तिथि परिवर्तित नहीं हो सकती है । भवन निर्माण हेतु ऋण आवेदन पत्र में अभिलेख से परे जाकर कोई जन्म तिथि अंकित करने मात्र से रिकार्ड में अंकित जन्म तिथि में कोई परिवर्तन नहीं हो जाता है । प्रार्थी द्वारा जन्म तिथि में परिवर्तन कराने की प्रार्थना नियमानुसार एवं उचित नहीं होने से स्वीकार नहीं की गई । 3958
THE GAZETTE OF INDIA : JUNE 23 , 2007/ ASADHA 2 , 1929
गई है, यह सही है कि जन्म तिथि के सम्बन्ध में डॉक्टर द्वारा किए गए मैडिकल मुआयने में जो उम्र बताई जाती है , उसमें आगे व पीछे वर्ष-छः मास का अन्तर आ सकता है, लेकिन 8-10 वर्ष का अन्तर कभी नहीं आ सकता है । ऐसी स्थिति में वर्ष 1968 में प्रार्थी की उम्र 25 वर्ष मानी जाने के पर्याप्त आधार हैं। विपक्षी संस्थान में सेवा की कुल अवधि 60 वर्ष की उम्र में थी, ऐसी स्थिति में प्रार्थों को वर्ष 2003 मेंसेवानिवृत्ति दी जानी चाहिए थी , लेकिन विपक्षी संस्थान ने प्रार्थी को 30-6-2001 को ही सेवानिवृत्ति दे दी जो कतई गलत थी । जब डॉक्टर ने प्रार्थी की जन्म तिथि मेडिकल मुआयना करने के बाद वर्ष 1968 में 25 वर्ष बताई थी तो फिर उस तिथि को विपक्षी संस्थान ने क्यों नजरअन्दाज किया और फिर प्रार्थी को दो वर्ष पूर्व क्यों सेवानिवृत्त किया । विपक्षी की यह कार्यवाही अनुचित एवं विधि- विरुद्ध थी। इन उपरोक्त हालात में प्रार्थी की जन्म तिथि 7-6-41 नहीं मानी जाकर 7-6-43 मानी जाती है तथा 60 वर्ष उम्र पूरी होने पर प्रार्थी की सेवानिवृत्ति की तिथि 7-6-2003 होती है , जबकि प्रार्थी को दो वर्ष पूर्व दिनांक 30-6-2001 को सेवानिवृत्त कर दिया गया। विपक्षी कीयह कार्यवाही गलत थी। इन हालात में प्रार्थी दिनांक 30-6-2001 सेदिनांक 30-6-2003 तक दो वर्ष की अवधि तक अपना वेतन भत्ते व अन्य परिलाभ प्राप्त करने का अधिकारी है। प्रार्थी ने अपनी जन्म तिथि दिनांक 1-3-49 बताकर उसके अनुसार सेवानिवृत्ति तक का लाभ प्राप्त करने की प्रार्थना की है , प्रार्थी द्वारा चाहा गया यह अनुरोध भी स्वीकार करने योग्य नहीं है । प्रार्थी का यह क्लेम आवेदन पत्र आशिक रूप से स्वीकार करते हुए प्रार्थी को दिनांक 30-6-2001 से 30-6-2003 तक के वेतन भत्ते एवं अन्य परिलाभ दिलाए जाना उचित है और उसकी सेवानिवृत्ति तिथि 30-6-2003 मानी जाना उचितहै ।
अतः भारत सरकार के श्रम मंत्रालय द्वारा प्रेषित विवाद को उत्तरित करते हुए पंचाट इस प्रकार पारित किया जाता है कि प्राथर्थी पूरणसिंह को दिनांक 30-6-2001 को सेवानिवृत्त किया जाना उचित नहीं था , प्रार्थी को दिनांक 30-6-2003 को सेवानिवृत्त करना था , ऐसी स्थिति में प्रार्थी दिनांक 30-6-2001 से 30-6-2003 तक विपक्षी संस्थान से उसे मिलने वाले वेतन भत्ते एवं अन्य परिलाभ प्राप्त करने का अधिकारी है। विपक्षी पंचाट प्रकाशन के दो माह में प्रार्थी को उक्त परिलाभों का भुगतान करे तथा उसे दिनांक 30-6-2003 को सेवानिवृत्त करने का आदेश जारी करे।
जाए। पंचाट प्रकाशनार्थ भारत सरकार के श्रम मंत्रालय को भेजा
हरसुखराम पूनिया, पीठासीन अधिकारी नई दिल्ली, 24 मई , 2007
का.आ. 1809. औद्योगिक विवाद अधिनियम , 1947 ( 1947 का 14) की धारा 17 के अनुसरण में, केन्द्रीय सरकार बौला क्रोमाइट माइन्स ऑफ एफएसीओआर के प्रबंधतंत्र के संबद्ध नियोजकों और उनके कर्मकारों के बीच , अनुबंध में निर्दिष्ट औद्योगिक विवाद में केन्द्रीय सरकार औद्योगिक अधिकरण/ श्रम न्यायालय , भुवनेश्वर के
[PART II-SEC. 3 ( ii ) ]
पंचाट ( संदर्भ आईडीसं. 182/2001 ) को प्रकाशित करती है, जो केन्द्रीय सरकार को 24-5-2007 को प्राप्त हुआ था ।
[सं. एल -29012/9/ 1998- आई आर ( एम ) ]
एन. एस. बोरा , डेस्क अधिकारी New Delhi , the 24th May, 2007
S.O.1809.--In pursuance of Section 17 of the Industrial Disputes Act, 1947 (14 of 1947) , the Central Government hereby publishes the award (Ref. No. I.D. No. 182/2001) of the Central Government Industrial Tribunal- cum-Labour Court , Nagpur as shown in the Annexure in the Industrial Dispute between the employers in relation to the management of Boula Chromit Mines of FACOR , and their workman , which was received by the Central Government on 24-5-2007 .
[No. L -29012/9/ 1998 - IR (M) ]
N. S. BORA , Desk Officer ANNEXURE
CENTRAL GOVERNMENT INDUSTRIAL TRIBUNAL- CUM -LABOUR COURT, BHUBANESWAR PRESENT:
Shri N.K.R. Mohapatra ,
Presiding Officer , C.G.I.T. -cum- Labour Court, Bhubaneswar .
Tr. Industrial Dispute Case No. 182/2001
Date of Passing Award-26th April , 2007
BETWEEN:
The Management of the Chief
Executive (Mines ) , Boula Chromite
Mines of FACOR , Kuans ,
Bhadrak -756100
1st Party -Management
And
Their Workmen , represented through the General Secretary, Chrome Zone Employees Union , At/PO -Soso, Distt. Keonjhar, Orissa
---2nd Party , Union APPEARANCES :
Ashok Kumar Mishra : For the 1st Party Management Ashok Kumar Rout : For the 2nd Party, Union
AWARD
The Government of India in the Ministry of Labour, in exercise of powers conferred by Clause (d) of Sub - section (1) and Sub-section 2(A) of Section 10 of the Industrial Disputes Act , 1947 ( 14 of 1947) have referred the following dispute for adjudication vide their Order No. L- 29012/1998- IR (M) , dated 19-8-1998 :
3959 [ भाग II-- खण्ड 3 (ii) ]
भारत का राजपत्र जून 23 2007/आषाढ़ 2 , 1929
ANNEXURE
CENTRAL GOVERNMENT INDUSTRIAL TRIBUNAL CUM-LABOUR COURT, BHUBANESWAR
Present:
"Whether the action of the Management of Boula Chromite Mines of FACOR in dismissing Shri A.K. Rout, Senior Office Assistant vide order dated 25-2-1997 without any charge sheet/conducting domestic enquiry is justified ? If not, to what relief the workman is entitled to?"
SHRI N.K.R. Mohapatra, Presiding Officer, C.G.I.T. -Cum . -Labour Court, Bhubaneswar .
Tr . INDUSTRIAL DISPUTE CASE NO . 104/2001 "Whether the demand of Shri A.K. Rout, workman of Boula Chromite Mines of FACOR for re- instatement with full back wages is justified ? If so, to what relief the workman is entitled to ? "
Date of Passing Award-30th March , 2007 Between:
The Management of the General Manager , (Chrome), OMC Ltd. , At . Po . J.K. Road , Dist. Jajpur , Cuttack.
... 1st Party -Management
And
2. After necessary issues were framed the parties filed a joint petition of compromise stating to have resolved thedispute on payment of Rs . 70,000 in full satisfaction of the claim of the workman . The workman in turn agreed to have received the aforesaid amount vide cheque bearing No. 677857 dated 6-4-2007 drawn on the State Bank of India, Bhadrak , Orissa and granted receipt thereof to the management in full satisfaction of the dispute under reference .
TheirWorkman , Shri B.K. Mohapatra, At./Po . Badabiruhan, P.O. Korai , Dist . Jajpur, Cuttack.
...2nd Party-workman .
Appearances:
3. Inview of the above this award on compromise is passed in terms of the above compromise dated 6-4-2007. Pursuant to the compromise , the workman is not entitled to be reinstated in service nor is entitled for any other relief except the amount he has already received in lieu of his reinstatement and other consequential benefits .
: 2nd Party-Workman .
M/ s . J. Mohanty &
4.Reference is answered accordingly.
M/s . J.B. Pattnaik , Advocate : For the 1st Party- Management M/ s . N.K. Mishra , Advocate For the 2nd Party-
Workman .
Dictated and corrected by me . N. K.R. MOHAPARTA, Presiding Officer नई दिल्ली , 24 मई , 2007
AWARD
The Government of india in the Ministry of Labour , inexercise of powers conferred by Clause (d) of sub -section (1) and sub - section 2(A) of Section 10 of the Industrial Disputes Act, 1947 ( 14 of 1947) have referred the following dispute for adjudication vide their Order No. L- 29012/ 56/ 95-IR(Misc.), dated 30-10-1995:
का. आ. 1810. औद्योगिक विवाद अधिनियम, 1947 ( 1947 का 14 ) की धारा 17 के अनुसरण में, केन्द्रीय सरकार ओ एम सी लिमिटेड के प्रबंधतंत्र के संबद्ध नियोजकों और उनके कर्मकारों के बीच , अनुबंध में निर्दिष्ट औद्योगिक विवाद में केन्द्रीय सरकार औद्योगिक अधिकरण/ श्रम न्यायालय भुवनेश्वर के पंचाट ( संदर्भ संख्या आई डी. सं. 104/2001 ) को प्रकाशित करती है , जो केन्द्रीय सरकार को 24-5-2007 को प्राप्त हुआ था ।
[सं. एल-29012/56/ 95- आई आर ( एम ) ] एन. एस. बोरा , डेस्क अधिकारी
New Delhi , the24th May, 2007
"Whether the action of the Management of OMC Ltd. , in terminating the service of workman Shri B.K. Mohapatra, Ex - Store Issuer of Kathpal Chromite Mines without following the principles of natural justice as well as the provisions of the Certified Standing Orders is justified ? If not, to what reliefthe workman is entitled to ? "
2. The shortly stated case of the workman is as follows:-
S. O. 1810. In pursuance of Section 17 of the Industrial Disputes Act , 1947 (14 of 1947) , the Central Government hereby publishes the award (Ref. I.D. No. 104/2001) of the Central Government Industrial Tribunal-cum -Labour Court, Bhubaneswar as shown in the Annexure , in the Industrial Dispute between the employers in relation to the management of OMC Ltd. and their workman, which was received by the Central Government on 24-5-2007 .
[No. L- 29012/56/95 - IR(M) ] N. S. BORA, Desk Officer
After an interview the workman was initially appointed on 21-9-1987 as a Store Issuer on daily wage basis for a period of 89 days vide Memo No. 10687 dated 15-9-1987 of the Management . This period of engagement wasfurther extended from time to time . While this being so on 12-8-1988 he left his place of work urgently on health ground and sent leave application on 12-8-1988 by post 2733 G1/07-7 3960
[PART II-SEC. 3( ii )] THE GAZETTE OF INDIA : JUNE 23 , 2007/ASADHA 2, 1929
addressedto the Mines Manager , Katipal ChromiteMines. In the meantime the Management in its order No. 8914 dated 16-8-1988 offered him engagement in a weekly post ofStore Issuer which he could not avail during such leave period as while on leave he met with an accident and hospitalized in a private hospital . As per the advice of the treating physician he again extended his leave by sending an application for leave and remained under medical treatment uptil 31-1-1992. After obtaining a fitness certificate from the doctor on 1-2-1992 he proceeded to join in his work place and submitted a joining report on 4-2-1992 to resume his duty but he was not allowed to do so nor his joining report was accepted . As a result he approached the General Manager at Jajpur and having received nothing positive submitted a representation to the Chairman-cum Managing Director of the Management on5-2-1992 followed by two reminders on 13-7-1992 and 8-9-1992 to consider his case . While these representations were pending for consideration he received a call letter from the Management vide Memo No. 14366 , dated 26-10-1992 to appear in an interview for the post of Store Issuer. As initially he had joined in that post after being selected in an interview he did not like to appear in the interview for the self same post. Rather he preferred O.J.C. 8000/1992 challenging the above order. After the Hon'ble High Court passed an order directing the Management to dispose of his representation he received a communication from theManagement vide Memo No. 611 , dated 1-3-1993 thathis case would be considered against future vacancies . After the above communication he made few more representations and ultimately when he was communicated in Letter No. 32121 , dated 18-10-1994 that his case cannot beconsidered for the present he raised an Industrial Dispute culminating the same in the present reference . It is alleged bythe workman that the action of the Management in not allowing him to join in duties pursuant to his joining letter dated4-2-1992 tantamounts to refusal of employment , the same having been done in violation of the Standing Order. The above action of the Management is further bad the same being violative of Section 25 - F of the Industrial Disputes Act.
application since 12-8-1988. A's nothing couldbe known about him up til 2-1-1989 the Management sent two show cause notices to him, one on 9-1-1989 and the other on 6-4-1989 by Regd. Post , but it were of no effect . As a result the Management took it for granted that the workman has voluntarily abandoned his job with effect from 12-8-1988 as per the Certified Standing Order applicable to him . Long thereafter the Management for the first time received a letter dated 4-2-91 from the workman to permit him to join after his recovery from illness . Thereafter two other letters dated 8-2-1991 and 11-3-1991 were received from the workmantopermit him to join one month later on the ground of his ill health . Thereafter in response to the show cause notice dated 6-4-1989 issued earlier the workman sent two replies one to the Manager P & A, J.K. Road and another toGeneral Manager , OMC Limited , J.K. Road on 14-3-1991 and 20-9-1991 requesting to reconsider his case for re- engagementent and then on 4-2-1992 he reported for duty by producing medical certificate and fitness certificate etc. before the Manager Mines , Kathpal . As by then the workman was considered to have already abandoned the job since 12-8-1988 the concerned Manager did not allow him to join for his prolonged unauthorized absence from 12-8-1988 . It is further averred by the Management that for remaining absent from 12-8-1988 the workman had never sent any application to the Management though it is otherwise claimed by him.It is also averred by the Management that after he was refused to join on 4-2-1992 by the Manager , Mines , Kathpal he made several representations to the Management in consideration of which he was offered a post of a Mazdoor on semi - skilled wage against a vacant post of Store Issuer on 44 days basis vide his Office letter No. 21483 dated 22-7-1992 but the workman in his subsequent representations insisted to be posted in his former post . In the meantime the various documents , medical certificates and other documents filed bythe workman along with his representations were found to be forged and not reliable and therefore , the Management in his subsequent letter No. 28354 , dated 1-10-1994 was compelled to cancel its earlier letter No. 21483 , dated 22-7-1992 in which he was offered with a post of Mazdoor . Subsequently as per the order of the Hon'ble High Court passed in O.J.C. 8000/92 preferred by the workman the Management also intimated him under the office letter No. 6117 , dated 1-3-1993 that his case can be considered in future when a vacancy would arise . On receipt of a further representation the workman in the year 1994 in the month ofAugust - September he was also further intimated that he cannot be absorbed as a permanent employee under any organization of the OMC Limited. Thus by narrating the above the Management in nutshell has pleaded that the refusal of employment to the workman on 4-2-1992 was justified for his remaining unauthorizedly absent without any leave application since 12-8-1988 tantamounts to abandonment of job as per the Certified Standing Order applicableto him .
3. In its written statement the Management admits that the workman was given appointment after necessary interview as a Store Issuer on temporary basis for a period of89 days from 21-9-1987 and subsequently it was extended from time to time till 17-9-1988 . It is further contended by theManagement that while the above terms of the workman was in vogue the Management on sympathetic consideration of his representation gave an offer in its letterNo. 1913 dated 16-8-1988 to join in a weekly post of Store Issuer. But the workman did not accept the said order nor did he join in that post within the given date . Subsequently it was learnt from the Mines Manager , Kathpal under whom the workman was working that he has absented himself from duty without any leave [ भाग II- खण्ड 3 (ii) ]
4. On the basis of the above pleadings of the parties the following two issues were framed.
ISSUES
1. Whether the action of the Management of O.M.C. Ltd. , in terminating the service of workman Shri B.K. Mohapatra, Ex-Store Issuer of Kathpal Chromite Mines without following the principles of natural justice as well as the provisions of the certified?
2. To what relief, if any , the workman is entitled?
5. Each party has examined one witness besides producing sorne documentary proof.
ISSUE NO . I & II
6. These issues are taken up together as they are inter- linked . At the very outset it may be stated that while according to the Management the workman had abandoned his service by remaining continuously absent unauthorizedly since 12-8-1988 , the workman contents otherwise that he had sent necessary leave application fromtime totime on medical grounds. In view of the above controversy the only question to be seen is how far each of them have been able to establish their stands .
7. Admittedly the workman was initially appointed as a Store Issuer after necessary interview with effect from 21-9-1987 for a period of 89 days (Ext . -2 ) . It is also the admitted case of the Management that on expiry of the above terms the workman was given extension time to time uptill 17-9-1988 but before expiry of such period he remained unauthorizedly absent from12-8-1988 . It is further contended by the Management that by remaining absent continuously the workman. had lost his lien over the post as per the certified Standing Order and therefore by the time he intended to rejoin in his post on 4-2-1992 he had already lost the job by operation of law. This averment and the evidence given to that effect by the Management witness shows that the Standing Order of the Management wassquarely applicable to the workman. Rule 14(3 ) ofthe Standing Order deals with loss of lien of a workman . But thisprinciple is found to be applicable only in cases where aworkman does not report for duty after expiry of the leave period already granted to him . As accordingly to the Management the workman had left the place of work without any leave application i.e. without any leave being granted, the Management can not therefore be said to be just in saying that the workman had already lost his lien by the time he intended to rejoin on 4-2-1992. Besides under the said rule, in case of a workman losing his lien the Management is to keep him on "Badli list' which is found to have not been done so by the Management.
8. Under Rule 20 of the Standing Order willful or habitual absence from duty without leave application amounts misconduct and according to Rule 18 (2) of the Standing Order a temporary worker like the workman can
3961
भारत का राजपत्र : जून 23 , 2007/आषाढ़ 2, 1929
not be terminated as a punishment unless he has been given an opportunity of explaining the charges of misconduct alleged against him in the manner prescribed in Rule 18 (1) . From the evidence of the Management it appears that the workman was simply issued with two show cause notices on 9-1-1989 and 6-4-1989 but he was never charge-sheeted nor issued with any termination letter as perthe Standing Order un- till the date of his reporting for duty on 4-2-1992 . Therefore , the entire action of the Management in not allowing him to join in duty on 4-2-1992 amounts to illegality .
1 9. On the other hand the workman in support of his case has filed several documents of which Ext . -21 to 35 appears to be more relevant for the present purpose . Under these exhibits he has produced copies of his several leave applications each supported with postal certificates of posting receipts and medical certificates granted by his treating physician during the period from 12-8-1988 to 13-9-1991 . On perusal of these postal receipts one can hardly believe that the same have been created subsequently by the workman for the purpose of this case and therefore the copy of his leave applications which he has enclosed to these postal receipts can safely be relied upon . From his evidence and the narration of these leave applications it is evident that on getting an information that his father has been murdered the workman left the place of work on 11-8-1988 and on the following day he fell down in shock in an unconscious state sustaining bone injury . Therefore , on the very day he sent his leave application dated 18-8-1988 (Ext . - 21) and then from to time he extended his leave on medical ground as it appears from his other leave applications , medical certificates and postal receipts covered under Ext . -22 to 35. From his another application marked Ext. - 10 /1and its enclosures it further appears that on17-3-1991 he sent the above application under certificate of posting for grant of medical leave . His other correspondences marked Ext : -6 to 10 further indicates that by narrating his plight and precarious health condition he in reply to one of the letters of the Management had requested time and again not to throw him out of service . From his several letters it also appears that while applying for extension of leave he had made positive reference to his earlier leave applications . Therefore , in these circumstances the stand of the Management that, it had received no communication from the workman regarding leave can not be believed .
10. It was argued by the Management that the various documents filed by the workman are all created ones . But inthe face of several postal receipts filed by the workman it can not be so believed . Besides had the Management pursuant to its Standing Order charge -sheeted the workman and asked himto face the enquiry the workman would have been in a position to explain his position and the Management having not done so cannot now question the genuiness ofthese leave applications . When admittedly 3962
[PART II -SEC. 3 ( ii) ] THE GAZETTE OF INDIA : JUNE 23 , 2007/ASADHA 2, 1929
Ext.11. ---Letter No.2565, dtd . 8-3-1991 regarding consideration of vacancies .
Ext. -12. --Copy of Fitness certificate dated 1-2-1992.
the workman has been refused employment without any departmental enquiry as envisaged under its Standing Order the entire action of the Management is bound to be vitiated.
Ext. -13 . --Copy ofthe Joining report dated.4-2-1992.
Ext.-14. ---Copy of the mercy petition dated. 4-2-1992.
Ext.-15. --Copy ofthe representation dated 8-9-1992 .
Ext. -16. ---Copy ofthe representation dated 23-8-1994.
Ext. -17. ---Copy of representation dated 5-9-1994 .
Ext. -18.
11. It is no doubt true that while making the reference the Government has failed to mention the exact date on which the alleged termination had taken place. This is no doubt a serious omission, which ultimately can render the reference bad . But when parties do not dispute the alleged termination date to be 12-8-1988 and that being the center of reference, no serious view of non- mentioning of such date in the reference can be taken at this stage .
---Copy ofthe letter dated 18-10-1994 rejecting the prayer for employment .
Ext.-19. --Copy of the counter dated 14-1-1995 filed before the A.L.C.
Ext. -20. --Copy ofthe failure report dated 12-5-1995.
Ext. -21. --Copy of the letter dated 12-8-1988 of the workman to the Mines Manager .
Ext. -22. --Copy of the application dtd 13-9-91 of the workman to the Mines Manager .
12. Accordingly in the result it is held that the action ofthe Management in treating the workman to have had abandoned the job voluntarily from 12-8-1988 and its further conduct of not allowing the workman to join in his duties on4-2-1992 amounts to illegality and not according to the procedure laid down in its Standing Order. Therefore the Management is directed to reinstate the workman in his former post with full back wages and other service benefits as applicable to an employee of his cadre .
Ext. -22/1.
13. Reference is answered accordingly.
--Postal receipt in support of sending letter under Certificate of posting.
Dictated & Corrected by me .
Ext. -23. --Copy of the letter dated 15-6-1991 of the workman to the Mines Manager.
Ext. -23/1
N.K.R. MOHAPATRA, Presiding Officer LIST OF WITNESSES EXAMINED ON BEHALF OF THEWORKMAN
Postal receipt in support of sending letter under certificate of posting .
Workman Witness No. 1 The workman Himself
Ext. -24.
Shri Basant Kr . Mohapatra .
--Copy of the letter dated 10-11-88 of the workman to the Manager , Mines .
Ext. -25.
LIST OF WITNESSES EXAMINED ON BEHALF OF THE MANAGEMENT
---Copy of the letter dated 1-1-1989 of the workman to the Manager , Mines .
Ext. -26.
Panda.
Management Witness No.1- Shri Bhaskar Chandra
---Copy of the letter dated 1-4-1989 of the workman to the Manager, Mines .
Ext. -27.
LIST OF EXHIBITS ON BEHALF OF THE 2ND PARTY - WORKMAN
--Copy of the letter dated 21-4-89 of the workman to the Manager , Mines .
-Interview Call letter dated 31-7-1986 .
Ext. -1.
Ext. -28.
Ext. -2.
Copy of appointment order dated 15-9-1987 .
--Copy of the letter dated 30-6-1989 of the workman to the Manager , Mines .
Ext. -3. -Duty Chart dated 30-9-1987.
Ext. -29.
Ext. -4. --Quarter allotment order dated 11-7-1988 .
---Copy of the letter dated 28-9-1989 of the workmanto the Manager, Mines .
Ext. -5. -Letter dated 6-4-1989 calling for explanation.
Ext. -30.
Ext. -6.
-Copy of the letter dated 27-12-89 of the workman to the Manager , Mines .
-Copy of the representation dated 7-1-1991 for extension of time .
Ext. -31.
Ext. -7.
-Copy of the letter dated 25-3-90 of the workman to the Manager , Mines .
-Copy of the representation dated 4-2-1991 for extension of time .
Ext. -32. -Copy of the letter dated 23-6-90 of the workman to the Manager Mines .
Ext. -8. -Copy ofthe representation dated 8-2-1991 forextension of time .
Ext-33.
Ext. -9.
--Copy of the letter dated 21-9-90 of the workman to the Manager , Mines .
---Copy of the representation dated 11-3-1991 for extension of time .
Ext. -34.
Ext. -10.
-Copy of the letter dated 20-12-90 of the workman to the Manager, Mines .
-Copy of the representation dtd . 14-3-1991 for extension oftime .
Ext -35. -Copy of the letter dated 4-1-91 of the workman to the Manager , Mines .
Ext. - 10/1. Copy of the representation dtd . 17-3-1991 for extension of time .
[भाग II- खण्ड 3 ( ii) ]
3963
भारत का राजपत्र : जून 23 , 2007/आषाढ़ 2, 1929
Ext. -36. -Copy of the letter dated 5-2-92 of the workman to the CMD , OMIC, BBSR Ext.-37. -Copy of the Postal receipt .
Ext. -38. -Copy ofthe application dated 13-7-1992.
Ext.-38/1. -Postal Receipt .
Ext. -38/2. -Postal A.D. Card .
LIST OF EXHIBITS ON BEHALF OF THE 1ST PARTY-MANAGEMENT
Ext. -A -Joining report dated 21-7-1987.
Ext. -B -Offer ofAppointment dated 16-8-1988 .
Ext. -C -Letter dated 8-3-1991 of the Management .
Ext. -D -Copy of Standing Order .
Ext. -E -Copy of letter No. 6117 /OMC/93 , dated 27-2-1993/1-3-1993
Ext. -El -Copy ofthe Letter No. 32121 /OMC/94 dated 18-10-1994.
Ext -F -Copy of Order No. 21483 /HO /OMC/ Bhubaneswar dated 22-7-1992 .
Ext-G -Copy of Order No.5, dated 26-11-1992 of OrissaHigh Court in OJC 8000/92 . नई दिल्ली, 24 मई , 2007
का. आ. 1811. औद्योगिक विवाद अधिनियम , 1947 (1947 का 14 ) की धारा 17 के अनुसरण में , केन्द्रीय सरकार आई. बी. पी. क. लिमिटेड के प्रबंधतंत्र के संबद्ध नियोजकों और उनके कर्मकारों के बीच , अनुबंध में निर्दिष्ट औद्योगिक विवाद में केन्द्रीय सरकार औद्योगिक अधिकरण/ श्रम न्यायालय , लखनऊ के पंचाट (संदर्भ संख्या आई डी. सं. 53/2003 ) को प्रकाशित करती है, जो केन्द्रीय सरकार को 24-5-2007 को प्राप्त हुआ था ।
[सं. एल-30011 / 1 /2003- आई आर ( एम ) ] एन. एस. बोरा , डेस्क अधिकारी New Delhi , the 24th May, 2007
S. O. 1811. In pursuance of Section 17 of the Industrial Disputes Act, 1947 ( 14 of 1947), the Central Government hereby publishes the award (Ref. No. I.D. 53/ 2003) of the Central Government Industrial Tribunal -cum- Labour Court , Lucknow, now as shown in the Annexure, in the Industrial Dispute between the employers in relation to the management of I.B.P. Corpn . Ltd. and their workman, whichwas received by the Central Government on 24-5-2007.
[No. L-30011/1/2003 - IR(M) ] N. S. BORA, Desk Officer
ANNEXURE CENTRAL GOVERNMENT INDUSTRIAL TRIBUNAL CUM-LABOUR COURT, LUCKNOW PRESENT: Shrikant Shukla : Presiding Officer I.D. No. 53/2003
Ref. No. L-30011/1 /2003 -IR(M) Dt. 1-5-2003
Between
Sh . B.P. Singh ((Authorised Representative) , EngineeringMazdoor Sangh , 281/171 Mavaiyya, PO Rajendra Nagar , Lucknow(U.P.)
And
Senior Depot Manager , IBP Corpn . Ltd. , Bulk Petroleum Depot, Near Amausi Railway Station , Amausi Lucknow (U.P. )
AWARD
The Government of India in the Ministry of Labour , New Delhi referred the following dispute vide No. L-30011/ 1/2003/IR(M) dt . 1-5-2003 for adjudication to the Presiding Officer CGIT- Cum - Labour Court, Lucknow.
" क्या प्रबन्धन मैं आई.वी.पी. कम्पनी लि.आमौसी , लखनऊ द्वारा श्री बच्चन लाल पासवान , पुत्र श्री चन्द्रभान पासवान को 17-3-97 से लगातार कैजुएल कर्मकार के पद पर कार्य लेते रहना एवं उसका नियमितिकरण नहीं करना न्यायोचित तथा न्यायसंगत है ? यदि नहीं तो कर्मकार किस अनुतोष की अधिकारी है ?
The case of the trade union is that Sri Bachchan Lal Paswan was appointed by the competent authority of IBP Co. Ltd. , Bulk Petroleum Depot, Near Amausi Railway Station, Lucknow on 17-3-1997 , but while conducting necessary proceedings before the Asstt . Labour Commissioner (C) , Lucknow who recommended the Central Government to refer the dispute for adjudication , the parties concernedby means of his letterdt . 13-1-2003 terminated the services ofthe workman . The employer also terminated the services of Sri Aftab Ahmed Siddiqui by the same order . The workman raised Industrial Dispute with regard totermination under the provisions of I.D. Act, 1947 before theAsstt. Labour Commissioner (C) , Lucknow and the authority after conducting the necessary formalities , submitted his failure of conciliation report to the Ministry concerned . Sri Aftab Ahmed Siddiqui who was also terminated alongwith workman Sri Bachchan Lal Paswan challenged the termination order before the Hon'ble High Courtby means ofthe writ petition No. 1175 (S/S) of2003. Aftab Ahmed Siddiqui Vs. General Manager (Northern Region), IBPCo. Ltd. and others and the Hon'ble High Courtby interim orderdt. 21-2-2003 stayed the operation of the impugned termination order . Since by the same order the services of the workman Sri Bachchan Lal Paswan were also terminated as such he has also advised to file the writ petition against the termination order and accordingly concerned workman filed a writ petition No. 1770 (S/S) of 2003 and challenged the termination order dt. 13-1-2003 . Initially by the interim orderdt . 28-3-03 the Hon'ble High Court also stayed the operation of the termination order dt. 13-1-03 , but subsequently the aforesaid writ petition has been dismissed vide judgment and orderdt . 31-7-03 on the ground that the workman 3964
THE GAZETTE OF INDIA : JUNE 23 , 2007 /ASADHA 2 , 1929
[PART II-SEC. 3( ii)] concerned has already availed the alternative remedy, which is available under the provisions of the ID Act, 1947 and the matter is still pending . It is also stated that in the statement of claim filed by the trade union that the writ petition No. 1175 (S/S) of 2003 is still pending before the Hon'ble High Court and till the date interim order passed by the Hon'ble High Court is continuing . In the circumstances it is clear that employees are adopting unfair labour practices which is prohibited under Section 25T of ID Act and the employers are using colourable exercise of powers , which is against the provisions of the ID Act as well as item 10 of Schedule 5 of the aforesaid Act. Accordingly , the worker has prayed that the court may hold that action of the employers in not regularising the services of the workman Sri Bachchan Lal Paswan is illegal and unjustified and accordingly he is entitled to get the regularisation of the services and all consequential benefits .
The worker has filed following documents alongwith applicationC-11;
1.Photo copy of letter dt. 28-4-99 issued by Depot . Manager.
2.Photo copy of letterdt . 25-9-01 issuedby Chief Manager (Personnel and Administration) .
3.Photo copy of letter dt . 13-1-2003 whereby services of the workman have been terminated.
4.Photo copy of the interim order dt . 21-2-03 passed inwrit petition No. 1175(S/S) of 2003 Aftab Ahmed Siddiqui VsGeneral Manageer IBP Co. Ltd. and others .
such the work at Amausi Depot of IBP Co. has been drastically reduced resulting into cut of expenditure of the Depot . In the circumstances the IBPCo. Ltd. has introduced a Voluntary Retirement Scheme for reduction of manpower for its permanent employees . It is admitted thatvide orderdt . 13-1-03 the services of Sri Bachchan Lal Paswan were discharged simplicitor . Sri Bachchan Lal Paswan has been paid an amount of Rs . 18,770 towards one month notice wages, compensation @ 15 days for every completed year of service and wages for the period 1-1-03 to 15-1-03 . Copy of termination order was received by Sri Paswan on 15-1-03 . Sri Paswan preferred an application under section 2A of the ID Act before the Asstt . Labour Commissioner ( C) , Lucknow seeking direction to the employer to take him back in service and if the employer was not ready to take him back in services , then recommended the Government to refer the dispute for proper adjudication before the competent court of law. The said application was sent by the Asstt . Labour Commissioner (C) , Lucknow to the IBPCo. Ltd. vide covering letter dt . 24-1-03 for attending the conciliation proceedings . The IBP Co. Ltd. filed objection to the application of Sri Paswan before the Asstt . Labour Commissioner ( C), Lucknow . While the proceedings were pending before the Asstt . Labour Commissioner (C), Lucknow . Sri Bachchan Lal Paswan filed a writ petition No. 1770 (S /S) of 2003 , Bachchan Lal Paswan Vs General Manager , IBP Co. Ltd. and others before the Lucknow Bench of Hon'ble High Court by concealing and suppressing the material fact about the proceedings pending before the Asstt . Labour Commissioner (C) , Lucknow and without furnishing a copy of the writ petition uponthe counsel of the IBP Co. Ltd. despite receiving the caveat . Vide interim orderdt . 28-3-03 the Hon'ble High Court admitted the writ petition and stayed the operation of the order of termination dt . 13-1-03 . On 27-3-03 Sri Bachchan Lal Paswan has replied to the objections of the IBP Co. Ltd. before the Asstt . Labour Commissioner ( C) , Lucknow. On receiving the copy of the interim order dt . 28-3-03 efforts were made by the IBP Co. to get the stay order vacated by filing the application for vacation of interim order supported with a counter affidavit . The Hon'ble High Court on 31-7-03 dismissed the writ petition No. 1770( S/S) of 2003 , since Sri Paswan had concealed material facts in the writ petition and had also not served copy of the writ petition upon IBPCo. Ltd. despite the service of caveat . It is further submitted that Amausi Depot of the IBP Co. Ltd. , no workman has been employed after the termination of services of Sri Paswan and there is no person juniorto Sri Paswan working at Amausi Depot of IBP Co. , Ltd. There is no vacant post of permanent workman at Amausi Depot of IBP Co. Ltd. Sri Paswan has alreadybeen terminated hence the above reference relating to regularisation of services of Sri Bachchan Lal Paswan isinfructuous and he is not entitled for any relief under the aforesaid reference .
The Depot Manager of the opposite party has filed the written statement stating that Sri Bachchan Lal Paswan had filed a complaintdt . 24-7-02 with the Asstt. Labour Commissioner (C) , Lucknow for regularization of his services in IBP Company Ltd. Simultaneously Engineering Mazdoor Sangh also filed an application under Section 10 of the ID Act, 1947 before Asstt . Labour Commissioner (C), Lucknow to espouse the case of Sri Bachchan Lal Paswan seekingthe relief of regularisation of services of Sri Paswan. Opposing the application of the Trade Union opposite party has stated that Engineering Mazdoor Sangh isnot connected with the Petroleum Industry and it has no membership among the employees of the IBP Co. Ltd. The conciliation proceedings were held on 20-12-02 and the same had filed a reportdt . 20-12-02 was sent by the Asstt . Labour Commissioner ( C) , Lucknowto the appropriate Government on 26-12-02. It is admitted that Bachchan Lal Paswan was engaged as a casual labour on 17-3-97 on some VIP reference for cleaning work of plant/ machinery at the Depot . And no letter of appointment was issued to him . He was engaged on consolidated monthly wages of Rs . 4250. Indian Oil Corporation had no terminal at Lucknow and it used to lift the supply of oil from IBPCo. Ltd. Depot at Amausi . The Indian Oil Corporation has constructed its own supply terminal and it does not lift the supply of oil from IBP Co. Depot. As 3965 [भाग II-खण्ड 3( ii) ]
भारत का राजपत्र : जून 23, 2007/आषाढ़ 2, 1929
Oppositepartyhas filed the photo copy ofdocuments alongwith list C-16;
Hon'ble High Court as such there is no relevancy ofthe interim order and present dispute .
By filing aditional written statement the opposite 1. Photo stat copy of comlaint dt. 24-7-02 of B. L. Paswan .
partyand statedthat the workman can not claim the relief 2 Photo stat copy of application under Section 10 of ID Act filed by Engineering Mazdoor Sangh .
of regularisation of service as there are no rules in IBP Co. Ltd. for regularisation of daily wager . Sri Bachchan Lal Paswan has filed affidavit who has 3. Photo copy of reply to the application under section 10 of the Act filed by employer .
been cross-examined by the opposite party where and opposite party has filed the affidavit of Sri AP Rao , Sr. Terminal Manager , IBP Co. Ltd. Amausi Depot Lucknow.
4. Photo copy of letterdt . 26-12-02 sent by the Asstt. Labour Commissioner ( C) Lucknow to the appropriate Government.
TheGovernment of India also referred the following dispute vide reference order No. L-30012/21/2003 - IR (Misc.) dt. 3-12-03 for adjudication:
5. Photo copy of Thruput of Petroleum Product for the month of Dec. 2002.
6. Photo copy of Thruput of Petroleum Product for the month of Jan. , 2003 .
7. Photo copy of Trupt of Petroleum Product for the month of Feb .. 2003 .
"Whether the action of the management of IBP Co. Ltd. Amausi Lucknow in terminating the services of Sri Bachchan Lal Paswan S/ o Sri Chandraman Paswan casual Depot Pump Operator w.e.f. 15-1-2003 is proper and justified? If not, to what reliefthe workman concerned is entitled . ?" 8. Photo copy of the order of termination of servicedt . 3-1-2003 .
The above reference order is registered as ID No. 1/2004 between Sri Bachchan Lal Paswan Vs. General Manager IBP Co. Ltd. Lucknow.
9. Photo copy application under Section ID Act preferred by BL Paswan .
10. Photo copy of objection to the application under Section 2A of ID Act, preferred by the Employer.
On the request of representative of the worker on 7-7-05 the cross -examination of the opposite party has been written on the back of the affidavit of Sri A.P. Rao filed in I.D. Case No. 1/04 above . Several dates were fixed for the argument from15-12-05 but opposite party did not appear to forward his arguments.
11. Photo copy of interim orderdt . 28-3-03 passed in W.P. No. 1770(S/S) of 2003 preferred by Paswan.
12. Photo copy of reply to the objection preferred by Paswan.
Heard learned representative of the trade union alone and perused evidence on record and the one available of I.D. No. 1/04 stated above .
13. Photo Copy of the judgement dt . 31-7-03 passed in W.P. No. 1770 (S/S ) of2003.
14. Photo copy of permanent workman working inAmusi Depot of IBP Co. Ltd.
15. Photo copy of the judgment dt . 23-10-03 passed in W.P. No. 1175 (S/S) of 2003.
Sri Paswan the worker has admitted in the cross- examination that he was not given any appointment letter and has admitted that he was not in the list of permanent workers . He has also admitted in his cross- examination that he was engaged for misc . work and also stated that he was asked to operate pump. He has also admitted in his cross-examination that none of his juniors are working with the employer.
The witness of workman has been cross examined the representative of trade union and he has stated where ever need of work arose , then the workman was engaged. He has also stated that work of regular worker is defined where as the work of the casual labour which is different from the regular worker is taken from the casual labour , who use to assist regular worker . During the cross- exmination Sri Rao has also stated that the work is reduced considerably as Indian Oil Corpn . has established his terminal.
The trade union has filed rejoinder . It is admitted that workman was not given appointment letter at the relevant time of his appointment . The trade union has denied that there is voluntary retirement Scheme as stated by the employer . This is admitted that the employers have terminated the services of the workman on 15-1-03 . However, trade unin has submitted that services of the workman were terminated due to reason that he challenged the action of the management in not regularising the services of the workman. Further , it would not but of place to mention here that no doubt the management had paid an amount of Rs . 18770 through cheque which was attached with the aforesaid letter but since the workman has challenged the action of the management as such the same was returned to the employers vide registered letterdt. 6-5-03 . It is also submitted that writ petition has been dismissed by the
In the absence of any appointment letter by the worker from the nature of work came on record , it is proved thatworker was engaged as casual labour 17-3-97 and not asPump Operator. Worker has claimed for regularization in 3966
[PART II-SEC. 3( ii) ] THE GAZETTE OF INDIA : JUNE 23 , 2007 /ASADHA 2, 1929
the opposite party. No law has been shown by the opposite party which entitles him to claim for regularization . In the circumstances the action of the management in not regularizing the worker neither illegal nor improper. The issue istherefore decided in favour of the management and against the trade union with the result the worker is not entitled to the regularization as claimed by the trade union .
the service .Worker has not stated as to under what scheme of the employer he claims his regularisation. During the course of argument also the representativce of the trade union has not stated that there exist any statutory rule of the employer which entitled the worker for regularization. The representative of the worker has drawn my attention to the 5th Schedule of I.D. Act, 1947 Sl . No. 10 which is as under:
Lucknow 4-5-07 SHRIKANT SHUKLA, Presiding Officer नई दिल्ली , 24 मई , 2007
10. To employ workmen as " badlis " , casuais or temporaries and to continue them as such for years, with the object of depriving them of the status and privileges or permanent workinen .
का. आ. 1812. औद्योगिक विवाद अधिनियम , 1947 ( 1947 का 14 ) की धारा 17 के अनुसरण में , केन्द्रीय सरकार दामोदर सिमेन्ट एवं स्लैग लिमिटेड के प्रबंधतंत्र के संबद्ध नियोजकों और उनके कर्मकारों के बीच, अनुबंध में निर्दिष्ट औद्योगिक विवाद में केन्द्रीय सरकार औद्योगिक अधिकरण/ श्रम न्यायालय , आसनसोल के पंचाट ( संदर्भ संख्या 20/1996 ) को प्रकाशित करती है , जो केन्द्रीय सरकार को 24-5-2007 को प्राप्त हुआ था ।
The question as to whether there are any rule for regularization of casual labour in the opposite party. In case there'is, no regularization scheme has the worker can claim for regularizaiton but in the instant case since there are no rules of regularization of casual labour therefore it can not be a case of unfair labour practice . I have gone through the judgement of Hon'ble Supreme Court (2006) 4 Supreme Court cases 1 of 5 Hon'ble judges Secretary State of Karnataka and other Vs. Uma Devi and others .
[सं. एल -29011/4/96- आई आर ( एम ) ] एन. एस. बोरा , डेस्क अधिकारी
New Delhi , the 24th May, 2007
S. O. 1812. In pursuance of Section 17 of the Industrial Disputes Act, 1947 (14 of 1947) , the Central Government hereby publishes the award (Ref. No. 20/1996) of the Central Government Industrial Tribunal -cum- Labour Court, Asansol now as shown in the Annexure , in the Industrial Dispute between the employers in relation to the management of Damodar Cement & Slag Ltd. and their workman, which was received by the Central Government on 24-5-2007 .
[No. L- 29011/4/96- IR (M) ] N. S. BORA, Desk Officer
ANNEXURE
BEFORE CENTRAL GOVERNMENT INDUSTRIAL TRIBUNAL- CUM - LABOUR COURT, ASANSOL
PRESENT : Sri Md . Sarfaraz Khan , Presiding Officer Reference No. 20 of 1996
PARTIES:
The Manager, Damodar Cement & Slag Ltd. , Madhukunda, Purulia Vrs.
Itistrue that Central Government controlled industry are run by economic consideration and financial implications . In the instant case the worker accordingto the opposite party was engaged on the reference of some VIP for cleaning work of plant and machinery at the Depot . However, the opposite party has failed to mention the name ofVIP. But certainly his engagement has not been done as per prescribed procedure and it is proved that the worker wants to seek back door entry in the opposite party by filing the case of regularisation . Sri Rao has also stated that there is no vacant post of workmen in IBP Co. Ltd. and certificate to this fact is annexure 13 to the affidavit . Sri Rao has also stated in affidavit that earlier Indian Oil Corporaiton had no terminal at Lucknow and it used to lift the supply of oil from IBP Co. Ltd. Depot at Amausi . The Indian oil Corporation has constructed its own supply terminal and it does not lift the supply of of from IBP Co. Depot . As such work at Amausi Depot of IBP Co. Ltd. has been reduced, resulting into cut of expenditure of the Depot . True copies of thruput of petroleum product for the month ofDecember 2002, January 2003 , February 2003 has been filed with the affidavit annexure 1 to 3 which shows the fallingtrend. I fall to understand as to in the circumstances now the employer could be asked to be over burden with the regular employees when the work is considerably decreasing.
The Asstt . Secretary , Damodar Cement & Slag Ltd. , Wokus ' Union Madhukunda, Purulia
REPRESENTATIVES :
Since I.D. 1/2004 of Sri Bachchan Lal Paswan and IBPCo. Ltd. is still pending for award which pertains to terminated of the worker therefore the legality and illegality oftermination is not to be looked into the present case .
For the management : Sri P.K. Das , Advocate For the union (Workman) : Sri M. Mukherjee , Advocdate
Industry: Cement ,
Itisnot case of the worker that any of juniors casual labour have been regularised . It is not case of the trade union that there exists any scheme of regularization with
State: West Bengal Dated the 18-4-2007 3967 [ भाग II- खण्ड 3 ( ii) ]
भारत का राजपत्र जून 23 , 2007/आषाढ़ 2, 1929
AWARD
एल. पी. जी. के प्रबंधतंत्र के संबद्ध नियोजकों और उनके कर्मकारों के बीच , अनुबंध में निर्दिष्ट औद्योगिक विवाद में केन्द्रीय सरकार औद्योगिक अधिकरण/ श्रम न्यायालय चेन्नई के पंचाट ( संदर्भ संख्या आई डी. 378/2004 ) को प्रकाशित करती है , जो केन्द्रीय सरकार को 24-5-2007 को प्राप्त हुआ था।
Inexercise of powers conferred by clause (d) of Sub- section ( 1 ) and Sub- section 2(A) of Section 10 of the Industrial Disputes Act, 1947 ( 14 of 1947) , Government of India through the Ministry of Labour vide its letter No. L- 29011 /4/96 - IR( Misc.) dated 31-5-1996 has been pleased to refer the following dispute for adjudication by this Tribunal .
[सं. एल-30011 / 38/2004- आई आर ( एम ) ] एन. एस. बोरा , डेस्क अधिकारी SCHEDULE
New Delhi , the 24th May, 2007 "Whether the action of the management of Damodar Cement & Slag Ltd. in denying the payment of bonus from the accounting year 1982-83 to the employees ofDamodar Cement & Slag Ltd, is justified ? If not to what relief the employees /workers are entitled ? "
S. O. 1813. In pursuance of Section 17 of the Industrial Disputes Act, 1947 (14 of 1947) , the Central Government hereby publishes the award (Ref. No. I.D. 378/ 2004) of the Central Government Industrial Tribunal - cum- Labour Court , Chennai now as shown in the Annexure , in the Industrial Dispute between the employers in relation to the management of I.O.C. L.P.G. and their workman , which was received by the Central Government on 24-5-2007.
[No. L-30011/38 /2004- IR(M) ] N. S. BORA, Desk Officer
ANNEXURE
BEFORE THE CENTRAL GOVERNMENT INDUSTRIALTRIBUNAL- CUM - LABOUR COURT, CHENNAI
Monday, the 26th March, 2007
Present : K. JAYARAMAN, Presiding Officer Industrial Dispute No. 378/2004 &
Onhaving received the Order No. L-29011/4/96- IR(Misc.) dated 31-5-96from the Govenment of India Ministry of Labour , New Delhi , for adjudication of the dispute , a reference case No. 20 of 1996 was registered on 12-6-96 and accordingly an order to that effect was passed to issue notices to the respective parties through the registered post directing them to appear in the court on the date fixed and to file their written statements along with the relevant documents and a list of witnesses in support of their claims . Pursuant to the said order notices by the registered post were issued to the respective parties . Sri M. Mukherjee , Advocate and Sri P.K. Das , Advocate appeared in the Court to represent the union and the Management respectively. Both the parties filed their written statement in support of their case .
I.A. No. 1/2007 in I.D. No. 378/2004
(Inthe matter of the dispute for adjudication under clause (d) of sub- section ( 1) and sub-section 2(A) of Section 10 of the Industrial Disputes Act, 1947(14 of 1947) , between the Management of Indian Oil Corporation LPG bottling Plant and their workmen)
From the perusal of the record it transpires that the reference was fixed for final hearing on 18-4-07. The learned lawyer for the management is present . The reference was taken up for hearing . The learned lawyer for the union submitted that he has got no instruction from the said union since long time . So he is not in a position to proceed with the case further .
Between
: I.Party/Claimant
The General Secretary, Indian Oil Corporation LPG Plant Labour Union , Salem.
And
In the aforesaid facts and circumstance of the case it is notjust and proper to keep the record pending any more . The court can't go on adjourning the date after date in anticipation of the appearance of the union or the workman for giving any instruction to the lawyer . The record is pretty old one . Neither the union nor the workmen are interested to proceed further with the record . As such it is hereby .
ORDERED
1. Shri T.K. Balachandran , IOC LPG Bottling Plant Handling & Housekeeping Contractor , Salem
II.Party/Management that let a "No Dispute Awarded" be and the same is passed. Send the copies of the award to the Ministry of Labour for information and needful . The reference is accordingly disposed of.
2. Indian Oil Corporation LPG ** BottlingPlant, Karuppur , Salem, ** Impleaded as 2nd Respondent by this Tribunal vide I.A. OrderNo. 231/05 dated 18-8-05
M. D. SARFARAZ KHAN , Presiding Officer नई दिल्ली , 24 मई , 2007
Appearance:
Forthe Claimant
: M/s. D. Hariparanthaman, Advocates
का. आ. 1813.-औद्योगिक विवाद अधिनियम , 1947 ( 1947 का 14 ) की धारा 17 के अनुसरण में , केन्द्रीय सरकार आई. ओ . सी.
2733 G1/07-8 3968
THE GAZETTE OF INDIA : JUNE 23 , 2007/ SADHA 2, 1929
[ PART 11-SEC. 3 (ii ) ] For the 1st Respondent : Mr. M. R. Raghavan , Advocate
Forthe 2nd Respondent : M/ s . T.S. Gopalan & Co .. Advocate
AWARD
The Central Government, Ministry of Labour , vide Order No. L- 30011/38/2004- IR(M) dated 11-6-04 has referred thedispute to this Tribunal for adjudication . The Schedule mentioned in the order is as follows :-
"Whether the action of Shri T.K.B. Balachandran , Handling & Housekpeeing contractor for IOCL , LPG Bottling Plant , Salem in terminating the services of Shri V. Siddan w.e.f. 1-4-2003 is justified ? If not , to what relief the concerned workman is entitled ?
that his age is only 55 years on that date . Since the conciliation ended in failure , the matter was referred to this Tribunal. It is contended that as per Clause 12 of Annexure B of Settlement dated 5.3.03 under section 12(3) of I.D. Act, the age of superannuation of workman employed by 1st Respondent is 60 years and the age recorded in PF records will be taken for this purpose . Hence , the order dated 31-3-2003 retiring the concerned employee Sri Siddhan from 1-4-2003 is violative of the said settlement . Further . there are two ages as per PF records , at one place there is no mention of date of birth and it is recorded as 1950 as the year ofbirth . In another place of PF records , it is mentioned as 10-11-1952 . Since the later record is specific with date and month apart from year of birth of Mr.Siddhan , it should be taken as the date of birth of the concerned employee . Further , the benefit of doubt in favour of workman should be given, if any doubt arises. Since the action of the 1st Respondent amounts to retrenchment under section 2(00 ) of the I.D.Act and since the mandatory conditions prescribed under section 25F of the I.D.Act were not complied the termination is void abinitio. Therefore , the Petitioner union prays to pass an award in favour of the concerned employee .
2. After the receipt of the reference , it was taken on file as I.D. No. 378/2004 and notices were issued to both the parties and they have entered appearance through their advocates and , filed their Claim Statement and Counter Statement respectively. After that the Petitioner has filed a petition to implead the 2nd Respondent and it was allowed and the 2nd Respondent is impleaded as a party to this dispute.
3. The allegations of the Petitioner in the Claim Statement are briefly as follows:
The Petitioner is a trade union registered under Trade Unions Act, 1926 and it is the only union representing all the contract workmen employed in LPG plant of 2nd Respondent at Salem and the 1st Respondent is a contractor in Handling & Housekeeping in LPG Plantat Salem under 2nd Respondent . The 1st Respondent namely contractor has retired Mr. V.Siddhan , a workman employed by him in LPG plant by an order dated 31-3-2003 w.e.f. 1-4-2003 on the ground that he reached 60 years the age of superannuation as per the PF records . The Petitioner Union sent a letter dated 10-4-03 to the Factory Manager of 2nd Respondent and also 1st Respondent namely contractor stating that the date of birth of Sri V. Siddhan as per nomination and declaration submitted on 31-10-06 under P.F. Act is 1950 and as per another declaration submitted on16-4-01 , the date of birth is 10-11-1952 and therefore , the Petitioner Union requested the Respondent to reinstate Sri V.Siddhan into service with all benefits as he did not reach 60 years . Since there was no reply , the Petitioner union raised the industrial dispute regarding non - employment of Sri V. Siddhan before Assistant Labour Commissioner (Central) , Chennai and he advised in conciliation talks that the 1st Respondent should arrange to get medical certificate as to the age of Mr.Siddhan through Govt . Doctor at Salem and also requested that he should be reinstated in service if he is not 60 years as per the certificate . Since the 1st Respondent did not take any steps in this regard, the Petitioner union got Mr.Siddhan examined by a Govt . Doctor . and obtained medical certificate in which it is stated
4. As against this , the 1st Respondent in its Counter Statement contended that he had taken the contract of handling & house keeping works at LPG bottling plant of IOC at Salem through work order No. SBP /HAC/2002-03 dated 31-7-2002 for the period from 31-7-02 to 31-7-03 for the period of one year and he had engaged 52 contract workmen out of 72. The contract workmen who are available at site and whichever contractor takes up the job will have to engage these contract workmen only and these contract workmen are engaged on daily wages on rotation basis and these workmen were not brought by the ist Respondent . The age of superannuation of these contract workman is 60 years . The concerned employee namely Mr.V.Siddhan since completed 60 years of age , he was informed that his period of employment had come to an end and he was further informed that his age was reckoned on the basis of PF records . In the meantime , the 2nd Respondent has informed the 1st Respondent that the work order placed on him would be pre -closed on 31.5.2003 . The work order came to a close two months prior to the appointed date. Thus , the 1st Respondent ceased to be the contractor . Subsequent to superannuation, the Petitioner union has raised an industrial dispute before Assistant Labour Commissioner ( Central) on the ground that Sri V.Siddhan had not completed 60 years of age and his termination was Wrongful . In the mean time, the 1st Respondent addressed a communication dated 26.9.2003 and 15.10.03to the Dean , Govt . Hospital , Salem and requested them to ascertain the age of the concerned employee Sri V.Siddhan on the basis of medical examination. In the mean time , the dispute raised by the concerned employee was taken on file and on failure of conciliation, the matter was referred to this Tribunal for adjudication .
[ भाग II-खण्ड 3 (ii ) ]
The age of concerned employee as 60 years was determined on the basis of P.F. records . Hence the dispute raised alleging termination is not valid in law . The 1st Respondent's contract made to be closed w.e.f. 31-5-2004 and therefore , the 1st Respondent cannot be made liable to answer the claim of the Petitioner . Further , the 1st Respondent cannot also be termed as an ' industry ' in order that valid claim could be made against him before this Tribunal . The allegation that the concerned employee isonly 55 years is incorrect. The order retiring the Petitioner on 31-3-2003 is not violative of settlement dated 5-3-2003 . It cannot be said that the action of the 1st Respondent amounts to victimisation and malafide . Therefore, the 1st Respondent prays that claim may be dismissed .
5. In the Counter Statement , the 2nd Respondent contended that this Respondent is covered under Contract Labour (Regulation & Abolition) Act. The 1st Respondent was one of the licenced contractors and he ceased to be a contractor after the expiry of contract period during which Mr.Siddhan was employed. The 2nd Respondent not being the employer of Mr. Siddhan , 2nd Respondent is not answerable to the claim of the Petitioner . Even if for any reason, the action of the 1st Respondent in retiring the concerned employee Sri V. Siddhan is found to be not justified or that he is entitled to any relief, the liability of 2nd Respondent cannot extend beyond the period of contract that it had entered into with the 1st Respondent . Therefore , neither the 1st Respondent nor the 2nd Respondent is answerable to the claim of the concerned employee after the period of contract . Hence , the 2nd Respondent prays that the claim may be dismissed with costs.
6. In these circumstances , the points for my consideration are-
(i) "Whether the action of the 1st Respondent in terminating the services of Sri V. Siddhan w.e.f. 1-4-2003 is justified ?
(ii ) To what relief the concerned workman is entitled?"
Point No. 1:
7. The admitted case of the Petitioner and the Respondent is the concemed employee namely Sri Siddhan is a contract labour employed under the 2nd Respondent through the 1st Respondent and the 1st Respondent through his order dated 31-3-2003 has retired the concerned employee with effect from 1-4-2003 on the ground that he reached 60 years namely the age of superannuation as per Provident Fund records .
8. On behalf of the Petitioner , it is contended that the concerned employee namely Sri V. Siddhan has not completed the age of 60 years and his date of birth is only 10-11-1952 and therefore the Petitioner union requested the Respondent to reinstate the concerned employee into service with all benefits . As against this , the 1st Res-
3969
भारत का राजपत्र जून 23 , 2007/आषाढ़ 2 , 1929
pondent contended that he had taken the contract of Handling & House keeping works of 2nd Respondent/ Management through a work order dated 31-7-2002 for a period of one year and the 2nd Respondent subsequently, informed him that the work order placed on him would be pre-closed on 31-5-2003 and even his contract had come to a close with effect from 31-5-2004 . It is his further contention that the concerned employee has been superannuated on completion of 60 years and the age of 60 years was determined on the basis of P.F. records . Therefore, the termination is valid in law. It is also further contended that the 1st Respondent cannot be termed as 'industry' in order that a valid claim could be made against him before this Tribunal . Though the 1st Respondent has addressed a communication dated 26-9-2003 and 15-10-2003 to the Dean, Government Hospital , Salem and requested them to ascertain the age of the concerned employee on the basis of medical examination , the Petitioner union has taken up the matter before Assistant Labour Commissioner (Central ) and the matter was referred to this Tribunal and in no way, he is responsible for the grievance ofthe Petitioner union .
9. The 2nd Respondent, in turn contended that he is the principal employer and therefore , he is not responsible for the grievance alleged by the Petitioner union and since the 2nd Respondent not being an employer of the concerned employee , the 2nd Respondent is not answerable to the claim of the Petitioner . Even if, for any reason the action of the 1st Respondent in retiring the concerned employee is found to be not justified or that he isentitled to any relief, the liability of the 2nd Respondent cannot be extended beyond the period of contract that it had entered into with the 1st Respondent and therefore, he alleged that he is not liable for any relief in this dispute .
10. In this case , the General Secretary of the Petitioner union was examined as WW 1 and 9 documents were marked on the side of the Petitioner . As against this , 1st Respondent examined himself as MW 1 and filled documents which are marked as Ex . Ml to M4 . Ex . W1 is the copy of 12 (3) settlement entered into between the Petitioner and the Respondent / Management dated 5-3-2003 . Ex. W2 is the copy of the letter sent by Petitioner union to the Factory Manager of the 2nd Respondent dated 10-4-2003 . EX.W3 is the copy of dispute raised by the Petitioner union before Assistant Labour Commissioner (Central) . EX.W4 is the copy of complaint made by Petitioner union before Assistant Labour Commissioner (Central). Ex .W5 is the copy of letter sent by Petitionp union to Manager of LPG Plant of 2nd Respondent. Ex. W6 is the copy of failure report submitted by Assistant Labour Commissioner (Gentral) . Ex. W7 is the copy of nomination and declaration form given by concerned employee dated 30- 10-1996 under P.F. scheme. Ex. W8 is the copy of nomiation and declaration form given by concerned employee dated 16-4-2001 . EX.W9 is the copy of medical certificate given by theDoctor at Salem Hospital dated 1-10-2003.
[PART II-SEC. 3 (ii) ] 3970
THE GAZETTE OF INDIA : JUNE 23 , 2007/ SADHA 2 , 1929
11. On the side of the Respondent, first document filed by the Respondent is copy of Form No. 9 under Employees Provident Fund Scheme, 1952, which contains the names ofworkmen and also date of birth which is given/ maintained by 2nd Respondent. EX. M2 is the copy of letter sent by 1st Respondent to the Hospital at Salem dated 26-9-2003 . EX.M3 is the copy of another letter sent by 1st Respondent to Hospital at Salem dated 15-10-2003 . EX.M4 is the copy of proof of delivery of the said letter .
and W8, in which in Ex . W7 it is mentioned only the year of birth as 1950 and in Ex.W8 the date of birth was clearly given by the concerned employee and he has signed this declaration . Though there is no proof to show how this date of birth was given by the concerned employee and there is no substantial evidence to establish that the date ofbirth mentioned in Ex. W2 alone is correct , I find in this case we have to see whether the order of termination given by the 1st Respondent on the ground that he was superannuated namely he has reached 60 years is correct or not .
15. In this case , since the employer namely the 1st tespondent has not established how he has come to the conclusion that the concerned employee has reached sixty yearswithout any proof, I find the order of terminating the services of concerned employee namely Sri V. Siddhan by the 1st Respondent is not justified.
The next thing to be decided in this case what is the age of concerned employee at the relevant period ?
12. Learned counsel for the Petitioner contended that there are two ages as per provident fund records and at one place in declaration , there is no mention of date of birth and only the year of birth recorded as 1950 and in another declaration of P.F. records , it is mentioned as 10-11-1952. As against this , though the Respondent produced Farm 9 , in which entry No. 93 which relates to the concerned employee Sri V. Siddhan , it is mentioned as 3-1-1942 as date of birth . The Respondent has not produced any evidence to show how the date of birth mentioned in Ex. Ml was recorded and there is no signature of the concerned employee nor there is any proof to show that this date of birth is the real date of birth of the concerned employee . As against this , copy of declaration given by the concerned employee to the P.F. records shows two ages. Since the later record namely declaration given in the year 2001 is specific with the date and month apart from the year of concerned employee's name which should be taken as date of birth of Sri V.Siddhan . Further , the benefit of doubt in favour of workmen should be given , if any doubt arises . Hence , the date of birth of Sri V.Siddhan must be taken as 10-11-1952 by this Tribunal and the relief must be granted to the concerned employee .
16. Though on the side of the Petitioner Ex. W9 namely certificate given by the Doctor at Salem produced before this Tribunal , the said certificate was given only on the appearance of the concerned employee and also on his own showing namely the concerned employee . Here again , there is no proof how the Doctor has come to the opinion that the Petitioner is only 55 years during the relevant period. Therefore , I am not inclined to accept the contention that the concerned employee has completed only 55 years during the relevant period. But, in his own admission , the Petitioner has made that his date of birth as 10-11-1952 as perEx . W2 . Out of these documents , we can take the date ofbirth as 10-11-1952 because the benefit of doubt should be given in favour of the workman , if any doubt arises with regard to his age . Therefore , I take the date of birth of Sri V. Siddhan as 10-11-1952 and I find the order of termination made by the 1st Respondent dated 1-4-2003 is not justified.
17. Then agarian , learned counsel for the 1st Respondent contended that the 1st Respondent cannot be termed as " industry " in order that valid claim should be made against the 1st Respondent before this Tribunal .
18. But, I find there is no point in the contention of the learned counsel for the isl Respondent because , it is not disputed that 1st Respondent contractor carried on the business from his own business premises or that he was drawing commission on the basis of contract agreement with the 2nd Respondent . Therefore , I find no doubt that the 1st Respondent can also be said to be an establishment and is responsible for the payment of wages to the concerned employee .
13. But , as against this , the 1st Respondent contended that though he has taken the contract for handling and house keeping works in the contract , the work has to be executed by engaging a contract workmen , who are available at the site and further whichever contractor takes up the job will have to engage these contract workmen only . Further , though he has taken the said contract of handling & house keeping work , the said contract was ended on 31-5-2004 and therefore , he cannot bemade liable to answer the claim of the concerned employce . It ishis further contention that the 1st Respondent cannot be termed as " industry " in order that a valid claim could be made against him before this Tribunal. The 1st Respondent further contended that the age of the concerned employee was determined on the basis of P.F. records namely Ex . M 1 and therefore , the termination is valid in law . But, it is not stated as to how the date of birth mentioned in Ex.M 1 has arrived at and he has not established before this Tribunal from which record the date of birth mentioned in Ex.Ml was entered into . As such , I find there is no valid contention made by the 1st Respondent with regard to the date of birth mentioned in Ex . MI .
19. Then again , on behalf of the 2nd Respondent it is contended that even if for any reason , the action of the 1st Respondent in retiring the concerned employee 14. On the other hand , the concerned employee has produced declaration under P.F. scheme namely Ex.W7 [ भाग II- खण्ड 3( ii) ]
3971
भारत का राजपत्र जून 23 , 2007/आषाढ़ 2, 1929
Sh . V. Siddhan is found to be not justified or he is entitled to any relief, the liability of 2nd Respondent cannot be extended beyond the period of contract it had entered into with the Ist Respondent .
20. I find some force in the contention of the 2nd Respondent because it is admitted by the Petitioner and also by the 1st Respondent that his contract with the 2nd Respondent ended on 31-5-2004 . Beyond this period, we cannot ask the 1st Respondent to pay the wages to the contract labour because the contract has admittedly ended on 31-5-2004. Therefore , I find this point that the action of the 1st Respondent namely the Contractor for the 2nd Respondent LPG Bottling Plant in terminating the services ofthe concerned employee with effect from 1-4-2003 is not justified and he is liable to pay wages upto 31-5-2004.
21. In view of the above findings , IA. No. 1/2007 filed by the Petitioner for issue of summons is dismissed as infructuous .
Point No. 2 :
23. The next point to be decided in this case is to what relief the concerned employee is entitled?
22. In view of my foregoing findings , the 1st Respondent is liable to pay wages to the concerned employee upto 31-5-2004 as per the contract entered into under Ex . W1 . In case , if the 1st Respondent fails to pay the said wages to the concerned employee , the principal employer namely the 2nd Respondent/Management is bound to pay the same , No Costs.
23. Thus , the reference is answered accordingly .
(Dictated to the P.A. , transcribed and typed by him , corrected and pronounced by me in the open court on this day the 26th March , 2007.)
K. JAYARAMAN, Presiding Officer Witnesses Examined :-
For the Claimant :
WW1 Sri C. Ramakrishnan
MW1 Sri T. K. Balachandran For the Respondent
Documents Marked :
Forthe I Party/Petitioner:
Ex. No. Date Description
5-3-03
W1 Xerox copy of the 12(3 ) settlement entered intoBetween 1st Respondent and 2nd Respondent
10-4-03
W2 Xerox copy of the letter sent by Petitioner toFactory Manager of LPG Plant
W3 13-5-03 Xerox copy of the dispute raised by Petitioner before Assistant Labour Commissioner (Central) 18-9-03
W4 Xeroxcopy ofthe complaint made by Petitioner Before Assistant Labour Commissioner (Central)
6-10-03
W5 Xerox copy of the letter sent by Petitioner to the Manager of LPG plant
23-3-04
W6 Xerox copy of the failure of conciliation report
W7 30-10-96 Xerox copy of the nomination & declaration form
W8 16-4-01 Xeroxcopyof the nomination & decal- ration form
W9 1-10-03 Xerox copyof the medical certificate For the II Panty/Management :
Date
Ex . No.
Description
M1 Nil Xerox copy of the Form 9 under the The Employees Provident Fund Scheme, 1952
26-9-03
M2 Xerox copy of the letter from 1st Respondent to Salem Hospital 15-10-03
M3 Xerox copy of the letter from 1st Respondentto Salem Hospital M4 Nil Xerox copy of the proof of delivery नई दिल्ली, 24 मई , 2007
का. आ. 1814. औद्योगिक विवाद अधिनियम , 1947 (1947 का 14 ) की धारा 17 के अनुसरण में , केन्द्रीय सरकार साऊथ इंडिया माईन्स और मिनरल इंडस्ट्रीज लिमिटेड के प्रबंधतंत्र के संबद्ध नियोजकों और उनके कर्मकारों के बीच , अनुबंध में निर्दिष्ट औद्योगिक विवाद में केन्द्रीय सरकार औद्योगिक अधिकरण/ श्रम न्यायालय , चेन्नई के पंचाट ( संदर्भ संख्या आई डी. 38/2005 ) को प्रकाशित करती है , जो केन्द्रीय सरकार को 24-5-2007 को प्राप्त हुआ था। [सं. एल-29012/16/2005 - आई आर ( एम ) ] एन. एस. बोरा , डेस्क अधिकारी New Delhi , the 24th May, 2007
S. O. 1814. In pursuance of Section 17 of the Industrial Disputes Act, 1947 ( 14 of 1947) , the Central overnment hereby publishes the award (Ref. No. I.D. 38/ 2005) of the Central Government Industrial Tribunal-cum- Labour Court, Chennai now as shown in the Annexure , in the Industrial Dispute between the employers in relation to the management of South India Mines & Minerals Ind. Ltd. and their workmen , which was received by the Central Government on 24-5-2007 .
[No. L-29012/ 16/2005 - IR(M) ] N. S. BORA, Desk Officer 3972
THE GAZETTE OF INDIA : JUNE 23 , 2007/SADHA 2 , 1929
[PART II-SEC. 3 ( ii) ] ANNEXURE
BEFORE THE CENTRAL GOVERNMENT INDUSTRIALTRIBUNAL- CUM-LABOUR COURT, CHENNAI
Thrrsday, the 29th March, 2007
PRESENT : K. JAYARAMAN, Presiding Officer
Industrial Dispute No. 38/2005
(Inthe matter of the dispute for adjudication under clause (d) of sub- section ( 1) and sub- section 2 (A) of Section 10 of the Industrial Act, 1947 (14 of 1947) , between the Management of the South India Mines & Minerals Ind. Ltd. and their workmen)
BETWEEN
Shri K. S. Uthandaraman
: I Party/Petitioner
And
: II.Party/Management
The Executive Director , The South India Mines & Minerals Ind . Ltd. Sankar Nagar, Tirunelveli.
APPEARANCE :
For the Petitioner
: M/ s . Row & Reddy , Advocates
: Mr. S. Sadagopan
For the Management
Advocate
AWARD
The Central Government, Ministry of Labour , vide Order No. L-29012 / 16/2005 - IR (M) dated 6-4-2005 has referred the dispute to this Tribunal for adjudication. The Schedule mentioned in the order is as follows :
"Whether the claim of Sri K.S. Uthandaraman for reinstatement with back wages and continuity of service against the management of South India Mines &Mineral Industries Ltd. (SIMMINDS ) , Sankar Nagar, Tirunelveli is legal and justified ? If not, to what relief the workman is entitled to ?"
2.After the receipt of the reference , it was taken on file as I.D.No.38 /2005 and notices were issuedto both the parties and both the parties entered appearance through their advocates and filed their Claim Statement and Counter Statement respectively .
3. The allegations of the Petitioner in the Clain Statement are briefly as follows:
convenience of the Respondent, the Respondent has redesignated the Petitioner for several times , though he had worked in clerical job . He was not provided with power ofappointment, power to take disciplinary action and power ofdismissal . He was only a workman as per Section 2( s) of the I.D. Act . The primary and basic duties and dominant purpose of employment must be taken into consideration andthe designation given to the Petitioner is not a decisive one and the Petitioner has worked in clerical job maintaining and writing accounts only . The appointing authority of the Respondent/Management is only Managing Director and as per Memorandum of Articles of Association , the Managing Director alone has got power to pass final orders . The Executive Director has no power to pass final order and this power cannot be delegated and no resolution was passed before passing final order in this ' case . While so, the Executive Director of the Respondent has passed an orderdated 25-2-2004 stating that the Petitioner is no longer required. Even this order of Executive Director is illegal , void , ab initio . The Respondent/Management is an industry / factory as per standing orders and the Executive Director is not an employer and has no power to pass such final order. The Respondent is doing business in limestone cum mines , and as per Section 17 of Mines Act , only person having prescribed qualification can be appointed as Manager . The Petitioner is not a competent person as prescribed in Mines Act and cannot be appointed as AGM (mines) or any other statutory post . Hence the various orders passedby Executive Director of Respondent are all inutter violation of Mines Act and they are unenforceable in law. At the time of redesignation , no agreement regarding terms and conditions were fixed and the Petitioner had been doing accounts clerical job and pinpointed the serious irregularities of Sri R. Rajagopal . Executive Director. In order to victimize the Petitioner , the said person has passed various orders within a short span of period from 21-6-2001 to 30-09-2003 and he has passed the orders in violation of principles of natural justice . Before issuing the final order dated 25.2.2004, the Respondent had not issued any charge sheet . Nodomestic enquiry was conducted observing principles of natural justice . No compensation as per Section 25F of the ID . Act was provided. Hence , the order passed by the Respondent/ Management is in violation of section 25F of the I.D.Act . Hence , the Petitioner raised a dispute before the labour authorities and since the conciliation ended in failure , the Government has referred this dispute for . adjudication. Hence , for all these reasons, the Petitioner, prays this Tribunal to pass an award directing the Respondent to, reinstate him in service with continuity ofservice and all other attendan: benefits .
4. As against this , the Respondent in its Counter Statement alleged that this claim is not maintainable. The Petitioner is a qualified person with B.Sc. , ( Maths ) B. Ed (Maths ) and also lower grade in Accountancy . Though he entered the service of Respondent in clerical The Petitioner was appointed by Agricultural farms Ltd. , Sankar Nagar as per order dated 20-08 77 as clerical assistant on probation for a period of one year and he joined the duty on 2.9.1977 and was confirmed as a Senior Clerk as per order dated , 1-9-78 . The Agricultural Farms Ltd. subsequently changed as the South India Mines & Mineral Industries Ltd. The Petitioner was transferred to various posts and served in that concern and to suit the 3973 [ भाग II- खण्ड 3 (ii ) ]
भारत का राजपत्र जून 23 , 2007/आषाढ़ 2, 1929
redesignated the Petitioner's job for several times and thus , they wanted to keep the Petitioner away from doing his usual clerical/ accounts work involving financial transaction of which less said is better in view of the irregularities committed by the Respondent and pinpointed by the Petitioner . It is wrong to contend that the Petitioner had exercised supervision and control over his subordinate staff and he was not empowered to initiate disciplinary action against any erring staff . Duties listed in order dated 1-4-2003 were handled by specific competent persons appointed for that purpose under various acts and rules . He has performed only his job of clerical nature . Telephope charge reimbursement was one of the beneficiaries and that will not presume that the Petitioner has exercised supervisory nature of work . Circulation of office order is not a supervisory nature of work . The Petitioner did not possess any technical qualification in mining . The assignments made by the Respondent/Management to the Petitioner require technical knowledge and understanding of various aspects of competent person in mining . Such posts were redesignated to the Petitioner with an ulterior motive to dismiss the Petitioner from service . The minimum wages as per Cement Wage Board fixed in Respondent is Rs.8000 per month . Hence , the monthly wages of Rs . 17 , 973 had no relevance at all in deciding the issue . Further mere endorsement in leave application will not prove the supervisory nature of work . The Petitioner was not authorised to sanction leave to any staff . The final order waspassed as per service conditions dated 20-8-77 , which isfor clerical job and there was no other service conditions issued to the Petitioner . Mere nomenclature of designation will not prove the supervisory nature . Hence, for all these reasons , the Petitioner prays that an award may be passed inhis favour .
6. In these circumstances , the points for my consideration are :-
(i) "Whether the Petitioner's claim for reinstatement with back wages and continuity of service against the Respondent/ Management is legal and justified ?
(ii ) "To what relief the Petitioner is entitled ? "
Point:
cadre in the year 1977, subsequently , he was designated as an officer namely Deputy Accountant as early as from 1-1-87 . Then he was redesignated as Manager (Accounts) and placed in managerial Scale III w.e.f. 1-6-94 and he was also entitled for reimbursement of conveyance bills and also LTA of Rs . 3500 which are fringe benefits and not applicable to workman of the Respondent/Management . Evenin the year 2000 the Board of Directors of the company passed a resolution on 26-6-2000 authorising the Petitioner among two others to operate the accounts with Karur Vysya Bank Ltd. Palayamkottai and to be an authorised signatory for various financial transactions on behalf of the company . Subsequently, he was redesignated as Senior Manager (Finance & Accounts) w.e.f. 6-6-2001 with total salary of Rs . 16,730 . Further his post was redesignated as Senior Manager (Personnel & Admn. ) w.e.f. 12-11-2001 . Even on 30-9-2003 the Executive Director of the Respondent issued orders specifying the duties and responsibilities of the Petitioner as AGM . From all these things , it is clear that the Petitioner cannot be considered as a workman under Section 2(s) of the I.D. Act. Further , the Petitioner had exercised powers in supervisory capacity and controlled the subordinate staff in Ramayanpatti quarry . Again the Petitioner was redesignated as Assistant General Manager (Personnel & Mines Admn. ) w.e.f. 1-4-2003 and in that order itself the duties and responsibilities have been specified and he was also permitted to get reimbursement of telephone charges upto Rs.1000/ bimonthly w.e.f. 1-4-2003. He has also circulated office orders with his initial among the staff under his control . Further , the Petitioner was asked to call for explanation from workers regarding long absenteeism . Thus , from all these documents , it is clear that he has exercised managerial functions and not worked as a clerical staff as alleged by him. He was discharged from his duties w.e.f. 25-2-2004 as per the terms and conditions governing him and he was also paid one month salary of Rs.17, 973 by means of cheque and he had encashed the same . Since he is not a workman as per I.D. Act this claim is not maintainable . It is also pertinent to note that the Central Government Ministry of Labour issued the order of reference datcd 6-4-2005 referring the dispute for adjudication to this Tribunal , but , on the other hand, the conciliation officer has sent the failure report only on 31-5-2005 . Therefore, the reference itself is not as per provisions of I.D. Act . The Petitioner has received Rs . 17,973 as salary and he having drawn such high salary, cannot claim the status of workman . Since the Petitioner is not entitled to the protection under I.D. Act, this petition is not maintainable and prays that the claim may be dismissed with costs.
5. Again, the Petitioner in its rejoinder contended that the status of Petitioner as workman has already been upheld in the reference itself and this Court had to adjudicate the claim of reinstatement with back wages and continuity of service alone . The Respondent/Management
7. In this case , it is an admitted fact that the Petitioner was appointed as a clerical assistant on 20-8-77 on probation and he was subsequently, confirmed as Senior Clerk and his salary was periodically revised by the Respondent /Management formerly known as Agricultural Farms Ltd. and he was transferred to various posts . But the Petitioner contended that to suit their convenience , the Respondent has redesignated the Petitioner , though the Petitioner worked in clerical jobs and he has not provided with any power of appointment , power to take disciplinary action and power of dismissal and the nature ofduties conferred on him will determine that he was only 3974
THE GAZETTE OF INDIA. JUNE 23 , 2007 / SADHA 2 , 1929
[PART II-SEC . 3 ( ii ) ]
subordinates and it did notfail within the scope of Section 2(s)(iv) ofthe Act and held the person is only a workman . " Relying on these decisions learned counsel for the Petitioner contended that on 20-8-1997 appointment order was issued to the Petitioner for clerical assistant and he joined as a Clerical assistant or 2-9-77 and on 4-7-94 his post was redesignated as Manager (Accounts ) . Though subsequently, his post has been redesignated several times , he has done only the clerical weak and though his salary was increased periodically, it cannot be said that merely because he has received high salary , he is not a workman . The redesignation of Manager (Accounts ) was extended for completion of 15 years and continuing the 17th year of service to do the same clerical duties and he was not provided with any power or change in duties . The redesignation in the newly introduced scale was on account ofthe fact that the Petitioner was stagnating in the highest clerical grade namely VII grade in the Cement Wage Board implemented by the Respondent company and the allowances mentioned are only against the various allowances under special benefits enjoyed in VII grade extended by the company to all their workmen . Though it is contended that he has posted as Senior Manager ( Personnel & Admn. ) the Petitioner was not provided with any power and assigned in the order and he has not exercised the duties supervision and control over his subordinate staff and he was not empowered to initiate disciplinary action against erring staff . Though it is alleged thatall the duties listed in the order dated 1-4-2003 were and are handled by specific competent persons appointed for that purpose under various acts , rules and regulations and he has performed his job only as a workman . Though it is alleged that the telephone charge reimbursement was allowedby the management , which allowance was not given to workman under the Respondent/ Management , it will not presume that the Petitioner had exercised supervisory nature ofwork . Even in letter dated 9-10-2003 it is explained that the Petitioner was not vested to take power to take disciplinary action against the workmen . It is admitted by MW1 himself that the Cement Wage Board fixed the wages as Rs . 8000 per month and hence , the monthly wages ofRs . 17,973 which alleged to have been received by the Petitioner has no relevance at all to decide whether the Petitioner is a workman or worked in managerial cadre . Further , the Petitioner was not authorised to sanction leave to any staff. Therefore , when the primary and basic duties anddominant purpose of employment is considered , the Petitioner has worked only in clerical cacre and therefore , mere nomenclature of designation will not prove that the Petitioner is not a workman. In this case , the Petitioner examined not only himself but also one Sri A.S. Kumar who worked as Executive Director of the Respondent Management and who has served for 16 years as Executive Director and he has stated that the Petitioner has worked as a clerk and he was doing only clerical work involving financial accounting besides material handling and other
dir gs and service . Tribunal aworkman as per Section 2( s) of the I.D. Act. Learned counsel for the Petitioner contended that the prunary and basic duties and dominant purpose of empl : vrucht must be taken into consideration in determining whether the person is a workman or working in supervir capacity and the designation given to the Petitioner is no decisive one and he was never anthorised to take independent decision with no power of command and he worked in clerical job maintaining and writing accounts only and therefore, at no stretch of imagination, he can be said he worked in Manager capacity. He relied on the rulings reported in 1999 I CLR 1156 SUNITA B. VATSARAJ VS. KARNATAKABANK LTD . AND ANOTHER wherein the Petitioner in that ' case was appointed as clerk ramee in the year 1971 and after successful training she was confirmed and promoted as officer grade lil in the year 1978 and she joined Bandra branch in her protmotion post and worked as Branch Manager and power of attorney was executed in her favour by the bank . Thereafter , however, she was involved in disciplinary pro after domestic enquiry, she was dismissed Shequestioned the dismissal order . The Industr . allowed the Respondent's plea and dismissed Inthe Writ Petition, the Bombay High Court held that she is only a workman and as such reversed the order of the Tribunal , wherein it is stated that "firstly, dominant purpose of the employrent is relevant and not some additional duties which may be performed by the employee; secondly, it is not the designation but the nature of duty; thirdly , whether the employee can bind the company in the matter of some decisions taken on behalf of the company; fourthly, the nature of supervisory duties performed by the employee whether it includes directing the subordinates and so on. " Considering all these factors , the High Court has come to the conclusion that the Petitioner in that case though designated as an officer as per power of attorney , was in fact , left to the situation of carrying out the work of clerical nature including the checking up of the work done by other workers in her own section and therefore , itheld that Petitioner is a workinan . The next decision relied on by the learned counsel for the Petitioner is reported in 2006 6 SCC 548 ANAND REGIONALCO - OP . OIL SEEDS - GROWERS' UNION LTD Vs. SHAILESHKUMAR HARSHADBHAI SHAH wherein the Supreme Court while considering whether the person who has called as workman , it held that " in determining the nature of work, the essence of matter should be considered and designation of the employee or the name assigned to his class should not be given undue importance . The primary duties performed by him are more important and the existence of subordinates whose work is required to be supervised is a sine qua non to prove supervisore work. An employee, incharge of a section and that 100 a small one in the quality control department of an oil seed growers' co- operative society, without any authority to initiate departmental proceedings against the 3975 [भाग II- खण्ड 3( ii) ]
भारत का राजपत्र : जून 23 , 2007/आषाढ़ 2, 1929.
clerical matters with specific decision making powers vested with him namely the Executive Director and the Petitioner has never worked in supervisory capacity which prove clinchingly prove that the Petitioner has worked only as a workman and not in supervisory capacity. Learned counsel for the Petitioner further contended that the General Secretary of India Cements Employees Union who was examined as WW3 , has also stated that the Petitioner has worked only in clerical cadre and the Petitioner has not exercised any supervisory control in a post which involved power or authority or taking disciplinary action against the employees . Thus , the Petitioner established the fact that he has worked only in clerical cadre by producing clinching documentary evidence and also by oral evidence and therefore , this Tribunal has to come to a conclusion that the Petitioner has worked only as a workman and the Respondent /Management has dismissed the Petitioner without any rhythm and without following the mandatory provisions of Section 25F of the Act and has to reinstate the Petitioner with all benefits .
instructions given by the Petitioner to quarry wherein he has issued administrative instructions to Ramayanpatti limestone quarry on 9-8-02 , wherein he has given instruction to staff and log boys in particular to avoid mistakes in future and he has also called for despatch particulars . Similarly, on 12-8-2002 the Petitioner had issued instructions to Manager Ramayanpatti limestone quarry and he has directed to take necessary action against the person for the lapses . From these documents , it is clear that the Petitioner has exercised managerial power as Assistant General Manager (Mines ) and subsequently he was redesignated as AGM (Personnel & Mines ) General Administration w.e.f. 1-4-2003 under Ex. M 9 wherein specific dutieswere enlisted and all the duties specified therein are ofmanagerial nature and not of a workman's duties . It is admitted that the Petitioner was reimbursed telephone chargesupto the limit of Rs. 1000 bimonthly from 1-4-2003 and it can be seen that no workman was permitted to have such a privilege of reimbursement of telephone charges . It is admitted that office orders were circulated by him to subordinate staff. If really , he worked as a workman , he can only receive the circulars and not circulate the circulars . Though the Petitioner alleged that he has not exercised anycontrol or supervision over the staff, from Ex. M 13 , it is clear that the Petitioner was authorised to call for explanation from workmen for their absenteeism . Thus , he has given power to exercise control over the subordinates . From Ex. M 15 in which the Mines Manager has applied for leave for one day and the Petitioner has made a lengthy notewhich clearly proves that he has exercised supervisory powers over the subordinates and the Respondent has produced number of documents under Ex . M 16 series that the Petitioner has authorised to draw materials from stores and has issued slips for drawal of materials and he has also signed acquittance register only as AGM (Personnel & Admn.) and he has received total salary and paid income tax to the tune of Rs . 4000 per mensum. All these clearly prove that he has exercised powers only as managerial cadre and notworked as a workman . He has countersigned the daily report containing various details of usage of machinery, materials , fuel and lubricants , which was prepared by the clerk and which establish that he has not done any clerical duties , on the other hand , he worked only in a supervisory capacity . All these documents were admitted by Petitioner but his only contention is that he put his signature and prepared all these documents on the direction of Executive Director which he has taken onlyto get over the situation . Though it is alleged that Sri A. S. Krishnan , who worked as Executive Director has stated that the Petitioner has worked only as a clerk and not as a managerial capacity, the said witness has admitted that only during his period the documents under Ex.M23 to M 29 were passed by him . Even from Ex. M 23 which is anoffice order dated 4-7-94 issued by WW2, it is clear that the Petitioner has been redesignated as Company Manager in the newly introduced Managerial Scale III . Even after 8. But , as against this learned counsel for the Respondent contended that though the Petitioner was appointed as a clerk in the Respondent/ Management , subsequently , his post has been redesignated as Manager (Accounts) which is a managerial scale post . Subsequently he was employed as Assistant General Manager (Mines) under Ex . M 35 of the Respondent and he wasdrawing monthly salary of Rs.17, 973 at the time of discharge from service . The Petitioner's predominant duties were of managerial nature as mentioned in detail in the order . He has not worked as a common workman but he was highly qualified namely B.Sc (Maths) & B.Ed. (Maths) and lower grade in Accountancy . The Petitioner was subsequently authorised to operate a current account in Karur Vysya Bank , Tirunelveli by a Board Resolution under Ex . M 30 which act no workman cando . Subsequently, he was a Senior Manager ( Finance & Accounts) with the monthly salary of Rs . 16,370 on 30-9-2003 . He was redesignated as AGM (mines) and his duties and responsibilities were specified therein namely under Ex. M6 , wherein it is clearly stated that his duties are ordering of explosives , supervision and distribution of explosives , checking of stock position of explosives at the magazine as and when necessary, supervision of explosives issued to contractors and proper return of unused explosives and control over the staff working in quarry and supervision of work done by staff and initiate action wherever lapses are notices and supervision of security personnel and also undertake surprise check of loads taken by contractors at frequent intervals ; monitoring of leave application of mines and office staff and review of long absenteeisrn and initiate action wherever necessary . It can be seen from Ex . M 6 that duties assigned to him were all managerial in nature and it cannot be saidthat all these duties were given to workman as claimed by him . Further , from Ex . M 7 namely copy of
2733 G1/07--9 3976
THE GAZETTE OF INDIA : JUNE 23 , 2007/ SADHA 2 , 1929
PART II-St . 3 ( i ) !
signing this office order , he has bold enough to say thai the Petitioner has worked only in a clerical cadre . In the same order , it is clearly mentioned that the Petitioner is entitled for reimbursement of conveyance bills and also leave travel allowance of Rs . 3500 which amount will not be given to a workman as allowance . From Ex . M 25. M 26, and M 27 , it is clear that WW2 has consulted the Petitioner as adecision making person and he has made an endorsement to contact him for discussion and these documents relate to increase of wages with regard to workmer and four officers in managerial cadre . Thus , it is clear that the Petitioner has been consulted on policy matters . Above all , Ex. M29 , which is a Memorandum of Settlement under Section 18 ( 1 ) of the I.D.Act entered into between the Respondent/Management and India Cements Einployees ' Union with regard to revision of wages and benefits to workers, wherein the Petitioner has signed as management representative and all the three management representatives are Executive Director , Senior Manager ( F & A) namely the Petitioner and Medical Officer (mines) whowere all worked in managerial cadre . Further , from the leave record , it is clear that the Petitioner was entitledto 30 days annual leave while the workman is enutled to leave @ 1 day per 20 days worked . Even these circumstances will clearly show that the Petitioner has not worked as a workman but only in managerial cadre . Ne doubt , the Petitioner has no power of appointment or dismissal as a Managerfor Assistant General Manager but merely because the Manager who has no power to appoint or dismiss a workman cannot be deemed to be said as a workman. Furthermore, under Ex .W19 it is clearly mentioned that the Petitioner had acted in the absence of Executive Director and no workman can act in the Executive Director's absence . Though it is alleged by the learned counsel for the Petitioner that the Petitioner has no power of appointment or dismissal , they wantonly burked the fact that the Petitioner has acted and has given the duties of managerial nature and he has exercised the duties as such and therefore , the Petitioner cannot be sated as a workman . All these will prove that the Petitioner was not doing the job of stereo type but was engaged in various activities and therefore , he is not a workman and since he has worked only in a managerial capacity , this petition is not maintainable before thisTribunal .
9. I find much force in the contention of the Respondent because though it is alleged that the Petitioner has worked only in a clerical cadre and not as a managerial cadre, all the documents produced by the Respondent clearly show that the Petitioner has exercised the managerial duties and he has also received perquisites as per the managerial cadre .
10. Further learned counsel for the Respondent relied onthe rulings reported in 1994 2 LLJ 1153 S.K. MAINI V's . M/ s . CARONA SAHU CO . LTD . , & ORS . , wherein the Supreme Court while considering who is a workman , has
stated that " designation of an employee is not of much importance. What is important is the nature of duties. The determinative factor is the main duties and not some work incidentally done . If the employee is mainlydoing supervisory work. but incidentally or for a fraction of time also does some manual or clerical work , the employee should be held to be doing supervisory work . " The next decision relied on by the connsel for the Responden 2004 LLR 506 TATASONS LTD . Vs. S. BANDYOPADHYAY AND ANOTHER wherein the Delhi High Court has b that the correspondence revealed that the Respondent was highly educated namely a chartered engineer , and b . was not doing any manual work as claimed by him. The nature of work clearly involved a considerable amount of mental inputs , creativity and imagination . Merely that the Respondent was required to report to a superior it woeld not bring him within the purview of the definition of workman..... What is in portance is the nature of his dutes particularly his primary or basic duties and the dorinat purpose of his employment. " The next decision relied on by the counsel for the Respondent is 2004 LLR 574 ( GUPTA VS. GLAXOSMITHKLINE PHARMACEUTIC LTD . AND ANOTHER wherein the Bombay High Court has held that " the appellant was not a workman as his work did not fall within the first part of definition of workman under Section 2 ( s ) of the Act and even assuming that he did fall within the first partby virtue of his work being technical , he wouldbe excluded since his duties were mainis of managerial nature . " Further, he relied on the tulings reported in 2004 LLR 612 JAIPRAKASH SINGH V PRESIDING OFFICER . LABOUR COURT, KANPUR AND OTHERS in which the Allahabad High Court has held that "the Petitioner was initially appointed as dairy supervisor and promoted as Manager Grade IV and was performing managerial /supervisory functions , hence he was not a workman . " Learned counsel for the Petitioner further relied on the rulings reported in 2006 3 LLJ 408 SUBIR GUHA THAKURTA VS. JOHNSON AND JOHNSON LTD . AND OTHERS wherein the Calcutta High Court has held that "burdenofproving that he is a workman , is on the employee and on facts , the person concerned is in managerial cadre and the findings of the Tribunal in favour of the employee isperverse and not sustainable . " Further , he relied on the rulings in an unreported case of Madras High Court in S. NALLATHAMBI VS. PRESIDING OFFICER, INDUSTRIAI. TRIBUNAL, CHENNAI & ANOTHER in W.P. No. 8949 of 2000 wherein the High Court while considering whether the Petitioner is a workman has held that " the Petitioner was drawing salary applicable to managerial staff and he had administrative control on the workman and had power to sanction leave for workmen and had power to pass bills and prepare estimates for civil works in the mines etc. and therefore, he is not a workman . " Relying on all these decisions, learned counsel for the Respondent contended that the Petitioner was though appointed as a clerk in 1977 his post was redesignated and he was given managerial 3977 भारत का राजपत्र : जून 23, 2007/आषाढ़ 2 , 1929
भाग II- खण्ड 3( ii) ]
Description
Ex. No. Date
W6 21-6-01
power and which power he had exercised and hence he is not a workman.
Xerox copy of the order of respondent posting Petitioner as Special Officer in Nellai Transports
12-11-01
W7
11. I find much force in the contention of the learned counsel for the Respondent and therefore, I find the Petitioner is not a workman . Since the Petitioner is not a workman , this Tribunal has no jurisdiction to decide whether the Petitioner is entitled for reinstatement as alleged by him. As such, I find this point against the Petitioner.
Xerox copy of the order issued to Petitioner Redesignating his post as Senior Manager (P & A) Point No.2 :.
27-3-02
W8
The next point to be decided in this case is to what relief the Petitioner is entitled ?
Xerox copy of the office order promoting the Petitioner as AGM
W9 12-11-02
Xerox copy of the transfer order issued to Petitioner
W10 19-11-02
12. In view of my foregoing findings that the Petitioner is not a workman and he is not entitled to the benefits of the ID Act , I find the Petitioner is not entitled to any relief. No Costs .
Xerox copy of the office order issued to Petitioner 13. Thus , the reference is answered accordingly.
W11 1-4-03
(Dictated to the PA transcribed and typed by him, corrected and pronounced by me in the open court on this day the 29th March , 2007) .
Xerox copy of the office order issued to Petitioner Redesignating him as AGM (Per&Mines)
4-2-04
W12
K. JAYARAMAN, Presiding Officer
Witnesses Examined :-
Xerox copy of the office order issued by Executive Director to the Petitioner
For the I Party/Petitioner :
W13 30-8-04
W14 8-9-04
WW1 Sri K. S. Uthandaraman WW2 Sri A. S. Krishnan WW3 Sri M. Yovan
Xerox copy of the Advocate notice issued to Respondent Xerox copy of the reply given by Respondent
W15 7-10-04
: MW1 Sri R. Rajagopal
For the II Party, Management
Xerox copy of the 2A petition filed by Petitioner MW2 Sri S. Padmanabhan
W16 20-10-04
Documents Marked :---
Forthe Party/Petitioner : ---
Ex. No. Date
Description
Xerox copy of the reply submitted by Respondent before Assistant Labour Commissioner (Central) 20-8-77
W17
Wi
4-11-04
Xerox copy of the appointment order issued to Petitioner
Xerox copy of the rejoinder filed by Petitioner .
13-12-04
22-8-77
W18
W2 Xerox copy of the Letter from respondent to Petitioner
Xerox copy of the letter from Respondent to Assistant Labour Commissioner (Central) 23-7-77
W19 31-1-05
Xerox copy of the failure of conciliation report W3 Xerox copy of the Respondent to Petitioner calling for Interview
W20 Nil
Xerox copy of the Chapter IV ofMines Act , 1952
27-9-03
W21
W4 1-9-78 Xerox copy of the officer order issued to Petitioner confirming as Senior Clerk .
Xerox copy ofthe instruction note issued to Petitioner W4A
W22 21-10-00
Xerox copy of theinstruction note issued by Respondent regarding production
W23 22-9-00
23-8-05 Xerox copy of the complaint from India Cement Employees Union to Registrar of Companies, Chennai regarding Mismanagement Respondent/Management . of
Xerox copy of the letter from Mines Manager to DMS
7-6-04
W24
Xerox copy of the service certificate issued to Petitioner
W5 64-01 Xerox copy of the office order issued to Petitioner to proceed on leave.
3978
THE GAZETTE OF INDIA : JUNE 23 , 2007/SADHA 2, 1929
Ex . No. Date
Description
W25 14-11-00
Xerox copy of the service certificate issued to Mines Manager
W26 Sept.02
Xerox copy of the rate of wages as per Cement Wage Board
W27 1-494
Xerox copy of the ready reckoner of wages
W28 1-4-03
Xerox copy of the split up details of special benefits W29 21-9-92
Xerox copy ofthe Form H 18(1) settlement revising Benefits and Allowances
W30 1-6-90
Xerox copy of the 18( 1) settlement
W31 29-9-96
Xerox copy of the 18(1) settlement
W32 9-1-02
Xerox copy of theoffice note regarding daily report from Mines
W33 10-9-03
Xerox copy of the direction note to Petitioner regarding Rectification of discrepencies W34 21-10-00
to Xerox copy of the note Petitioner to maintain Separate cash receipts
W35 Series 01-01-00 3-2-00
24-12-99
Xerox copy of the instruction to Petitioner by ED Mr.Rajagopal
W36 21-10-00
Xerox copy of the order note to Petitioner to stop working W37 17-9-03
Xerox copy of the instruction to Petitioner regarding Sale of reject stones
W38 20-8-99
Xerox copy of the instruction to Petitiner to pay his monthly payment by Mr. Rajagopal , E.D.
Forthe II Party/management:-
Ex. No. Date
Description
M1 21-1-87
Xerox copy ofthe office order designating the Petitioner as Deputy Accountant .
M2 19-8-89
Xerox copy of the application of Petitioner for service certificate .
M3 23-8-89
Xerox copy of the service certificate issued to Petitioner .
[PART II-SEC . 3( ii);
Ex . No. Date
Description
M4
4-7-94
Xerox copy of the office order issued to Petitioner Manager (Accounts). as M5 6-6-01
Xerox copy of the certificate issued by respondent .
M6 30-9-03
Xerox copy of the office order specifying duties of Petitioner .
M7
9-8-02
Xerox copy of the instructions note to quarry at Ramayanpatti .
M8 12-8-02
Xerox copy of the recommendation of Petitioner to take Disciplinary action against persons.
M9 1-4-03
Xerox copy, of the order redesignating the Petitioner as AGM (Per& Mines) .
M10 24-4-03
Xerox copy of the office order regarding reimbursement of telephone charges
M11 3-9-03
Xerox copy of the office orders circulated by Petitioner .
11-9-03
23-9-03
M12 10-8-03
Xerox copy of the circular regarding telephone expenses.
M13 9-10-03
Xerox copy ofthe authorisation givenby Executive Director to Petitioner .
M14 11-11-03
Xerox copy of the certificate issued to Petitioner .
M15 11-1-04
Endorsement made by petitioner regarding leave sanction.
M16 series 2-2-04 to 21-2-04
Xerox copy of the slips signed by Petitioner .
M17 Nil
Xerox copy of the wage slips pertaining to petitioner .
M18 15-7-77
Xerox copy of the letter from Petitioner to Respondent.
M19 27-3-02
Xerox copy of the office order issued by respondent.
M20 26-2-04
Xerox copy of the sick leave application of Petitioner .
M21 2-3-04
Xerox copy of the letter from Respondent to Petitioner .
M22 10-4-03
Xerox copy of the daily report of respondent.
M23 4-7-94
Xerox copy of the office order redesignating the Petitioner as Manager (Accounts) .
3979 [ भाग II-खण्ड 3( ii) ]
भारत का राजपत्र जून 23, 2007/आषाढ़ 2, 1929
M40
M24 20-4-96
04-03-04
Xerox copy of the report to Chairmanregarding increase in Salary.
Xerox copy of the complaint filed by Executive Director with police against the Petitioner.
04-03-04
M25
M41
2-4-97
Xerox copy of the note from NTLO.
Xerox copy of the receipt given bypolice.
M42 14-03-04
M26 27-5-97
Xerox copy of the legal notice sent by Respondent to Petitioner .
Xerox copy of the note of Executive Director to Board of Directors.
M43 06-04-05
M27 22-4-98
Xerox copy of the order of reference issued by Ministry of Labour.
Xerox copy of the note submitted by Petitioner to Executive Director.
M44 31-05-05
M28 27-8-98
Xerox copy of the failure of conciliation report .
Xerox copy of the order changing designation of Petitioner .
नई दिल्ली , 28 मई , 2007
M29 Nil
Memorandum of Settlement under Form H between Respondent/management and India Cements Employees Union.
M30 26-06-00
का.आ. 1815.-औद्योगिक विवाद अधिनियम , 1947 (1947 का 14 ) की धारा 17 के अनुसरण में , केन्द्रीय सरकार एस.सी.सी.एल. के प्रबंधतंत्र के संबद्ध नियोजकों और उनके कर्मकारों के बीच , अनुबंध में निर्दिष्ट औद्योगिक विवाद में औद्योगिक अधिकरण , गोदावरीखनी के पंचाट ( संदर्भ संख्या 156/2005 ) को प्रकाशित करती है , जो केन्द्रीय सरकार को 28-5-2007 को प्राप्त हुआ था। Copy of minutes of proceedings of Board of Directors.
03-10-03
M31
Xerox copy of the note of Executive Director to Petitioner for liaison work .
[सं. एल-22013/1 /2007- आई आर ( सी- II ) ] अजय कुमार गौड़ , डेस्क अधिकारी New Delhi , the 28th May, 2007 M32 09-10-03
Xerox copy of the note of Executive Director to Petitioner Regarding production for despatches.
M33 10-10-03
Xerox copy of the note of Executive Director to Petitioner Regarding despatches .
S.O. 1815. In pursuance of Section 17 of the Industrial Disputes Act, 1947 ( 14 of 1947) , the Central Government hereby publishes the award (Ref. No.156/2005) of the Industrial Tribunal , Godavarikhani as shown in the Annexure in the Industrial Dispute between the employers in relation to the management of SCCL and their workmen , which was received by the Central Government on 28-5-2007.
M34 01-10-03
Xerox copy of the note of Executive Director to Peti- tioner Regarding quality maintenance .
[No. L-22013/1/2007-IR (C- II) ] AJAY KUMAR GAUR, Desk Officer ANNEXURE
M35 Nil
Xerox copy of the attendance register showing the position ofPetitioner as AGM.
BEFORE THE CHAIRMAN, INDUSTRIAL TRIBUNAL- CUM -LABOUR COURT, GODAVARIKHANI
M36 09-06-99
Xerox copy of theBoard reso- lution nominating ED as Nominee under MinesAct .
M37 24-12-99
PRESENT : Sri M. Shanmugam , B. Com . , B. L. , Chairman- cum- Presiding Officer Saturday, the 23rd Day of December, 2006 İndustrial Dispute No. 156 of 2005
BETWEEN :-
Xerox copy of the Board reso- lution appointing ED as whole Time Director .
M38 Nil
Xeroxcopyof the leave record ofPetitioner.
24-04-02
M39
Budiga Rajaiah , S/o , Gangaiah , Aged about 46 yrs . , E. C. No. 09035043, Ex-CoalFiller , R/o. 20-3-133 , Vidyanagar, PO, Godavarikhani , Dist. Karimnagar A. P. 505 209.
..... Petitioner
AND
Xerox copy of the note submitted by Petitioner to ED Recommending regularisation ofastaff.
3980
THU. GAZETTE OF INDIA NE 23 , 2007 / ASADHA 2,1929
PART II- SEC. 3 (ii) 1. The Superintendem of Mines , GDK. No. 7 ( LE ) Project , S. C. Co Ltd .. RG -4. Godavarikhani , Dist . Karimnagar .
2. The Chief General Manager , S. C. Co. Ltd. , Ramagundam Area- I. Godavarikhani . Dist. Karimnagar .
3. The Chairman & Managing Director. S. C. Co. Ltd. , PO . Kothagudem, Dist. Khammam .
Responderts
respondents condoned the absence of the petitioner and took the petitioner into service . The petitioner attended to his duties under the 1st respondent in the year 1998 and 1999 also , duly taking treatment That the petitioner underwem treatment in compary's hospital and other private/Government hospital . Thus , there is reasonable and sufficient cause for the dleged absence of the petitioner. It is not at all a habitual one or deliberate . His personal treatment , and other domestic problems are mevitable and beyond the control of the petitioner . His previous attendance for more than 15 years proves the punctually and loyalty of the petitioner to his duties . The total paid National Holidays and weekly holidays of 1997 were also unjustly shown as absent
as This Industrial Dispute petition coming a belora me for final hearing on 11-12-2006 upon petasies, The documents on record and upon hearing argomenti Sri D. Krishna Murthy , Advocate for the respendents , the petitioner , he filed the petition . Afterwards , h called absent, set - exparte , he did not engage the corsi . As per Rule 24 of A. P. , I. D. , Rules , if without sufficem cause . the petitioner fails to attend or to be represented before this court , it shouldbe considered as if the tiety had duly attended or had been represented , and marriag stood over for consideration :----
AWARD
1. This is à petition filed U 'Sec . 2A(2
1947 praying to set aside the dismissal onger t 6/12-12-1999 passedby the 2nd respondent and the respondents company to reinstate the petalon service, with continuity of service , all other conseqлоді benefits and full back- wages , to meet the cres
2. The petition affidavit allegations vicily
4. But the respondent company got conducted a farce ofdomestic enquiry in an eye wash manner . The petitioner was not ali given opportunity to cross - examine the management witnesses te.. Shri B. lylaiah , office Superintendent and Shri Abdui Alcem , pay sheet Clerk . He was denied fair opportunity to defend himself during the alleged domestic enquiry . Even the basic principles of natural justice were not followed. The entire statements are proformas and the blanks were filled up by the E.O. , the petitioner wanted to preduce evidence on his behalf. but the E.O.. denied the same However , the responden! authorities , not at all contradicted the statement of the petitboner that he could not attend to his duties regularly due to ill health . It was not all rebutted and remained unchallenged . The am conuadictory statement of the titioner shall prevail. The tradings of the enquiry officer are biased and perse. The enquiry officer not at all constiered the true fe's This court raav declare the Jomestic enquiry as invalid and vitated , as a prelisninga point.
follows: The Petitioner suniis that he was appoin asBadli Filler in the respondents compary in adva 1982. Later, the petitioner was promoted as coal fusa his services were confirmed . Ever since ais appointner in the year 1982 , the petirio ser discharged his duties utmost satisfaction of ais superiors without any ind blemish . He served the respondents company for than 18 years loyally and cerely.
3. The petition.brats that the work of co , i ..
5. That the 2nd respondent failed to consider the representation of the petitioner on the enquiry report and proceedings . Straight away, the 2nd respondent issued the final order and dismissed the petitioner from service 13-8-1999 . No show cause notice was issued to the titioner proposing the capital punishment of dismissal from service . It is void . abiniuo and contrary to the well- settled law. The said order No. P..RG . 1/32/99/5116 . dt. 5/12-8-1999 are highly arbitrary unjust. ill: gal and cannot be sustained under law .
in the underground sy stenuous and hazarus. the year 1997-1998 be suffered from serious ill health. chronic chest pain and twisting of nerves & joint pains to his legs etc. , Even then, ne worked for seval da hơi could not compléte the required minimum 1000 ron , The was constrained to under go prolonged and te treatment in SCCL and other hospitals . Due to ila was not in a position to attend his duties regularly art was confiend to bed. Bu 1st respondent issued charge dt . 5/15-11-1998 alleging absenteeism in the year 17.2 misconduct :
"C. S. O. No. 25. 25 : Habitual late attendance or habitual absence from duty without sufficient cause
The petitioner submitted his explanation to the said charge sheet along with medical certificates . The
6. Further, the euenic and capital punishment of dismissal imposed by the 2nd respondent on the petitioner s highly excessive and show kingly disproportionate to the aireged charge for the short for the 100 mimnium required musters during 1997. It is not at all commensurate and amount to economic death of the petitioner . He served the company from 1982 to 1999 ie , for more than 18 years without any blemish . Now he is over aged and has not only few years of service . He spent huge amounts for his 3981
भारत का राजपत्र : जून 23 , 2007/आषाढ़ 2 , 1929
[भाग II- खण्ड 3 ( ii) ]
treatment, and other domestic problems . He and his entire large family faced lot of hardship for livelihood and incurred several debts .
Act is not applicable to the respondent company and the petition filed by the petitioner is not maintainable under law and and is liable to be dismissed in limine .
11. In replyto para No. 1 of the petition, the petitioner was appointed in the respondent company on 2-9-1982 as Badli filler and later he was designated as coal filler . The averment ofthe petitioner that eversince his appointment in the year , 1982 , he dischared his dutiesto the utmost satisfaction of his superiors without any kind of blemish is denied and the petitioner is put to strict proof of the same.
7. That the petitioner hails from a very poor family and has no other source of income, except this job . He is the sold breadwinner for his entire large family. He has to feed his ailing old aged parents , wife and children , due to the unjust dismissal from service by the respondent's company, they are thrown on the streets . The petitioner is facing lot of hardship and mental agony . Eversince his dismissal from service , the petitioner remained unemployed and could not get any other job inspite of his best efforts .
8. That this court has got every jurisdiction to adjudicate his case and wide powers vested u/ s . 11 -A of I.D. , Act to quash the dismissal order . That no civil or criminal case is filed by the petitioner before any other court or authority, except the present petition before this court. Therefore prayed this court to set - aside the dismissal order dt . 6 / 12-12-1999 passed by the 2nd respondent ; and direct the respondents ' company to reinstate the petitioner into service , with continuity of service , all other consequential benefits and full back- wages . to meet the ends ofjustice.
12. In reply to para No. 2, that the averment of the petitioner that in the years , 1997-1998 he suffered from serious ill health, chronic chest pain and twisting of nerves and joint pains to his legs etc. , Even then, he worked for several days but could not complete the required minimum 100 musters is denied and the petitioner is put to strict proof thereof. That an underground employee should put 190 mandatory musters minimum per year . That the petitioner did not inform regarding his ill health to his superiors or mine authorities at any point of time . That the respondent company is carrying a :nining operation , which is engaged in exploration , excavation , extraction and winning of coal in the 4 Districts of Andhra Pradesh i . e . , Khammam, Karimnagar , Adilabad and Warangal and has a well established chain of hospitals in all its areas and also in the nearby to cater to the health requirements of its employees and their family members . It is also mandatory under the Mines Act /Regulations to maintain the hospitals that are mannedby the qualified medical practitioners . Also the respondent company has rules and regulations to refer the cases of complicated diseases to out side hospitals like Osmani General Hospital , Gandhi Medical hospital and Nizams Institute of Medical Sciences and the charges are also borne by the respondent- company . The petitioner is fully aware of the same but did not avail the facilities . He didnot report at company's hospital for sick and treatment . That he remained absent from duty without sufficient cause on a number of days during the year 1997 and he put in only 80 days attendance during the year 1997. Hence he was issued with a charge sheet dt . 5 /15-11-1998 under company's standing orders No. 25.25 which reads as follows:-
"25.25 . Habitual late attendance or habitual absence from duty without sufficient cause" .
9. The averments of the conter filed by the respondents are that it is a Government company incorporated under the provisions of Companies Act , 1956 for carrying out the business of winning and selling the coal . That since the coal mining industry is a central subject the appropriate Government for this respondent- management is Central Government . The respondent submits that as per S. 7A( I) of I.D. , Act , the appropriate Government may be notifications in the official gazette constitute one or more industrial tribunals for the adjudication of industrial disputes relating to any matter whether specified in the 2nd schedule or 3rd schedule and for performing such other functions as may be assigned to them under this Act. The respondent submit that Central Government established an Industrial Tribunal- cum- Labour Court at Hyderabad from 29-12-2000 for adjudication of industrial disputes and the petitioner oughtto have approached the said tribunal for the redressal of grievance , ifany , But , the petitioner conveniently avoided to file his petition before the tribunal established by the Central Government for the reasons best known to him . That the petition is not maintainable under law and the same maybe dismissed on this ground alone.
The contention of the petitioner that the respondents condoned the absence of the petitioner and took the petitioner into service is not correct . As per regular practice whenhe reported for duty he was allowed . Allowing for duty is not condoning the absence of the petitioner .
The averment of the petitioner that the petitioner under went treatment in the company's hospital and other private/Government hospitals is denied and the petitioner isputto strict proof of the same . He did not submit any documentary evidence to that effect . The contention of 10. That the maintainability of the dispute raised by the petitioner before this court may be decided as preliminary issue before proceeding with the trial. That the petitioner failed to exhaust the conciliation procedure as laid down in the I. D. Act and filed the present petition before this Tribunal under S. 2A (2) of I. D. , Act , 1947 as amended by A. P. , Amendment Act , 1987 (A: No. 32 of 1987). That as the appropriate Government for coal mining industry is the Central Government the State Amendment 3982
THE GAZETTE OF INDIA : JUNE 23 , 2007 /ASADHA 2, 1929
the petitioner that the total paid national holidays and weekly holidays of 1997 were also unjustly shown as absent is not correct. That as per rules if the paid holidays or weekly playdays falls between absents they will automatically be treated as absents . The petitioner is not aware of the rules .
13. In reply to the para No.3 , that the all averments of the petitioner made in this para are denied and the petitioner is put to strict proof of the same . That the petitioner submitted an explanation dated nil to the charge sheet which was found not satisfactory .
Hence , a domestic enquiry was odered vide enquiry notice dt. 15-2-99 fixing the enquiry on 22-2-99 . The petitioner acknowledged the same . He fully participated in the enquiry on 22-2-99 . He was given full and fair opportunity to defend his case in the enquiry . At the begining of the enquiry , the enquiry officer has explained the procedure of the enquiry in telugu to the both parties . That the petitioner did not chooses to take any assistant's help during the enquiry proceedings . The management witnesses have produced the documents i.e. , pay sheets and attendance registers pertaining to the petitioner in supportof their statements . The documents were verified in the presence of the petitioner and it was found that the absence mentioned in the charge sheet were correct . The petitioner accepted the same . During the enquiry proceedings the petitioner admitted the charge levelled against him under company's standing orders 25.25 . Ali contents of the enquiry proceedings were explained in telugu to the petitioner . The petitioner put his signature as atoken of acceptance . The enquiry officer conducted the enquiry by following the principles of natural justice.
14. In reply to para No. 4 that a show cause notice dt. 22-5-99 was issued to the petitioner alongwith the copy ofthe enquiry report and proceedings by advising him to make representation , if any. He acknowledged the same and submitted a representationdt. 27-5-99 which was found not satisfactory . His attendance particulars from 1996 are furnished hereunder :--
Year
Actual attendance 1996
89
1997 ( charge sheeted year ) 80
1998
84
41
1999(uptoJune)
15. From the above, it is observed that the petitioner did not improve his attendance after issuing the charge sheet also . The respondents' company employed more than 83,000 persons , which includes workmen , executives and supervisors . The production results will depend upon the over all attendance and performance of each and every individual . They are inter - linked and inseparable . In this regard , if any one remains absent, without prior leave or without any justified cause , the work to be performed gets
[PART II-SEC. 3( ii)] effected . Such un- authorised absence created sudden void, which at time is very difficult to fill - up , and there will be no proper planning and already planned schedules get suddenly disturbed without prior notice . That is the reason why the respondents's company is compelledto take servere action against the un - authorised absentees . In the instant case , the petitioner is one such unauthorised absentee having been only 80 days attendance in the year 1998 and he has not improved his attendance and work performance even after issuing the charge sheet . With the advent and implementation of new industrial and economic policies by the Central /State Governments as well as the company, the company cannot go on employing the persons who are chronic absentees , who are a burden to the company. As the charge levelled against the petitioner was proved and his attendance in the previous years was very poor and he did not improve his work performance after issuing the charge sheet also , the respondents manageinent was constrained to dismiss the petitioner from the services w.e.f. , 13-8-1999.
16. It is submitted that this court may decide the validity of the dometic enquiry as a preliminary issue and permit this respondent to lead evidence if this court comes to a conclusion that the domestic enquiry is not valid . Therefore prayed this court to dismiss with costs , for which act of justice the respondents shall ever pray.
17. On behalf of the petitioner side , after filling the claim statement and also on 3-7-2006 , vakalat was filed alongwith consent petition . On 10-7-2006 for consent petition, leave was granted . On 16-10-2006 when the petitioner not at all attending the court, the petitioner counsel endorsed on the vakalat stating that he is withdrawing vakalat in this case by intimating the same to the party as the vakalat is mistakenly filed , so withdrawing the vakalat. Hence the court case is posted for appearance ofthe petitioner to file vakalat with consent. On 30-10-2006 petitioner called absent and no representation . On 13-11-2006, the petitioner called absent . The petitioner is not turned- up to the court since from the begining . When the petitioner not turned - up nearly for a period of more than one year , no purpose would be served by simply adjourning the case except the court has no other go made set- exparte . On that day also , petitioner called absent and no representation . Hence , made set -exparte . The petitioner did not turn-up to the court to prove his innocence . On the petitioner side , no documents are filed , no oral evidence and no decisions filed into the court. On behalf of the respondent side , no oral evidence and no documents are marked and also no decisions were filed . Only arguments heard as per Rule 24 of I.D. Act, followed on behalf of the petitioner , and heard oral arguments on behalf of the respondent side.
18. Before going to the merits of the case , I would like to submit the delay of the petition for disposal and also delay for the disposal . The petitioner filed this petition on [ भाग II- खण्ड 3( ii) ]
21-12-2005 and it was numbered on 29-12-2005 . Counter was filed on 16-10-2006. When the petitioner has filed vakalat , afterwards the counsel withdrawn the vakalat stating it was filed mistakenly. In the petition , the verification also signed by the petitioner himself, itself shows that the petitioner is not correctly filed. In this case the consent was inferred . In the claim statement there is no signature who verified affidavit allegations . After filling of the claim statement, the petitioner did not turn - up to the court to defend his case .
19. It is an admitted fact that the petitioner was appointed in the respondent company and he worked as coal filler . He was dismissed from the service vide letter dt . 12-8-1999 under the provisions of 25 (25) of certified standing orders i.e. absenteeism .
20. The claim statement allegations the petitioner was suffered from serious ill -health , chronic chest pain, twisting of nerves and joint pains to his legs etc. , in the year, 1997-98 . Even then he worked for several days, but could not complete the required minimum 100 musters . Due to illness, he was not in a position to attend his duties regularly . So he confined to bed. The absence of the petitioner was not intentional , but due to ill -health which deserves to be condoned . The act of punishment of dismissal from service of the petitioner by the respondent isshockingly disproportionate to the gravity of charges . Hence , he prayed this courtto set - aside the clismissal order directing the respondent to reinstate the petitioner into service with continuity of service with all other attendant benefits including the back - wages etc.
21. The respondent counsel argument was that the company is established under the company's Act under Central Government . Central Government established an Industrial Tribunal- cum - Labour Court at Hyderabad for adjudication of Industrial Disputes. The petitioner filed this petition in this court is not maintainable under law . Hence, the same may be dismissed on that ground alone . The petitioner had only pat 80 days of attendance during the year 1997 without leave or permission . The petitioner received with the charge -sheet under clause No. 25.25 of standing orders of the respondent company for his mis- conduct for habitual absenteeism and the petitioner was suspended . The petitioner submitted his explanation stating that due to his ill - health suffering from various diseases, he had not attended the duty and he requested the company to excuse him for this time. As his explanation was not satisfactory, a domestic enquiry was ordered and issued enquiry notice and conducted the enquiry . The petitioner attended the enquiry and participated in the domestic enquiry. The charges were explained to the petitioner and he has no objection to record the proceedings of the enquiry in english language . He did not take the assistance ofany defence and he accepted the charge levelled against him and pleaded guilty of mis-conduct . He was also not chooses to cross - examine the management witnesses 2733 GI/ 07--10
3983
भारत का राजपत्र जून 23, 2007/आषाढ़ 2, 1929
during the domestic enquiry . In the domestic enquiry , he clearly stated and he admitted that he had absented from his duties habitually from 1996 to 1999 due to ill -health . The petitioner did not give any explanation to the charge sheet served on him . Petitioner also did not file any documents to prove that he was suffered from ill - health . The petitioner gave assurance to the respondent that he will attend regularly without absenteeism . On his undertaking he was kept under observation , but the petitioner failed to attend to his duties inspite of his undertaking given . The charges framed against him were proved in the domestic enquiry . Respondent issued show cause notice by enclosing the copies of enquiry report and enquiry proceedings . The petitioner gave the reply to the show cause notice . The petitioner failed to improve his performance inspite of giving fair opportunity and his past performance is also not satisfactory. Hence, the respondent company constrained to terminate the services of the petitioner. The petitioner concealing all the above facts filed this petition. Hence , he prayed this court to dismiss the petition in the ends of justice , else the respondent company suffer from irreparable loss .
22. From the petitioner's claim statement and on its perusal and also the arguments of the respondent counsel , the following issue is framed as preliminary issue for determination :
Whether the enquiry officer was not at all given an oportunity to defend the petitioner's case and the findings of the enquiry officer are biased and perverse without following the basic principles of natural justice . So the enquiry is invalid and vitiated .
23. In this case, the petitioner himself did not chooses to attend the court and defend his case . The respondent counsel argument was that the petitioner is habitual absentee without obtaining any prior permission from the authorities concerned and his absconding from duties . The petitioner also did not file any documents that he was suffered with ill -health , due to various diseases . The respondent followed the procedural principles of natural justice by issuing the charge sheet by sending a notice of enquiry to the petitioner and he was also perticipated in the enquiry and in the enquiry, he admitted the guilt and he has also given an undertaking stating that here afterwards he will not be absented to his duties . He was also given family counsilling , even then he was continuingto absent, not attending to the duties . During the observation period also, he failed to attend to his duties . He was also given fair opportunity to defend his case in the domestic enquiry. After issuing show casue notice to the petitioner , the petitioner also gave the reply. The respondent was not satisified with the reply given by the petitioner . The respondent followed the principles of natural justice by issuing notices and conducting equiry by giving an 3984
THE GAZETTE OF INDIA : JUNE 23 , 2007/ASADHA 2, 1929
opportunity to the petitioner . The petitioner did not raise any objection or any dispute . So the petitioner did not got any prejudice in conducting the enquiry. So I did not find that the petitioner was not prejudiced in any way on accountof conducting enquiry by the respondent. It cannot be said that the enquiry was conducted in gross violation ofprinciples of natural justice . The findings recorded by the respondent is perfectly legal and valid . It need not be interfered with by this court . So the petition contention is refused. The court thinks the case of the petitioner is not at all real one , substance or there is substantiate possibility ofsuccess of that the result will not be different even ifthe natural justice is followed. Hence , the domestice enquiry conducted is legal , proper valid and binding on the parties .
24. From the respondents counsel argument the petitioner in failed to report for duty and remaining absent without obtaining leave , had acted in a manner irresponsibility and unjust fiedly that on the findings of the enquiry officer, the charge was proved that the petitioner remained absent without obtaining leave in advance . The respondent company has not resorted to extreme punishment at the very first instance of absenteeims of the petitioner-workman . The respondent company has toleratedhim for quite some time and ultimately when there was no improvement in his behaviour to attend the duties. The respondent has no other go except to dismiss the petition from the service.
25. As per the claim statement , allegations , the contention ofthe petitioner that the punishment of dismissal ofthe petitioner from service of the company is totally disproportionate to the proved mis-conduct of unauthorised absenteeism of the petitioner. The disciplinary authority failed to advert itself to this aspect of the matter . I find it difficult to accept the submissions made by the petitioner inhis claim statement . In this case, the petitioner admitted the un-authoried absenteeim in the enquiry proceedings . The petitioner also did not turn - up to the court to prove hiscase. The petitioner also did not file any documents to prove that he has taken treatment from the hospitals.
26. The mis-conduct committed by the petitioner is un-authorised absence , as he did not obtain any prior permission from the main authorities for absconding from his duties is undoubtedly an irregularity and serious in nature. In the circumstances , this court cannot take any lenient view and substitute its opinion for that of the respondent. The findings of the respondent even on the question relating to the propertionality of punishment is basedupon the evidence available on record . In this case, the petitioner did not turn -up to the court and he did not file any documents , he was suffered with ill- health and taken treatment. The past record of the petitioner also shown his habitual absenteeism in attending to his duties .
27. Inmy considered opinion that the findings taken bythe respondent does not suffer from any error whatsover .
[PART II --SEC. 3 (ii ) ] Having regarding all the aspects and circumstances of the case, the punishment imposed by the management is not disproportionate requiring any interference in exercising the descirtion U/ sec.11 -A of the I.D. , Act . In thesc circumstances, I do not find any merit in this petition.
28. In my view this court would have no jurisdication to show any sympathy for such a workman who is guilty of un- authorised absence should not be shown any leniency especially when he continuous to absent himself and for a long period . The enquiry officer and the disciplinary authority both have considered all the facts and circumstances of the case and have correctly recorded their findings against the petitioner . Ido not find any serious illegality or any infirmity in the order of the respondent . Hence, I therefore dismiss the petition .
In the result, the petition is liable to be dismissed and is accordingly dismissed . But in the circumstances , no costs.
Typed to my dictation by Typist directly , corrected and pronounced by me in the open court on this , the 23rd dayofDecember, 2006.
M. SHANMUGAM , Chairman - cum- Presiding Officer Appendix of Evidence
Witnesses examined
Forworkman
: -Nil-
-Nil-
ForManagement :
Exhibits
-Nil-
Forworkman :
-Nil-
ForManagement :
नई दिल्ली , 28 मई , 2007
का.आ. 1816.-औद्योगिक विवाद अधिनियम , 1947 ( 1947 का 14 ) की धारा 17 के अनुसरण में , केन्द्रीय सरकार सी. पी. डब्लू. डी. के प्रबंधतंत्र के संबद्ध नियोजकों और उनके कर्मकारों के बीच , अनुबंध में निर्दिष्ट औद्योगिक विवाद में केन्द्रीय सरकार , औद्योगिक अधिकरण नं. - 2 , नई दिल्ली के पंचाट ( संदर्भ संख्या 117/2005 ) को प्रकाशित करती है , जो केन्द्रीय सरकार को 28-5-2007 को प्राप्त हुआ था।
[सं. एल-42012/13/2005- आई आर ( सी- II ) ] अजय कुमार गौड़ , डेस्क अधिकारी New Delhi, the 28th May, 2007
S.O. 1816.- In pursuance of Section 17 of the Industrial Disputes Act , 1947 ( 14 of 1947) , the Central Government hereby publishes the award (Ref. No.117/2005 ) of the Cent . Govt. Indus . Tribunal -cum-Labour Court No. 2, New Delhi as shown in the Annexure in the Industrial Dispute between the managerment of CPWD, B- Division , CPWD , and their 3985 भारत का राजपत्र : जून 23 , 2007/आषाढ़ 2, 1929
[ भाग II- खण्ड 3 (ii) ]
workmen , received by the Central Government on 28-5-2007.
[No. L-42012/13/2005 - IR (CM -II ) ]
AJAY KUMAR GAUR, Desk Officer
That the services of the workmen have not been regularized as Regular Beldars on workcharged establishment w.e.f. 12-12-1985 and 6-5-1986 respectively whereas the services of some of the junior workmen to these workmen were regularized by the above managements .
ANNEXURE
BEFORE THE PRESIDINGOFFICER: CENTRAL GOVERNMENT INDUSTRIAL TRIBUNAL- CUM- LABOUR COURT- II , RAJENDRA BHAWAN, GROUND FLOOR, RAJENDRA PLACE, NEW DELHI
I.D. No. 117/2005
PRESIDING OFFICER : R. N. RAI
In the matter of :-
That consequent uponjudgment of Hon'ble Supreme Court of India in the matter of Surender Singh and others Vs. Engineer - in -Chief, CPWD and others , the workmen Shri Naresh Kumar and Shri Anand have been granted temporary status which includes basic pay, increment, leave , HRA, CCA w.e.f. 1-9-1993 and the workmen did not get other fringe benefits such as medical facilites , liveries cycle allowance, washing allowance etc. being as temporary status beldars .
Shri Naresh Kumar and Anr ;
C/o . All India CPWD ( MRM) Karamchari Sangathan
(Regd.)
House No. 4 , Gali No. 1 , Karkardooma Village , Delhi- 110092 .
Versus
That in accordance with the judgment of Hon'ble Supreme Court in the matter of Surender Singh and others Vs. Engineer - in- chief, CPWD and others and as per provisions of Model Standing Orders the workmen Shri Naresh Kumar and Anand , Beldars were entitled to be regularized from the respective dates of initial employment i.e. 12-12-1985 and 6-5-1986 in the regular pay scale along with all consequential benefits after putting in 90 days of service.
1. The Superintending Engineer , Electical Coordination Circle , CPWD , East Block , R. K. Puram , New Delhi .
That the workmen had put in 240 days of service in each year under the respondents and have been in continuous service since 12-12-1985 and 6-5-1986.
2. The Executive Engineer , B-Division , CPWD , I. P. Bhawan , NewDelhi .
AWARD
That the workmen have been performing the duties ofBeldars which are essentially the same duties that the performed by regular Beldars in the CPWD . The work being done by the workmen is essential to the work of the CPWD for day to day maintenance etc.
The Ministry of Labour by its letter No. L-42012/13/ 2005 - IR( CM - II ) Central Government Dt . 8-11-2005 has referrred the following point for adjudication .
The point runs as hereunder :--
That the workmen being designated as Temporary Status Beldars and that also from a subsequent date they are suffering by way of regular promotion, assured career promotion scheme benefits , pensionary benefits , seniority whereas similarly placed workmen in the regular establishment of the CPWD are entitled to all these benefits .
That vacant sanctioned posts are available with the respondent against which the services of these workmen canbe considered for absorption as work charged beldars in the estalishment of CPWD .
"Whether the demand ofthe All India CPWD (MRM) Karamchari Sangathan (Regd. ) , Gali No. 1 , Karkardooma Village , Delhi - 92 against the Superintending Engineer , Electrical Coordination Circle , CPWD, R. K. Puram, New Delhi/Executive Engineer , B-Division , CPWD , I.P. Bhawan, New Delhi for regularization of Shri Naresh Kumar and Shri Anand, Beldar w.e.f. 12-12-1985 and 6-5-1986 respectively i.e. from the date of initial appointment is legal and justified ? If so , to what benefits the workmen are entitled to ." ?
That the Hon'ble Tribunal in other similar cases viz . Shri Ram Khilari , Beldar, Mohan Lal and others, Kashi Nath and others has awarded regularisation from the date of initial employment on muster roll with all consequential benefits . An extract of the award of this Hon'ble Tribunal incase ofRam Khilari is enclosed and marked as Annexure- 1. The management of CPWD has implemented the award ofthe Hon'ble Tribunal .
That by its actions , the management is guilty of commission ofunfair labour practices as per provisions of the IDAct, 1947.
The workmen applicants have filed statement of claim. In the statement of claim it has been stated that the workman S / Shri Naresh Kumar and Anand have been working as Beldars on muster roll ( daily rated) w.e.f. 12-2-1985 and 6-5-1986 and the workmen are still working under the above managements as Beldars on muster roll .
3986
THE GAZETTE OF INDIA : JUNE 23 , 2007/ASADHA 2 , 1929
That the workmen Shri Naresh Kumar and Shri Anand, Beldars are legally and rightfully entitled to regularisation as work charged Beldars w.e.f. 12-12-1985 and 7-5-1986 with all consequential benefits .
The management has filed written statement. In the written statement it has been stated that the junior workers , Shri Randhir Singh whose date of appointment is 11-11-1986 and Shri Ram Prasad Tewari whose date of appointment is 10-1-1991 and Shri Kalu Ram whose date of appointment is 28-11-1985 respectively were regularized w.e.f. 3-8-2002 and 27-11-2001 as per Court's Order in O.A. No.2569 dated 22-2-2001 and O. A. No.362 / 2000 of 25-1-2001 and C.P. No.329 /2001 of dated 9-11-2001 respectively
TheHon'ble Supreme Court in its recent judgment dated 10-04-2006 in SLP ( C) No.9103-9104 of2001 had held asfollows:
"R. There is no case that any assurance was given by theGovernment or the concerned Department while making the appointment on daily wages that the status conferred on him will not be withdrawn until some rational reasons comes into existence for withdrawing it . The very engagement was against the constitutional scheme . Though the Commissioner of the Commercial Tres Department sought to get the appointments made permanent , there is no case that at the time of appointment any promise was held out. No such promise could also have been held out in view of the circulars and directives issued by.
The Government after the Dharwad decision . Though there is a case that the State had made regulations in the past of similarly situated employees , the fact remains that such regularizations were done only pursuant to judicial directions , either of the Administrative Tribunal or of the High Court and in some case by this Court. Moreover , the invocation of the doctrine of the legitimate expectation cannot enable the employees to claim that they Must be made permanent or they mustbe regularized inthe service though , they had not been selected interms of the Rules for appointment . The fact that in certain cases the Court had directed regularisation of the employees involved in those cases cannot be made use of to found a claim based on legitimate expectation. The argument if accepted would also run counter to the constitutional mandate . "
That regulation of service of daily rated workers depends on availability of vacancies in the respective category as per the terms and conditions of the prescribed recruitment rules .
[PART II-SEC . 3 (ii)] Inimplementation of the court's order in Surinder Singh case , the department got created 8982 posts in September , 1992 for regularisation of the eligible daily rated muster roll workers who were engaged prior to imposition of ban i.e. 19-11-1985 . Since the posts were created in September, 1992 therefore , all such woekers were regularized from the prospective dates and not from the date of their initial engagement . All the daily rated workers who were on the roll of the department have been paid difference of wages on the principle of equal pay for equal work from the date of their respective employment as casual labour .
Itisdenied that no one was regularized from the date ofhis /her initial date of engagement as stated by the workmen in para under reply . It is submitted that the case ofShri Ram Khilari is pending with DGW Office for direction and in the case of Shri Mohan Lal and Others the department has already filed a writ petition in the High Court ofDelhi and is still pending for final disposal and the case of Shri Kashi Nath and Others the department is going to challenge the award by filing writ petition in the High Court of Delhi is near future .
It is, therefore, respectfully prayed that the claim filed by the workmen may kindly be dismissed/rejected with heavy cost in the interest of justice.
From perusal of the records it transpires that reply was filed on 05-09-2006 and the workmen were directed to file rejoinder and affidavit . They did not file rejoinder and affidavit on 24-2-2006, 27-11-2006 , 3-1-2007 , 13-2-2007 , 7-3-2007, 23-3-2007 . Last opportunity has been given 4 times still no rejoinder and affidavit has been filed till 17-05-2007. The opportunity of filing rejoinder and affidavit was closed and the case was posted for award .
The workmen have failed to establish that juniors to them have been given regular appointment from the initial date of their engagement . The workmen were appointed as casual Beldar in 1985-86 . A casual Beldar has no right to regularisation in case there are no vacant posts . The workmen have not filed any evidence documentary or by way of affidavitto establish the statement of the claim . The averments of the claim stands not proved .
The reference is replied thus :-
The demand of the All India CPWD (MRM) Karamchari Sangathan ( Regd . ) , Gali No. 1 , Karardooma Village , Delhi - 92 against the Superintending Engineer , Electrical Coordination Circle , CPWD , R.K. Puram , New Delhi /Executive Engineer, B -Division , CPWD , I.P. Bhawan , New Delhi for regularization of Shri Naresh Kumar and Shri Anand, Beldar w.e.f. 12-12-1985 and 06-05-1986 respectively i.e. from the date of initial appointment is neither legal nor justified . The workmen applicants are not entitled to get any relief as prayed for .
The award is given accordingly . Date: 18-05-2007
R. N. RAI , Presiding Officer [भाग II- खण्ड 3( ii) ]
नई दिल्ली , 28 मई , 2007
का.आ. 1817-औद्योगिक विवाद अधिनियम , 1947 (1947 का 14 ) की धारा 17 के अनुसरण में, केन्द्रीय सरकार एस.सी.सी.एल. के प्रबंधतंत्र के संबद्ध नियोजकों और उनके कर्मकारों के बीच , अनुबंध में निर्दिष्ट औद्योगिक विवाद में औद्योगिक अधिकरण , गोदावरीखानी के पंचाट ( संदर्भ संख्या 30/2005 ) को प्रकाशित करती है, जो केन्द्रीय सरकार को 28-5-2007 को प्राप्त हुआ था । [सं. एल-22013/ 1/2007-आई आर ( सी- II ) ] अजय कुमार गौड़ , डेस्क अधिकारी New Delhi , the 28th May, 2007
S.O. 1817.-In pursuance of Section 17 of the Industrial Disputes Act, 1947 (14 of 1947 ) , the Central Government hereby publishes the award (Ref. No.30/2005) of the Industrial Tribunal Godavarikhani as shown in the Annexure in the Industrial Dispute between the employers in relation to the management of SCCL and their workman, which was received by the Central Government on 28-5- 2007.
[No. L-22013/1/2007- IR(C- II) ] AJAY KUMAR GAUR, Desk Officer
ANNEXURE
BEFORE THE CHAIRMAN, INDUSTRIAL TRIBUNAL-CUM - LABOUR COURT, GODAVARIKHANI
Present: Sri M. Shanmugam, B. Com. , B. L. , Chairman -cum -Presiding Officer Saturday, The 23rd Day of December, 2006 Industrial Dispute No. 30 of2005 Between:--
Pallikonda Chandraiah , S/o Chinna Lingaiah , Age45 yrs . , Occ: Ex -SCCL Employee, (CoalCutter in RKNT incline , Srirampur Area, (E.No. 2760868), R/ o Sunnambatti Wada ,
Mancherial town & Mdl . of Adilabad Dist .
3987
भारत का राजपत्र : जून 23, 2007/आषाढ़ 2 , 1929
for consideration till this date, the court passed the following:
AWARD
1. This is a petition filed U/Sec . 2-A(2) of I.D. , Act, 1947 praying to set - aside the proc. , Ref . No. SRP/PER/ 13.008/692, dt . 27-1-2005 passed by the respondent and direct the respondent's company to reinstate him into service with continuity of service and all sorts of consequential attendant benefits thereof including full back-wages to meet ends of justice.
2. The petition affidavit allegations briefly are as follows:-
The petitioner submits that he was appointed in the SCCo . Ltd. , in the year 1985 and served the company for about 19 years without any adverse remarks . He adhered to the instructions of the respondent's authority and discharged his duties to the utmost satisfaction of his superiors.
3. He had not habitually absented from his duties during the year, 2002 , as has been alleged by the management without sufficient cause . It was repeatedly reportedto all concerned that his father was suffering from paralysis . He had been attending on him on the days of his absence to the duties as there was no other member of his family to look after as carefully as he does . A farce of enquiry was conducted turning a deaf ear to his explanation . It was all done at the behest of the management only to dismiss him without paying any attention to the cause shown by him for his absence.
4.The management's out look is evident by this that workman is a machine tool . He has to attend to his duties by hook or crook welfare of the workman includes his father, mother, wife and children atleast if not more than that . The management should also have the human face to be sympathetic to the problem being faced by the workman .
5.All that isto pray this court is that he is not habitual absentee of his duties . He had to remain during the days on his absence at home in 2002 only to help his paralysis father under forced circumstances .
....Petitioner
AND
TheGeneral Manager,
TheSCCo.Ltd. , Srirampur Area,
Adilabad Dist .
6. It is also pertinent to take into consideration that he has undergone treatment for viral fever from 4-11-2004 to 30-11-2004. The Civil Asst . Surgeon . Peddapalli , who treated him had given him fitness certificate to this effect .
....Respondents
This Industrial Dispute petition coming on before me for final hearing on 11-12-2006 upon perusing all the documents on record and upon hearing arguments of Sri D. Krishna Murthy, Advocate for the respondents . For the petitioner , he filed the petition . Afterwards , he was called absent, set-exparte, he did not engage the counsel . As per Rule 24 ofA. P. , I. D. , Rules, ifwithout sufficient cause , the petitioner fails to attend or to be represented before this court, it shouldbe considered as ifthe party had duly attended or had been represented, and having stood over 7. He hails from a very poor family and his entire family members are facing much hardships for livelihood. He remained unemployed and could not secure any alternate employment , despite best efforts. He did not file any petition before any court of law , seeking this relief. Therefore prayed this courtto set - aside the proceedings Ref. No. SRP/PER/13.008 /692 ,dt. 27-1-2005 passed by the respondent and direct the respondent's company to reinstate him into service with continuity of service and all sorts of consequential attendant benefits thereof including full back -wages to meet ends of justice.
3988
THE GAZETTE OF INDIA : JUNE 23 , 2007/ ASADHA 2 , 1929
[ PART II-SEC. 3 (ii )]
the enquiry the charges ievelled against the petitioner were explained to him by the enquiry officer . The petitioner was advised to take the assistance of any of his co - worker to defend his case . The petitioner did not want to take the assistance of any of his co - worker , and admitted his guilt . The petitioner did also not choose to cross - examine the management witnesses during the enquiry proceedings . During the enquiry the petitioner stated before the enquiry officer that he was absent for duties due the paralysis to his father and assured the respondent company that he will be regular in future and requested to excuse him in view of his long service in the company . That he did not submit any documents in support of the ill- health of his father. With a view to give him a final opportunity he was issued with a show- cause noticedt . 28-1-2004 . The petitioner submitted his representationdt . 6-2-2004 requesting the company that he may be given final opportunity and he will put up 20 musters per month in future and if he fails , action may be taken against him.
8. The averments of the counter filed by the respondent are that it is a Govt. company incorporated under the provisions of Companies Act , 1956 for carrying out the business of winning and selling the coal . That since the coal mining industry is a central subject , the appropriateGovernment for this respondent -management is Central Government . The respondent submits that as per S.7 ( i ) of ID Act , the appropriate Government may by notification in the official gazette constitute one or more Industrial Tribunals for the adjudication of industrial disputes relating to any matter whether specified in the 2nd schedule or 3rd schedule and for performing such other functions as may be assigned to them under this Act . That the Central Government established an Industrial Tribunal- cum-Labour Court at Hyderabad from 29-12-2000 for adjudication of Industrial Disputes and the petitioner ought to have approached the said tribunal for the redressal of grievance, if any. But the petitioner conveniently avoided to file his petition before the tribunal established by the Central Government for the reasons best know to him. That the petition is not maintainable under law and the same may be dismissed on this ground alone .
9. That the maintainability of the dispute raised by the petitioner before this court may be decided as preliminary issue before proceeding with the trial .
That in pursuance of his representation dt . 6-2-2004 and undertaking dt . 11-2-2004 the petitioner was allowed to worked and to improve his performance and kept the punishment in abeyance . The in sipite of giving opportunity the petitioner has put in only 82 days of attendance during the entire year of 2004 and failed to put -up 20 musters per month as assured by him during the observation period. That the petitioner worked 79 days in the year 2002, 88 days in the year 2003 ; and 82 days in the year , 2004. The petitioner failed to improve his attendance in the year 2003 in spite of receipt of charge sheet arid did not improve his performances as per his undertaking in the year 2004. As such, the services of the petitioner were terminated vide orderdt . 27-1-2005 w.c.f. , 1-2-2005 .
10. That petitioner failed to exhaust the conciliation procedure aslaid down in the ID Act and filed the present petition before this tribunal under S. 2A( 2) of ID Act , 1947 asamendedby A.P. , Amendment Act , 1987 (Act No. 32 of 1987) . That as the appropriate Government for coal mining industry is the Central Government the State Amendment Act is not applicable to the respondent and the petition filedby the petitioner is not maintainable under law and is liable to be dismissed in limine .
11. The respondent submits that in reply to para i of the petition that the petitioner was appointed in the respondent company vide order dt . 27-1-2005 for his mis- conduct of habitual absence from his duties during the year 2002. That prior to his dismissal , he is not regular in his duties .
15. It is submitted that the respondent company is doing the business of winning and selling of coal by employing more than 90,000 persons . It is further submitted that if the employees habitually abstain/abscond from their duties the required production/planned production targets will not be achieved resulting in huge lossesto the respondent company . To avoid this contingency the respondent company incorporated the absenteeism as one of the acts of misconduct which is approved by the Central Government in accordance with the procedure laid down in the industrial employment ( Standing orders) Act, 1946 .
12. In reply to para 2,3 &4 of petition the respondent submits that the petitioner attended 150 days in the year , 1999, 147 days in the year 2000 and 141 days in the year 2001. He attended for only 79 days during the year 2002 and remained absent for the remaining period without leave or permission. As such the petitioner was issued with the charge sheet t . 25-3-2003 for his mis- conduct of habitual absence from duty without leave or permission under clause 25.25 of the certified standing orders of the company. In spite of receipt of the chargesheet the petitioner failed to submit his explanation . The date of enquiry into the above charge-sheet was fixed on 19-7-2003 and enquiry notice wasserved on the petitioner on 15-7-2003.
16. In reply to para 5 of the petition , it is submitted thatthe petitioner had never submitted any documents to prove the illness of his father before the enquiry officer . Thatthe petitioner had never represented to the respondent company regarding his illness from 4-11-2004 to 30-11-2004 . That the charge sheetdt . 25-3-2003 issued to the petitioner pertaining to his unauthorised absence for his duties during the year 2002 and the alleged illness stated by the petitioner isnot pertaining to the charge- sheeted period.
13. The petitioner attended the enquiry on 19-7-2003 and fully participated in the enquiry proceedings . During
17. That the respondent - company is maintaining a chainof hospitals to cater health and medical needs of its [ भाग II- खण्ड 3 ( ii) ]
भारत का राजपत्र : जून 23 , 2007/ आषाढ़ 2 , 1929
workmen and their family members . Had the father of petitioner really suffered from paralysis he would definitely have taken treatment in the respondent's hospital . That only to gain sympathy the petitioner is coming with all such false pleas. The petitioner concealing all the above facts filled this petition for his wrongful gain. Therefore , the respondent company prays his court to dismiss the petition in the ends of justice ; else the respondent company suffers irreparable loss .
18. On behalf of the petitioner side , after filing of the claim statement, the petitioner did not choose to turn -up to the court to prove his innocence . On the petitioner side , no documents are filed , no oral evidence and decisions filed into the court. On behalf of the respondent side also no oral evidence and documents are marked, and also no decisions are filed . Only arguments heard by the respondent side . As per Rule 24 of ID Act followed on behalf of the petitioner and heard argument on behalf of the respondent .
19. Before going to the merits of the case . I would like to submit the delay of the petition for disposal , he filed the petition on 28-2-2005 and it was numbered on 29-3-2005 . Counter was filed on 8-8-2005 . He was made set- exparte for his failure to appear on 21-8-2006 . Respondent sideheard arguments on 11-12-2006 . Vakalat was not filed nearly 6 months . In this case , consent was inferred. In the claim statement , there is no signature who verified the affidavit allegations . After filing of claim statement , the petitioner did not turn -up to the court to defend his case .
20. It is an admitted fact that the petitioner was appointed in the company and he worked as coal cutier. fle was dismissed from the services vide letter dt. 27-1-2005 under the provisions of 25 (25) of certified standing orders i.e. , absenteeism .
21. The claim statement allegations , the petitioner's father was suffered from paralysis . He had been attended onhim on the days of his absence to look- after as carefully asthe petitioner do. The absence of the petitioner was not intentional , but accidental which deserves to be condoned. The act of punishment of dismissal from service by the petitioner by the respondent is highly shocking and dis- proportionate to the gravity of the charge . Hence , he prayed this courtto set- aside the dismissal order directing the respondent to re- instate the petitioner into service with continuity of service with all other attendant benefits including the back-wages etc.
22. The respondent counsel argument was that the company is established under the Companies Act . Central Government established an industrial Tribunal -cum - Labour Court at Hyderabad for adjudication of industrial disputes . The petitioner filed this petition in this court is not maintainable under law, hence , the same may be dismissed on that ground alone. The petitioner had put only 82 days of attendance during the year 2002 without leave or permission . The petitioner was issued with a charge sheet
3989 under clause No. 25.25 of standing orders of the respondent company for his misconduct of habitual absenteeism and the petitioner was suspended . The petitioner submitted his explanation stating that due to his father's suffered from paralysis he had not attended duty and requested the company to excuse him for this time. As his explanation was not satisfactory a domestic enquiry was ordered and issued enquiry notice and conducted the enquiry . The petitioner attended the enquiry and participated in the domestic enquiry. The charges were explained to the petitioner and he has no objection to record the proceedings of the enquiry in English language . He did not take the assistance of any defence and he accepted the charges levelled against him and pleaded guilty of misconduct . He was also not chooses to cross - examine the management witnesses during the domestic enquiry. In the domestic enquiry , he clearly stated and he admitted that he had absented from his duties habitually from January, 2002 to December , 2002 due to ill-health . The petitioner did not give any explanation to the charge sheet served on him . Petitioner also did not filed any documents to prove that he and his father suffered ill - health . The petition gave assurance to the respondent that he will attend regularly without absenteeism. On his undertaking he was kept under observation, but the petitioner failed to attend to his duties in spite of his undertaking given . The charges framed against him were proved in the domestic enquiry . Respondent issued show cause notice by enclosing the copies of enquiry report and enquiry proceedings . The petitioner gave the reply to the show cause notice . The petitioner failedto improve his performance in spite ofgiving fair opportunity and his past performance is also not satisfactory. Hence , the respondent company constrained to dismissal the service of the petitioner . The petitioner concealing all the above facts filed this petition . Hence , he prayed this court to dismiss the petition in the ends of justice ; else the respondent company suffers from irreparable loss.
23. From the petitioner's claim statement and on its perusal and also the arguments of the respondent counsel , the following issue is framed as preliminary issue for determination.
Whether the enquiry was conducted , turning a deep ear to thepetitioner's explanation.
24. As per the above , the respondent counsel argument was that the petitioner is habitual absenteeism without obtaining any prior permission from the authorities concerned and his absconding from duties. The petitioner also did not filed any documents that his father was suffered with paralysis and he attended to look - after him. The respondent followed the procedure of principles of natural justice by issuing the charge sheet by sending a notice of enquiry to the petitioner and he was also participated in the enquiry and enquiry he admitted the guilt and he was also given and undertaking stating that the hereafterwards he will not be absented to his duties . He was also given family 3990
THE GAZETTE OF INDIA : JUNE 23 , 2007/ASADHA 2, 1929
counselling.Eventhen , he was continuing to absent. During the observation period also he failed to attend to his duties . He was also given fair opportunity to defend his case in the domestic enquiry . After issuing show cause notice to the petitioner, the petitioner also gave the reply. The respondent was not satisfied with the reply given by the petitioner . The respondent followed the principles of natural justice i.e. , by issuing notice and conducting enquiry by givinganopportunity to the petitioner . The petitioner did not raised any objection or any dispute , so the petitioner did not got anyprejudice in conducting the enquiry . Hence , Idid not find the petitioner was not prejudice in any way on account of conducting enquiry by the respondent . It cannot be said that the enquiry was conducted in gross violation of principles of natural justice . The findings recordedby the respondent is perfectly legal and valid . It need not be interfered with by this court . So , the petitioner's contentionwill be refused. The court thinks the case of the petitioner is not at all real one substance or that there is substantiate possibility of success or that the result will be not different even if natural justice is followed . Hence , the domestic enquiry conducted is legal , proper , valid and binding on the parties .
25. The misconduct committed by the petitioner is unauthorised absence , as he did not obtain any prior permission from the main authorities for absconding from his duties is undoubtedly and irregularity and serious in nature. In the circumstances , this court cannot take any lenient view and substitute its opinion for that of the respondent. The findings of the respondent even on the question relating to the proportionality of punishment is based upon the evidence available on record . In this case , the petitioner did not turned- up to the court and he did not filed any documents to prove that his father suffered ill- health and takentreatment . The past record of the petitioner also shows his habitual absenteeism in attending to his duties.
[PART II-SBC. 3 (ii)] was no improvement in his behaviour to attend the duties, the respondent has no other go except to dismiss the petitioner fromthe service.
28. As per the claim statement allegations , the contentionof the petitioner that the punishment of dismissal ofthe petitioner from service of the company is totallydis- proportionate to the proved misconduct of unauthorised absenteeism of the petitioner . The disciplinary authority failed to advert itself to the aspect of the matter. I find it difficult to accept the submissions made by the petitioner in his claim statement . In this case , the petition admitted the unauthorised absenteeism in the enquiry proceedings . The petitioner also did not turn - up to the court to prove his case. The petitioner also did not file any documents to prove that he had taken treatment from the hospitals.
29. In my view his court would have no jurisdiction to show any sympathy for such a workman who is guilty of unauthorised absence should not be shown any leniency especially when he continuous to absent himself and for long period . The enquiry officer and the disciplinary authority both have consierded all the facts and circumstances of the case and have correctly recorded their findings against the petitioner . I do not find any serious illegality or any infirmity in the order of the respondent . Hence, I therefore dismiss the petition .
In the result, the petition is liable to be dismissed and isaccordingly dismissed. But in the circumstances , no costs.
Typed to my dictation by Typist directly, corrected and pronounced by me in the open court on this , the 23rd day ofDecember , 2006 .
M. SHANMUGAM , Chairman -cum- Presiding Officer Appendix ofEvidence Witnesses examined
ForManagement : ---
Forworkman:-
-Nil
26. In myconsidered opinion that the findings taken by the respondent does not suffer from any error whatsoever . Having regarding all the aspects and circumstances of the case , the punishment imposed by the management is not disproportionate requiring any interference in exercising the discretion u/ sec.11 - A of the I.D. Act.
27. From the respondents counsel argument the petitioner in failed to report for duty and remaining absent without obtaining leave , had acted in a manner irresponsibility and unjustifiedly that on the findings of the enquiry officer, the charge was proved that the petitioner remained absent without obtaining leave in evidence. The respondent company has not resorted to extreme punishment at the every first instance of absenteeism of the petitioner -workman . The respondent company has tolerated him for quite some time and ultimately when there
Nil-
Exhibits
ForWorkman : ------ -Nil-
ForManagement : ---- -Nil- नई दिल्ली, 28 मई , 2007
का. आ 1818. औद्योगिक विवाद अधिनियम , 1947 (1947 का 14) की धारा 17 के अनुसरण में , केन्द्रीय सरकार टेलीग्राफ ऑफिस , रामपुर के प्रबंधतंत्र के संबद्ध नियोजकों और उनके कर्मकारों के बीच , अनुबंध में निर्दिष्ट औद्योगिक विवाद में केन्द्रीय सरकार औद्योगिक अधिकरण/ श्रम न्यायालय नं.- II , नई दिल्ली के पंचाट ( संदर्भ संख्या 95/2000 ) को प्रकाशित करती है , जो केन्द्रीय सरकार को 28-5-2007 को प्राप्त हुआ था।
[सं. एल-40012/282/2000- आई आर ( डी.यू. ) ] सुरेन्द्रसिंह, डेस्क अधिकारी 3991 [ भाग II-खण्ड 3( ii) ]
भारत का राजपत्र जून 23, 2007/आषाढ़ 2, 1929
New Delhi , the 28th May, 2007
complaint either from the public or his superiors and colleagures . Thus the workman remained in service of Opposite Party for more than 10 years .
That it is unfortunate that the workman was not allowed to perform his duties after the aforesaid date without any notice and thus his termination from service was illegal and arbitrary.
S.O. 1818. In pursuance of Section 17 of the Industrial Disputes Act, 1947 (14 of 1947) , the Central Government hereby publishes the award (Ref. No. 95/2000) Government Industrial Tribunal-cum- Labour Court No.II, New Delhi as shown in the Annexure in the Industrial Dispute between the employers in relation to the management of Telegraph Office , Rampur and their workman , which was received by the Central Government on28-5-2007 .
[No. L-40012/282/2000- IR(DU) ]
SURENDRA SINGH , Desk Officer
ANNEXURE
That another unfortunate aspect is that a new hand was employed in his place while the workman was ousted from the department of Opposite Party . That the Opposite Party admitted during the proceedings before the ALC( C) , Dehradun that the workman was initially appointed by Vibhagya Tar Ghar , Rampur ( UP) which was at that time independent and separate entity but later on came under the control ofTelecom Divisional Manager , Rampur(UP) .
BEFORE THE PRESIDING OFFICER CENTRAL GOVERNMENT INDUSTRIAL TRIBUNAL- CUM-LABOUR, COURT - IL,
NEWDELHI
L.D. No. 95/2000
PRESIDING OFFICER : R.N.RAL
PRESENT:
Shri Bhawani Shankar Sharma -1st Party
That the workman comes within the purview of ID Act, 1947 and thus he is entitled for the claim as envisaged under the Act viz . his reinstatement in service with all consequential benefits of pay and seniority etc. that in the whole process from the date of appointment of worker till he was terminated from service, he had neither committed any illegality nor irregularity.
Shri V.S.R. Krishna
-2ndParty
IN THE MATTER OF :-
Shri Ram Niwas ,
S/o. Shri Rattan Lal , R/ o . Mohalla Beldaran , Rampur (UP), PIN -144901.
That the opposite party did not give its consent for voluntary arbitration or joint refernce although the workman agreed to it . The opposite party concealed the fact that the Government of India through their Memo No. 269-13/99- STN- 11 dated 16-9-1999 approved the conversion of part time casual labour working for four hours or more regularized as full time casual labour . The copyf memo dated 16-09-1999 is placed at Annexure "G".
Versus
The Officer Incharge , Telegraph Office, Rampur(UP) , PIN - 244901 .
AWARD
TheMinistry of Labour by its letter No. IL-40012/282/ 2000- IR(DU) Central Government dt. 29-8-2000 has referred the following point for adjudication.
That the workman worked with the opposite party for more than10 years and thus he has lost his youth period to the organization . Unfortunately the workman got bitter results in as much as that he was ousted from service without assigning any reason what to talk of giving any notice . The opposite party has committed an inhuman act by ousting the workman from service and totally ignored the fate of his dependents but was thrown at the brink of starvation.
The point runs as hereunder : --
"Whether the action of the management of Vibhagiya Tar Ghar merged with Telecom Departrnent, Rampur in regard to terminating the services of Shri Ram Niwas, Part Time Sweeper w.e.f. 16-5-1999 is just, fair and legal? If not, to what relief the workman is entitled and from what date ?"
In the aforesaid circumstances , the workman respectfully prays for his reinstatement in service from the date of his termination with all consequential benefits of pay, allowances and seniority etc. It is specifically prayed that the workman may kindly be ordered to be paid the emoluments which were not paid to him for the period he had with the opposite party .
The workman applicant has filed statement of claim.
Inthe statement of claim it has been stated that the workman was initially appointed as a Sweeper on part time basis on 7-3-1989 by the Opposite Party and was posted in the Telegraph Office at Rampur . The related letters are enclosed at Annexures " D" and "E" respectively.
That the workman continued to perform his duty with full devotion , dedication up to 15-5-1999 without any
The management has filed written statement. In the written statement it has been stated that the above claim is pending before this Hon'ble Tribunal and the next date of hearing of the case is now fixed for 20-9-2005 . The issue raised for adjudication by the Central Government is as to whether the alleged termination of the workman by the Vibhagya Tar Ghar merged with Telecom District Rampur is justand proper.
2733G1/07-11 3992
[PART II-SEC. 3 ( ii) ] THE GAZETTE OF INDIA : JUNE 23 , 2007/ASADHA 2, 1929
complaint either from the public or his superiors and colleagues. He remained in service of the opposite party for more than 10 years .
That inthis contention the respondents wish to bring to the notice of this Ld . Tribunal that there had been no termination of the claimant as alleged and therefore the claimant is not entitled to any relief from this Ld . Tribunal.
It was further submitted that OM dated 16-9-1999 approved the conversion of part time casual labours working for 4 hours or more as full time casual labours .
The workman has filed engagement letter of4-3-1989. It has beenmentioned in this letter that he was engaged for 2hours daily.
That as a matter of fact the claimant was engaged in the respondents' office as a part time sweeper on purely temporary basis for a period of two hours and was paid accordingly. In such circumstances for the claimant to claim permanent employment is without any basis and the relief prayed for is misconceived.
Itwas further submitted that on 11-4-1994 competent authority directed the management for increasing the period ofthe workman. It has been mentioned in this engagement letter that the workman should be engaged in case of weekly rest of the Chowkidar or some Group-D Staff goes on leave . Ithas been also mentioned in this letter that the workman should be given 5 hours work daily. The workman has filed OM dated 16-9-1999 and it has been directed in this OM that part time casual labourers working for 4 hours or more should be converted into full time casual labourers .
That since the claimant is only a part time worker he is not entitled to any relief prayed for. That apart it is submitted that the Vibhagya Tar Ghar merged with Telecom District Rampur on 31-12-1995 and since then the claimant is not working in the office of the respondents . The petitioners reliance on the provisons of Government of India'sCM is not applicable as the petitioner was engaged and disengaged prior to the issuance of the said notification. Be as it may be it is submitted that the petitioner having been engaged on a part time basis no rights accrue tohim for being permanently absorbed in the office of the respondents. It is submitted that the petitioner was not terminated as alleged but he himself stopped coming to the office and therefore the question of violation of any provisions of ID Act does not arise .
That the allegation of the petitioner/claimant that he had worked in the office of the respondents till 18-5-1999 is totally false and misleading. The petitioner was disengaged in the year 1995 itself and at the time of disengagement he was engaged only as a part time sweeper and hence no rights accrue to him to be regularized in the office of respondents .
Itwas submitted from the side of the management that the workman has not filed any document regarding his employment till 1999. He was initially engaged for 2 hours daily and from 11-4-1994 he has been given work in stop gap arrangement . It has been specifically mentioned in the letter dated 11-4-1994 that this workman should be given work for 5 hours during the rest period of Chowkidar or leaveperiod ofsome Group - Demployee . It indicates that this workman was not even casual part time worker . It has beendirected by letter dated 11-4-1994 that he should be engaged as stop gap arrangement . The workman has not filed any document to show that he has worked continuously from 1989 to 1999.
That apart the present reference is highly belated and to this extent the claim petition is liable to be dismissed.
He has filed only two documents one relating his engagement as part time sweeper for 2 hours daily . The other document filed by the workman regarding his employment is letter dated 11-4-1994 by which it has been directed that the workman should be engaged as stop gap arrangement in view of some contingency.
The workman applicant has filed rejoinder. In the rejoinder he has reiterated the averments of his claim statement and has denied most of the paras of the written statement. The management has also denied most of the paras of the claim statement.
Evidence ofboth the parties has been taken.
The workman has filed no document to show that evenhis stop gap arrangement continued up to 16-5-1999 .
Heard arguments from both the sides and perused the papers on the record.
The workman has stated that he has worked continuously from 7-3-1989 to 16-5-1999. He has filed no document regarding his period of employment . Engagement letter establishes that he was engaged for a period of 2hours on daily wages basis . Letter dated 11-4-1994 shows that the workman was given engagement when Chowkidar orGroup -D employee was on leave .
Itbecomes quite obvious from perusal of the record that this case was decided ex -parte and ex -parte award dated 29-12-2005 was sent to the Ministry of Labour for publication but subsequently the management moved an application for setting aside the ex -parte award within time . The ex-parte award has been set aside by order date 30-3-2006.
The workman was not in employment prior to OM dated 16-9-1999. Had he been in employment he would have filed application for being converted into a full time casual labour . The workman has not filed copy of any application addressed to the management for converting him to full time casual labour. The workman has not filed Itwas submitted from the side of the workman that he was engaged by the management w.e.f. 07-03-1989 as part time sweeper . He performed his duties regularly with full devotion and dedication upto 15-05-1999 without any 3993
भारत का राजपत्र : जून 23, 2007/आषाढ़ 2, 1929
[भाग II-खण्ड 3 (ii) ]
any document to establish the fact that he worked even as parttime sweeper up to 16-5-1999 . He has filed only affidavit in evidence . It is settled law that the claim of the workman cannot be decided on the basis of only his affidavit. He has not filed any cogent documentary evidence in support of his claim statement . The averments of the claim do not stand established for lack of documentary evidence .
The reference is replied thus:
The action of the management of Vibhagiya Tar Ghar merged with Telecom Department, Rampur in regard to terminating the services of Shri Ram Niwas , Part Time Sweeper w.e.f. 16-5-1999 is just, fair and legal . The workman applicant is not entitled to get any relief as prayed for.
The award isgiven accordingly.
Date: 16-5-2007
R. N. RAI , Presiding Officer नई दिल्ली, 28 मई , 2007
का. आ. 1819. औद्योगिक विवाद अधिनियम, 1947 ( 1947 का 14 ) की धारा 17 के अनुसरण में , केन्द्रीय सरकार सी.पी.डब्ल्यू. डी. के प्रबंधतंत्र के संबद्ध नियोजकों और उनके कर्मकारों के बीच , अनुबंध में निर्दिष्ट औद्योगिक विवाद में केन्द्रीय सरकार औद्योगिक अधिकरण/ श्रम न्यायालय नं.- II , नई दिल्ली के पंचाट ( संदर्भ संख्या 5/2007 ) को प्रकाशित करती है , जो केन्द्रीय सरकार को 28-5-2007 को प्राप्त हुआ था।
['सं. एल-42011 /92/2006- आई आर ( डी.यू.) ]
सुरेन्द्र सिंह , डेस्क अधिकारी
Versus
The Executive Engineer (Civil ) , CPWD,
Central Division No. 20,
Subhash Road,
Dehradun (Uttrakhand)
AWARD
TheMinistry of Labour by its letter No.L- 42011/92/ 2006- IR (DU) Central Governmentdt. 12-2-2007 has referred the following point for adjudication .
The point runs as hereunder :-
"Whether the action ofthe management ofCPWD in not granting ACP upgradation I and II on completing 12 and 24 years of service , in scale of pay of Rs . 2610-4000 and 2750-4400 respectively to their WorkmenShri Laxman Shah S/o . Shri Sital Shah and Shri Anil Kumar Chopra, S/o . Shri Tilak Raj is legal and justified ? If not, to what relief the workmen are entitled to and from which date ."
The workmen applicants have not filed claim statement. Itwas submitted from the side of the management that the workmen have been provided the scale demanded by them, so they have not filed claim . The copy of the order regarding upgradation in the scale of Rs . 2650-65- 3300-70-4000 have been filed .
No dispute award is given.
Date: 15-5-2007
New Delhi , the 28th May, 2007
S.O. 1819. In pursuance of Section 17 of the Industrial Disputes Act, 1947 ( 14 of 1947) , the Central Government hereby publishes the award (Ref. No. 5/2007 ) Government Industrial Tribunal-cum-Labour Court No.II , New Delhi as shown in the Annexure in the Industrial Dispute between the employers in relation to the management of CPWD and their workmen , which was receivedby the Central Government on 28-5-2007.
[No. L-42011/92/2006- IR(DU)]
SURENDRA SINGH, Desk Officer
ANNEXURE
BEFORE THE PRESIDING OFFICER CENTRAL GOVERNMENT INDUSTRIAL TRIBUNAL CUM- LABOUR, COURT- II, NEW DELHI PRESIDING OFFICER : R.N.RAL.
L.D. No. 5/2007
IN THE MATTER OF :
Shri Laxman Shah and Anr.
C/o . The Secretary,
CPWD MazdoorUnion, 55-A, E.C. Road, Subhash Road, Dehradun (Uttrakhand)
R. N. RAI , Presiding Officer नई दिल्ली, 28 मई , 2007
का. आ. 1820. औद्योगिक विवाद अधिनियम, 1947 (1947 का 14 ) की धारा 17 के अनुसरण में , केन्द्रीय सरकार टी.डी.ई. , बी.एस.एन.एल. के प्रबंधतंत्र के संबद्ध नियोजकों और उनके कर्मकारों के बीच , अनुबंध में निर्दिष्ट औद्योगिक विवाद में केन्द्रीय सरकार औद्योगिक अधिकरण/ श्रम न्यायालय नं.- II , नई दिल्ली के पंचाट (संदर्भ संख्या 24/2005 ) को प्रकाशित करती है, जो केन्द्रीय सरकार को 28-5-2007 को प्राप्त हुआ था।
[सं. एल -40012/156/2004- आई आर ( डी.यू.) ] सुरेन्द्रसिंह , डेस्क अधिकारी New Delhi , the 28th May, 2007
S.O. 1820. In pursuance of Section 17 of the Industrial Disputes Act, 1947 ( 14 of 1947) , the Central Government hereby publishes the award (Ref. No. 24/2005) Government Industrial Tribunal-cum -Labour Court No.II , New Delhi as shown in the Annexure in the Industrial Dispute between the employers in relation to the management ofT.D.E. , B.S.N.L. and their workman, which was received by the Central Government on 28-5-2007.
[No. L-40012/156/2004- IR(DU) ] SURENDRA SINGH, Desk Officer 3994
THE GAZETTE OF INDIA : JUNE 23 , 2007/ASADHA 2, 1929
ANNEXURE
BEFORE THE PRESIDING OFFICER, CENTRAL GOVT. INDUSTRIAL TRIBUNAL- CUM- LABOUR, COURT - II,
NEW DELHI
I.D. No. 24/2005 Presiding Officer : R.N. Rai .
Present:
[PART 11-SEC. 3 (ii) ] illegally terminated the service of the applicant on 01-03-2002 without any notice or information . Retrenchment compensation and notice pay was not paid to the applicant by the respondents.
1stParty
Sh. R.S. Seingar
That after his termination the applicant visited the office of the respondents various times for joining his duties but the respondents misbehaved with the applicant and refused to take him on duty.
2ndParty
Sh . Dinesh Agnani
IN THE MATTER OF :
Shri Inder Singh , S/o. Shri Surta Ram, R/o . Vill. Sudkain Kalan , Tehsil Narwana,
Distt.:Jind (Haryana)
Versus
1. The Sub Divisional Officer (Telephone) , Bharat Sanchar Nigam Limited, Narwana, District : Jind (Haryana)
2. The T.DE. ,
Bharat Sanchar Nigam Limited , Jind(Haryana)
AWARD
TheMinistry ofLabour by its letter No. L-40012/156/ 2004 - IR (DU) Central Governmentdt . 22-03-2005 has referred the following point for adjudication .
The point runs as hereunder :
"Whether the action of the management of BSNL , Jind in terminating the services of Shri Inder Singh , S/o. Shri Surta Ram , daily wages worker w.e.f. 01-03-2002 is just and legal? If not , to what relief the workman is entitled . "
Theworkman applicant has filed statement of claim . Inthe staterment of claim it has been stated that the applicant was employedwith the above named respondent No.1 since 1991, 1992 as a regular (Welder) and he had regularly worked upto28-02-2002 and his last drawn wages were Rs.1500 per month.
That the applicant always performed his duties with hard labour and due diligence , never given any chance of complaintsto the respondents nor he was chargesheeted. Applicant has worked under kind control of many SDOS i.e. Mr. Ishpal Dhillon , Mr. V.P. Singh , Tyagi Sahab and lastlywith Mr. Amar Singh Malik.
That in spite of this the respondents did not give any legal facilities to the applicant i.e. appointment letter, attendance card, pay slip , leave wages , medical leaves , uniform, bonus etc. which were orally demanded by the applicant several times to the respondents , but the respondents did not provide the same .
Thatthe applicant demanded his legal facilities again and again from the respondents , then the respondents That thereafter the applicant sent a demand letter dated 20-09-2002 to the respondents which have been served upon the respondent but the respondents have not paid any heed to the request of the applicant and thereafter the applicant sent a second demand letter dated 08-09-2003 by Registered A/D post to the respondents but the management also did not give any reply of the same.
Thatthereafter the applicant filed an application for reinstatement in service before the office of the ALC ( C) , S.I. overmain shopping centre NH - IV , Faridabad but the management did not agree to concile the above said matter then the ALC ( C) , Faridabad referred this matter before this Hon'ble Tribunal for adjudication.
That the above said acts of the respondents are highly illegal unjust , improper and against the provisions ofIndustrial Disputes (Central ) Rules , 1957 .
That the applicant is unemployed since his illegal termination by the respondents . The applicant is a very poorperson and has no other source of income to maintain himself and his family members . Due to the termination of the applicant from his service the applicant and his family members are living in starvation.
Thatthe workman applicant further pray that an award may kindly be passed in favour of the applicant for reinstatement in old and devoted service alongwith full backwages and 18% interest may also be awarded to the applicant . And also award all the consequential benefits to the applicant in the interest of justice .
The management has filed written statement . In the written statement it has been stated that the present reference is without application of mind in as much as the appropriate government has made the present reference without appreciating the fact that Shri Inder Singh was never appointed by the answering management as such while referring the disputes the appropriate government has erred in coming to the conclusion that there has been termination of services of Shri Inder Singh when admittedly no documents whatsoever has been placed on record to show the alleged termination of Shri Inder Singh as such the present reference is liable to be answered in negative .
That the present claim is bad for delay and latches as admittedly , it has been alleged by Shri Inder Singh that he was working regularly upto 28-02-2002 and has raised present dispute only in the year 2004 , which clearly establish that the present petition is not only bad for delay [भाग II- खण्ड 3(ii) ]
and latches but also merits no consideration in as much as there has been no relationship of employer and employee between Shri Inder Singh and the respondents at any point of time . As such also, the present reference is liable to be answered in negative .
Thatthe statement made in the claim petition are not only vague and do not disclose any fact and infact Shri Inder Singh has not annexed any document in support of the statements regarding the alleged employment with the respondents. As such also the present claim petition is liabletobe rejected.
That the respondentsBharat Sanchar Nigam Limited came into existence only w.e.f. 01-10-2000 . It is the case of the petitioner that he was employed by the Respondent No.1 since 1991-1992, which clearly shows that the statements made in the present statement of claim are false , mischievous and have been made with malafide intention andulterior motive . As such also the present claim petition is liable to be dismissed.
That it has been alleged by the petitioner that he was working as a regular employee since 1991-1992 but no documents in support thereof has been placed on record to establish the said fact. It is submitted that the said Shri Inder Singh has neither placed on record the letter of appointment nor the alleged letter of termination, as such the present claim is misconceived and has no basis whatsoever and the present petition is liable to be dismissed on this sole ground.
That it is specifically denied that Shri Inder Singh was employed with the Respondent No.1 since 1991-1992 as a regular employee as alleged or otherwise. It is submitted that since Shri Inder Singh was never regular employee, therewas no question of his working till 28-02-2002 or his last drawn wages being Rs.1500 as alleged or otherwise. The statement made in para under reply are false and denied.
That it is specifically denied that the applicant was performing his duty with hard labour and due diligence . It is submitted that as the applicant was never employed with the answering respondent, there was no question of his performing his duty with hard labour and due diligence as alleged or otherwise. It is specifically denied that Shri Inder Singh worked under the control of SDOs ie. Harpal Dhillion, Mr. V.P. Singh, Tyagi Sahib and Shri Amar Singh Malik as alleged or otherwise.
That it is submitted that since Shri Inder Singh was never employed by the answering respondent there was no question of giving any legal facility i.e. appointment letter, medical leave, attendance card, pay slip , leave wages, medical leave , uniform and bonus etc. as alleged or otherwise. It is further submitted that since Shri Inder Singh was never employed by the answering respondent there was no question of making oral admission as alleged in paraunder reply.
3995
भारत का राजपत्र : जून 23, 2007/आषाढ़ 2, 1929.
That it is submitted that since Shri Inder Singh was never employed with the answering respondents there was no question of demanding legal facilities as alleged or otherwise . It is submitted that as Shri Inder Singh was never employed by the answering respondents as such there was no question of illegal termination of services also of Shri Inder Singh on 01-03-2002 without any notice orinformation, hence Shri Inder Singh was also not entitled for any retrenchment compensation or notice pay as alleged.
That it is denied that after the alleged termination Shri Inder Singh visited for joining his duty and the respondents misbehaved with him as alleged and refused totake him on duty. It is submitted that statement made in the claim petition and as well as in the present para are after thought as is apparent from the fact that though Shri Inder Singh alleged that respondents have misbehaved, however , Shri Inder Singh has failed to give the name of the concerned persons, which is clearly established that the statement made in para under reply as well as in the claim petition are false and baseless .
That it is specifically denied that any notice was served by Shri Inder Singh upon the respondents as alleged or otherwise . It is submitted that as there was no relationship of employer and employee between Shri Inder Singh and the respondents, there was no question of replying to any alleged notice even if the same was written by Shri Inder Singh.
That filing of application for reinstatement in service before the ALC(C) , Faridabad is a matter of record . However, it is submitted that since there was no relationship of employer and employee between the answering respondents and Shri Inder Singh there was no question ofany conciliation taking place between the parties . The matter being referred for adjudication is a matter of record.
That it is specifically denied that the acts of the respondents as alleged in the statement of claim are highly illegal , unjust, improper and against the provisions of Industrial Disputes (Central ) Rules, 1957. It is submitted that since there was no relationship of employer and employee between Shri Inder Singh and answering respondents there was no question of any alleged acts being illegal or unjust as stated in para under reply.
That it is submitted that the applicant Shri Inder Singh was never employed by the answering respondents as such there was no question of his services being illegal terminated or him being under unemployment since then . The statement made in para under reply are without any basis whatsoever.
It is most respectfully prayed that this Hon'ble Tribunal may be pleased to dismiss the present statement of claim with cost and pass such other or further order which this Hon'ble Tribunal may deem fit and proper in the facts and circumstances of the present case .
3996
THE GAZETTE OF INDIA : JUNE 23 , 2007/ASADHA 2, 1929
[PART II-SEC. 3 (ii)]
to produce those documents .
The workman applicant has filed rejoinder . In the rejoinder he has reiterated the averments of his claim statement and has deniednost of the paras of the written statement . The management has also denied most of the paras of the claim statement .
Evidence of both the parties has been taken .
The workman has no case at all . He has miserably failed to prove the averments of his claim statement either by oral evidence or by documentary evidence . It was the duty of the workman to prove the contents of his claim statement either by oral evidence or by documentary evidence but he has failed to do so , so he is not entitled to get any relief.
Heard arguments from both the sides and perused the papers on the record.
The reference is replied thus:
The action of the management of BSNL, Jind in terminating the services of Shri Inder Singh , S/o . Shri Surta Ram, dailywages worker w.e.f 01-03-2002 is just and legal. The workman applicant is not entitled to get any relief as prayed for.
The award is given accordingly.
Date: 15-05-2007
Itwas submitted from the side of the workman that the workman was engaged as casual labour/ daily wager in the year 1991-1992 and worked continuously up to 28-02-2002 . He has performed 12 years of regular service ondailywagebasis. The workman has worked under SDOS namely Shri Ishpal Dhillion, Mr. V.P. Singh , Mr. Ajay Shah and Mr. Amar Singh Mallick. His services were terminated on 28-02-2002 without making payment of retrenchment compensationand one month's pay in lieu of notice.
R.N. RAI , Presiding Office
नई दिल्ली, 28 मई , 2007
Itwas submitted from the side of the management that the workman has filed only 2 ( two) documents i.e. Identity Card allegedly issued by the BSNL and Photo of Garlanding some authority. No other document has been filedbytheworkman.
का. आ. 1821 , औद्योगिक विवाद अधिनियम , 1947 ( 1947 का 14 ) की धारा 17 के अनुसरण में, केन्द्रीय सरकार दूर संचार विभाग के प्रबंधतंत्र के संबद्ध नियोजकों और उनके कर्मकारों के बीच , अनुबंध में निर्दिष्ट औद्योगिक विवाद में केन्द्रीय सरकार औद्योगिक अधिकरण/ श्रम न्यायालय नं.- I , चंण्डीगढ़ के पंचाट ( संदर्भ संख्या 125/99 ) को प्रकाशित करती है , जो केन्द्रीय सरकार को 28-5-2007 को प्राप्त हुआ था।
B-36 is the Identity Card . There are interpolation and overcuttings in this document . This document does not bear the seal of the respondents . It is not reliable . The otherdocument B - 37 is of Garlanding some authority by the workman . No specific names have been mentioned . The management witnesses have stated that theydo not knowthe person who has been shown to be garlanded by theworkman.
[सं. एल -40012/94/98- आई आर ( डी यू) ] सुरेन्द्र सिंह, डेस्क अधिकारी
New Delhi , the 28th May, 2007
It was further submitted that the workman himself has stated that he is uneducated and he was given appointmentby Shri Jai Prakash , Hon'ble M.P. ofthe area. The workman has not even disclosed as to who engaged him. An M.P. is not supposed to engaged a casual labour .
S.O. 1821. In pursuance of Section 17 of the Industrial Disputes Act , 1947 (14 of 1947) , the Central Government hereby publishes the award (Ref. No. 125/99) Government Industrial Tribunal- cum -Labour Court No.I , Chandigarh as shown in the Annexure in the Industrial Dispute between the employers in relation to the management of Telecom Department and their workman , which was received by the Central Government on 28-5-2007.
[No. I -40012/94/98 - IR(DU) ] SURENDRA SINGH , Desk Officer It was further submitted that the management has produced evidence of Mr. Dhillion and Mr. Tara Chand Kundu . The workman has stated that he worked under them. These witnesses have denied that the workman ever worked with the managerpent . The name of Mr. Dhillion and Mr. Tara Chand Kundu have been mentioned by the workman and it has been stated that he worked under these two SDOs but these witnesses have refused that the workman worked under them . There is absolutely no evidence either documentary or oral in support of the case of the workman .
ANNEXURE BEFORE SHRI RAJESH KUMAR, PRESIDING OFFICER, CENTRAL GOVERNMENT INDUSTRIAL TRIBUNAL-CUM - LABOUR COURT- I,
CHANDIGARH Case No. I.D. 125/1999
Shri Mehar Chand Son of Shri Jitwar Singh , V& P.O. Khabal . The Chirgoan , District Shimla ......Applicant
Versus
After conclusion of the evidence an application has beenfiled for directing the management to file documents . The particulars of the documents have not been mentioned and the management has stated that the documents mentioned cannot be produced as they are very much voluminous . The workman has demanded attendance register, accounts books etc. No specific document has beenmentioned, so it was not possible for the management [ भाग II-खण्ड 3( ii ) ]
3997
भारत का राजपत्र : जून 23 , 2007/आषाढ़ 2, 1929
The General Manager , Telecom, Sanjay Sadan Choete , Shimla (Himachal Pradesh)
.....Respondent
APPEARANCES
For the workman : Workman Shri Mehar Chand inperson
For the management : Shri Rahul Mahajan Advocate for Shri Manoj Chauhan
AWARD
Passed on 13th April, 2007
Central Government vide notification No. L-40012/ 94/98 - IR ( DU ) dated 6-5-1999 has referred the following dispute to this Tribunal for adjudication:
"Whether the action of the Division Engineer Telecom, Shimla and Sub - Division Officer (T) Rohru in terminating the services of Shri Mehar Chand son of Shri Jitwar Singh is legal and justified ? If not , to what reliefthe workman is entitled ? "
2. Today the case is fixed at Camp Court Shimla for evidence of the workman . Workman today appeared and made a statement that he is the petitioner in this case and at present he is fairly settled . Hence he does not want to proceed further with this present reference any more and the same may be closed and return the same and he is making the statement voluntarily of his own . Proxy counsel forthe management also made a statement that management has no objection and request of the workman may be allowed.
3. Inview of the statements of the workman and the proxy counsel for the management , the present reference is returned to the Appropriate Government as withdrawn . Central Government be informed. File be consigned to record.
Chandigarh Camp, Shimla
13-4-2007
RAJESH KUMAR, Presiding Officer नई दिल्ली, 29 मई , 2007
का. आ. 1822. औद्योगिक विवाद अधिनियम , 1947 ( 1947 का 14 ) की धारा 17 के अनुसरण में , केन्द्रीय सरकार दूर संचार विभाग के प्रबंधतंत्र के संबद्ध नियोजकों और उनके कर्मकारों के बीच , अनुबंध में निर्दिष्ट औद्योगिक विवाद में श्रम न्यायालय पुणे के पंचाट को प्रकाशित करती है , जो केन्द्रीय सरकार को 29-5-2007 को प्राप्त हुआ था।
[सं. एल -40012/291/99- आई आर ( डी यू) ] सुरेन्द्र सिंह , डेस्क अधिकारी New Delhi, the 29th May, 2007
S.O. 1822. In pursuance of Section 17 of the Industrial Disputes Act, 1947 ( 14 of 1947) , the Central Government hereby publishes the award of the Labour Court Pune as shown in the Annexure in the Industrial Dispute between the employers in relation to the management of Department of Telecom and their workman, which was received by the Central Government on29-5-2007.
1
[No. L-40012/291/99- IR (DU)] SURENDRA SINGH, Desk Officer ANNEXURE
BEFORE SHRI V.M. KAKADE, PRESIDING OFFICER 2ND LABOUR COURT, PUNE
Reference (I.D. A.) No. 06 of2000
Between:
The Divisional Engineer ,
Telecom Department, OFCProject,
Pune-37
......First Party AND
Shri Eknath Nanasaheb Nagwade, Anandwadi, Post : Ajnuj ,
..... Second Party Tal. Shrigonda, Dist . Ahmednagar
Coram: Shri V.M. Kakade
APPEARANCES : Mr. A.M. Joshi , Advocate for1st Party
Mrs. Supriya Maharolkar , Advocate forSecond Party
AWARD
(Date:10-11-2006)
1. On failure of conciliation, this reference is preferred by the Deputy Labour Commissioner (Conciliation) under Sec . 10(1) and Sec . 12 (5 ) of Industrial Disputes Act, 1947 for adjudication in the matter of reinstatement with full back wages of the second party . With full back wages .
2 Second party joined services of the first party on its coaxial cable project at post Jintur from 16-6-1985. He worked continuously for more than 240 days without any leave .
3. During his service tenure and after two months of his joining , he came to know irregularities committed by the lineman and the assistant engineer incharge . The line man and the assistant engineer at the time of payment of wages were taking false thumb impressions and signatures of those labourers in front of the names of the labourers who were not actually working at the project. Thus , they were collecting money from the department for the wages by fabricating the record of more number of labourers than the number of labourers whowere actually working .
3998
THE GAZETTE OF INDIA : JUNE 23 , 2007/ASADHA 2, 1929
4. It is contended that second party refused to give such false thumb impression , therefore , lineman and assistant engineer incharge were threating himto dismiss from the services . So also, they were compelling second party to work more than prescribed norms .
5. It is contended that in the month of April -May , 1996, second party was working at Parbhani Camp , he informed to C.B.I. Office, Bombay and Delhi by registered A.D. Letters about irregularities being committed by the lineman and assistant engineer incharge. When they came to know about the same , they started harassing and threating the second party and ultimately , orally terminated services of the second party on 30-6-1986 and never allowed to work though repeatedly requested .
6. It is contended that immediate after termination , second party again intimated fraudulent act of the lineman and assistant engineer incharge to CBI , Bombay and Delhi on 1-7-1996 . He communicated his grievance through superiors as well as to the Chief Minister of Maharashtra and then concerned Minister. In this context, Parbhani Police Station has also recorded the second party on 26-7-1994.
7. It is contended that though requested that first party did not allow him to join the duties , hence, second party agitated his grievance by making reference to Additional Commissioner for Labour (Central Government) Pune and on failure this reference is preferred.
8. First party appeared and resisted this reference strongly by filing its W.S. at Exh . 13 and denied allegations of fraudulent misappropriation of the amount.
9. Firstly, this reference is resisted on the ground that this Court has no territorial jurisdiction as BSNL is established under Central Government .
10. Secondly , it is resisted on the ground that BSNL Organization is not an industry as defined under Sec. 2(j ) of Industrial Disputes Act.
11. Thirdly , as per the contentions of the second party, hisservices has been terminated on 30th June , 1986 andthis case is filed on 30-6-1998 i.e. almost after lapsof 12 years which is way beyond the period of limitation prescribed by the Law . On this ground also reference is liable to be dismissed .
12. It is contended that groups between Aurangabad and Parbhani commission on 2nd March , 1988 and therefore, the project in question on which second party was engaged has come to an end .
13. It is contended that there is no record available in the office of the first party as the case is more than 12years old and as per office procedure, the records
[PART II-SEC. 3 ( ii )] are maintained for upto 10 years only . Hence , no record is available to see whether second party was working or not . However, as per the identity card submittedby the second party, he might have worked in this department for the period mentioned in the identity card. There is no record with this office which shows that second party was removed or he himself had left the work. Hence , reference be rejected.
14. Inview of pleading of the parties , following issues have been framed at Exh . 14. My findings thereon and reasons for the same are as under :
Issues
Findings 1. Does the first party prove that Yes the reference is not tenable on account of delay ?
2. Does the second party prove that ' No his services areterminated illegally by first party ?
No 3. Does the second party prove that he is entitled for the reliefs claimed as mentioned in the Schedule of reference ?
4. What Award ?
As per Inal order 15. To establish his claim of his reinstatement , second party filed his affidavit in lieu of examination in chiefat Exh . 18 and also examined himself to prove the documents filed by him and closed his evidence by filing pursis at Exh . 34.
16. On the other hand , first party without leading evidence closed its oral evidence by filing pursis at Exh. 36.
17. With this evidence before me , I have discussed my reasons for findings are as under :
REASONS
18. Issue No. 1 : Maintainability of this reference is strongly resisted on the ground of delay caused in raising the dispute.
19. Ld. Advocate for the second party to explain delay about 12 years submitted that second party is not educated , illiterate and he was not aware of the procedure . He was engaged in labour work for his day today needs therefore , delay is caused . Considering this delay as reasonable delay , Ld . Advocate for the second party has placed her reliance on following cases :---
1. Ajib Singh Vs. Sirhind Co- op . Marketing- cum- Processing Service Society Ltd. , reported in 1999 ( 1 ) CLR - 138 ( SC) .
[भाग II- खण्ड 3( ii) ]
भारत का राजपत्र : जून 23 , 2007/ आषाढ़ 2 , 1929
2. SharikAhamad Sayyad Mohd. Vs. Union of India reported in 2002 (1) CLR 811 (Bombay High Court) and submitted that Limitation Act is not applicable to the Industrial Disputes Act and relief under the act cannot be denied to the workman merely on the ground of delay .
20. On the other hand , Ld . Advocate for the first party submitted in his written argument that second party has alleged that he is terminated in the year 1986 , he raised the dispute on 30-6-1998 by filing complaint to the Additional Commissioner for Labour (Central Government) , Pune and thereafter reference is received by this Court on 5-1-2000 .As such Industrial Dispute has not been raised within reasonable time , but raised after laps of 12 years from the date of termination . It is further submitted that no such sufficient cause is explained by the second party for an unreasonable delay caused in raising the dispute. Therefore, second party is not entitled to the reliefs claimed. Ld . Advocate for the first party has placed his reliance on a case U.P. State Road Transport Corporation Vs. Babu Ram reported in 2006 delivered by Hon'ble Supreme Court on 4th July, 2006 and reported in 2006 (III) LLJ-1.5.
21. Before proceeding to discuss the reasons in detail . I would like to mention that second party neither in his statement of claim nor in his affidavit in lieu of examination in chief has uttered a single word about delay caused in raising the dispute . Though burden is on the second party, he has neither pleaded nor sufficiently explained delay caused in raising dispute either in his statement of claim or in his affidavit in lieu of examination in chief.
22. On persual of the facts, put forth for appreciation by the second party himself, it appears that according to him his services have been terminated w.e.f. 30th June, 1986 and admittedly, he has first time raised dispute after laps of 12 years on 30-6-1998 by filing complaint before the Additional Commissioner for Labour ( Central Government) , Pune. Therefore , admittedly, long delay of 12 years has been caused by the second party in raising the dispute.
23. On perusal of the statement of claim, it appears that alleged fraudulent act and irregularities committed by the lineman and assistant engineer in charge of first party, when came to the knowledge of the second party , he took lead to bring it to the notice ofauthorities . Not only this , but he intimated their fraudulent act to the CBI , Bombay & Delhi , Chief Minister of Maharashtra and then concerned minister of the first party. He also gave his statement for the same to the Parbhani Police Station . The way in which second party looked into the alleged 2733G1/07-12
3999 irregularities of lineman and assistant engineer in charge shows that second party was well aware as to how and to where to put up his grievances .
24. On perusal of the letters filed by the second party at Exh . 24 , 26, 27, 28, 29, 30 & 31 it appears that inspite offighting for his right of reinstatement, he was engaged in throwing light on alleged fraudulent act ofthe lineman and assistant engineer in charge of first party .
25. On perusal of Exh.32, it appears that first time on 25-8-1998, second party put up his grievance of termination before Labour Commissioner (Central Government) , Pune .
26. On perusal of the proceedings, thus , it appears that delay of 12 years is not sufficiently explained by . the second party either inthis statement of claim or in his affidavit in lieu of examination in chief.
27. Considering the approach of the second party to the various authorities , I am not agree with the submissions of Ld. Advocate for the second party that delay is caused becuase second party is not educated illiterate and not aware of the procedure . Pertinent to note that even cause of illiteracy is also not mentioned by the second party in his statement claim or in his affidavit in lieu of examination in chief.
28. L.d. Advocate for the second party has placed her reliance on :-
1. Ajib Singh Vs. Sirhind Co -op . Marketing cum Processing Service Society Ltd. , reported in1999 (1) CLR- 138 (S.C.)
2. SharikAhemad Sayyad Mohd. , Vs. Union of India reported in 2002 (1) CLR 811 (BombayHigh Court) . In both these Authorities , Their Lordships of Hon'ble Supreme Court and Hon'ble BombayHigh Court havegiven relief of reinstatement by molding prayer ofback wages through delay of 7 years and 9years was caused by the worker in the authorities cited supra . Their Lordship have held that relief underthe Industrial Disputes Act cannot be denied to the workman merely on the ground of delay as Limitation Act is not applicable and in case , delay isestablished, the Labour Court or, Tribunal can be mold relief as to back wages .
29. Contrary views of the Hon'ble Supreme Court of India is brought to my notice by the Ld . Advocate for the first party in a case U.P. State Road Transport Corporation Vs. Babu Ram reported in 2006 deliveredby Hon'ble Supreme Court on 4th July , 2006 and reported in 2006 (III) LLJ - 15 . While studying for this case , I have also come across a recent Judgment of the Hon'ble Supreme Court delivered in a caseAsstt. Engineer , CAD , Kota and 4000
THE GAZETTE OF INDIA : JUNE 23 , 2007/ASADHA 2, 1929
Dhan Kumar reported in 2006 (III) LLJ- 12. Both above cases are recent and of Divisional Bench of Honble Supreme Court of India . In both the cases , Their Lordships have held that , "because the Industrial Disputes Act, 1947 did not provide a limitation period for raising the dispute, it didnot mean that dispute can be raised at anytime."
30. In both the cases , Hon'ble Supreme Court declined reliefor reinstatement to the workman on the ground ofdelay in raising the dispute .
31. Considering the facts , in the light of ratio laid down by Their Lordships with due respect, I made ratio laid down by the Their Lordship of Hon'ble Supreme Court in recent cases
1. UP. State Road Transport Corporation Vs. Babu Ram reported in 2006 delivered by Hon'ble Supreme Court on 4th July, 2006 and reported in 2006(III) LLJ - 15 .
2.Asstt. Engineer, CAD Kota And Dhan Kumar reported in 2006(III) LLJ - 12 as facts ofdelay are similar in the facts before me.
32. Considering the ratio laid down by the Hon'ble Supreme Court in the cases cited supra and facts before me, I am of the opinion that 12 years delay is caused in raising the dispute . So also delay is not sufficiently explained to my satisfaction . Hence , I am of the opinion that second party is not entitled ofrelief claimed due to delay caused in raising the dispute, hence , I answer this issue in the affirmative.
33. Issue No. 2 and 3 : Second party has stated on oath he joined services as a casual labour on 16-6-1985 the continued his work till 1986. It is further stated that he continuously worked for more than 240 days . Therefore, termination amount to retrenchment , as the provisions of retrenchment are not complied with, termination is illegal and he is entitled to reinstatement .
34. It is not necessary to mention that first party has not examined any witness , but contended that matter being old. Service record of the second party is not with the first party as it is destroyed . Therefore , first party is not aware whether he was terminated or abandoned his services . However , first party admitted the identity card issued to the second party. This is the only relevant evidence of the parties.
35. With this evidence , Ld. Advocate of second party submitted that oral evidence of the second party is supported with the documentary evidence i.e. identity card issued to the second party . This evidence is neither denied nor challenged by the first party . It is submitted that evidence or record discloses that second party has worked for more
[PART II-SEC. 3 (ii) ] than 240 days continuously . His services are orally and illegally terminated by the first party without givingnotice and without complying provisions of retrenchment . Ld . Advocate for second party has placed her reliance on a case Bank of Baroda Vs. Vimalbhai Arjibhai reported in 2005 (II) CLR- 279 , wherein it is held that facts established by the workman when has not been denied by the company and company had not examined any witness to prove the facts otherwise . Then , question ofworkman further proving his case does not arise because there was no challenge at all to his evidence by way of rebuttal .
36. In reply, Ld . Advocate for the first party submitted that burden is on the second party to prove that he served continuously without any break fill 30-6-1986 and has completed 240 days . It is submitted that there is no documentary evidence except identity card produced by the second party. The card is not exhibited as it is not proved . Therefore, it is not correct to say that second party worked continuously for more than 240 days .
37. It is submitted that admittedly second party joined the services as a casual labourers and causal labourers are not entitled to claim regularization of his services and consequential benefits . It is further submitted that project on which second party alleged to be employed has came to an end , therefore , he is not entitled to the relief of reinstatement . Reliance is placed on Rajendra Kashinath Vs. Union of India reprted in 2006 (III) Mh . LLJ and BSNL, Pune Vs. Balasheb Maruti Poojari wherein Hon'ble Bombay High Court has held that casual project , termination is out come of administrative exigencies and petitioner is not entitled to regularization and consequential reliefs .
38. Considering the entire evidence on record , it appears that as submitted first party is not with any documentthrowing light on service record of the second party, according to first party, as per Rule - 69 , service record upto 5 years is to be preserved and thereafter it is to be destroyed . This reference is initiated after 12 years , so service record of the second party is not available with the first party.
39. Under such circumstances, only evidence available before the Court is identity card and communication made by the second party to various authorities . Onpersual of those documents , it appears that second party was working as a casual labourer and the same is not disputed by the first party . It also disclosed from the identity card that second party is working co - axel cable project from 16-6-1985 till 15-6-1986 . Work done by the second party is mentioned on the identity card . This shows 4001 [ भाग II- खण्ड 3(ii) ]
भारत का राजपत्र जून 23, 2007/आषाढ़ 2, 1929
that second party worked for more than 240 days . Thus, fact is clear that second party joined his services on co exle cable project as casual labourer .
of the Ld . Advocate for second party simply because second party was working on a project andwas posted by Poona Division . As per Sec. 10. reference is preferred to this Court considering the poona Division as employer. Therefore, this Court has territorial jurisdiction.
ORDER
40. As adrnissions given by the second party in his cross examination . It appears that he was not appointed by following procedure on permanent post. So also, contentions of project of co axle project is not denied seriously by the second party..
1. Reference is hereby rejected. 2. No order as to costs
PLACE: PUNE
DATE: 10-11-2006
V. M. KAKADE, Presiding Officer
नई दिल्ली, 30 मई , 2007
का..आ. 1823. औद्योगिक विवाद अधिनियम , 1947 (1947 का 14 ) की धारा 17 के अनुसरण में, केन्द्रीय सरकार सिंडिकेट बैंक के प्रबंधतंत्र के संबद्ध नियोजकों और उनके कर्मकारों के बीच , अनुबंध में निर्दिष्ट औद्योगिक विवाद में केन्द्रीय सरकार औद्योगिक अधिकरण/ श्रम न्यायालय नं.- II , नई दिल्ली के पंचाट ( संदर्भ संख्या 133/2003 ) को प्रकाशित करती है , जो केन्द्रीय सरकार को 28-5-2007 को प्राप्त हुआ था।
41. Considering this admitted facts and ratio laid down by . Their Lordship in a recent cases Rajendra K: nelainath Vs. Union of India reported on 2006(III) M'LLLJ and BSNL, Pune Vs. Balasheb Maruti Poojari, wherein . Their Lordships have held that casual labourers are not entitled to claim re gularization in the services and consequential be pefits. So also , though , casual labour has worked cobtinuously for more than 240 days , it is not necessary for the employer to issue notice or to follow the provisions of Sec . 25 (F) , in my view the factis before me are somewhat similar , therefore , I have made applicable principles laid down by their Lor dship to the facts before me and reached to the con clusion that termination is not illegal and second party is not entitled to the reliefs claimed. Hence , I ans wer the issues accordingly.
[सं. एल-12012/110/2003 - आई आर ( बी- II ) ] राजिन्द्र कुमार , डेस्क अधिकारी New Delhi, the 30th May, 2007
S.O. 1823. In pursuance of Section 17 of the Industrial Disputes Act, 1947 ( 14 of 1947), the Central Government hereby publishes the award (Ref. No. 133/ 2003)of the Central Government Industrial Tribunal - cum- Labour Court No , II , New Delhi as shown in the Annexure in the Industrial Dispute between the the management of SyndicateBank and their workmen, received by the Central Government on 28-5-2007.
42. Ld . Advocate for the first party submitted that first par ty is not an industry and Industrial Disputes Act is not applicable , hence , reference is not ma intainable . The same submissions are brushed aside by the Ld . Advocate for the second party by pla çing reliance on a well known case General Ma nagerTelecom Vs. S. Shrinivasan Rao reported in 1 998 (1) CLR- 184 (S.C.) (D.B. ), wherein Hon'ble Div ision Bench of Supreme Court elaborately discussed land mark case of Bangalore Water Sup ply and held that :-
[No. L- 12012/110/2003- IR(B-II) ] RAJINDER KUMAR, Desk Officer
ANNEXURE
BEFORE THE PRESIDING OFFICER : CENTRAL GOVERNMENT INDUSTRIAL TRIBUNAL-CUM- LABOUR, COURT - IL, NEW DELHI
I.D. No. 133/2003
PresidingOfficer : R.N.RAI .
PRESENT:
"As per the case laid down in the case ofBangalore WaterSupply, the Telecommunication is an industry as defined under Sec.2(j ) of the Act , that at is not enga ged in discharging any sovereign functions of the status and that decisions in the cases of Sub- Divisional Inspector of Post, Vaikam Vs. They ram Joseph reported in 1996 (II) CLR-237 & BomlyTelecom Canteen Association Vs. Union of India reported in 1997 ( II ) CLR 218 cannot be treated as laying down the correct law?"
SH. RAJINDER SAINI
SH . HARI KAPOOR
-1st Party -2nd Party
IN THE MATTER OF :-
4.3. Hon't le Division Bench of Supreme Court in Shrin ivasan's case over rulling its previous judgn ment concluded that Telecommunication Depar tinent is an Industry. Therefore, no doubt is left that Telecommunication Department is an Indust ry and reference is maintainable .
Loni Road, Shahdra,
Shri Jintender Pradeep , C-260 , LIG , DDA Flats, Delhi-110093 .
Versus
44. First party has also challenged territorial jurisdiction ofthisCourt, I am not agree with this submission 4002
THE GAZETIE OF INDIA : JUNE 23 , 2007/ASADHA 2, 1929
[PART II-SBC. 3 (ii) ] TheAssistant General Manager ,
Syndicate Bank,
Sarojini House , 6, Bhagwan Das Road , NewDelhi - 110001 .
misappropriating and converting to his own use Rs. 77401and for having temporarily misappropriated Rs . 1795 for four days, which were received by him from different parties for the credit of account of CBSE while he was working as cashier.
AWARD
TheMinistry of Labour by its letter No.L- 12012/110/ 2003- IR(B - II) Central Government dt. 9-9-2003 has referred the following point for adjudication .
The point runs as hereunder :-
It was further submitted from the side of the bank that the workman has not only misappropriated the money deposited by the customer but also by his acts damaged the fair image of the bank besides exposing the bank's funds to financial risk and loss . The acts of the workman hare highly detrimental to the image , reputation and standing of the bank and it amounts to moral turpitude as such the bank has lost faith and confidence in his integrity, devotion to duty and his honesty , and he has become undependable and unreliable for the bank therefore cannot be continued in the service of the bank.
"Whether the action of the management of Syndicate Bank in terminating the service of Shri Jitender Pradeep , Ex . Clerk cum Cashier by imposing a punishment of termination from the service of the bank with immediate effect with three months pay and allowances in lieu of notice vide proceedings dated 29-10-2001 is just , fair and legal? If not , to what relief the workman is entitled and from which date . "
Heard arguments from both the sides on the point of quantum of punishment .
The Preliminary issue regarding fairness of the inquiry was decided on 5-3-2007 . The inquiry was found proper . The order dated 5-3-2007 will form part of the award.
Itwas submitted from the side of the workman that punishment is excessive and shockingly dis - proportionate inview of the misconduct of the claimant .
My attention was drawn to 2000 LLR 1271. It has beenthat Section 11 A - Powers of Labour Court or Industrial Tribunal to give appropriate relief in case of dismissal or discharge or workmen - Disciplinary action- Quantum of punishment Discretion of Labour Court- Labour Court giving specific finding that charge of misappropriation and breach of trust established It, however , setting aside dismissal order and ordering reinstatement with 25 % back wages while imposing penalty of stoppage of 5 increments with cumulative effect Unsustainable - Once act of misappropriation is proved , may be for a small or large amount, there is no question of showing uncalled for sympathy and reinstating employee in service Labour Court cannot substitute penalty imposed by employer in such cases .
Itwas submitted from the side of the management that the workman in the present case at the relevant time was working as Cashier at CBSE extension counter during the period from February 1992 to November 1992 , the workman accepted/received cash of Rs . 77401 from different parties for the credit of CBSE account and he issued counterfoils by fixing rubberstamp , but he did not account for the same in the books of extension encounter for the creditof account of the CBSE .
In case of proved misappropriation there is no question of considering past record, It is discretion of the employer to consider the same in appropriate cases , but the Labour Court cannot substitute the penalty imposed by the employer in such cases .
It is found proved that the workman has misappropriated Rs.77401 . He has committed a grave misconduct.
In the facts and circumstances of the case the punishment inflicted on the claimant is neither excessive nor disproportionate . The claimant is not entitled to get any relief as prayed for .
The reference is replied thus :-
Similarly the workman received the cash of Rs . 1795 vide three receipts for the examination fee ,. but failed to account for the same in the book of EC on 17-11-1992 and to cover up his misdeeds , he prepared duplicate challans ofthe same and deposited Rs . 1795 only on 21-11-1992 thereby temporarily misappropriating the same for four days .And accordingly an inquiry was conducted into the matter and the same has been held to be fair and proper by this court. The workman during the inquiry was afforded allthe opportunities to defend himself.
The action of the management of Syndicate Bank in terminating the service of Shri Jitender Pradeep , Ex . Clerk cum Cashier by imposing the punishment of termination from the service of the bank with immediate effect with three months pay and allowances in lieu of notice vide proceedings dated 29-10-2001 is just , fair and legal . The workman applicant is not entitled to get any relief as prayed for.
The award is given accordingly. Date: 17-05-2007.
Itwas further submitted that before passing the punishment order it was observed by the disciplinary authority that management is a service industry and financial institution dealing in public money , all the employees are not only required to render prompt and efficient customer service but also required to exhibit utmost honesty and integrity in the day to day transactions and functioning of the bank . The workman has resorted to activities detrimental to the interest of the bank by
R. N. RAI , Presiding Officer [ भाग II- खण्ड 3(ii) ]
नई दिल्ली , 30 मई , 2007
का. आ. 1824. औद्योगिक विवाद अधिनियम , 1947 (1947 का 14) की धारा 17 के अनुसरण में, केन्द्रीय सरकार पंजाब व सिंध बैंक के प्रबंधतंत्र के संबद्ध नियोजकों और उनके कर्मकारों के बीच , अनुबंध में निर्दिष्ट औद्योगिक विवाद में केन्द्रीय सरकार औद्योगिक अधिकरण/ श्रम न्यायालय नं.- II , नई दिल्ली के पंचाट ( संदर्भ संख्या 113/2000 ) को प्रकाशित करती है , जो केन्द्रीय सरकार को 28-5-2007 को प्राप्त हुआ था।
[सं. एल-12012/11/2004- आई आर ( बी- II ) ] राजिन्द्र कुमार, डेस्क अधिकारी New Delhi , the 30th May, 2007
S.O. 1824. In pursuance of Section 17 of the Industrial Disputes Act, 1947 ( 14 of 1947 ) , the Central Government hereby publishes the award (Ref. No. 113/ 2004) of the Central Government Industrial Tribunal -cum- Labour Court No. II , New Delhi as shown in the Annexure in the Industrial Dispute between the employers in relation to the management of Punjab & Sind Bank and their workmen, received by the Central Government on 28-5- 2007.
[No. L- 12012/11 /2004- IR(B- II) ] RAJINDER KUMAR, Desk Officer
ANNEXURE
BEFORE THE PRESIDING OFFICER : CENTRAL GOVERNMENT INDUSTRIAL TRIBUNAL-CUM- LABOUR, COURT- II, NEW DELHI Presiding Officer : R.N.RAI .
I.D. No. 113/2004 PRESENT : SH. V. K. AGGARWAL
-1stParty SH . RAJAT ARORA
-2nd Party IN THE MATTER OF :-
Shri Harswaroop , S/o. Shri Hiru Ram, H. No. C- 1246, Dr. Ambedkar Nagar, Tigari , New Delhi
Versus
The Chairman, Punjab and Sind Bank, 21, Bank House , RajendraPlace, New Delhi - 11.0008 .
AWARD
TheMinistry of Labour by its letter No.L- 12012/11/ 2004- IR(B - II ) Central Government dt. 23-6-2004 has referred the following point for adjudication.
The point runs as hereunder : --
"Whether the action of the management of Punjab & Sind Bank to treat the workman Shri Harswaroop , to have voluntairly retired from service under Clause 17 (a) of the Bipartite Settlement is legal and
4003
भारत का राजपत्र जून 23 , 2007/आषाढ़ 2, 1929
justified ? Ifnot, what relief is the concerned disputant entitled to ."
Theworkman applicant has filed claim statement. In the claim statement it has been stated that the workman was appointed in Punjab And Sind Bank as Peon w.e.f. 18- 4-1975. After working at various branches he had been posted at Merchand Banking Bureau , Cannaught Circus branches since 1995 .
On 24-2-1996 the workman fell sick and was given Medical Treatment at Government Hospital Bulandshahar up to 2-6-1996, thereafter he was treated at Government Hospital at Noida (U.P. ) . the doctor at Noida Hospital diagnosed his disease as labyrinths C. Ventigo which requires long treatment . After a long treatment he was declared fit w.e.f. 22-2-2002 by the doctor
All the necessary applications/ informations together with medical certificates were sent to the bank by ' the workman from time to time ..
That after getting fitness certificate from the doctor theworkman approached the Chief Manager of MBB Dep . , Cannaught Circus, New Delhi branch on 22-2-2002 to resume his duties but the Chief Manager did not allow him to join. The Chief Manager verbally informed that the services of theworkman had been terminated by the Bank. No reason was given by the ChiefManager .
Whenthe Chief Manager did not allow the workman to join his duties, the workman approached the Dy. General Manager (Personal) on 25-2-2002 and requested him to take him back into service . He again sent his representation to the Chief Manager , MBB , Connaught Circus under registered post on 7-3-2002 but no response was received from the Management.
Having failed to persuade the management, the workman served a demand notice dated 19-12-2002 to the Chairman to take him back into service .
That finding no reply/ response to or action on his demand ,he raised an industrial dispute in the matter before the Asstt . Labour Commissioner , New Delhi . During the Conciliation Proceedings the Management submitted a letter dated 17-2-2003 in response to his letter dated 19-12-2002 informing the workman that his service had been terminated under Para 17A bipartite settlement by the Disciplinary authority. It is pertinent to mention that no letter was received by the workman earlier to this effect .
That on failure of conciliation proceedings , the dispute has been referred for adjudication to this Hon'ble Tribunal .
That the provision of voluntary cessation of employment as provided under clause 17 of 5th Bipartite Settlement dated 10-8-89 have been altogether deleted vide clause No. 33 of 7th Bipartite Settlement dated w.e.f. 1-11-1997 . There is no provision of voluntary cessation of employment in Banking Industry after 1-11-1997 .
4004
THE GAZETTE OF INDIA : JUNE 23 , 2007 /ASADHA 2, 1929
[PART II-SEC. 3 ( ii) ] That clause 17 of Fifth Bipartite Settlement dated 10-4-1989 which has been deleted by 7th Bipartite Settlement as stated in Para 3 stated as below:
he has not taken up another employment or avocation and that he has no intention of not joining.
"17 voluntary cessation of employment by the Employees:
The workman remained on leave on account of his illness and not intentionally . The management was well informed in this regard . Leave applications along with medical certificates were sent from time to time . It shows hiswillingness to resume his duties after getting fit for it .
The earlier provisions relating to the voluntary cessation of employment by the employee in the earlier settlements shall stand substituted by the following:
The Management did not issue any letter I notice as required under clause 17 ( a) of the bipartite Settlement furnishing any reason or ground or evidence for comingto the conclusion that the workman had no intention of joining duties and/or has taken up other employment in India . Whatever letters received by the workman were in respect ofhis illness and to get himself checked up by the Bank's Doctor but the Management never provided the address of the Bank Doctor . However the workman replied all the letters which he received and explained the cause of his absence .
That the workman was not given a reasonable opportunity of presenting his case before terminating his services of the workman concerned . It is illegal and unjustified which deserves to be set aside by the Hon'ble Tribunal .
It istherefore prayed that the Hon'ble Tribunal may be pleased to make an award setting aside the management to reinstate the workman with full back wages .
When an employee absents himself from work for a period of 90 or more consecutive days , without submitting any application for leave or for its extension or without any leave to his credit or beyond the period of leave sanctioned originally/subsequently or when there is a satisfactory evidence that he has taken up employment in India or when the management is reasonably satisfied that he has no intention of joining duties , the management may at any time thereafter give a notice to the employee at this last known address calling upon him to report for duty within 30days ofthe date of notice, stating inter - alia , the grounds for coming to the conclusion that the employee has no intention of joining duties and furnishing necessary evidence, where available . Unless the employee reports for duty within 30 days of the notice or gives an explanation for his absence within the said period of 30 days satisfying the management that he has not taken up another employment or avocation and that he has no intention of not joining duties, the employee will be deemed to have voluntarily retired from the Bank's service on the expiry of the said notice . In the event of the employee submitting a satisfactory reply, he shall be permitted to report for duty thereafter within 30 days from the date of the expiry of the aforesaid notice without rejudice to the Bank's right to take any action under the law or rules of service .
Thataccording to clause 17 ofVth Bipartite Settlement, the employee will be deemed to have voluntarily retired from the Bank's Service only after fulfilling following requirements:-
(a) The employee must be absent from work for a period of90 or more days .
(b) There should be satisfactory evidence that he Has taken up employment in India or he has no intention of joining duties .
(c) The management must have issued a notice to the employee calling upon him to report for dutywithin 30days of the date of the notice or give an explanation for his absence .
(d) The notice must have stated the grounds and necessary evidence for coming to the conclusion that the employee has no intention ofjoining duties and he has not taken up another employment or avocation .
The management has filed written statement . In the written statement it has been stated that before replying parawise to the statement of claim , the management states thatthe claimant has himself ceased to be in the services of the management bank in terms of Para 17(a) of the BPS which provides for voluntary cessation of employment of employees . It is stated that the claimant who was an employee of the respondent bank had remained absent without any permission/ leave/ intimation from 24-02-1996 and a medical certificate dated 5-06-1996 was given by him stating therein that he was suffering from some disease from 1-03-1996 to 2-06-1996 and advised rest . The claimant had not reported for duties on 3-06-1996 nor did he apply for any leave or informed the bank about his sickness and thereafter registered letters were sent to him on 30-12-1995 , 26-04-1996, 6-07-1996 and 21-08-1996. The claimant did not reply to any of these letters , he was also advised to present himself before the Bank's Doctor for examination which also he did not do . Thereafter , a final notice under Clause 17 of the BPS was sent to him on 17-10-1996 to which also he did not reply and therefore in accordance with the provisions of BPS, the claimant has ceased to be in the service of the management. The claimant was duly informed about the same vide letter dated 13-01-1998 of the management.
That representation and medical certificates were reccived from him . However , the claimant had already ceased (e) The employee does not report for duty within 30 days of notice or give an explanation for this absence satisfying the management that [ भाग II- खण्ड 3(ii) ]
4005
भारत का राजपत्र जून 23 , 2007/आषाढ़ 2 , 1929
to be in the services of the management bank in the year 1998.
Itissubmitted thatthe claimant had never informed the bank about the disease from which he was suffering . In fact only the following medical two certificates ( if they can be called as such) were submitted by the claimant.
1. Certificate dated 5-06-1996 of Dr. M.M. Aggarwal from 1-03-1996 to 2-06-1996 .
2. Certificate dated 21-02-2002 of Dr. S.P. Jain stating that the claimant was suffering from the said disease from 6-07-2000 and was advised rest for 80 weeks from 6-07-2000 to 21-02-2002 .
It has already been explained in the foregoing paragraphs that various registered letters dated 26-04-1996, 6-07-1996 and 21-08-1996 were sent to him but he did not reply to the same and a final notice under clause 17 of the BPS was sent to him on 17-10-1996 . Even to this notice, no reply was received . In fact , the claimant in this para has stated that he remained in the hospital from 24-02-1996 to 2-06-1996 and thereafter he was getting treatment at the Noida Hospital and he was declared fit on 22-02-2002 . It is vague and unimaginable that someone would remain sick for 8 long years without any information/intimation to the bank.
It is wrong and denied that any medical certificate except what has been admitted were received by the management . It is wrong and denied that any medical certificate was sent to the management from time to time .
It is not clear as to what was the disease from which the claimant was suffering . In fact in none of the medical certificates the disease of the claimant has been mentioned and it is unknown as to what is the nature of ailment of the claimant which forced him to be in the hospital for long 8 years . The authenticity and genuineness of the medical certificate is itself in doubt /cloud . It is further submitted that the claimant had already been informed on 13-01-1998 that he had voluntarily ceasd to be in the employment in terms of clause 17 of the BPS .
It is further stated that the deletion of the provision of the BPS would not make any difference to the case of the claimant. It is but natural that the workman was not interested in joining his duties and had remained unauthorisedly absent for long period of time as far as 8 years .
It isfurther stated that various letters were issued to the claimant and he did not reply to the same . It is only thereafter that the provision of Regulation 17 of the BPS had been resorted to . It is wrong and denied that the workman got himself checked by the Bank's Doctor as alleged . It is also wrong and denied that the claimant had replied to the various letters written to him by the management .
It is stated that a reasonable and fair opportunity had been givento the claimant and having failed to avail of those opportunities , the provisions of Regulation 17 of the BPS have been invoked .
It is unbelievable that workman can remain absent for such long years i.e. for 8 years without any intimation/ information to the management. It is also not clear what was the disease from which he was suffering. In these circumstances , the action of the management in applying regulation 17 of the BPS is perfectly legal and just . It is also stated that even earlier the claimant was in the habit of remaining absent . The bank had granted him leave without pay for a period of 893 days during the period 1991-1995 . He started absenting from his duties w.e.f. 25-10-1995 and was sent telegrams by the bank on 6-11-1995 & 6-12-1995 directing him to join duties . He was thereafter issued letter dated30-12-1995 to present himself and explain his absence .
It is, therefore , respectfully prayed that the pending reference may be answered in favour of the management .
The workman applicant has filed rejoinder in the rejoinder he has reiterated the averments of his claim statement and has denied most of the paras of the written statement . The management has also denied most of the paras of the claim statement .
Evidence of both the parties has been taken .
Heard arguments from both the sides and perused the papers on the record.
Itwas submitted from the side of the workman that he fell ill on 24-02-1996 and was given treatment at Government Hospital , Bulandsahar ( UP) to 2-06-1996 and thereafter he was treated in Government Hospital at Noida (UP) . The Doctor at Noida Hospital diagnosed his disease as Labyrinth-C Ventigo which requires long treatment . The workman was declared fit w.e.f. 22-02-2002 to resume his duty by the Doctor.
It was further submitted that the workman approached the bank on 22-02-2002 for resuming his duties but he was verbally informed that services of the workman have been terminated by the bank. The management adopted an adamant attitude , so the workman went in Conciliaiton Proceedings and the case was referred to this Tribunal . The workman has been ordered illegal voluntary retirement from employment in breach of the provisions of Clause 17 of the Vth BPS .
Itwas further submitted that the workman was not in a position to resume his duties . He had no intention of not resuming his duties . He sent applications with medical certificates for extension of leave again and again . He has not taken up any employment or avocation and he has no intention of not joining .
Itwas further submitted from the side of the management that the workman was issued registered letters dated 30-12-1996, 24-04-1996, 6-07-1996, 21-07-1996. These 4006
THE GAZETTE OF INDIA : JUNE 23 , 2007/ASADHA 2, 1929
letters were served but the workman did not turn up . He was advised to get himself examined by the bank's Doctor buthe did notdo so . He remained absent for long 8 years without any sanctioned leave . Ultimately he was served 30 days notice for giving satisfactory explanation and reporting to duty but the workman did not submit satisfactory explanation and he did not turn up . So the orderofvoluntary cessation of service was passed by the competent authority and the workman was informed by letter dated 13-01-1998 .
Itwas further submitted that the workman was not really ill . He has not filed any medical certificate showing hislong and serious illness . He did not turn up despite several registered letters , so it was presumed that he had no intention of joining duty . The order of voluntary cessation from service is just and legal .
Itwas further submitted that the workman submitted only 2 certificates . Certificate dated 5-6-1996 of Dr. M.M. Aggarwal for illness from 1-3-1996 to 2-6-1996 and certificate dated 21-2-2002 of Dr. S.P. Jain stating that the claimant wassuffering from the said disease from 6-7-2000 and was advised restfor 80 weeks from 6-7-2000 to 21-2-2000 . The workman has failed to file any medical certificate from 3-6-1996 to 5-7-2000 advising him complete rest .
Itwas further submitted that the workman is a habitual absentee . He remained absent for 893 days during the period 1991 to 1995.
The workman has filed prescription B - 30 dated 4-10-2000 in which medicines have been prescribed up to 2-2-2002 . There is no certificate that the workman was not in a position to resume his duty and he was advised rest for80 weeks .
The workman has further submitted the prescription ofDr. S.P. Jain dated 3-6-1996 to 7-2-2000 . These are only prescriptions and medicines are to be taken by the workman have been mentioned in the prescription . There is no certificate of any Doctor that the workman has been advised rest for 80 weeks .
The workman has admitted in his cross examination asunder:
" I do not know the name of my disease but I was curedby the Doctor . I was cured after number of years . I was not hospitalized during the treatment from 1996 to 2002. Vol . Iwas getting treatment by prescription . Vol . I was getting examined at my house only. It is wrong to say that I was so sick that I could not visit my office ."
These admissions of the workman show that he was not suffering from any such ailment which prevented him to visit his office . He has admitted that he has not been hospitalized even for a single day during his absence from 1996 up to 2002. The workman was in a position to get himself examined by the Dr. of the Personnel Department ofthe management but he intentionally avoided as he was not really suffering from any ailment which required long
[PART II-SEC. 3 ( ii)] treatment . He has not filed any certificate to establish the fact that he has been advised rest due to his serious illness . He has remained at home and got prescription from the Doctor for long 8 years . It appears that the prescriptions are forged and cooked up. The workman has not filed the original prescriptions . All these are photocopies .
The workman has admitted that he was advised by the bank to get a certificate from the Personnel Department . Had he been seriously ill he would have approached the Doctor of the management to get himself examined. He avoided the directions of the bank deliberately.
In the circumstances it is held that the workman was not seriously ill and he was in a position to approach the bank and to visit the office and get his leave sanctioned on producing medical certificate . It appears that these photocopies ofthe medical certificates have been obtained in 2002 after manipulation . He has not sent any medical certificate to the bank along with letter under certificate of posting. He has not been able to disclose the disease from which he was suffering . His bare statement is that he did not know the name of his disease but he was cured by the Doctor . The disease Labyrinth - C is not a serious disease which may prevent the workman to attend his duties .
It was submitted from the side of the bank that he has been absent for 893 days during the year 1991 to 1995 and his absence has been treated on leave without payment .
It was submitted from the side of the management that he has been treated as voluntarily retired after a long period and after issuance of 30 days notice .
In case 30 days notice is issued the workman should send satisfactory explanation. Fresh notice u/ s 33 need not be sent in case it has been received by the workman . The workman has admitted in his cross examination that he received the letters sent by the management .
It was further submitted by the workman that the bank should have held an inquiry . No inquiry is necessary under Clause 17 of the Vth BPS . The duty is cast on the workmanto report to duty or give satisfactory explanation . After receipt of30 days notice the workman did not respond it . He did not report for duty . He reported for duty after long 8 years and he has no medical certificate to the effect that he was seriously ill and the Dr. advised him bed rest .
It has been held in 2005 (3 ) LLN 57 that the bank was justified in resorting to the same after arriving at a satisfaction that the appellant has no intention to join his duties.
Ithas been held in 2001 Lab IC 301 as under :-- "Employee not intending to join nor offering any explanation regarding his unauthorized absence Presumption drawn under Rule that employee stands retired from service Order terminating his services not punishment for misconduct - Not violative of principles of naturaljustice." 4007
भारत का राजपत्र : जून 23, 2007/आषाढ़ 2, 1929
[ भाग II-खण्ड 3 ( ii) ]
BETWEEN
The ZonalManager,
Union Bank of India,
Inthe instant case altio, it is apparent fromthe record that the workman did not intend to resume his duties. The law citedbythe workman is not applicable in the facts and circumstances of the present case.
First Party
Jeevan Prakash Building, University Road, Pune-411005.
And
TheGeneral Secretary, UnionBank of India Employees Union. C/o Shri Sanjay Dahale .
At&post-Palse,
Second Party
TalukaDistrict, Nashik.
PRESENT
Shri M.M. Agrawal , Judge
Appearances: Shri C.A. Deolalkar Advocate first party
Shri S.V. Joshi Advocate for second party AWARD
From the evidence on record it is established that the workmanwas unauthorisedly absent for 893 days during 1991 to 1995 and he was again absent from 1996 to 2002for 8 years. The workman has remained on unauthorized absence for almost over 10 years in between 1991 to 2002. The bank cannot afford to continue such an employee. The plea of the workman that he was seriously ill is ill-found. No medical certificate has been filed on the record showing that the workman was seriously ill and he was advised bed rest from 1996 to 2002. The workman has manipulated the prescriptions. He has miserably failed to prove the averments of claim statement. He is not entitled to get any reliei as prayed for .
(23-4-2007)
The reference is replied thus:
Theactionofthe management of Punjab & Sind Bank to treat the workman Shri Harswaroop to have voluntarily retired from service under Clause 17 (a) of the Bipartite Settlement is legal and justified. The workman applicant is not entitled to get any relief as prayed for.
The award is given accordingly.
Date: 17-05-2007.
R. N. RAI, Presiding Officer
नई दिल्ली, 30 मई , 2007
This is a reference sent to this Court by the Government of India, Ministry of Labour, New Delhi under Section 10 of the Industrial Disputes Act, 1947 for adjudication of the dispute whether the claim of Shri Sanjay Narhari Dahale that he had worked continuously from 15-4-94 to 15-12-94 and put more than 240 days ofservice as apeonunder Palse Branch ofUnion Bank of India is true ? If so , whether the action of the management in terminating the service of Shri SanjayNarhari Dahale w.e.f. 16-12-94 is legal and justified? Ifnot, towhat relief the said workman is entitledto.
2. After receipt of the reference, notices were sent toboth the parties vide Ex. 0-2 to 0-4.
का. आ. 1825 औद्योगिक विवाद अधिनियम, 1947 (1947 का 14 ) की धारा 17 के अनुसरण में , केन्द्रीय सरकार यूनियन बैंक ऑफ इंडिया के प्रबंधतंत्र के संबद्ध नियोजकों और उनके कर्मकारों के बीच , अनुबंध में निर्दिष्ट औद्योगिक विवाद में श्रम न्यायालय नासिक के पंचाट ( संदर्भ संख्या 2/1998 ) को प्रकाशित करती है , जो केन्द्रीय सरकार को 28-5-2007 को प्राप्त हुआ था।
3. Thereafter second party filed statement of claim atEx . U-5 . The first party filed written statement atEx.C- 17 opposing the claim of workman.
[सं. एल-12025/ 1/2007- आई आर ( बी- II ) ]
राजिन्द्र कुमार , डेस्क अधिकारी
New Delhi, the 30th May, 2007
S.O. 1825. In pursuancearsuance of Section 17 of the Industrial Disputes Act, 1947 (14 of 1947) , the Central Government hereby publishes the award (Ref. No. 2/98) of the Labour Court Nashik as shown in the Annexure in the Industrial Dispute between the employers in relation to the management of Union Bank of India and their workman , which was received by the Central Government on 28-5-2007.
[No. L-12025/1/2007- IR(B- II)]
RAJINDER KUMAR, Desk Officer
ANNEXURE
4. On the rival contentions of both the parties, my learned predeceesor framed issues at Ex . 0-7. Thereafter the workman filed his own affidavit at Ex. U-14 in lieu of oral evidence . However, he did notoffer himself for cross examiation. Hence , his affidavit Ex. U- 14 cannot be read in evidence . The second party has not filed any documentary evidence to show that the workman Shri Sanjay Dahale worked for 240 days with the first party. Hence the action of management in terminating the services of Shri Sanjay Dahale cannot be termed as illegal or unjustified . Hence , the workman Shri Sanjay Dahale is not entitledto any relief.Hence, the reference is rejected. The award be sent to the Government of India, Ministry of Labour, NewDelhi for publication.
Nashik
BEFORE SHRI M.M.AGRAWAL, PRESIDING OFFICER, LABOURCOURT, NASHIK
Date:23-4-2007
Reference (IDA) No. 2/1998
M.M. AGRAWAL, Presiding Officer 2733G1/07--13 4008
THE GAZETTE OF INDIA : JUNE 23 , 2007/ASADHA 2, 1929
नई दिल्ली, 30 मई, 2007
का.आ. 1826.-औद्योगिक विवाद अधिनियम , 1947 ( 1947 का 14 ) की धारा 17 के अनुसरण में, केन्द्रीय सरकार सिंडिकेट बैंक के प्रबंधतंत्र के सम्बद्ध नियोजकों और उनके कर्मकारों के बीच, अनुबंध मेंनिर्दिष्ट औद्योगिक विवाद में केन्द्रीय सरकार, औद्योगिक अधिकरण/श्रम न्यायालय नं . - 2, नई दिल्ली के पंचाट ( संदर्भ संख्या 88/2001 ) को प्रकाशित करती है, जो केन्द्रीय सरकार को 28-5-2007 को प्राप्त हुआ था।
[सं. एल-12012/58/ 2001- आई आर ( बी- II ) ] राजिन्द्र कुमार, डेस्क अधिकारी New Delhi , the 30th May, 2007
S.O. 1826.- In pursuance of Section 17 of the Industrial Disputes Act , 1947 ( 14 of 1947) , the Central Government hereby publishes the Award (Ref. No. 88/2001 ) ofthe Central Government Industrial Tribunal -cum -Labour Court No. 2, New Delhi as shown in the Annexure in the Industrial Dispute between the management of Syndicate Bank and their workman, which was received by the Centra! Government on 28-5-2007.
[No. L- 12012/58/2001 - IR(B- II) ] RAJINDER KUMAR, Desk Officer
ANNEXURE
BEFORE THE PRESIDING OFFICER, CENTRAL GOVERNMENT INDUSTRIAL TRIBUNAL-CUM- LABOUR COURT- IL, NEW DELHI R.N. Rai , Presiding Officer I.D. No. 88/2001
IN THE MATTER OF :
1
Shri Ramesh Gupta, H. No. 479, Sec . 15-А, Opposite Vidya Mandir School , Faridabad (Haryana) .
Versus
The Asstt . General Manager,
Syndicate Bank, ZonalOffice, 6, Bhagwan Das Road, NewDelhi- 110001 .
AWARD
The Ministry of Labour by its Letter No. 12012/58/ 2001 - IR(B - II) Central Government Dt . 10/ 16-7-2001 has referred the following point for adjudication.
The point runs as hereunder:
Whether the action of the management of Syndicate Bank in dismissal of the service of Shri Ramesh Gupta w.e.f. 20-4-1999 is just and legal ? If not , what relief theworkman is entitled to ? "
[PART II- SEC . 3 (ii) ] The workman applicant has filed claim statement . In the claim statement it has been stated that the workman concerned is an employee working as clerk with M/ s Syndicate Bank since 24th June , 1996 and has been confirmed in service as such .
That the service record of the workman concerned has been clean as a result ofwhich the workman concerned has been confirmed and regularized in service after completion of the probation period.
That despite this workman concerned has been implicated in an alleged fraudulent act/ misappropriation vide chargesheet dated 23rd May, 1998 and prior to it the workman concerned has been suspended vide letter dated 12th February, 1998 .
That the management appointed the enquiry officer on 13th July, 1998 itself without waiting for the explanation to be given by the workman concerned.
That the enquiry has been held against the workman concerned in a mechanical manner and the same has been proceeded ex parte on 11th and 12th August, 1998 despite the workman's request to postpone the enquiry on medical ground in support of which a medical certificate was also sent to the enquiry officer.
That the workman concerned informed the enquiry officer on phone on 11th November, 1998 about his illness and for postponement of enquiry by a day concerning which the enquiry officer insisted on production of medical certificate which the workman concerned has produced. The medical certificate was of the Government Hospital, Faridabad which was sent by fax by the workman concerned despite this enquiry has been held ex parte against the workman concerned on 12th February, 1999. The workman concerned produced copy of the letters to defend himself but the enquiry officer asked the workman concerned to get the same attested by the Branch Manager . The next date of the enquiry fixed on 11th March , 1999 on which date Shri S.C. Lamba , Defence representative of the workman concerned informed the management about his having pain in ears and requested to inform the enquiry officer to postpone the enquiry for a day till 12th March, 1999 about which the enquiry officer also agreed.
Thatthe defence assistant of the workman concerned went to the doctor and got him medically checked up and on taking the prescribed medicine got relief due to which he could resume duty at 11.45 a.m. with due permission .
That the enquiry officer has also wrongly and illegally held that the workman concerned has produced fabricated document which cannot be correct as the workman concerned has not been provided to lead evidence and `give explanation .
The allegation of encashment of cheques is also wrong and illegal in view of the fact that the workman [ भाग II-खंड 3 ( ii ) ]
4009 भारत का राजपत्र : जून 23, 2007/ आषाढ़ 2, 1929
concerned being simply a clerk cannot get encashed a cheque without having any account as alleged since it involves handling of a cheque by an officer to pass the same and cashier for making payment thereof which process has not been resorted to as such the workman concerned cannot be held liable for having committed the alleged act.
charges against the workman concerned on similar issue before a criminal court and the management has not waited for the criminal trial to be over and has erred in law by dismissing the workman concerned from service . In the aforesaid circumstances the alleged charges cannot be said to have been proved against the workman concerned and the dismissal order so passed is wrong and illegal against which the workman concerned has protested and demanded forwithdrawal of the same .
That the defence assistant of the workman concerned has requested for re -opening of the enquiry proceedings and even that request has not been allowed . The workman concerned has not received a letter pertaining to personal hearing fixed for 16th April, 1999 to 19th April , 1999.
That the enquiry officer and disciplinary authority have violated the relevant paras ofthe bipartite settlement dated 19th October, 1999 specifically para 19.4 of the same has been violated so the workman concerned has been put ontrial in the court by the police on 21st April , 1999 .
That the workman's representation dated 15th April , 1999 along with the medical certificate has also not been consideredby the management .
In the aforesaid circumstances the dismissal order somade is liable to be set aside being wrong , mala fide and illegal.
It is also stated that the order of dismissal which has been sent vide covering letter dated 28th April, 1999 carries a letter dated 20th April, 1999 with a view to cover up the lapse since the workman concerned has been put on trial in the Court of Law on 21st April , 1999 which is a matter of record.Accordingly the management ought to have waited for the outcome of the criminal trial before initiating enquiry proceedings and dismissing the workman concerned. The said criminal proceeding is still pending and the workman concerned has been dismissed during the pendency of the same.
That the workman concerned is not gainfully employed elsewhere and is meeting his day -to-day expense from the help and assistance of friends and relatives since the dismissal from service .
In the aforesaid circumstances the enquiry as held is a sham one and has been held in violation of the principle of natural justice with the biased and prejudicial mind .
TheManagement has filed written statement. In the written statement it has been stated that the present dispute has been referred in a mechanical and routine way without the application of mind by the Ministry of Labour and the same is bad in law and is liable to be dismissed .
That the charges so alleged are also mala fide and have been labeled with ulterior motives to harass the workman concerned who has been an active member of the Syndicate Bank Employees Union. The workman concerned has represented against the dismissal so made vide letter dated 31st January, 2000 and also made an appeal against the same vide appeal dated 14th June , 1999.
That the workman has suppressed the material facts from this Hon'ble Court and has tried to mislead this Hon'ble Court, as such, the workman is not entitled to any relief. Since, the workman has tried to create a wrong picture , as such, the following facts of the case are brought before the Court:
That the enquiry officer's report is based on conjectures and surmises as there is no sufficient evidence in support of the findings so arrived at which are perverse hence liable to be set aside .
That the workmanwhile working at Farookh Nagar Branch of the Bank was placed under suspension on 12-2-1999 pending initiation ofdisciplinary action into the serious allegations of gross misconduct of doing acts prejudicial to the interest of the Bank vide Clause 19.5 (J ) of theBipartite Settlement for the following reasons .
That the workman concerned is innocent and cannot be held guilty of the allegations as leveled against him since firstly he has not been given time to give reply to the chargesheet and secondly the enquiry has been held ex parte in violation of the principles of natural justice, thirdly no defence evidence has been allowed to be produced by the workman concerned and fourthly the fact of the workman concerned not having any account has been altogether ignored as without having an account the alleged cheques cannot be encashed.
The representations made by the workman concerned and defence representative have also not been taken into account .
That the management has erred in law by dismissing the workman concerned from service despite framing of
That while working in the Branch , he got opened and operated the various accounts , such as SB STF -5 , SB 4216 and OD 3/96 , standing in his name and SB No. 13562- maintained by him jointly with Mrs. Raj Gupta , Mrs. Ritu Gupta and Kumari Rashu Gupta . Apart from above , he introduced and opened S.B. No. 13579 in the name of Ms.Meenu. He also got opened S.B. A/c. No. 4900 in the name of Smt. Santosh Jain, who was his neighbour, Shri Bhoj Kumar Jain was authorised to operate these accounts . There were about 44 credit entries purportedly by cash appearing in the above - mentioned S.B./D.D . accounts [PART II- SEC . 3 ( ii )] THE GAZETTE OF INDIA : JUNE 23 , 2007/ASADHA 2 , 1929
4010
is not entitled to any relief, as such, the case of the workman is liable to be rejected.
The workman was suspended from the service vide suspension order dated 12-2-1998 and subsequently served the chargesheet dated 23-5-1998 for his misconduct which was serious in nature . Various misconducts observed on his part includes misappropriating money, making fictitious entries in various accounts falsifying Bank records fraudulently encashing cheques and the transaction appearing in his/his family members account are apparently disproportionate through his known source of income and to conceal his fraudulent acts , he committed various other irregularities.
Itissubmitted that since the workman failed to submit his explanation to the chargesheet . therefore , it was decided by the DA to proceed with the departmental enquiry and the Enquiry Officer was appointed.
aggregatingto Rs. 7.09 lacs , which were reported to be fictitious crodit entries made by the workman during his periodfrom 30-7-1996 to 3-2-1998 . The accounts werc standing in the name of Shri Ramesh Gupta, his family members , neighbours , acquaintance and fraudulently withdrew/utilized the amounts from these accounts . To conceal his fraudulent acts . the workman falsified the bank records . Further on 14-8-1996 and 17-3-1997 he fraudulently encashed two cheques for Rs . 40,000 and Rs . 10,000 respectively drawn from his OD accounts and to conceal his fraudulent acts , he falsified , fabricated and manipulated the bank records . He fraudulently encashed two cheques unspecified OD accounts for Rs . 20,000 and Rs . 15,000 on 14-3-1997 and 21-3-1997 and to conceal these fraudulent acts . he falsified the bank records , destroyed or caused destruction of these two cash paid instruments . He had maintained various SB /FD /ODD accounts in the branch and the deposits held at the Branch in his name/in the name of his wife/his family members were apparently disproportionately source of his income indicating that the amounts fraudulently withdrawn by him through various fictitious credits were invested in various SB /FD accounts held in his name and his family members . By his above fraudulent acts , he caused a financial loss of Rs . 7.94 lacs besides interest to the bank.
Forwhich chargesheet bearing Reference No. ZOD/ IRC/CSW. 9/98 dated 23-5-1998 was issued to the workman . elaborating the charges leveled against the workman and the workman was called upon to submit his reply. The workman did not submit his explanation , as such , the departmental enquiry was conducted in the matter and Shri V.Desikan Manager 1.R. Cell was appointed as the Enquiry Officer. in terms of the provisions of Bipartite Settlement . The Enquiry Officer submitted his report and charges were proved against the workman. The findings of the Enquiry Officer were based on oral as well as the documentary evidence and the report dated 18-3-1999 was submitted. The DA considered the seriousness of the charges which were proved in the enquiry, awarded the punishment of dismissal from the services of the bank with immediate effect after serving a show cause notice . The appeal preferred by the workman was also dismissed by the Appellate Authority as no extenuating factor was brought in warranting reconsideration .
It is submitted that the Enquiry Officer sent notice dated 15-7-1998 which was duly received by the workman for conducting the enquiry on 11-8-1998. The workman sent a letter dated 27-7-1998 along with medical certificate. inresponse to that Enquiry Officer issued another registered letter dated 29-7-1998 which was duly received by him on 4-7-1998 advising him either to send a medical certificate from a government hospital or to attend the enquiry proceedings on 11-8-1998 . However , he did not send the certificate or participated the enquiry on that day. As such , the Enquiry Officer directed the managementto commence their evidence on that day and one management's witness was examined on that day and the examination - in - chiefof the said witness was completed on 12-8-1998 . Even on 12-8-1998 the workman did not appear and proceedings were continued as ex parte and deposition of the management's witnesses were concluded . The Enquiry Officer with the intention to provide an opportunity to the workman to cross-cxamine the witness adjourned the proceedings to 3-9-1998 . On 3-9-1998 the workman participated in the enquiry and requested to adjourn the proceedings due to non - availability of his Defence Representative . At his request , Enquiry Officer adjourned the enquiry to 6-10-1998 . On 6-10-1998 the workman appeared along with his Defence Representative and his Defence Representative also sought time to cross -examine the witness .Although, the enquiry was commenced at 11 AM. The Enquiry Officer gave sufficient time to the Defence Representative of the workman on that day and the workman's Defence Representative started cross- examination at 4 PM. The cross examination was continued on 7-10-1998 and on the same day, the Defence Representative was again requested for adjournment , which was granted by the Enquiry Officer and the enquiry was adjourned to 12-10-1998 and the cross - examination of the management's witnesses was completed on 14-10-1998. the Defence Representative once again sought adjournment and the enquiry was adjourned to 11-11-1998.
The management is placing on record the entire record. The perusal of the record would reveal that the workman was given full opportunity and the principles of natural justice were complied with and the submission of the workman were considered and the conclusion were drawn on the basis ofevidence placed on record and further the enquiry was conducted as per the provisions of the Bipartite Settlement and the charges leveled against the workman were duly proved during the enquiry . The workman inthe prosent claim petition has levelled false and frivolous allegations which are without any basis and the workman 4011
भारत का राजपत्र: जून 23, 2007/आषाढ़ 2, 1929
[भाग II- खंड 3 ( ii ) ]
there was any need to wait for the outcome of the criminal trial as alleged. It is submitted that the management was well within its right to proceed against the workman and there was no need to wait for the outcome of the criminal trial.
It is denied that the management has erred in law in any manner by dismissing the workman, specially in view ofthe charges framed by the criminal court against the workman, as alleged. It is further denied that there was any need to wait for the outcome of the criminal trial. All the allegation levelled by the workman are false and frivolous inthis regard . It is submitted that the management was well within its rights to proceed against the workman . The misconducts committed by the workman were grave and serious in nature and shakes the confidence ofthe Bank in hisintegrity and honesty. Further, the Bank being a Financial Institute cannot keep and continue the services of the employees, like workman, who has defrauded the bank by indulging in various objectionable acts , which are criminal in nature. Moreover, the acts committed by him constitute an act of moralturpitude and the punishment awarded by the management was proportionate to the misconduct committed by him . The Bank has lost confidence in the workman and cannot be expected to keep such employee .
The workman applicant has filed rejoinder. In the rejoinder he has reiterated the avernments of his claim statement and has denied most of the paras of the written statement . The management has also denied most of the paras ofthe claim statement .
Evidence of both the parties has been taken .
Heard arguments from both the sides and perused the papers on the record .
The enquiry was fixed for 11-11-1998, but on that day neither the workman nor his Defence Representative appeared for the reasons best known to them and the enquiry proceedings were concluded as ex parte. In the meantime, the workman represented the matter to DA to reopen the enquiry so as to lead his evidence and the enquiry proceedings were held on 12-2-1999 . The documents introduced by the workman were disallowed, as the same were photocopies of the letters . However, he was permitted to either deposit the original or duly attested copies by the signatures of these letters and the enquiry was adjourned to 13-2-1999 for enabling the workman to file the same . On 13-2-1999 workman again sought an adjournment over phone and the proceedings were adjourned to 11-3-1999. On 11-3-1999 again the Defence Representative ofthe workman informed telephonically that he is not feeling well, as such, he could not attend the enquiry. It is denied that on 11-3-1999 the Enquiry Officer has agreed to postpone the hearing till 12-3-1999, as alleged . The Enquiry Officer sought the confirmation of the same fact from the Branch where the Defence Representative of the workman was working . The branch where the Defence Representative was working , confirmed that at about 11:55 AM the Defence Representative was present in the branch and discharged his duties , which shows that the Defence Representative of the workman told a lie just to delay the proceedings . Moreover, the workman also did not attend the enquiry proceedings on that day, as such , the enquiry proceedings were concluded ex parte on 11-3-1999. It is denied that the Enquiry Officer wrongly and illegally held that the documents . It is clear from the above that the workman was solely interested to delay the proceedings and he was not serious to produce his evidence , that is why he decided not to appear and, as such there was no other alternative with the Enquiry Officer, but to conclude the proceedings .
It isobvious from the perusal of the record that the issues of fairness of the domestic inquiry has been decided by order dated 5-3-2007. The inquiry has been held valid. The Inquiry Officer has followed the principles of natural justice and he has given sufficient opportunity.
Theorder dated 5-3-2007 regarding fairness of the domestic inquiry will form part of the award.
It was submitted from the side of the workman that punishment of removal as made is wholly unwarranted. illegal, unfair and unjustified since the workman has worked as clerk for the bank w.e.f. 24th June , 1996 and has also beenconfirmed in service .
It is submitted that the enquiry was reopened by the DA at his request and the workman was given opportunity to lead his evidence on 12-2-1999. The subsequent request of the workrnan to reopen the enquiry again was rightly rejected as no merit was found in that request . It is submitted thatinitially the personal hearing was fixed for 12-4-1999 in the matter of proposed punishment and the same was adjourned to 16-4-1999 at the request of the workman. Instead of appearing 16-4-1994 , the workman again sought adjournment vide his letter dated 15-4-1999 and the enquiry was once again adjourned to 19-4-1999, which was informed to him vide letter dated 16-4-1999.
It was further submitted that the service record of the workman concerned remained clean owing to which the workman has successfully completed the probation period and has been confirmed in employment .
Itwas further submitted that the departmental inquiry is neither proper nor fair. The workman was not given sufficient opportunity to cross examine the witness and to TheDA passed the orders awarding the punishment on 20-4-1999 and same was sent to Farookh Nagar Branch vide letter dated 20-4-1999 for delivery to the workman . However, the branch informed that the workman did not receive the same. A copy of the DA proceedings dated 20-4-1999 was then directly sent to the residential address of the workman vide letter dated 28-4-1999 . It is denied that 4012
THE GAZETTE OF INDIA : JUNE 23 , 2007/ASADHA 2, 1929
[PART II- SEC . 3 (ii) ] produce his defence evidence while deciding the issues of fairness of the inquiry, these matters have been discussed atlarge and affer considering the entire aspect of the case it has been held that the inquiry is fair . These issues should not be agitated again.
Industrial Tribunal to give appropriate relief in case of dismissal or discharge or workmen Disciplinary action- Quantum of punishment---Discretion of Labour Court- Labour Court giving specific finding that charge of misappropriation and breach of trust established-It , however, setting aside dismissal order and ordering reinstatement with 25 % back wages while imposing penalty of stoppage of 5 increments with cumulative effect- Unsustainable-Once act of misappropriation is proved , may be for a small or large amount , there is no question of showing uncalled for sympathy and reinstating employee in service - Labour Court cannot substitute penalty imposed by imployer in such cases .
In case of proved misappropriation there is no question of considering past record. It is discretion of the employer to consider the same in appropriate cases , but the Labour Court cannot substitute the penalty imposed by the employer in such cases .
It was submitted from the side of the management that the workman in the present case while working at the branch got opened various account such as SB STF-5 , SB.4216 andOD 3/96 in his name and SB 13562 maintained by himjointly with Mrs. Raj Gupta and Kumari Rashu Gupta. Apart from this he also introduced and opened SB 4900. In the name of Smt . Santosh Jain who was his neighbour . There were 44 credit fictitious entries in these account aggregating to Rs . 7.05 Lakh , the said amount was withdrawn and utilized by him . To conceal his fraudulent acts he falsified the bank record . Further he encashed two chequesfor Rs . 40,000 and Rs . 10,000 from his OD account and falsified and fabricated the bank record . He also encashed two unspecified cheques of Rs . 20,000 and Rs. 15.000 and falsified and fabricated the bank record . The amount fraudulently withdrawn by him was invested in various SB /FD accounts held in his name and his family members . By his fraudulent act the total loss suffered by him was to the tune of Rs . 7.94 Lakh .
The case laws cited by the workman are not applicable in the facts and circumstances of the case . Their are several fictitious entries and those entires cannot be justified by any amount of evidence . The bank is a service industry and financial institution. It deals in public money. The employees are required to exhibit utmost honesty and integrity and day to day transactions and functions of the bank. He has misappropriated public money deposited by the customers and he has caused heavy loss to the bank . The punishment inflicted on the workman is proportionate . It is not shocking to the conscience of the Court . In the facts and circumstances of the case no punishment other than dismissal from service is justified . The workman is not entitled to get any relief as prayed for.
The reference is replied thus :
It was further submitted that the management is a service industry and financial institution dealing in public money. all the employees are not only required to render prompt and efficient customer service but are also required to exhibit utmost honesty and integrity in the day to day transactions and functioning of the bank . The workman has resorted to activities detrimental to the interest of the bank by misappropriating the money and falsifying the bank records . It was also observed that the workman has not only misappropriated the money but also by his acts damaged the fair image of the bank and caused financial loss to the bank .
The action of the management of Syndicate Bank in dismissal of the service of Shri Ramesh Gupta w.e.f. 20-4-1999 is just and legal . The workman applicant is not entitled to get any relief as prayed for .
The award is given accordingly.
Date: 16-5-2007
R.N. RAI . Presiding Officer It was further submitted that the acts of the workman arehighly detrimental to the image, reputation and standing of the bank and amountto moral turpitude as such the bankhas lost faith and confidence in his integrity, devotion to duty and his honesty, and he has become undependable and unreliable for the bank therefore cannot be continued in the service of the bank .
नई दिल्ली, 1 जून, 2007
का.आ. 1827.-औद्योगिक विवाद अधिनियम , 1947 ( 1947 का 14 ) की धारा 17 के अनुसरण में, केन्द्रीय सरकार मिलिट्री फॉर्म के प्रबंधतंत्र के सम्बद्ध नियोजकों और उनके कर्मकारों के बीच , अनुबंध में निर्दिष्ट औद्योगिक विवाद में श्रम न्यायालय , पुणे के पंचाट ( संदर्भ संख्या 98/2005 ) को प्रकाशित करती है, जो केन्द्रीय सरकार को 1-6-2007 को प्राप्त हुआ था ।
It was further submitted that the punishment imposed to the workman is proportionate to the gravity of the misconduct committed by him . In view of the settled proposition of law that the courts normally should not interfere in the punishment awarded by the management to the workman it is submitted that non - interference is required tobe made by this Hon'ble Court in the quantum of the punishment imposed by the management to the workman .
[सं. एल-14012/48/2004- आई आर ( डीयू) ]
सुरेन्द्र सिंह, डेस्क अधिकारी My attention was drawn to 2000 LLR 1271. It has been that Section 11 A-Powers of Labour Court or 4013 [भाग II-खंड 3 ( ii ) ]
भारत का राजपत्र: जून 23 , 2007/ आषाढ़ 2, 1929
New Delhi , the 1st June , 2007
interested in prosecuting his claim . I , therefore, have no alternative , but to dispose of the reference for want of prosecution by second party. I , therefore , proceed to pass followingOrders:
ORDER
1. Reference is hereby disposed of for want of prosecution by 2nd party.
S.O. 1827. In pursuance of Section 17 of the Industrial Disputes Act , 1947 ( 14 of 1947 ), the Central Government hereby publishes the Award (Ref. No. 98/2005) of the Labour Court , Pune as shown in the Annexure in the Industrial Dispute between the employers in relation to the management of Military Farm and their workman, which was received by the Central Government on 1-6-2007.
2. No. order as to costs .
[No. L- 14012/48/2004 - IR( DU) ] SURENDRA SINGH, Desk Officer
Place: Pune
Date: 4-10-2005
ANNEXURE
P. E. HAVAL , Presiding Officer BEFORE SHRI P.E. HAVAL, PRESIDING OFFICER, 2ND LABOUR COURT, PUNE
नई दिल्ली, 1 जून, 2007 Reference (I.D.A. ) No. 98 of 2005
BETWEEN
The Director.
Military Farm,
Southern Command , Khadki , Pune-3
FirstParty
का.आ. 1828.- औद्योगिक विवाद अधिनियम, 1947 ( 1947 का 14 ) की धारा 17 के अनुसरण में, केन्द्रीय सरकार दूर संचार विभाग के प्रबंधतंत्र के सम्बद्ध नियोजकों और उनके कर्मकारों के बीच, अनुबंध में निर्दिष्ट औद्योगिक विवाद में श्रम न्यायालय , पुणे के पंचाट ( संदर्भ सं. 652/2004) को प्रकाशित करती है, जो केन्द्रीय सरकार को 1-6-2007 को प्राप्त हुआ था ।
AND
Shri Laxman Narayan Prabhune,
[सं. एल-40012/27/2004- आई आर ( डीयू) ] सुरेन्द्र सिंह, डेस्कअधिकारी Sr. No. 156,
New Delhi, the 1st June , 2007 Near Vasantdada Sugar Factory, Manjari , Ta. Haveli , Dist. Pune
Second Party
AWARD
(Date 4-10-2005)
S.O. 1828. In pursuance of Section 17 of the Industrial Disputes Act, 1947 ( 14 of 1947) , the Central Government hereby publishes the Award (Ref. No. 652/2004 ) ofthe Labour Court, Pune as shown in the Annexure in the Industrial Dispute between the employers in relation to the management of Department of Telecom and their workman, which was receivedby the Central Governinent on 1-6-2007.
This is a reference made by the Desk Officer under Clause(d) of sub - sec. ( 1) and Sec . 2 and Sec . 12(5 ) r /w. Sec . 2( A) of the Industrial Disputes Act , 1947 for adjudication of industrial dispute between parties as above mentioned in Schedule which reads as under :
[No. L -40012/27/2004- IR(DU)] SURENDRA SINGH, Desk Officer SCHEDULE
ANNEXURE
BEFORE MRS . S. S. SAWANT, PRESIDING OFFICER, FIRST LABOUR COURT, PUNE
Ref. I.D.A. No. 652 of 2004
ThePrincipal General Manager,
BSNL
BajiraoRoad, Pune-411002
I Party "Whether the action of the management of Military Young Stock Farm , Manjari now under the Military Farm, Khadki in closing down the Military Young Stock Farm w.e.f. 31-12-2001 without following the procedure laid down under the ID Act , 1947 and also terminating the services of Sh . Laxman Narayan Prabhune w.e.f. 8-12-2001 and denying him adequate compensation under the provisions is legal and justified ? If not , to what extent the concerned employee is entitled to ? "
AND
Shri Balu Baliram Shelar,
Post. Kedgaon, Station, Tal . Daund,
Pune
IIParty Notice was sent to the second party, but second party has not claimed the notice . The postal authority returned the notice with endorsement in sufficient address . It was the responsibility of the second party to give proper/ changed address . It seems that second party is not
1 4014
THE GAZETTE OF INDIA : JUNE 23 , 2007/ASADHA 2, 1929
AWARD
This is a reference made to this Court by Govt. of India, Ministry of Labour / Shram Mantralaya , New Delhi for adjudication as mentioned in the schedule :
SCHEDULE
"Whether the workman Balu Baliram Shelar was in employment as casual mazdoor in the Deptt. of Telecom BSNL , under sub - division Daund continuously from 1999. If so , the action of the management in orally terminating/disengaging him without any notice and compensation is legal and justified and to what relief the concerned workman is entitled to and from which date ?"
Second party absent when called out . Second party failed to lead evidence . Hence reference stands disposed offor want ofprosecution.
Pune Date: 31-1-2007
Mrs. S.S. SAWANT, Presiding Officer नई दिल्ली, 1 जून , 2007
का.आ. 1829.- औद्योगिक विवाद. अधिनियम, 1947 ( 1947 का14) की धारा 17 के अनुसरण में, केन्द्रीय सरकार दूर संचार विभाग के प्रबंधतंत्र कि सम्बद्ध नियोजकों और उनके कर्मकारों के बीच, अनुबंध में निर्दिष्ट औद्योगिक विवाद में केन्द्रीय सरकार, औद्योगिक, अधिकरण/ श्रम न्यायालय , नागपुर के पंचाट ( संदर्भ संख्या 43/2001 ) को प्रकाशित करती है, जो केन्द्रीय सरकार को 1-6-2007 को प्राप्त हुआ था । [सं. एल-40012/36/2001- आई आर ( डीयू) ] सुरेन्द्र सिंह, डेस्कअधिकारी New Delhi , the 1st June , 2007
S.O. 1829. In pursuance of Section 17 of the Industrial Disputes Act , 1947 ( 14 of 1947 ) , the Central Government hereby publishes the Award (Ref. No. 43/2001 ) Government Industrial Tribunal -cum-Labour Court . Nagpur as shown in the Annexure in the Industrial Dispute between the employers in relation to the management of Telecom Department and their workman , which was received by the Central Government on 1-6-2007 .
[No. L-40012 /36/2001 - IR (DU ) ] SURENDRA SINGH, Desk Officer
ANNEXURE
BEFORE SHRI A. N. YADAV PRESIDING OFFICER, CGIT-CUM - LABOUR COURT, NAGPUR Case No. CGIT /NGP/43/ 2001 Date: 25-05-2007
Petitioner Party No. 1
Smt . Ushabai W/o Ganesh Khobragade.
R/oNr . Boddha Vihar,
Minil Nagar, Panchpaoli,
Nagpur -440001 .
Versus
[PART II- SEC . 3 (ii) ] Respondent Party No. 2
The General Manager, Telecom, Door Sanchar , Near Morries College , Nagpur-440001.
AWARD (Dated: 25th May , 2007)
1. The Central Government after satisfying the existence of disputes between Smit . Ushabai W/ o Ganesh Khobragade , R/ o Nr . Boddha Vihar , Minil Nagar , Panchpaoli , Nagpur- 440 001 Party No. 1 and the General Manager, Telecom, Door Sanchar , Near Morris College . Nagpur - 440 001 Party No. 2 referred the same for adjudication to this Tribunal vide its Letter No. L-40012/ 36/2001 - IR( DU) Dt . 27-4-2001 under clause (d) of sub- Section ( 1) and sub -Section (2A) of Section 10 of Industrial Dispute Act , 1947 ( 14 of 1947) with the following schedule.
2. "Whether the action of the Management of Telecom through its General Manager , Telecom in terminating the services of Smt . Ushabai W/o Ganesh Khobragade a daily rated worker w.e.f. 15-6-2000 is legal , proper and justified ? If not , to what relief the workman is entitled ? "
3. The petitioner Smt . Ushabai is a wife of Ganesh Khobragade has approached to the court with the contentions that her removal from the service is illegal and requested to reinstate her in the service w.e.f. 15-6-2000 with the back wages . Her case in short is that she has worked from 17-6-1998 to 15-6-2000 without any break in the service and she has acquired a permanency . She was working on a daily wages basis as a permanent employee . She was paid Rs . 800 per month . She was appointed in the year 1996 for 2 months for sprinkling water on Khas Tatti and filling the coolers. After completion of summer season her service was automatically terminated . In the year 1996 she was again called to resume the duty for the period of 2 months and on completion of summer period her services were terminated. Thereafter in the year 1997 she was again called for duty for 2 months . And after completion of 2 months her services were terminated. In the year 1998 she was called on 16-6-1998 to work as a daily wages employec during the office hours and she used to work from 11.30 a.m. to 5.30 p.m. she was not appointed for 2 months but was appointed permanently on the daily wages . She used to clean the office, fix the papers in Xerox machine , supplying drinking water and was also distributing the dak from the office to another . She worked in the office of the non- applicant from 7-6-1998 to 15-6-2000 without any break or disruption of the service and getting a salary of Rs. 800 per month on 15-6-2000 she worked for a whole day without assigning any reason her services were terminated orally. The oral termination is colourable exercise of powers . wasted on non- applicant which is totally illegal as the 4015 [ भाग II-खंड 3( ii ) ]
भारत का राजपत्र: जून 23, 2007/आषाढ़ 2, 1929
protection given to the non - applicant . She has prayed for. reinstatement with full back wages as indicated above.
the office , feeding papers in Xerox machines , supplying dakfrom one table to another table as messenger and giving water to the employees . But besides her bare words there is no other evidence on record to substantiate her contentions .
4. On behalf of the management the Written Statement has been filed resisting the claim of the petitioner. It has denied that the petitioner has worked continuously and regularly after 1998 till 15-6-2000. According to the management she had worked with the respondent as Khas TattiMazdoor for 2 months every year from 1996 to 2000 and there is no continuity of the service as such as regarding the payment as per notification issued by Government of Maharashtra she has paid Rs . 800 per month during the spell of summer season. No other work was given to her or no other liability was saddled on her . She was not even a daily wager or permanent employee . Normally the summer season start from 16th April and it ends on 15th of June every year. On expiry of summer scason- the services are automatically terminated. Payament ofwages of the work of Khas Tatti Mazdoor has already been made as per government scheduled rate and there is no question of back wages . According to it she is neither permanent servant nor she has worked continuously for the requisite period during any year. Her appointment was also not as per recruitment rules and she has not at all entitled for the relief as prayed by her.
5. On the basis of the above submissions the point that arises from my consideration is as under:--
"Whether the termination of the petitioner is legal , proper and whether she is entitled for any reinstatement or any other relief as prayed by her. "
7. It appears that she was working as Khas Tatti Mazdoor and normally in this area the ladies are given the work of sprinkling the water during the summer season for 2months only. It starts particularly on 15th ofApril and it continues upto 15th of June. As there is no evidence regarding the continuous work for more than 240 days, her contentions she acquired permanency cannot be accepted. Similarly the observance of Section 25 [ F] I.D. Act by paying a retrenchment compensation etc. was not necessary . She has never worked continuously and her services cannot be treated as a continuous service . In a reported case of Umadevi the full bench of Hon'ble Supreme Court has already observed that the management has a right to engage any person for a particular period. If her engagement was for the period of 2 months only in every year, it was legal as per the above authority. In such circumstances there is no need of issuing any termination notice or paying any retrenchment compensation. This cannot be a retrenchment . In this circumstance in the light ofthe above principles ofabove judgment also no relief can be granted to her . She is neither entitled for reinstatement as her appointment was not as per recruitment rules. Inthe result she is not at all entitled for any relief and there is no other go than to reject her claim . The reference stands as dismissed and it is answered in negative .
Hence this award.
Dated: 25-5-2007 A. N. YADAV, PresidingOfficer नई दिल्ली, 1 जून, 2007
का.आ. 1830.-औद्योगिक विवाद अधिनियम, 1947 (1947 का 14 ) की धारा 17 के अनुसरण में, केन्द्रीय सरकार दिल्ली मिल्क स्कीम के प्रबंधतंत्र के सम्बद्ध नियोजकों और उनके कर्मकारों के बीच, अनुबंध में निर्दिष्ट औद्योगिक विवाद में केन्द्रीय सरकार, औद्योगिक अधिकरण/ श्रम न्यायालय नं. - 1 , नई दिल्ली के पंचाट ( संदर्भ संख्या 106/2000 ) को प्रकाशित करती है, जो केन्द्रीय सरकार को 1-6-2007 कोप्राप्त हुआ था ।
[सं. एल-42011/38/2000- आई आर ( डीयू) ] सुरेन्द्र सिंह, डेस्क अधिकारी
New Delhi , the 1st June , 2007
S.O. 1830. In pursuance of Section 17 of the Industrial Disputes Act , 1947 ( 14 of 1947 ) , the Central Government hereby publishes the Award (Ref. No. 106/ 2000) Government Industrial Tribunal-cum - Labour Court No. I. New Delhi as shown in the Annexure in the Industrial Dispute between the employers in relation to the 6. In order to prove her case the petitioner examined herself and on behalf of the management Gopal Padole is examined. Both the parties have also filed the written notes of argument 1 have heard their counsels also. From the evidence as well as from the documents filed by the management it is clear that she was working only for 2 months in a year for sprinkling the water on khas tattis . No doubt she was paid Rs . 800 as per month , but the payment was on vouchers and her services were come to an end on the expiry of summer season . Every year she used to work upto 15th of June . In their cross examination the petitioner Smt . Ushabai has admitted all these facts . Similarly it is also undisputed facts that her appointment was not against the permanent vacant post nor it was as per recruitment rules . Her name was not called from the employment exchange nor any test was taken. She was given job for 2 months only for sprinkling the water on khas tattis . There is nothing on record to show that some other work was allotted to her . Though she has contended that in the year 1998 she was given an appointment nor for the specific period. but it was for the continuous period till the date of her termination . According to her she worked from 15-6-1998 till 15-6-2000 continuously and thus she was a permanent casual labour. During this period she has worked not only of sprinkling the water on khas tattis but cleaning
733 GI/07-14 4016
THE GAZETTE OF INDIA : JUNE 23 , 2007/ASADHA 2 , 1929
[PART II -SEC . 3 ( ii ) ] management ofDelhi Milk Scheme and their workman, which was received by the Central Government on 1-6-2007.
[No. L -42011 /38/2000 - IR(DU ) ] SURENDRA SINGH, Desk Officer
ANNEXURE
the claim of the claimant in the reference stands satisfied and he requested to pass a No Dispute Award . In view of the above statement of Shri Narender Singh , Secretary, Driver- cum- Salesmen Welfare Association the claim in reference stands satisfied and No Dispute Award is accordingly passed . File be consigned to record room.
Dated: 3-5-2007 SANT SINGH BAL, Presiding Officer
नई दिल्ली, 1 जून , 2007
BEFORE SHRI SANT SINGH BAL , PRESIDING OFFICER, CENTRAL GOVT. INDUSTRIAL TRIBUNAL NO . L, NEW DELHI
I.D. NO . 106/2000
In the matter of dispute between :
The Secretary,
का.आ. 1831.-औद्योगिक विवाद अधिनियम, 1947 ( 1947 का 14 ) की धारा 17 के अनुसरण में, केन्द्रीय सरकार दूर संचार विभाग के प्रबंधतंत्र के सम्बद्ध नियोजकों और उनके कर्मकारों के बीच , अनुबंध में निर्दिष्ट औद्योगिक विवाद में केन्द्रीय सरकार, औद्योगिक अधिकरण/ श्रम न्यायालय नं.- I , चण्डीगढ़ के पंचाट ( संदर्भ संख्या 315/2000 ) को प्रकाशित करती है , जो केन्द्रीय सरकार को 1-6-2007 को प्राप्त हुआ था ।
[सं. एल-40012/293/2000 - आई आर ( डी यू) ] Driver-cum- Salesmen Welfare Association , House No. T- 595 /A - 1 , Gal No. 3 , near Shiv Mandir, PremNagar Road , BaljeetNagar, New Delhi - 110001
......Workmen
सुरेन्द्र सिंह, डेस्कअधिकारी Versus
New Delhi , the Ist June , 2007 The General Manager, Delhi Milk Scheme,
West Patel Nagar,
NewDelhi - 110008
..Management
APPEARANCES
Shri Narender Singh Secretary of Drivers - cum Salesmen Welfare Association.
S.O. 1831.-In pursuance of Section 17 of the Industrial Disputes Act , 1947 ( 14 of 1947) , the Central Government hereby publishes the Award ( Ref. No. 315 / 2000) Government Industrial Tribunal - cum - Labour Court No. 1 , Chandigarh as shown in the Annexure in the Industrial Dispute between the employers in relation to the management of Telecom Department and their workman. which was received by the Central Government on 1-6-2007.
Shri A. R. Bansal Cash Clerk with Shri Anoop Srivastava for management .
AWARD
[No. L-40012/ 293/2000 - IR( DU ) ] SURENDRA SINGH Desk Officer
ANNEXURE
The Central Government in the Ministry of Labour vide its Order No. L - 42011 /38 / 2000 / IR ( DU ) dated 11-9-2000 has referred the following industrial dispute to thisTribunal for adjudication:
BEFORE SHRI RAJESH KUMAR, PRESIDING OFFICER, CENTRAL GOVT. INDUSTRIAL TRIBUNAL CUM - LABOUR COURT - 1 , CHANDIGARH
Case No. I. D. 315/2000
Shri Raj Kumar C /o Sh. R. K. Sharma ,
H. No. 372 , Sector - 20 - A .
Chandigarh ( U.T. )
Applicant "Whether Driver- cum - Salesmen also discharging duties as being done by cash clerks /Asstt . Cashier . Delhi Milk Scheme are eligible to be considered for promotion to the post of Asstt . Milk Distribution Officer in Delhi Milk Scheme alongwith cash clerks/ Asstt . Cashier ? If not , to what other relief they are entitled ?"
Versus
1 1. The Chief General Manager, Telecom Punjab Circle , Sector 34 ,
Chandigarh - 160001 ( U.T. ) .
2. The Principal General Manager, Telecom , Telephone Deptt . Sector - 18,
Respondents
Chandigarh, 160 001 (U.T. )
2. After completion of pleadings i.e. fifing of claim statement written statement , replication and recording of evidence the case was posted for arguments when Shri Narender Singh , Secretary, Driver - cum - Salesmen Welfare Association made statement on 3-5-07 to the effect that the notification dated 31-3-07 has been issued providing 10% quota in promotion to feeder cadre posts of Assistant MilkDistribution Officer and with the publication of this [ भाग II-खंड 3 (ii) ]
4017 भारत का राजपत्र: जून 23, 2007/आषाढ़ 2, 1929
APPEARANCES
New Delhi , the 1st June, 2007
For the Workman :None
For the Management ShriG. C. Babbar
AWARD
Passed on 10th May, 2007
S.O. 1832. In pursuance of Section 17 of the Industrial Disputes Act, 1947 ( 14 of 1947) , the Central Government hereby publishes the Award (Ref. No. 52/2006) ofthe Central Government Industrial Tribunal -cum -Labour Court No. 1, Chandigarh as shown in the Annexure , in the Industrial Dispute between the management of Central Bank of India, and their workmen, which was received by the Central Government on 1-6-2007.
Central Govt . vide notification No. L -40012/293/2000- IR ( DU) dated 24-8-2000 has referred the following dispute to this Tribunal for adjudication :
[No. L- 12011 /39/2006- IR(B- II) ] RAJINDER KUMAR, Desk Officer
ANNEXURE
BEFORE SHRI RAJESH KUMAR, PRESIDING OFFICER, CENTRAL GOVT. INDUSTRIAL TRIBUNAL-CUM - LABOUR COURT-1 , CHANDIGARH
"Whether the action of the Chief General Manager, Telecom, Punjab Circle, Chandigarh and the Principal General Manager, Telecom , Chandigarh Distt . in ordering disengagement/ termination of services of Sh. Raj Kumar, a workman engaged through contractor Sh . Anil Kumar w.e.f. 22-2-99 is just and legal ? If not,to what relief the workman is entitled and from which date ?"
Case No. L. D. 52/2006
The President, Central Bank of India Employees UnionHaryana, 129, Lal Kurti , Ambala Cantt . (Haryana) -133 001 .......Applicant
Versus
The Regional Manager, CentralBank of India Regional Office, Ambala Cantt. , (Haryana) -133 001 Respondent
APPEARANCES
For the Workman :None .
2. Case repeatedly called . None has put up appearance on behalf of the workman . Shri G. C. Babbar advocate for the management submitted that workman petitioner is not appearing in this case since 10-5-06 till today on 7th date and on 10-5-06 after disposal of the case appeared in late hours and noted the date in the order sheet and thereafter never came on sixth date including today. Lastly notices were issued for 20-2-07 and 10-5-07 which were duly noted by him and despite noting the date. himself he did not appear. Shri Babbar submitted that. workman appears to be gainfully employed somewhere and he is not pursuing his case and for this very reason he did not appear for the last 6/7 dates despite two court notices issued to him and one time noting the date in the order sheet.
Shri Raj Kumar For the Management
AWARD Passed on 16th May, 2007
3. In view of the above , since the workman is not appearing despite notice , no purpose will be served in keeping this case pending . Therefore, the present reference is returned for want of prosecution to the Central Govt. File be consigned to record.
CentralGovt. vide notification No. L -40011 /39/2006/ IR (B. II ) dated 4-8-2006 hás referred the following dispute - to this Tribunal for adjudication:
Chandigarh. RAJESH KUMAR, Presiding Officer
10-5-2007
नईदिल्ली, 1 जून, 2007
"Whether the punishment imposed by the management of Central Bank of India, Haryana, Ambala on Shri Bal Kishan vide order dated 19-12-2003 is in violation of Clause 19.6 of Bipartite Settlement dated 10-4-2002 andjustified ? If not what relief the concerned workman is entitled to ?" का.आ. 18:32.-औद्योगिक विवाद अधिनियम, 1947 (1947 का 14 ) की धारा 17 के अनुसरण में, केन्द्रीय सरकार सेन्ट्रल बैंक ऑफ इंडिया के प्रबंधतंत्र के सम्बद्ध नियोजकों और उनके कर्मकारों के बीच, अनुबंध में निर्दिष्ट औद्योगिक विवाद में केन्द्रीय सरकार, औद्योगिक अधिकरण/ श्रम न्यायालय नं. - 1, चण्डीगढ़ के पंचाट ( संदर्भ संख्या 52/2006 ) को प्रकाशित करती है , जो केन्द्रीय सरकार कों 1-6-2007 को प्राप्त हुआ था ।
[सं. एल-12011/39/2006- आई आर ( बी- II ) ]
2. Authorized representative of the management Shri Raj Kumar submitted that Union appears to be not interested asfive times court notices were issued to the workman and after notice Shri B. S. Gill appeared for workman and request date for filing of the written claim for 5-4-07 but claim statement not filed nor workman or his authorized representative appeared . As none appeared for the workman despite notices , nor claim statement filed, it appears that workman is not interested to pursue his case राजिन्द्र कुमार , डेस्क अधिकारी 4018
THE GAZETTE OF INDIA: JUNE 23 , 2007/ASADHA 2, 1929
[PART II-SEC . 3 ( ii ) ]
AWARD
1. The Central Government in the Ministry of Labour vide its Order No. L - 42012/ 192/ 2002 /IR ( CM- II ) dated 11-3-2003 has referred the following industrial dispute to this Tribunal for adjudication: -
and therefore , not appearing and no useful service will be served in keeping this reference pending. In view of the above, as the workman is not appearing despite court notices, the present reference is returned to the Central Govt. for want of prosecution. Central Govt . be informed. Filebe consigned to record.
RAJESH KUMAR, Presiding Officer
Chandigarh 16-5-2007
नई दिल्ली, 1 जून , 2007
"Whether the action of the management of M/s. Kendriya Vidyalaya Sanghathan , New Delhi in Terminating the services of Sh . Jahangir Khan, Ex- Peon w.e.f. 13-6-2001 is legal and justified ? If not , to what reliefthe workman is entitled to and from which date ?"
का.आ. 1833.-औद्योगिक विवाद अधिनियम, 1947 ( 1947 का 14) की धारा 17 के अनुसरण में, केन्द्रीय सरकार केन्द्रीय विद्यालय के प्रबंधतंत्र के सम्बद्ध नियोजकों और उनके कर्मकारों के बीच, अनुबंध में निर्दिष्ट औद्योगिक विवाद में केन्द्रीय सरकार, औद्योगिक अधिकरण नं. 1 , नई दिल्ली के पंचाट ( संदर्भ संख्या 38/2003 ) को प्रकाशित करती है, जो केन्द्रीय सरकार को 1-6-2007 को प्राप्त हुआ था ।
[सं. एल-42012/192/2002- आई आर ( सी एम- II ) ] अजय कुमार गौड़ , डेस्क अधिकारी
New Delhi , the 1st June , 2007
S.O. 1833. In pursuance of Section 17 of the Industrial Disputes Act , 1947 ( 14 of 1947) , the Central Government hereby publishes the Award (Ref. No. 38/ 2003) ofthe Central Government Industrial Tribunal -cum- Labour Court No. I, New Delhi as shown in the Annexure in the Industrial Dispute between the management of Kendriya Vidyalaya and their workmen, received by the CentralGovernment on 1-6-2007 .
2. Notice of the reference was issued to parties for filing claim statement/ written statement and Shri S. Rajappa A/R for management appeared on 22-9-03 and moved an application stating that the proceedings in this I.D. has been stayed by the Hon'ble High Court vide order dated 28-5-03 certified copy of which was also filed alongwith application and the matter was posted for further orders awaiting orders from High Court to 13-11-03 , 1-3-04, 15-4-04, 13-7-04 , 4-10-04, 23-12-05 , 21-3-05 , 9-6-05 , 5-9-05 . 2-1-06 , 29-3-06, 10-7-06 , 6-11-06, 6-2-06 and today 21-5-07 whena letter dated 30th March , 2007/ 10th April, 2007from Shri Ajay Kumar Gaur Desk Officer [ IR ( C.II) ] Ministry of Labour received which mentions that the proceedings in above I.D. has been quashed . Copy of the said letter from the Ministry of Labour is enclosed herewith. Copy of the judgement of the Hon'ble High Court is not enclosed as mentioned in the above letter dated 10-4-07 . Thus the proceedings in this I.D. stands quashed . File be consigned to record room .
Dated: 21-5-2007 SANT SINGH BAL , Presiding Officer [No. L-42012/ 192/2002 - IR ( CM - II) ] AJAY KUMAR GAUR, Desk Officer
नई दिल्ली, 1 जून , 2007
ANNEXURE
का.आ. 1834. औद्योगिक विवाद अधिनियम, 1947 (1947 BEFORE SHIRI SANT SINGH BAL : PRESIDING OFFICER, CENTRAL GOVT. INDUSTRIAL TRIBUNAL NO. I, NEW DELHI
I. D. No. 38/2003
Inthe matter of dispute between:
का 14 ) की धारा 17 के अनुसरण में , केन्द्रीय सरकार एफ सी आई के प्रबंधतंत्र के सम्बद्ध नियोजकों और उनके कर्मकारों के बीच, अनुबंध में निर्दिष्ट औद्योगिक विवाद में केन्द्रीय सरकार, औद्योगिक अधिकरण नागपुर के पंचाट ( संदर्भ संख्या 29/2000 ) को प्रकाशित करती है , जो केन्द्रीय सरकार को 1-6-2007 को प्राप्त हुआ था ।
Shri Jahangir Khan,
C/o. DelhiMazdoor Sangathan,
[सं. एल -22012/431 / 1995- आई आर ( सी- II ) ] अजय कुमार गौड़, डेस्क अधिकारी
New Delhi . the 1st June, 2007 .
Plot No. I, Near Udaseen Mandir, AaramBagh, Pahar Ganj ,
Workman
NewDelli - 110055
Versus
ThePrincipal .
Kendriya Vidalaya , Sector-IV R.K. Puram, NewDelhi
...Management
S.O. 1834. In pursuance of Section 17 of the Industrial Disputes Act , 1947 ( 14 of 1947) . the Central Government hereby publishes the Award (Ref. No. 29/2000 ) ofthe Central Government Industrial Tribunal -cum - Labour Court , Nagpur as shown in the Annexure in the Industrial Dispute between the employers in relation to the management of Food Corporation of India and their workman, which was received by the Central Government on 1-6-2007.
APPEARANCES:
None
[No. L -22012/ 431 / 1995 - IR ( C - II )] AJAY KUMAR GAUR , Desk Officer [ भाग II- खंड 3 ( ii) ]
ANNEXURE
BEFORE SHRI A. N. YADAV PRESIDING OFFICER, CGIT-CUM-LABOUR COURT, NAGPUR Case No. CGIT/NGP/29/ 2000
Petitioner Party No. 1
Shri Shamrao Mahadeo Naranaware, R/ o F.C.I. Quarter No. 15, Chuna Bhatti Ajni , Nagpur-440001
Versus
Respondent Party No. 2 The District Manager, FoodCorporation of India, Ajni , Nagpur-440001
AWARD
(Dated : 22nd May, 2007)
1. The Central Government after satisfying the existence of disputes between Shri Shamrao Mahadeo Naranaware R/ o F.C.I. Quarter No. 15 , Chuna Bhatti Ajni , Nagpur -440 001 Party No. 1 and The Distruct Manager , Food Corporation of India, Ajni , Nagpur -440 001 PartyNo. 2referred the same for adjudication to this Tribunal vide its Letter No. L -22012/431 / 95 - I.R. [C- II] Dt. 7-1-2000 under clause( d) ofsub Section (1 ) and sub Section (2A) of Section 10 of Industrial Dispute Act, 1947 [ 14 of 1947] with the following schedule.
2. "Whether the action of the Management of District Manager, Food Corporation of India , Ajni , Nagpur in retiring Shri Shamrao Mahadeo Naranaware, from the services w.e.f. 31-7-94 treating his date ofBirth as 4-7-1934 and not as 4-7-35, as claimedby that workman is justified and proper ? If not to what relief the workman is entitled to and what directionare necessary in the matter ?"
3. The petitioner has approached to the Tribunal by filing his Statement of Claim in response to the order by the Ministry of Central Government vide reference mentioned above . His case in short is that he was appointed bythe respondent w.e.f. 7-2-1961 in a capacity ofwatchman and later on in the year 1990 he was promoted as a head watchman.
4. His date ofbirth as per School Leaving Certificate and the certificate isued by the District Magistrate was 4-7-1935 and it was recorded in the service record also . However, subsequently the department has changed his date of birth as 4-7-1934 for the reason best known to it without any intimation or notice to him . The management displaced a seniority list in the year 1997 mentioning his date ofbirth as 4-7-1934 . The petitioner submitted a several
4019
भारत का राजपत्र : जून 23, 2007/आषाढ़ 2, 1929
applications and representations immediately after getting the knowledge about the change in the date of birth and requested to correct it. However, the management did not give any source on the basis of which it has mentioned the date ofbirth as 4-7-1934 when all the documents submitted by himwere showing the date of birth as 4-7-1935. Despite the repeated representations and requests the management did not corrected it. It finally served the petitioner with an order retiring him w.e.f. 31-7-1994 on superannuation i.e. oncompletion of60 years. Treating his date ofbirth as 4-7- 1934. Thus he was retired by the management one year earlier i.e. at the age of 59 years in stead of60 years . He was entitled to continue in the service upto 31-7-1995 i.e. till completion of60 years as his date of birth was 4-7-1935 . According to him this is an illegal termination without complying the provisions of Industrial Disputes Act . He had prayed to set aside the illegal arbitrary termination and reinstate him till he attends the age of 60 years i.e. upto 31- 7-1995 . The management has forcibly retired him and therefore, he should be allowed to continue in service.
5. The management by filing his Written Statement has denied the contentions of the petitioner. According to itthe date ofbirth of the petitioner is 4-7-1934 and it was recorded as a 4-7-1934 only in the service record and seniority list . By clerical mistake it was recorded as 4-7-1935 , however, later on the mistake was corrected by anofficer who had attested the corrections . The applicant hasjoined the service on 7-2-1961 . With U.O.I. and when he was serving in that department the said correct was made by the officer after verifying the documents on 2-4-1961 . However, in token of correction the officer has certified the correction under his signature on 6-5-1964. No representation could be entertained after the period of 24years and therefore , his representation was rejected. He was specifically informed to that effect on 15-1-1992 that whatever was recorded about his date of birth was correct. Again an intimation was given on 7-7-1993 the applicant has filed an application on 20-3-2000 , the entry was made by the Government of India in record and later it was transferred to F.C.I. The original entry about his date of birthwas takenby the Government of India on the basis of original School Leaving Certificate, therefore , the duplicate copyofthe School Leaving Certificate indicating his date ofbirth as 3-7-1935 was not genuine and therefore , it was not accepted. He was specifically informed about his date ofbirth but he has not raised any dispute immediately and therefore , the dispute is not maintainable and it should be rejected. The management is firm on its recording of the date of birth as well as further action of retiring him on the basis of it w.e.f. 31-7-1994. It has prayed to reject the prayer of the petitioner to continue him in the service upto 31-7-1995 .
6. Both the counsels have filed their written notes of argument after adducing evidence and allowing the parties to cross-examine their witnesses . The petitioner 4020
THE GAZETTE OF INDIA : JUNE 23 , 2007 /ASADHA 2, 1929
[PART II-SEC . 3 (ii) ] examined himself to support his claim while on behalf of management to Jacob Mathew has been examined. Besides this petitioner workman has filed Letter of the District Manager Dt . 23-3-1990 . His application received to thie management on 30-2-1989 . Under another list , a certificalte of age, Nationality and Domicile issued by District Magistrate. Letter issued by D.MF.C.I. Dt . 11-7-1991 , Memo issuedby District Magistrate Dt. 29-10-1982 . Again a merno issued by D. M. Dt. 22-2-1991 and Original School Leaving Certificate
8. From the above evidence one thing is clear that the date of birth was initially at the time of entry in the service was written as 4-7-1935 and later on it was corrected as 4-7-1934 . There is nothing on record to indicate on what basis it was corrected . The certificate of Shri K. B. Katkar ofthe year 1964 simply discloses that it was on the basis of Original School Leaving Certificate , but either the original or the duplicate of it is not on the record filed by the management . The certificate which is on record is also a school leaving certificate . Though the management has denied to correct it because it was a duplicate certificate. there is nothing on record to indicate that the certificate on record is a duplicate. It is original having signature and issued long back in the month of April 1952. There was no reason to disbelieve the same .
9. Similarly the management rejected it because he had applied after completion of 5 years of service . In fact immediately from the year 1988 on getting knowledge of a mistake the petitioner has requested the management repeatedly on several occasions. He has given the date of the representations alongwith the copies of the letters . There cannot be a delay in getting it corrected. In fact the management is misguiding when it says that it was a change in date of birth. The petitioner was simply requesting to correct the mistake of changing his date of birth from 1935 to 1934. It cannot be a change of the date of birth but was the request to rectify the mistake of the management therefor . There may be a rule as indicated by the management without showing any text will not help it to substantiate its action of rejecting the representation of the petitioner . The mistakes can be corrected at any time . There cannot be a limitation for correction . It is also a fact that the management has while issuing a final withdrawal ofG.P.F. issued the letters mentioning his date of birth as 4-7-1935 and the petitioner has also in some letters has written his date of birth as 4-7-1934 will not affect either of the petitioner or management . The truth will remain that at the time of entry his date of birth was recorded as 4-7-1935 here is also a document Dt . 19-4-1952 under the signature of head master to support it. There is nothing on record either original or duplicate document showing his date of birth as 4-7-1934 . Consequently in my view the management has wrongly rejected the petition of petitioner, which resulted in causing illegal retirement one year before completion of 60 years of age by the petitioner. The action of the management causing his retirement w.e.f. 31-7-1994 is totally illegal . He was entitled to continue in service upto 31-7-1995 and illegal premature retirement will have to be set aside . Accordingly the illegal retirement which amounts to termination to set aside and pass the final order .
ORDER
7. Undisputedly the petitioner was entitled to serve upto 60 years of age . The disputes are regarding the correction of the date of birth by the Management. The management i.e. F.C.I. has refused to correct if because it was earlier corrected by an officer of U.O.I. where he was earlier serving . Undisputedly he was transferred from that department to the F.C.I. The management is denying to correct iton theground that the petitioner was late in making representations and after completion offive years he is not. entitled to change the date of birth . The management had already rejected his prayer . Again there was a delay in raising the dispute. These are the reasons , which appear to have been given by the management to correct the service record. The petitioner has filed a certificate of the domicile issued by the management which supports his contentions that his date ofbirth was 7-4-1935 . Similarly a original School Leaving Certificate issued by Head Master of the Depressed Classes , N.D.P. Education Society, Lashkaribagh, Nagpur . It is a certificate issued on 9-4-1952. It is in Marathi and his date of birth both in words and in figures is mentioned as "Fourth of July Ninteen Thirty Five" . He had left the school in the month of April , 1946 on passing his 4th standard examination of the Marathi School. Besides this he has filed the letters issued by the District Manager of F.C.I. in which his date of birth is shown as 4-7-1935 . Similarly the management has filed the documents in support of its claim i.e. a seniority list as on 31-12-1993 and his service record of U.O.I. wherein his date of birth was corrected from 4-7-1935 to4-7-1934 under the signatures of technical officer Central Storage Department , Raipur. Though the management is containing that it was corrected in the year 1961 but it is not clear whether it was correctd on 6-5-1961 or later to it . The Xerox copy does not disclose the date when it was corrected. But the certificate of technical officer by K. B. Katkar Dt. 6-5-1964 and Dt . 2-4-1964 shows that it was corrected after verifying the original school leaving certificate. It is also contended on behalf of the management that some letters issued by the petitioner shows that he himself has mentioned his date ofbirth as 4-7-1934. Further ithas filed the documents showing that his prayer was rejected by the management because earlier it was corrected afterverifying original and later on it was rejected because he had applied for change in the date of birth , after 5 years
from entry in the service .
(i) The action of the management retiring the petitioner w.e.f. 31-7-1994 being illegal is set aside.
[ भाग II-खंड 3 ( ii) ]
(ii) The management is directed to treat him in the service upto 31-7-1995 till completion ofhis 60 years as his date ofbirth is 4-7-1935.
(iii) The management shall pay the salary of the period from 31-7-1994 till 31-7-1995 and make the necessary corrections in the benefits to which the petitioner was entitled on his retirement as on 31-7-1995.
Hence this award.
Dated:22-5-2007
4021
भारत का राजपत्र : जून 23, 2007/आषाढ़ 2, 1929
through the General Secretary, Lal Bavta Koyla Kamgar Union, Near Masjid, Nukoom , Chandrapur (M. S. ) Party No. 1 and the Sub Area Manager, Hindustan Lalpeth CollieryofWCL, PO Hindustan, Lalpeth , Dist. Chandrapur Party No. 2 referred the same for adjudication to this Tribunal vide its Letter No. L- 22012 / 186/ 89 - IR (C - II) dt. 30-11-1989 under clause (d) ofSub -section ( 1 ) and Sub- section ( 2A) of Section 10 of Industrial Disputes Act , 1947 (14 of 1947) with the following schedule.
A. N. YADAV, Presiding Officer
नईदिल्ली, 1 जून , 2007
का.आ. 1835.-औद्योगिक विवाद अधिनियम, 1947 (1947 का 14 ) की धारा 17 के अनुसरण में , केन्द्रीय सरकार डब्ल्यू. सी. एल. के प्रबंधतंत्र के सम्बद्ध नियोजकों और उनके कर्मकारों के बीच, अनुबंध में निर्दिष्ट औद्योगिक विवाद में केन्द्रीय सरकार, औद्योगिक अधिकरण, नागपुर के पंचाट ( संदर्भ संख्या 100/2004 ) को प्रकाशित करती है, जोकेन्द्रीय सरकार को 1-6-2007 को प्राप्त हुआ था । [सं. एल-22012/186/1989- आई आर ( सी- II ) ] अजय कुमार गौड़, डेस्क अधिकारी New Delhi , the 1st June , 2007
S.O. 1835. In pursuance of Section 17 ' of the Industrial Disputes Act, 1947 ( 14 of 1947) , the Central Government hereby publishes the Award (Ref. No. 100/ 2004) of the Central Government Industrial Tribunal - cum- Labour Court, Nagpur as shown in the Annexure in the Industrial Dispute between the employer in relation to the management of WCL and their workman, which was receivedby the Central Government on 1-6-2007.
[No. L- 22012/ 186/ 1989 -IR(C- II) ] AJAY KUMAR GAUR, Desk Officer
ANNEXURE
BEFORE SHRI A. N. YADAV, PRESIDING OFFICER, CGIT-CUM-LABOUR COURT, NAGPUR Case No. CGIT/ NGP/ 100/ 2004
Petitioner/
PartyNo. 1
: Shri Kishan Muttayya , through the General Secretary, Lal Bavta Koyla
Kamgar Union , Near Masjid , Nukoom, Chandrapur (M. S.) .
Versus
Respondent/ :
PartyNo. 2
The Sub Area Manager, Hindustan Lalpeth Colliery of WCL , PO Hindustan, Lalpeth, Dist. Chandrapur.
AWARD
(Dated: 4th May, 2007)
1. The Central Government after satisfying the existence of disputes between Shri Kishan Muttayya , 2."Whether the action of the management ofW. C. Ltd. , (Hindustan Lalpeth) in terminating services ofSri KisanMuttayya , Tub Repairer w.e.f. 29-10-88 is justified ? If not, to what relief the workman concerned is entitled ?"
3. The petitioner approached to the Tribunal by filing itsStatement of Claim with the contentions that he has been illegally terminated by the management Western Coalfields Ltd. He was tub repairer /acting driver and was working right from 14-8-1970 as a permanent employee .He was absent on 15-6-1988 as he was ill and as his health was not recovered in a colliery hospital , he was taking a treatment from private doctor. However, on 24-10-1988 he receiveda notice from the management Dt . 16-22-10-1988 . Callingupon him under Section 9 (d) of the standing order to explain as to why he shall not be treated as deserter having terminated his contract of services on his own accord, since he was remaining absent without permission continuously for more than 10 days . He was called upon to explain it within 7 days and failure will result in treating as adeserter.
4.According to the petitioner he replied the notice within 7 days from the date of receipt explaining that he was ill and taking treatment, but without considering his explanation or without initiating any inquiry against him, evenbefore the expiry of7 days , the management terminated his services by an order dt . 30-10-1988 . It is contended that the action of the management is highly illegal . He has been punished without any enquiry and without giving any opportunity to defend himself. He was a permanent employee having been worked for more than 18 years . According to him termination, in such manner totally illegal and therefore, he reported the matter to ALC who tried to reconcile it and due to the failure of settlement referred the dispute to the ministry for sending it to this tribunal for adjudication. Accordingly under the above referred order a reference has been made by the Labour Ministry. 5. The management by filing a reply denied the contentions of the petitioner and supported the action taken under Clause 9 ( d) of certified standing order . According to it the management has treated him as a deserter and his contract of service or employment comes to an end automatically. After filing a statement right from 1983 to 1988 for 5 years showing his working days of each year submitted that the petitioner deliberately did not attend 4022
[PART II-SEC. 3 (ii) ] THE GAZETTE OF INDIA : JUNE 23 , 2007/ASADHA 2 , 1929
thework. On the contrary he was unauthorisedly running a liquor shop and as he was not interested in the service of the management he himself remained absent without any permission or sanction from the competent authority w.e.f 15-6-1988 , therefore, after issuing a show cause notice histermination automatically come in to effect by operation of statutory provisions of standing orders . Thus he deserted himself from the service . His absence was unauthorized, there was no need of any enquiry. However, it has also prayed if the tribunal is of the opinion that it was necessary to make a proper enquiry, it is ready to prove the charges against the petitioner before the tribunal . It has also prayed that the management should be given a permission to prove the charges before the tribunal . Finally ithas requested to dismiss the claim petition.
mentioning any specific date. However, it can be presumed that it was upto the date of notice . But it was not a charge sheet nor he was given any opportunity showing , which misconduct has been committed by him and giving any opportunity to him to explain and defend the charges against him. When it was misconduct it was obligatory for the management to dismiss him only after enquiry. Here I would like topoint that there are no dispute or that he is permanent employee . The Management has not denied that he was a permanent workman. Undisputedly he was working from 14 August 1970 till he was terminated i.e. 29-10-1988 for more than 18 years . Undisputedly he was appointed on the vacant post and working on it. Therefore, being permanent employee the enquiry was necessary. In the absence of any domestic enquiry the termination will have to be treated as illegal punishment, which cannot be sustained on any count .
6. I have heard the counsel of the petitioner as well as of the management they have filed a Written Notes of Argument. The points that arise for my consideration are asfollows:
(1) Whether the action of the management in terminating the services of the petitioner Kisan Muttayya by an order dated and w.e.f. 29-10-1988 is justified, legal and proper ?
9.Letus consider the submissions ofthe management that the contract of employment due to the unauthorized absence automatically comes to an end and the Management is entitled to treat him as a deserter consequently entitled to terminate his services . It is also contended on behalf of the Management that specific procedure has been provided under the standing order and he was quoted the standing order 9(d) of its colliery. The standing order Section 9 (d ) runs as follows :
(ii) Whether he is entitled for the any other relief as claimedbyhim ?
"9 (d) If a workman absents himself without permissioncontinuously for 10 days or more , he shall betreated as a deserter having terminated his contract ofhis service of his own accord and shall be liable to payment ofnotice pay to the employer. The employer shall have the right to adjust dues , if any, payable to theworkman for notice pay.
7. In ordertoprove the charge the petitioner examined himself and the management examined one Janakram Sharma, Deputy Chief Managing Engineer . They both have in their affidavit supported their contentions and remained un- shattered to their stand despite the cross examination . In fact oral evidence has less importance in present case , the question being on the legal point.
The Manager before taking action under this sub- clause shall issue a notice on the workman concerned by Regd. A. D. Post at his last known address giving him further seven days time within which to show cause as to why he should not be treated as a Deserter under this sub -clause. Acopy of this notice shall be pasted on the notice board of the office of the Mine and one copy at the Register Keeper's Officer".
10.Oncareful reading of this standing order I failed to understand as to how a service of the workman stands terminated automatically for his unauthorized absence only by issuing a 7 days notice . By no stretch of the imagination this standing order is giving right to the management to terminate the services of its workers without any enquiry for absence without permission or so-called unauthorisedly. In fact it is misconduct . It is obligatory for the management toprove the charges giving opportunity to him by holding adomestic enquiry . This is a procedure given only to treat any person as a deserter , which does not automatically results into the termination . The Section is provided not 8. Undisputedly no enquiry has been taken place . It is also undisputed that the order of termination is dt. 29-10-1988 and the notice issued by the Management for treating him deserted is dt. 22-10-1988 . It is received to the petitioner on 24-10-1988 . In the light of these undisputed facts let us considered how far the action of the management is proper ? In the cross examination even the witness of the management has admitted that to unauthorized absence from the duty is a misconduct. It is alsoundisputed fact that the certified standing Order No. 14 (1) makes it obligatory to issue a punishment order only after informing to the workman in writing of alleged misconduct and giving him an opportunity to explain the allegations made against him in the departmental enquiry. Abare perusal of the standing order makes it clear that before punishing any workman the departmental enquiry is necessary. No doubt the petitioner in habit of remaining absent and in the past years before his termination order heworked for few days only. But the fact remains that even asper notice issued under standing order 9 (d) is in respect ofonly for the absence w.e.f. 15-6-1988 onwards without [ भाग II-खंड 3 ( ii ) ]
4023
भारत का राजपत्र : जून 23, 2007/ आषाढ़ 2, 1929
for terminating the services but for computing the notice pay.As per this standing order the managernent is entitled to recover the one month notice pay from the worker and it can also adjust it while computing the other amount to be paid to the workman. It does not give any right oftermination to the Management nor is it an automatic termination . Therefore, the termination only by issuing a notice without initiating a departmental enquiry and giving any opportunity to the petitioner to explain the charges , cannot be supported.
The Tribunal cannot be expected to be an enquiry officer ofany management . In my view such liberty cannot be given to the petitioner as is lightly granted in cases of invalid enquiry. The allegations made by the Management regarding his absence and even that he might be running any illegal liquor shop instead of working in the colliery or he might have lost the interest in his work are true and correct how, the management now can be allowed to prove the charges against him . In such circumstances the permission as sought by the management for proving charges before the Tribunal cannot be accepted. In the result the termination order dt. 29-10-1988 will have to be set aside and the order of reinstatement will have to be passed.
11.Moreover, the submissions of the petitioner that even before expiry of 7 days his services were terminated appears to be true . The notice is dt. 16-22-10-1988 . It was received to hirn on 24-10-1988 and the management hastily terminated his services w.e.f. 29-10-1988 . In fact the day of issuance of notice is to be excluded. The period of 7 days was to be counted from the date of receipt of the notice and then after clear expiry of 7 days the management was entitled to take any action as per the provisions of this standing order of treating him deserted and recovering the notice pay from his amount payable to him at the time of his termination etc. The evidence shows that he is terminated even before the expiry of 7 days from the date of issuance of notice. Besides this the management has thrown the representation or explanation of petitioner in response to notice in dustbin . The order nowhere discloses that it has considered , before passing a termination order. There is nowhisper ofhis explanation though he was saying that he was ill etc. Without considering any submissions madeby him the management concluded it as unauthorized absence . This appears to be totally illegal , the provision never permits the termination under this rule and without even considering the merits of his submissions . The action of management seems to be totally illegal . Hence the termination requires to be quashed.
13. So far as back wages is concern as it is illegal termination the workman is definitely entitled for the back wages and even for the full back wages: But here the petitioner has never pleaded and proved by evidence that he was without work right from the date of his termination andhad no other source of income to maintain himselfand hisfamily. It is a fact that he had maintained a family and the allegations of the management are that he was running an illegal liquor shop. Again if the record is perused it is a fact that he had worked occasionally only prior to his termination. The chart filed by the petitioner supportedby the other documents indicates that in the year 1983 he worked 166 days, in 1984, 87 and halfday, in 1985 only 39 days , in 1986 , 74 days , in 1987 , 26 days and in 1988 of course upto month of October for 20 days . This indicates that the petitioner was not interested in work . The submissions of the management regarding running of an illegal liquor shop may be true . Even assuming that there was no termination order he would not have worked for the complete days in each year . The minimum attendance as perstanding orders for underground workers is 190 days in a year. He has never completed 190 days during last 5 years before his termination and I do not think that he could have improved his attendance even had he remained in service . In such circumstances in my opinion 40% back wages will suffice to meet the ends of justice . I pass the following order.
ORDER
1.The termination order dt . 29-10-1988 being illegal is quashed and set aside . Instead it is ordered to treat the petitioner in the service .
2. The Management/Respondent is directed to reinstate the petitioner within a month from the date of publication of theAward.
3. The Management is further directed to pay 40% backwages to the petitioner from the date of his termination till the date ofhis reinstatement .
Hence this Award .
Dated: 4-5-2007
12. The management has requested to allow it to prove the charges before the Tribunal . In case the Tribunal is of the opinion that the enquiry was necessary, it is ready to prove the charges . How this can be permitted. It is not the case that the management has initiated the enquiry and while considering its validity it was found illegal . Here no enquiry has been initiated and now the management wants to prove the charges before the tribunal . There are no reasons at all for not holding the enquiry against the petitioner when he was absent for a considerable long time right from 1983 till 1985. The chart shows that he has worked for few days in the above years . The management was never prohibited to take any action against him even earlier to 1988. The notice issued u/s 9 ( d) of standing order is onlyfor the period from 15-6-1988 and now the management wants to prove the charges that he was absent even from 1983 till 1988. If such permission or liberty is given to the Management like Western Coalfields Ltd. having considerable large workers the duty of the Tribunal will only to perform. The domestic enquiry of the WCL only.
A. N. YADAV, PresidingOfficer 2733 GI/07-15 4024
[PART II- SEC. 3 ( ii ) ] THE GAZETTE OF INDIA : JUNE 23 , 2007 /ASADHA 2 , 1929
नई दिल्ली, 1 जून , 2007
Tribunal vide its Letter No. L- 22012/ 81/2004 - IR(CM - II ) dt . 23-9-2005 under clause (d) of Sub- section ( 1 ) and Sub- section (2A) of Section 10 of Industrial Dispute Act , 1947 (14 of 1947) with the following schedule.
का.आ. 1836.- औद्योगिक विवाद अधिनियम , 1947 ( 1947 का 14 ) की धारा 17 के अनुसरण में, केन्द्रीय सरकार डब्ल्यू. सी. एल. के प्रबंधतंत्र के सम्बद्ध नियोजकों और उनके कर्मकारों के बीच, अनुबंध में निर्दिष्ट औद्योगिक विवाद में केन्द्रीय सरकार , औद्योगिक अधिकरण, नागपुर के पंचाट ( संदर्भ संख्या 77/2005 ) को प्रकाशित करती है , जो केन्द्रीय सरकार को 1-6-2007 को प्राप्त हुआ था ।
2. "Whether the action of the Management in relation to Chandrapur Area of WCL in denying promotion to S/ Shri W. V. Panghate , D. R. Shende , V. N. Nikhar and B. M. Todekar , Sr. Mechanic ( Excv. ) to the post of Foreman Tand S Gr. ' B ' is legal and justified ? If not, to what relief the workman is entitled ? "
[सं. एल-22012/81/2004- आई आर ( सी एम- II ) ] अजय कुमार गौड़ , डेस्क अधिकारी New Delhi , the 1st June , 2007
S.O. 1836. In pursuance of Section 17 of the Industrial Disputes Act, 1947 ( 14 of 1947) , the Central Government hereby publishes the Award (Ref. No. 77/2005 ) ofthe Central Government Industrial Tribunal -cum-Labour Court, Nagpur as shown in the Annexure in the Industrial Dispute between the employers in relation to the management of Chandrapur Area of Western Coalfields Limited, and their workmen, which was received by the Central Government on 1-6-2007.
[No. L-22012/ 81/2004- IR(CM - II)] AJAY KUMAR GAUR, Desk Officer
ANNEXURE
BEFORE SHRI A. N. YADAV, PRESIDING OFFICER, CGIT-CUM- LABOUR COURT, NAGPUR
Case No. CGIT /NGP /77 /2005 Date: 16-5-2007
3. The petitioner and the management representative have filed a copy of settlement which has taken place out of the court . The parties have submitted the original settlement on record , which is having signature of Ramchandra Rao Personal Manager, Chandrapur Area . Shri C. J. Khandre General Secretary of Koyla Shramik Sangh , Shri Qureshi Area Personal Manager, G. Sharma Sub AreaManager , D. Ramrao Personal Manager ( ER) . It is signedby four witnesses also . It seems that the petitioners aresatisfied after the management had issued a promotion order in their favour on 1-9-2006 . They have agreed that they would not be entitled for any notional placement , if any on account ofthis promotions . Now there remained no disputes by filing a petition they have applied that it should be treated to have finally and fully settled the dispute between themselves in the terms incorporated in the agreement and they had requested to pass a compromise Award.Accordingly it is declared that the dispute has been settled by way of compromises between the parties and now there remains no dispute . In respect of the claim pendingbefore this Tribunal .
Hence this award .
Petitioner/ PartyNo. 1
Dated: 16-5-2007 A. N. YADAV, Presiding Officer नई दिल्ली, 1 जून , 2007
: Shri W. V. Panghate and 3 others , through Shri Chandrakant Khandre , General Secretary , Koyla Shramik Sabha (HMS ) , C/ o C. J. Khandre , NearMahakali Mandir, Chandrapur Post, Chandrapur.
Versus
Respondent/ : The Chief General Manager , Party No. 2 Chandrapur Area of Western Coalfields Limited, Post and Distt. Chandrapur.
का.आ. 1837.- औद्योगिक विवाद अधिनियम, 1947 ( 1947 का 14) की धारा 17 के अनुसरण में, केन्द्रीय सरकार भारत पैट्रोलियम कॉ. लि. के प्रबंधतंत्र के सम्बद्ध नियोजकों और उनके कर्मकारों के बीच, अनुबंध में निर्दिष्ट औद्योगिक विवाद में केन्द्रीय सरकार, औद्योगिक अधिकरण/ श्रम न्यायालय, एर्नाकुलम, कोच्चि, के पंचाट ( संदर्भ संख्या 170/2006 ) को प्रकाशित करती है, जो केन्द्रीय सरकार को 31-5-2007 को प्राप्त हुआ था ।
AWARD (Dated: 16th May, 2007)
[सं. एल-30012/26/97- आई आर ( सी-1 ) ] स्नेह लता जवास, डेस्क अधिकारी
New Delhi , the 1st June , 2007
S.O. 1837. In pursuance of Section 17 of the Industrial Disputes Act , 1947 ( 14 of 1947) , the Central Government hereby publishes the Award (Ref. No. 170/ 2006) of the Central Government Industrial Tribunal/Labour Court, Ernakulam, Kochi now as shown in the Annexure in 1. The Central Government after satisfying the existence ofdisputes between Shri W. V. Panghate and 3 others , through Shri Chandrakant Khandre , General Secretary, Koyla Shramik Sabha (HMS ) , C/o C. J. Khandre, NearMahakali Mandir, Chandrapur Post, Chandrapur Party No. 1 and The Chief General Manager , Chandrapur Area of Western Coalfields Limited, Post and Dist . Chandrapur Party No. 2 referred the same for adjudication to this [भाग II-खंड 3 (ii) ]
the Industrial Dispute between the employers in relation tothe management of Bharat Petroleum Corporation Ltd. and their workman, which was received by the Central Government on 31-5-2007.
[No. L-30012/26/97 -IR(C-I) ]
SNEH LATA JAWAS, Desk Officer
ANNEXURE
IN THE CENTRAL GOVERNMENT INDUSTRIAL TRIBUNAL- CUM- LABOUR COURT, ERNAKULAM PRESENT :
Shri P. L. Norbert, B. A. , L. L. B. , PresidingOfficer.
(Thursday, the 17th day of May, 2007/27th Vaisakha,
1929)
L. D. 170/2006
(L. D. 19/1998 of Labour Court, Ernakulam) Workman : C. Sadhisan,
C/o P. N. N. Kaimal,
Munnappallil House,
Kollakkad P. O. ,
Palakkad-678732
Adv. Shri Paulson, C. Varghese .
The Senior Manager ,
Management :
Bharat Petroleum Corporation Ltd. , 1, Ranganathan Gardens ,
Opp. 11th MainRoad, AnnaNagar, P. B. No. 1212 and 1213 , Chennai -600040.
Adv. M/s . Menon and Pai
AWARD
Thisis a reference made by Central Government under Section 10( 1 ) (d ) of Industrial Disputes Act, 1947 for adjudication. The reference is:
" Whether the action of the management of Bharat Petroleum Corporation , Madras in terminating the service of Shri C. Sadhisan, an ex -clerk in the LPG Depot at Palakkad with effect from 28-2-1991 without complying provision of I. D. Act, 1947, is just, proper and legal ? If not , what relief the workman is entitled ?"
2. The facts of the case in brief are as follows :
The workman, Shri C. Sadhisan contends that he was appointed as clerk in the LPG depot at Palakkad of Bharat Petroleum Corporation Limited. He worked there continuously from 2-3-1987 to 28-2-1991 . Thereafter he was denied employment on the ground that there was no work due to lock out . No notice was given and no compensation was also given . There was no departmental action against him during the service . The 2nd management was appointed
4025
भारत का राजपत्र : जून 23 , 2007/ आषाढ़ 2, 1929
by the 1st management company as a Depot Manager for managing the affairs of the depot at Palakkad . There was another reference on a previous occasion by State Government to Labour Court, Kozhikode . Since that Court had nojurisdiction to adjudicate the dispute the claim was rejected without prejudice to the right of the workman to move appropriate Government for reference . Thus the present reference was made by the Central Government . Theworkman was employed directly by the 1st management and he was paid salary by the 1st Management . However he was denied employment without complying with the procedure u/ s - 25F of Industrial Disputes Act . If the records of the company are called for it can be seen that the workman was employed by the 1st management company. Hence the workman is entitled to be reinstated with back wages.
3. The 1st management filed a written statement contending that the workman was an employee of the 2nd management , Shri P. B. Achan and not the employee ofthe 1st management company. The 2nd management was a contractor engaged by the 1st management company. There is no master and servant relationship between the workman and the 1st management. Since there is no employer- employee relationship between the company and the workman the reference is not maintainable . The depot at Palakkad is a commission operated LPG depot . The operation ofthe depot was entrusted to Shri P. B. Achan, a contractor who had submitted the lowest quotation . The depot functioned from 1987 to 1991. When the Chief Controller of Explosives imposed certain restrictions for storage of LPG on account of safety and it became difficult for the company to continue the operation of the depot at Palakkad . Accordingly the contract with Shri P. B. Achan was terminated w.e.f. 1-3-1991 . Consequently the 2nd management dispensed with the service of the workman. The 1st management has not denied employment to the workman. There is no lock out . The question of complying with the provision of S - 25F of I. D. Act does not arise as the workman was not an employee of the company. The 2nd management was not the depot manager of the 1st management . He was only a contractor. The burden is on the employee to prove that he was employed by the 1st management. The contract labour is not abolished by notification u/s - 10 of the Contract Labour (Regulations and Abolition) Act . Hence there is no obligation on the part of the 1st management to absorb the labourers ofthe contractor.Hence the workman is not entitled for any relief claimed.
4. The workman filed a rejoinder disputing and denying the allegations in the written statement and reiterating the contentions raised in the claim statement.
5. The points that arise for consideration are:
(1) Whether the workman is an employee ofBharat Petroleum Corporation Ltd. ?
4026
[PART II-SEC. 3 (ii)] THE GAZETTE OF INDIA : JUNE 23 , 2007/ASADHA 2 , 1929
(2) As the workman entitled to be reinstated ?
The evidence consists of the oral testimony of WW1 anddocumentary evidence of Exts. W1 to 15 on the side of workman and MW1 and Exts .M1 to 8 on the side of management .
6. Point Nos . (1) and (2) :
8.Exts. W2 to 4 are wage slips issued to workman . It. is seen signed by Shri P. B. Achan. The wage slip is a printed form as per Rule 29 (2 ) of Kerala Minimum Wages Rules . But the management contends that it is as per the requirement of statute that the wage slip was issued by Shri P. B. Achan and it is not a wage slip or pay slip of the company. Ext . M6 is produced by the company to refute the contention of the workman that the payment was made by the company. It is a pay slip of the company issued to one of its employees , Shri B. Balagopalan . It is a printed pay slip in the name of BPCL . The salary of the employee under different heads are shown in the pay slip , like Basic Pay, DA , HRA and other allowances as well as deductions . Whereas in Exts . W2 to 4 a total sum ofRs . 800 is shown as the salary per month without specifications as to Basic Pay, DA, etc. It is evident that for the purpose of compliance with the requirements of Kerala Minimum Wages Rules printed wage slip was used by Shri P. B. Achan while disbursing salary to the workman . That is how Exts . W2 to 4 found a place among the records of depot . It is worth noting that Ext . M6 shows that the salary of a company employee (clerk) in 1987 was Rs . 1882 , whereas the workman (clerk) as per Exts. W2 to 4 was drawing only Rs . 800 in 1990. The difference in salary itself will reveal that the workman was not an employee of BPCL .
TheBharat Petroleum Corporation Limited is a Central Government o vned company. It has its own procedure for selection and appointment of employees . The workman admits that he was not given an appointment order by the BPCL, but only promised to issue an appointment order (WW1 ) . He says that he had applied for clerical post on information that there was vacancy in the depot at Palakkad and not on the basis of any paper advertisement. He says that he was interviewed and selected by the company and appointed by the company. However the company has the case that the workman was never appointed by them , but he was taken by the contractor, Shri P. B. Achan. According to the management company the LPG depot at Palakkad wasstartedion commission basis through contractor , P. B. Achan. The infrastructure , like building , some furniture and telephone, were provided by the company. Rest of the things had to be arranged by the contractor for running the depot . The payment to the contractor was on commission basis . Therefore the company contends that the company had no involvement in the appointment of employees in the depot.
9. Ext. W5 is service record of the workman. It is a printed form as per Rule 10 ( 1 ) A of Kerala Shops and Commercial Establishments Rules . In the column for signature of employer Shri P. B. Achan has signed . The Establishment's name is shown as Bharat Petroleum Corporation LPG Staging Depot , Palakkad with rubber seal . The service record is maintained as per statutory requirement of the Kerala Shops and Commercial Establishments Act and Rules . The Management has strongly challenged the rubber seal of the company. It is also their case that the company's forms are printed forms in the name of the company and not by affixing rubber seal . The company also questions the authority of Shri P. B. Achan to maintain service records of employees of the company. Since Ext . W5 is a service record maintained as per statutory requirement and it is not in the printed form ofthe company it cannot be taken as a piece of evidence to prove the employment of the workman in the company.
10. Ext . W6 is a letter issued by Shri P. B. Achan to the Plant Manager of the Company at Madras . The letter was issued to inform the company that an employee , Shri V. R. Sunil had left the service and in his place the workman , Shri C. Sadhisan was appointed. The names of three clerical staff including the workman were also shown inthe letter . The letter is issued in the letter pad of BPCL . The letter pad is one used by company for inter -office correspondence. It is contended by the workman that Ext . W6 will show that Shri P. B. Achan was acting as the Depot manager and as an officer of the company and not as a contractor. Therefore the workman too was an employee of 7. The workman was there in the depot from 1987 to 1991. The workman has produced Exts . W1 to 14 documents to prove that he was really employed by the company and not by Shri P. B. Achan who , according to the workman, was the depot manager, not the contractor . Ext . W1 is a certificate of employment issued by Shri Achan on 7-9-1990 certifying that the workman was working as clerk in BPCL LPG Staging Depot at Palakkad for a period of 3½ years . It is not in the letter pad of the company. But underneath the signature of Shri P. B. Achan a rubber seal is affixed . The seal is in the name of BPCL LPG Staging Depot , Palakkad. The management company strongly denies that it was issued by the company and also challenges the authority of Shri P. B. Achan to issue a certificate on behalf of the company. It is relevant to note that being a public sector company an employment certificate cannot be issued by any officer, but only by a designated officer. First of all there is no evidence to show thatShri P. B. Achan was Depot Manager or an employee ofthe company. Assuming that he was the depot manager ifhe had to issue an employment certificate , it would have been issued in the letter pad of the company. The workman was not able to show that Shri P. B. Achan was a competent officer to issue the certificate . The certificate is not one issued by the company and consequently it will not show that the workman was employed by the company.
[भाग II- खंड 3 ( ii) ]
4027
भारता का राजपत्र : जून 23, 2007/आषाढ़ 2, 1929
Depot, Palakkad. The name of employer in the certificate is shown as Shri P. B. Achan. The number of employees is shown as 3. The certificate is issued under Kerala Shops and Commercial Establishments Act . There are specific columns for names of employer and employees and the names are as mentioned above . The certificate reveals that so far as the Depot at Palakkad is concerned, the employer was Shri P. B. Achan. Naturally 3 employees in the Depot were under him.
13. Exts . W9 and 10 are muster rolls relating to August , 1990 and February, 1991. The names of 3 employees are shown in the muster roll and attendance is marked. The muster roll is in the prescribed form as per Rule 130 ofKerala Factories Rules . The rubber seal ofBharat Petroleum Corporation LPG Staging Depot is affixed. MW1 denies that these are muster rolls of the company. According to him, if it were so, it would have been in company's printed form. At any rate , Exts . W 9 and 10 will not go to show that the 3 employees mentioned therein are the employees of the company.
14. Exts . W11 and 12 are registers of wages for the relevant periods . The 3 workers in the Depot had signed the registers and obtained their wages . The Register of Wages is a printed form as per Rule 29( 1 ) of Kerala Minimum Wages Rules. The name of Depot is shown by affixing rubber seal . MW1 denies that the seal belongs to the company and further that the Register ofWages is not that of the company. If it were the Register of Wages of the company it would have been in company's printed form. The workman has no case that the salary was paid by any officerofthe company other than Shri P. B. Achan . But the workman says that Shri P. B. Achan is the branch manager ofthe depot . I have already mentioned that he is not branch manager of the depot, but only a contractor . Therefore Exts. W11 and 12 will not come to the help of the worker .
the company and not of the contractor. But the letter reveals that it was an intimation given to the company that the workman was appointed and there were two more clerical staff in the Depot . If the company had appointed the three clerks mentioned in Ext . W6 there was no need to inform the company that so and so was appointed and two other clerical staff were already working . On the other hand , it was for the company to inform Shri P. B. Achan that so and so was selected and appointed and he would be joining service in Palakkad Depot. The fact that the letter pad of the company is used for writing Ext . W6 will not help the workman to prove that either his appointment is made by the company or appointment of Shri P. B. Achan as Depot Manager . Regarding the appointment of Shri P. B. Achan there is documentary evidence produced by the management . Ext . Mi is an appointment order dated 27-2-1987 appointing Shri P. B. Achan as Operator of LPG commission -operated Depot at Palakkad. Exts . M2 andM3 are copies of orders extending the period of contract from 1988 to 89 and 1990. Ext . M4 is copy of agreement executed between company and Shri P. B. Achan. It contains various terms concerning the operation of the Depot . The entire responsibility of running ofDepot including appointment, payment of salary to staff, maintenance and repair ofthe depot, distribution ofLPG, financial liabilities , electric, water and communication charges , etc. are to be borne and done by Shri P. B. Achan. The operator had to furnish a bank guarantee also to the company. The operator had to reside at Palakkad at his own expenses . The payment of taxes, fees , etc. under law and remuneration and other benefits to staff had to be borne by the operator/contractor. Clause 7 of the agreement says that the company will supply to the operator its standard forms for delivery documents , returns, etc. against a monthly requisition and only those forms as appropriate shall be used by operator . Thus Shri P. B. Achan was appointed as contractor and not as Depot Manager . There is absolutely no piece of evidence to prove that Shri P. B. Achan was ever recognized by the company as its employee or anything to show that salary was paid to Shri P. B. Achan by the company. A letter pad ofcompany was used by Shri P. B. Achan to write Ext. W6 . It was supplied as per Clause 7 of Ext. M4 agreement referred above . That will not help the workman to prove his case that he is an employee of the company.
11. Ext . W7 is a certificate issued by Assistant Commissioner of Sales Tax, Ernakulam to BPCL on 20-6-1987 certifying that BPCL is a registered dealer under KGST Act and that they have a branch office at Palakkad, and that registration was renewed for the period 1987-88 . The Depot at Palakkad is owned by BPCL and necessarily the registration has to be taken in the name of BPCL, not in the name ofcontractor. This will not indicate that the Depot was run directly by the company.
15. Exts . W13 and 14 series are cash memos issued to purchasers ofLPG from Palakkad Depot . It is seen issued by the workman to dealers . The cash memos are in the printed form of BPCL . These forms are issued to the Depot by the company as per Clause 7 of Ext. M4 agreements with Shri P. B. Achan and the Depot has to utilize the prescribed forms issued by the company while distributing LPG to dealers. The staff in the Depot has to do the clerical workwith regard to distribution of LPG . The workman was authorized by Shri P. B. Achan to sign cash memos as per Ext . M6 . The authorization was done by Shri P. B. Achan , notby the company. Since the Depot was being run by the contractor, Shri P. B. Achan , at his direction cash memos were issued by the workman . The other two clerks were also authorised to issue cash memos to purchasers of LPG . Therefore Exts . W13 and 14 series cash memos also will not show that the workman is an employee of the company.
16. It is to be noted that WW1 , when he was cross- examined, stated that he does not know whether Shri P. B. 12. Ext . W8 is a registration certificate issued by Assistant Labour Officer, Palakkad to BPCL. LPG Staging 4028
THE GAZETTE OF INDIA : JUNE 23 , 2007/ASADHA 2 , 1929
Achan was appointed as a contractor. He also said that he was not aware whether the depot was entrusted on contract basis to Shri P B. Achan. On the other hand Exts . MI to 4 prove the case of the management that Shri P. B. Achan was a contractor entrusted to run the depot at Palakkad on commissionbasis . Thus the workman was not able to prove thatthere is any relationship between BPCL and him in the matter of employment, without which he cannot claim tobe a 'workman' falling within the definition of S - 2 ( s) of I. D. Act or any of the provisions of I. D. Act . The contract of Shri P. B. Achan was renewed from year to year untill 28-2-1991 . Then the Depot was stopped. When the contract came to an end the employment of workers under the contractor too came to an end . At any rate there was no direct relationship between the workman and the company. He was never appointed by the company and he was not paid by the company. He was also not terminated from service by the company. Therefore he cannot have any remedy against the company. There is no violation of any service conditions by the company. As a result , he is not entitled for reinstatement or back wages . The points are answered accordingly.
17. It has become necessary to mention about the array of2nd management as a party in the claim statement of the workman as well as the reference to the 2nd management by the 1st management company in their written statement . But on going through the file it is seen that as per reference there is only one management and thatisBPCL . It is by mistake that in the claim statement the workman has mentioned 2nd management in the cause title. Probably it is an oversight on a wrong impression that since there were two managements in the previous reference which culminated in Ext . W15 award, in the present reference too there are tivo managements.
18. In the result, an award is passed finding that the action of the management , Bharat Petroleum Corporation Limited in terminating the service of Shri C. Sadhisan is legal and proper as he was not an employee of the company and there is no violation of any provisions of I. D. Act . The workman is not entitled to any relief. No cost . The award willtake effect one month after its publication in the Official Gazette.
Dictated to the Personal Assistant , transcribed and typedby her, corrected and passed by me on this the 17th day ofMay, 2007.
P. L. NORBERT, Presiding Officer APPENDIX
Witness for the Workman :
WW1 -C. Sadhisan-31-12-2001 .
Witness for the Management :
MW1K. Sankaran- 14-8-2002 .
[PART II- SEC. 3 ( ii) ]
Exhibits for the Workman:
W1 --Employment certificate dated 7-9-1990 issued to Shri C. Sadhisan .
W2 --Wage slip dated 31-8-1990.
W3 -Wage slip dated 30-9-1990.
W4 -Wage slip dated 31-11-1990.
W5 -Copy of service record.
W6 -Copy of the letter dated 17-2-1988 issued by COD , Palakkad to Sr. Plant Manager , Madras.
W7 Copy of certificate dated 20-6-1987 issued by Asstt . Commissioner of Sales Tax, Ekm.
W8 -Copy of registration certificate issued under Kerala Shops and Commercial Estts . Act.
W9 -Copy of muster roll .
W10 -Copy ofmuster roll .
W11 Copy of Wage Register for the period from 1-7-1990 to 31-7-1990.
W12 -Copy of Wage Register for the period from 1-1-1991 to 31-1-1991 .
W13 -Copy of cash memo .
W14 series-Copies of cash memos (4 Nos.) W15 -Copy of award in I. D. 51/94 of Labour Court , Kozhikode and its Gazette Notification dated 20-10-1995 .
Exhibits for the Management:
M1 Copy of appointment order dated 27-2-1987 appointing Shri P. B. Achan as Operator of LPG Commission Operated Depot at Palakkad.
M2 -Copy of order extending the period of contract, dated 6-1-1989 .
M3 Copy of order extending the period of contract, dated 5-3-1990 .
M4 Copy of agreement dated 18-4-1990 between company and Shri P. B. Achan .
M5 -Copy of intimation of closing down the depot, dated 27-2-1991 .
M6 Copy of pay slip .
M7 --- Copy of appointment order dated 3-5-1991 issued to Smt . K. Sheela .
M8 -Voucher ofBPCL .
[भाग II- खंड 3 ( ii ) ]
4029
भारत का राजपत्र : जून 23, 2007/ आषाढ़ 2, 1929
> नई दिल्ली, 1 जून, 2007
services of Shri Chandrakant Burman, Temporary Messenger w.e.f. 16-8-1999 , while he has worked in Devgan Branch of the Bank from 8-1-1994 to 15-8-1999, is justified ? Ifnot, what relief he is entitled ?"
2.The case ofworkman Shri Chandrakant Burman in brief is as follows :
का.आ. 1838.-औद्योगिक विवाद अधिनियम, 1947 ( 1947 का 14 ) की धारा 17 के अनुसरण में, केन्द्रीय सरकार स्टेट बैंक ऑफ इण्डिया के प्रबंधतंत्र के सम्बद्ध नियोजकों और उनके कर्मकारों के बीच, अनुबंध में निर्दिष्ट औद्योगिक विवाद में केन्द्रीय सरकार, औधोगिक अधिकरण, जबलपुर के पंचाट ( संदर्भ संख्या 183/2000 ) को प्रकाशित करती है , जो केन्द्रीय सरकार को 1-6-2007 को प्राप्त हुआ था ।
[सं. एल-12012/247/ 2000- आई आर ( बी- I ) ] अजय कुमार, डेस्क अधिकारी
New Delhi , the 1st June, 2007
That he was in the permanent employment as messenger/waterman at the branch of State Bank of India, Devgan (Katni ) w.e.f. 8-1-1994 to 15-8-1999. He worked for more than 240 days in every year. His services were terminated on 15-8-1999 without any reasonable cause which is an illegal act . He prayed for reinstatement with all back wages and benefits .
S.O. 1838. In pursuance of Section 17 of the Industrial Disputes Act, 1947 ( 14 of 1947) , the Central Government hereby publishes the Award (Ref. No. 183/ 2000) ofthe Central Government Industrial Tribunal/Labour Court, Jabalpur as shown in the Annexure in the Industrial Dispute between the management of State Bank of India and their workman, which was received by the Central Government on 1-6-2007.
3. Vide order dated 8-5-2007 of this Tribunal the reference proceeded ex parte against the Workman/Union . The order dated 15-5-2007 reveals that Shri Vijay Tripathi , Advocate for the Management made submission that no evidence is to be adduced on behalf of Management and no argument is to be submitted for the Management. He requested for closing the reference for award . Therefore the reference was closed for award.
[No. L - 12012/247/2000- IR (B- 1 ) ] AJAY KUMAR, Desk Officer
ANNEXURE
BEFORE THE CENTRAL GOVERNMENT INDUSTRIAL TRIBUNAL-CUM- LABOUR COURT, JABALPUR
No. CGIT/LC/R/ 183/2000
Shri C. M. Singh, Presiding Officer.
Shri Chandrakant Burman, C/ o Shri N. K. Patel,
4. It is a case of no evidence by the parties. Under the circumstances , the reference deserves to be answered in favour of the management and against the Workman/ Union without any order as to costs . It is, therefore, held that the action of the management of State Bank of India, Marhatal , Jabalpur in terminating the services of Shri Chandrakant Burman, Temporary Messenger w.e.f. 16-8-1999, while he has worked in Devgan Branch ofBank from 8-1-1994 to 15-8-1999, is justified. Consequently the workman is not entitled to any relief. The party shall bear their own costs ofthis reference . The reference is answered accordingly.
Dy.General Secretary,
5. Copy of the award be sent to the Government of India, Ministry ofLabour as per rules.
StateBank of India Staff Congress , 5/235, Pragati State Bank Staff Colony, Vikasnagar,
C. M. SINGH, PresidingOfficer Jabalpur (M. P. )-482002
Union/Workmen
Versus
नईदिल्ली, 1 जून , 2007
TheAssistant General Manager, Region- I , State Bank of India, Divisional Office, CivilCentre, Marathal, Jabalpur ( M. P. ) -482002
Management
AWARD
Passed on this 15th day of May, 2007
का.आ. 1839.-औद्योगिक विवाद अधिनियम, 1947 ( 1947 का 14 ) की धारा 17 के अनुसरण में, केन्द्रीय सरकार ईस्टर्न रेलवे के प्रबंधतंत्र के सम्बद्ध नियोजकों और उनके कर्मकारों के बीच, अनुबंध में निर्दिष्ट औद्योगिक विवाद में केन्द्रीय सरकार, औद्योगिक अधिकरण, लखनऊ के पंचाट ( संदर्भ संख्या 27/2004 ) को प्रकाशित करती है, जोकेन्द्रीय सरकार को 1-6-2007 को प्राप्त हुआ था ।
[सं. एल-41012/119/2003- आई आर ( बी-1 ) ] अजय कुमार , डेस्क अधिकारी 1. The Government of India, Ministry of Labour vide its Notification No. L- 12012/ 247/2000 - IR (B - I ) dated 16-10-2000 has referred the following dispute for adjudication by this tribunal :
NewDelhi , the 1st June, 2007
S.O. 1839.- In pursuance of Section 17 of the Industrial Disputes Act , 1947 ( 14 of 1947) , the Central "Whether the action of the management of State Bank of India , Madhatal , Jabalpur in terminating the 4030
[PART II-SBC . 3 (ii)] THE GAZETTE OF INDIA : JUNE 23 , 2007/ASADHA 2 , 1929
Government hereby publishes the Award (Ref. No. 27/2004) ofthe Central Government Industrial Tribunal -cum -Labour Court, Luckuow as shown in the Annexure in the Industrial Dispute between the management of Eastern Railway and their workman, received by the Central Government on 1-6-2007.
[No. L-41012/ 119/2003 -JR(B -I ) ]
AJAY KUMAR, Desk Officer
ANNEXURE
CENTRAL GOVERNMENT INDUSTRIAL
TRIBUNAL-CUM - LABOUR COURT,
LUCKNOW
PRESENT
Shrikant Shukla, PresidingOfficer.
I.D. No. 27/2004
adjudicationbefore CGIT-cum - Labour Court, Kanpur which was I.D. 71/96 . The Tribunal did not adjudicate the said disputes and returned unanswered . workman concerned with other casual labours moved an application to the Secretary Ministry of Labour, Govt . of India, New Delhi. Afterconsidering the said application the Government directed to raise industrial dispute fresh vide letter dt . 20-10-2000 and accordingly worknaan concerned raised the industrial dispute and government referred the dispute vide order dt . 11-3-2004. It is submitted that there is no delay in raising industrial disputes and the stands explained by the worker. Workman has therefore prayed that the action of the management in terminating the services of the workman w.e.f. 23-12-76 be decleared illegal and bad in law and accordingly workman be reinstated back in service with continuity of service and all consequential benefits arising therefrom including back wages . Workman filed attested photo copies purported to be record of casual labour .
Ref . No. L- 41012/ 119/2003 - IR (B - I) dt . 13-2-04
BETWEEN
SriNandKishore S/ o Jagdev, Village-BoliaPandey, Post Raita Kothi , Distt Bewaria (U.P. )
AND
The General Manager,
Eastern Railway, Gorakhpur -273001
The Railway Road Inspector (Const .)
EasternRailway,
Gonda
AWARD
The opposite party disputed the claim and denied that the worker was ever engaged by the opposite party as alleged . It has been submitted by the opposite party that the worker has put false concocted and imaginatory facts. It is specifically denied that the worker ever worked under opposite party or acquired temporary status . The worker has filed rejoinder wherein the worker has stated that he has worked for 658 days w.e.f. 16-3-75 to 23-12-76 without any break in service . Thus as per Railway Manual and provision of I.D. Act . 1947 his services would not have dispensed with by the opposite party without assigning any reason . notice, retrenchment compensation . It has been reiterated that worker has acquired temporary status of railway servant . Worker has filed photo copies of the following documents ; Certificate of PWI ( Construction) 13-2-91 showing 648 days working paper No. 20/4.
Worker has also filed photo copy of the followintg documents:
The Government of India, Ministry of Labour, New Delhi referred the following dispute vide No. L -41012/ 119/ 2003 - IR (E - I ) Dt. 13-2-2004 for education to the Presiding Officer, CGIT -cum- Labour Court , Lucknow;
1. Record of service of casual labour of Nand Kishore showing 658 days of work from 16-3-75 to 23-12-76, certificate, age certificate of Gram Sabha, Bolia Pandey 1-1-75 .
" क्यारेल पथ निरीक्षक ( निर्माण ) , पूर्वोत्तर रेलवे गोण्डा द्वारा कर्मकार श्री नन्द किशोर आत्मज श्री जगदेव की दि. 23-12-76 सेसेवा समाप्त किया जाना न्यायोचित है ? यदि नहीं, तो कर्मकार किस अनुतोष का हकदार है ? "
2. Photocopy of school leaving certificate 15-9-95.
3. Photocopy of his own application .
4. Photocopy of order passed in I.D. 71/96.
5. Photocopy of unsigned letter addressed to Secretary Ministry of Labour alongwith list of some worker dt. 5-10-2001 .
Worker has examined himself. Opposite party has not produced any evidence . Heard the arguments and perused written arguments submitted by the parties. Following facts are material in the present case .
The worker's allegation is that he was terminated from 23-12-76 and he worked w.e.f. 16-3-75 .
The worker has alleged in his statement of claim that he was engaged as casual labour on 16-3-75 at Tikoniya and had worked w.e.f. 16-3-75 to 23-12-76 continously as casual Khalasi and acquired the status of temporary railway servant and in this view the service could not have dispensed with by the opposite party on 23-12-76 without assigning any reason or without giving him notice and compensation . Any deviation or departure from the provision under section 25F of the I.D. Act while terminating the services of workman concerned would render the same is illegal and unjustified . It is also stated that the workman concerned raised industrial dispute with some other casual labours which was referred for 4031
भारत का राजपत्र: जून 23, 2007/आषाढ़ 2, 1929
[ भाग II- खंड 3 ( ii) ]
According to the own submission of the worker that he alongwith other worker raised I.D. 71/96 before CGIT- cum-Labour Court, Kanpur which was numbered as 71/96 . No. original document have been filed nor certified copy of the award passed in I.D. 71/96. But even then whatever worker has stated is taken to be true there is the delay of approximately 20 years in raising the dispute after alleged termination w.e.f. 23-12-76. Opposite party is not expected to retain the casual labour record for such a long years . So there is abnormal delay in raising the dispute which has caused the management of railways a considerable prejudice.
Worker has alleged that he worked during 16-3-75 to 23-12-76 for 658 days but the record which has been produced before the court has been scrutinised by me . I have carefully calculated the number ofdays given in record of casual labour paper No. 7/5 . After calculating the days it comes out to 618 days and not 658 days as written inthe said record of the casual labour paper 7/5.
The representative of the workman has argued that workman concerned has rendered continuous service for more than 240 days in one calendar year. The railway management has dispensed with the service of the worker w.e.f. 24-12-76 without making payment of retrenchment compensation or notice pay in lieu thereof and hence the termination of the workman amounts to be in the breach of provision ofSection 25F of the I.D. Act and the workman is entitled to reinstated in the services of the railway management. In support of his case the workman testified himself on oath before Tribunal apart from filing of documentary evidence such as casual labour card issued by the railway and is available in the record. The oral testimony of the workman has been corroborated by the documentary evidence as well. In this way the workman has been able to establish his case to the effect that he render continuous service for more than 240 days precedings 12 months from the date of illegal termination i.e. 24-12-76 and the management has failed to put witness inthe witness box before the court .
On the other hand the representative of the management has argued that if a person was not in service what negative evidence he has produce in the court . The case has come up before the court after 30 years and the management cannot have any record of such old time and ifthe claim statement is allowed in the circumstances there will be miscarriage of Justice. Representative of the management has also argued that the railway establishment is vast deparment and employed highest number of labourers and casual labour book is issued to them . Any worker engaged as casual labour is issued casual labour book mentioning therein monthwise working days of the worker with the initial ofthe railway officer. He has argued that worker has concocted the false story that he was terminated about 30 years back and has also argued that photo copies of the documents produce before this court are false and not genuine .
It is evident from the paper No. 7/5 that there is no signature of any officer on paper No. 7/5 and the same is blank but the worker has again produced the photocopy of casual labour card alongwith application C-21 wherein I find the signature of Railpath Nirikshak, Sri Swami Nath. Again I find the same PWI issuing the certificate mentioning 648 days . It is not possible for the railways to dig out a person after such a long lapse to disprove the worker's case but on over all evaluation of the evidence of the worker the said document appears to be not genuine . It is further clarified that the worker ought to have produced the original certificates for corroborating his case . It is also not worthy thatworker has filed the certificate of Gram Pradhan, though original has not been produced and the one produced before the court is not signed and has over writing which makes it fictitious . Even if it is presumed that worker through trade union raised the industrial dispute No. 7/96 even then it had delay. Worker has measurably failed to justified the delay. It is also noteworthy that so called record of service of casual labour shows that upto 23-12-76 the workman worked as follows:
To
From
No. ofdays
The representative of the management has also argued that worker has not produced satisfactory documentary evidence to prove that he was a casual labour and that as has required temporary status and in the circumstances he should not be believed. 31-3-1975
16-3-75
16days
30-4-1975
1-4-75
30 days
31-5-1975
1-5-75
31 days
30-6-1975
1-6-75
30days
31-7-1975
1-7-75
31days
30-8-1975
1-8-75
31days
30-9-1975
1-9-75
30days
The representative of the opposite party has argued that there appears to be break in service as the worker has worked 31 days in 2 months i.e. from 1-11-75 to 31-12-75 butwhen he was cross examined he said " मुझे नौकरी में कोई नागा. नहीं दिया । मुझे एक दिन भी नहीं बैठाया गया । नौकरी में यदि break है तो लिखने वाला जाने । यह सही नहीं है कि मुझे बीच में बैठाया गया। Temporry Status के बारे में कोई प्रमाण नहीं है । " 31-10-1975
1-10-75
31days
31-12-1975
1-11-75
31 days
30-6-1976
1-1-1976
181 days
The representative of the opposite party has argued that there is concoction and such contradictions bound to come as called service record filed by the worker is forged. 1-7-1976
23-12-1976
176 days
2733 GI/07--16 4032
Onconsidering the entire evidence on record I come to the conclusion that evidence of the workman is not trustworthy and it can not be believed that workman was ever in the employment of the opposite party. The issue therefore is decided against the workman and therefore he is not entitled to any relief.
Lucknow 24-5-2007
SHRIKANT SHUKLA, Presiding Officer नई दिल्ली, 1 जून , 2007
का.आ. 1840.-औद्योगिक विवाद अधिनियम, 1947 ( 1947 का 14 ) की धारा 17 के अनुसरण में, केन्द्रीय सरकार बीजापुर ग्रामीण बैंक के प्रबंधतंत्र के सम्बद्ध नियोजकों और उनके कर्मकारों के बीच, अनुबंध में निर्दिष्ट औद्योगिक विवाद में केन्द्रीय सरकार, औद्योगिक अधिकरण, बैंगलोर के पंचाट ( संदर्भ संख्या 114/1999 ) को प्रकाशित करती है , जो केन्द्रीय सरकार को 1-6-2007 को प्राप्त हुआ था । [सं. एल-12011/14/1999- आई आर ( बी -1 ) ] अजय कुमार, डेस्क अधिकारी New Delhi , the 1st June , 2007
S.O. 1840. In pursuance of Section 17 of the Industrial Disputes Act , 1947 ( 14 of 1947) , the Central Government hereby publishes the Award (Ref. No. 114/ 1999) of the Central Government Industrial Tribunal - cum- Labour Court, Bangalore as shown in the Annexure in the Industrial Dispute between the management of Bijapur GraminaBank and their workman which was received by the Central Government on 1-6-2007.
[No. L- 12011/ 14/ 1999 - IR(B -I) ] AJAY KUMAR, Desk Officer
ANNEXURE
BEFORE THE CENTRAL GOVERNMENT INDUSTRIAL TRIBUNAL- CUM - LABOUR COURT, BANGALORE
Dated 24th May, 2007
PRESENT
Shri A.R. Siddiqui , Presiding Officer
C.R. NO . 114/99 I PARTY
The General Secretary,
BijapurGrameena Bank ,
Employees Association, Vital Niwas , Assan Road, Bijapur586 101
II PARTY
The Chairman,
BijapurGrameena Bank, P.B. No. 30 , Vivek Nagar (West ) , Bijapur. HeadOffice,
THE GAZETTE OF INDIA : JUNE 23 , 2007 /ASADHA 2 , 1929
[PART II-SEC . 3 ( ii) ]
AWARD
1. The Central Government by exercising the powers conferredby clause (d) of sub-section 2A of the Section 10 ofthe Industrial Disputes Act, 1947 has referred this dispute vide order No. L- 12011 / 14/99 - IR (B - I) dated 22nd October, 1999 for adjudication on the following schedule:
SCHEDULE
"Whether the action of the management of Bijapur Grameena Bank, Head Office , Bijapur is legal and justified in denying TA/ DA to defence representatives . If not to what relief the defence representatives are entitled ? "
2. The case of the first party union , represented through the General Secretary, as made out in the Claim Statement , in brief, is that there is a practice in all the Regional Rural Banks to facilitate the management representative participating on behalf of the management in the Domestic Enquiries being held against the delinquent employees with the TA and DA. But the co- workers who appeared as a defence representatives in the domestic enquiries conducted against the delinquent workmen, there is no such provision or facility available to the Defence Representatives to claim TA and DA though in most of the cases the delinquent workman had to meet the expenses of their defence representatives with respect to lodging and boarding. therefore , unless the TA and DA is given to the Defence Representatives , it will amount to compelling the charge sheeted workman to spend money tantamounting to a punishment in itself; that the neighbouring RRB Tungabhadra Grameena Banks operating in Bellary and Raichur districts have been providing TA and DA to the Defence Representatives and Defence witnesses also and in case such TA/DA facilities is extended to the Defence Representatives it will further the cause and principles of natural justice and in case it is denied it will be undue hardship to the charge sheeted employees and it will amount todiscrimination in the process ofholding domestic enquiry. Moreover, denial of such a facility to the employees of the Bijapur Grameena Bank as against the employees working in other Regional Rural Banks will be a differential treatment amounting to discrimination and therefore, the management may be directed to pay the TA and DA to the Defence Representatives .
3. The management by its counter Statement however, contended that the demand made by the first party union is not maintainable either in law or on facts as the Staff Service Regulations of Bijapur Grameena Banks framed by the Board of Directors after consultation with the Syndicate Bank/ NABARD)/Reserve Bank of India and the prior sanction of the Central Government applicable to all the officers and employees of the bank in the matter of any allowance or other benefits do not provide a provision or benefit of payment of TA/ DA to the Defence [ 'भाग II- खंड 3 ( ii) ]
4033
भारत का राजपत्र : जून 23, 2007/आषाढ़ 2, 1929
Representatives appearing for the charge sheeted employees, since those Staff Service Regulations , 1983 of the bank revised in the year 2001 did not provide such a facility to the Defence Representative . However, on receipt of the demand from the first party union , the management sought clarification from the NABARD and in response to the said clarification received a letter dated 28-12-1996 stating that there is no such provision under the above said Regulations and therefore , the demand of the first party union cannot be acceded to; that these staff service regulations have got statutory force and bind both the employees and the management ; that as per the guidelines received from the sponsor bank namely, the Syndicate,Bank, the second party management however, extended the benefit of TA/DA to the Defence Representatives w.e.f. 1-1-2002 and thereby the demand of the first party union has been fulfilled . This benefit ofTA/DA has been extended to the Defence Representatives with prospective date and in the result the union now cannot claim the benefit for the earlier period as there was no provision in the Service Regulations to that effect earlier to the above said date. Therefore , the management requested this tribunal to reject the reference .
4. During the course of trial , the management on its behalf examined one Mr. K. Panduranga, Senior Manager, Personnel & Secretariat of the management bank by filing . his affidavit evidence as MWI . In his affidavit said witness just reiterated the various contentions taken by the management in its counter Statement . In his further examination chief three documents namely, the aforesaid Staff Regulations , 1983, the letter written by the Chairman of the Bijapur Grameena Bank, Head office to the Management Bank and the Circular dated 1-1-2002 were marked at Ex-M1 to M3 . There was no cross examination to this witness on behalf of the first party union, he being discharged there being no representation on behalf of the union as on the date the witness was present for his cross examination. The first party union also did not come forward to lead any oral or documentary evidence , thereafter. On 24-4-2007 when the matter was posted for evidence of first party union, once again there was no representation from the first party union . Therefore , the matter was taken closed and after hearing the learned counsel for the management it is posted this day for award.
6. I find substance in his arguments . Undisputedly, therehas been no such provision under the aforesaid staff regulations with regard to the payment of TA/DA benefits to the Defence Representatives . It is also not the case of the first party union that such a benefit is being denied to the Defence Representatives despite any such provision or rule under the aforesaid staff regulations . The only contention taken by the first party union is that such a benefit was being extended to the Defence Representatives by the other regional rural banks and therefore , ends of justice demanded for such a provision/benefit to the Defence Representatives of the management bank employees , merely because such a benfit is available to the Defence Representatives appearing for the charge sheeted employees working under other Regional Rural Banks , the first party union in this case cannot claim the said benefit by way of right. The first party union as noted above , neither adduced any oral or documentary evidence in support ,of its claim nor challenged the statement ofMW1 to the effect that under the aforesaid staff regulations the first party union cannot maintain the present claim . Moreover, as seen above , the demand in question has been fulfilled by the management by issuing the guidelines as perthe circular marked before this tribunal at Ex.M3 . Para 10 (VI) (2) of the aforesaid circular as provides the benefit of TA and DA to the Defence Representatives and this benefit has been extended to them prospectively w.e.f. 1-1-2002 . As per the reference schedule there is no demand by the first party union with respect to TA and DA to the Defence Representatives earlier to the date of reference or from the date of the reference or from any specific date . The reading of the reference schedule will just speak to the demand of the first party union without giving any specific date. In the Claim Statement also the first party did not make out any case or had given any date from which date the Defence Representatives should be paid TA/DA by the management bank. Therefore, keeping in view the evidence prduced by the management and at the same time taking into consideration the fact that the first party union did not come forward to establish its claim much less from a particular specific date and so also taking into account the fact that the demand of the first party union has already beenmet by the management, there is no hesitation in the mind of this tribunal to come to the conclusion that the dispute raised by the first party union not only fails on merits but also does not survive any more and hence reference is liable to be dismissed . Hence the following Award:
AWARD
The reference stands dismissed . No costs .
(Dictated to PA, transcribed by her , corrected and signedby me on 24th May 2007).
A.R. SIDDIQUI , Presiding Officer 5. Learned counsel for the managernent in his arguments submitted that the aforesaid staff regulations since did not provide facility/benefit of availment ofTA/ DA to the Defence Representatives , question of any payment towards TA/DA never arose . He submitted that thereupon the management bank received clarifications with regard to the payment of TA/DA benefit to the Defence Representatives by way of the aforesaid circular at Ex.M3 w.e.f. 1-1-2002 such a benefit is being extended and therefore, the demand of the first party union having been fulfilled as on today the reference is liable to be rejected as the dispute no more survive .
4034
THE GAZETTE OF INDIA : JUNE 23 , 2007/ASADHA 2 , 1929
नई दिल्ली, 1 जून , 2007
का.आ. 1841.-औद्योगिक विवाद अधिनियम, 1947 ( 1947 का14 ) की धारा 17 के अनुसरण में, केन्द्रीय सरकार स्टेट बैंक ऑफ भैसूरके प्रबंधतंत्र के सम्बद्ध नियोजकों और उनके कर्मकारों के बीच, अनुबंध में निर्दिष्ट औद्योगिक विवाद में केन्द्रीय सरकार, औद्योगिक अधिकरण, बैंगलोर के पंचाट ( संदर्भ संख्या 08/2005 ) को प्रकाशित करती है , जो केन्द्रीय सरकार को 1-6-2007 को प्राप्त हुआ था । [सं. एल-12012/234/2004- आई आर ( बी-1 ) ] अजय कुमार, डेस्क अधिकारी New Delhi, the 1st June , 2007
S.O. 1841-In pursuancersuance of Section 17 of the Industrial Disputes Act, 1947 ( 14 of 1947 ), the Central Government hereby publishes the Award (Ref. No. 08/2005 ) ofthe Central Government Industrial Tribunal-cum - Labour Court, Bangalore as shown in the Annexure , in the Industrial Dispute between the management of State Bank ofMysore and their workmen,which was received by the Central Government on 1-6-2007.
[No. L - 12012/234/2004 - IR(B -I) ] AJAY KUMAR, Desk Officer
ANNEXURE
BEFORE THE CENTRAL GOVERNMENT INDUSTRIAL TRIBUNAL CUM - LABOUR COURT, BANGALORE
Dated: 17th May, 2007
PRESENT
Shri A. R. Siddiqui , Presiding Officer
C. R. No. 08/2005
II PARTY
I PARTY
The General Manager , State Bank of Mysore, Head Office , K.G. Road, Bangalore- 560009 Shri S. T. Srinivas , No. 289, 3rd Cross , Nagappa Street, Palace Guttahalli , Bangalore-560 003
AWARD
1. The Central Government by exercising the powers conferred by clause (d ) of sub - section 2A ofthe Section 10 ofthe Industrial Disputes Act, 1947 has referred this dispute vide order No. L - 12012 / 234 /2004 - IR (B - II ) dated 28th December, 2004 for adjudication on the following schedule:
SCHEDULE
"Whether the management of State Bank of Mysore isjustified in removing Shri S. T. Srinivas , a Temporary Attender, from the services of the Bank in the year 1989 ? If not, to what relief he is entitled to ? "
[PART II- SEC . 3 ( ii) ] 2. The case of the first party workman , as made out inthe Claim statement , in brief, is that he being appointed asAttender in the State Bank of Mysore in the year 1986 , has discharged his duties in various branches such as Cunningham Road Branch , Sheshadripuram Branch . Between 16-1-1984 to 27-8-1987 he was working in S C Road, SBM branch against the clear vacancy on account ofdeath of Shri Muniraju and Shri Harshawardhana and in between 1987 and 1989 he worked against the vacancy of Shri Satyanarayana Rao and Shri Bhaskar ; that subsequently in the year 1987 and 1989 while he was working at S C Road Branch , he was temporarily removed from service in pursuance to the complaint lodged by the BranchManager to the police under Section 468 & 420 of IPC; that after investigation the police filed a " B " Report and charges against the first party were dropped and he was acquitted . However, despite his innocence being proved he was not taken back in service . He filed a civil suit against the management seeking the reinstatement in service and that was disposed of in the year 2003; that the firstparty worked continuously for a period of more than 240 days therefore , his case should have been considered for reinstatement on regularisation but the management did not do so and that shows a clear case of victimization. He made requests on several occasions for his reinstatement but in vain . Finally on 10-12-2003 he gave representation to corisider his case . The first party then referred to paras 20.7 , 20.8 and 2.12 of the Bipartite Settlement to show that temporary workman also is a workman appointed temporarily against permanent vacancy etc.He requested this tribunal to pass an award reinstating him in service giving all other benefits .
3. The management by its counter statement while resisting the claim of the first party among other grounds contended that by his own admissions the first party was working as a temporary peon and never worked in any of the branch of the bank for a period of 240 days and more in anyblock period of 12 months . The management contended that though the first party was involved in a case of fraud and misappropriation and in fact deposited the misappropriated amount , the management did not take any disciplinary action against him he being a temporary peon . The management contended that the first party is not entitled for any relief either for reinstatement or for absorption as claimed . The management also contended that the present reference and the dispute is liable to be dismissed being a state dispute raised after a lapse of a period of 15 years from the date of alleged termination of the services of the first party.
4. During the course of trial , the management examined the branch Manager , SBM, SC Road branch as MW1 and got marked four documents namely, the certificates issued in favour of the first party at Ex. Ml to M4. His statement in brief was that the first party was [ भाग II- खंड 3 (ii ) ]
4035
भारत का राजपत्र : जून 23, 2007/आषाढ़ 2, 1929
the management. In this respect he quoted decisions reported inJT2002(2) SC 238, 2004(8 ) SCC 161 , 2004 LAB IC4041 SC and AIR 1997 SC 3657 .
doing thejob of temporary peon against the leave vacancy ofpermanent peon and he did not work continuously for a period of 240 days in any of the branch of the management bank. In his cross examination nothing worth was elicited except to elicit that ' B ' Report was filed by the police and the case against the first party was closed. It was elicited that the said Shri Muniraju and Shri Harshawardhanawho were working as Peons expired and there was clear vacancies on account of their deaths . It was elicited that no muster roll , attendance register etc. have been produced bythe management and that no records are available with the management for having engaged the first party.MW1 was unable to say if during the year 1986 to 1989 the first party worked continuously for a period of 240 days and more in each calendar year .
5. As a rebuttal , the first party filed his affidavit evidence reiterating the averments made in the Claim Statement . In his further examination chief he produced 3 attendance certificates marked at Ex. W1 series (M1 , M3 & M4).He also produced extract of two death certificates of Shri Muniraju and Shri Harshawardhan at Ex. W2 series , police 'B ' report at Ex. W3 , letter dated 21-7-1990 written by the Manager to the Sub - Inspector of Police at Ex. W4 . In his cross examination he admitted that he joined the services of the bank as a temporary peon and contents of Ex . W1 series are correct. He denied the suggestion that he was engaged by the bank whenever permanent peons were absent from duty for some reason or the other. He admitted that his name was not sponsored by the Employment Exchange . He denied the suggestion that he did not work for 240 days continuously in any of the calendar year . He admitted that he was interrogated by the police as per Ex. M6,
6. Learned counsel for the first party vide his written arguments once again repeating the various contentions of the first party made in his Claim Statement, further contended. His next contention that the management failed to produce the muster roll , attendance register etc. which records would have disclosed as to whether the first party worked or not continuously for a period of 240 days in any calendar year. He took support of the documents at Ex. W1 to W4 in support of the case of the first party to prove that he was working with the management bank during the year 1986 to 1989 . :
7. Whereas , the learned counsel for the management in his arguments submitted that the reference in the first instance is to be dismissed for the undue delay caused in raising the dispute . He took support of a decision reported in (2001 ) 1 SC cases 424 and a decision reported in AIR 2000 SC 839 and other two decisions . He also contended that the first party being engaged on temporary basis and since he did not work continuously for a period of 240 days , he cannot take the benefit of Section 25F of the ID Act to challenge the alleged termination of his services by
8. After having gone through the records I find substance in the arguments advanced for the management. Keeping in view the respective contentions of the parties and the evidence brought on record the only relevant point to be considered is whether the first party worked continuously for a period of240 days and more during the block period of 12 months immediately preceding the date of his alleged termination from services. The first party himself has produced three certificates marked at Ex. Wi series to show as to for how many days he worked with different management branches . The first certificate produced by him is dated 16-12-1987 suggesting that he worked for 17 days during the year 1986 and for 9 days during the year 1987 as a temporary peon at State Bank of Mysore branch . The second certificate dated 21-12-1987 reads to the effect the first party worked temporarily for 27 days during the calendar year 1986 at the Cunningham Road branch. The third certificate dated 19-5-1989 shows that he worked for a period of 144 days totally during the years 1987to 1989. As per the details given in the certificate it can be seen that the first party worked for a period of 22 days in the month of February 1989 and for 8 days in the monthMay 1989. He worked for a period of 30 days in the month ofDecember 1988 and for a period of 84 days in the year 1988. Therefore, the first party during the years 1987 and 1989 put together hardly,worked for a period of 144 days . He never worked for a period of 240 days in any calendar year as per the aforesaid three certificates produced by him in support of his case . The management also produced these three certificates along with another certificate dated 29-11-1988 and according to this also the first party worked hardly for a period of84 days in between 16-1-1984 and 27-8-1987. The other documents produced bythe first party namely, the said two death certificates of ShriMuniraju and Shri Harshawardhana to show that after their death he worked in their place against the permanent vacancy will be of no help to the first party in any way. Onlybecause he worked as against the permanent vacancy he will get no rights either to claim reinstatement or to claim absorption in service on permanent basis . He admittedly being a temporary peon will succeed in the present case only after he establishes that he worked for a period of240 daysand more continuously in a block period of 12 calendar months that too preceding immediately to the date of his alleged termination. In the instant case as noted above , in between the year 1984 & 1989 he never crossed his continuous service for a period of 240 days much less continuous service of 240 immediately before his alleged termination. In fact , as per the averments in the claim statement he is not sure as to whether his services were terminated in the year 1987 or 1989. As seen above , he worked hardly for a period of 30 days in the year 1988 and 4036
[PART II- SEC . 3 (ii) ] THE GAZETTE OF INDIA : JUNE 23 , 2007/ASADHA 2 , 1929
New Delhi , the 12th June , 2007
for a period of another 30 days in the year 1989. The contention of the first party that the management should have produced muster roll and attendance register in order to find out as to how many days he worked with the management is not tenable for the simple reason that the burden squarely cast upon the first party himself to substantiate his case for having worked 240 days and more continuously in any block period of 12 months. Moreover, whenthe first party himself has produced the certificates referred to supra , he cannot be allowed to contend that he had worked with the management bank branches for the periodbeyond the period mentioned in those certificates. Therefore, claim of the first party must fail.
S.O. 1842. Whereas the Central Government having been satisfied that the public interest so requires that in pursuance of the provisions of sub-clause (vi ) ofthe clause (n) ofSection 2 of the Industrial Disputes Act , 1947 (14 of 1947) , declared by the Notification of the Government of India in the Ministry of Labour S.O. No. 4891 dated 11-12-2006 the service in the industry engaged in the Processing or Production of Fuel Gases (Coal Gas , Natural (Gas and the like ) which is covered by item 29 of the First Schedule to the Industrial Disputes Act , 1947 ( 14 of 1947) to be a Public Utility Service for the purpose of the said Act for a period of six months from the 15th December, 2006.
And whereas , the Central Government is of opinion that public interest requires the extension of the said period by a further period of six months .
9. Even otherwise, as contended for the management and theprinciple laid down by their Lordship of Supreme Court on the point of delay in the aforesaid decisions , the present dispute deserves to be rejected for the simple reason that it has been raised by the first party after a lapse of period of 15 years from the date of the alleged termination, that too, without giving any explanation for the delay caused. As on the date the dispute was raised , certainly, it was a stale dispute and therefore, on this count also the reference deserves to be rejected.
Now, therefore, in exercise of the powers conferred by the provise to sub - clause (vi) of clause (n) of Section 2 ofthe Industrial Disputes Act, 1947, the Central Government hereby declares the said industry to be a Public Utility Service for the purposes of the said Act, for a period of six months from the 15th June , 2007 .
Hence the following award :
AWARD
[File No. S- 11017/2/2003 - IR (PL) ] GURJOT KAUR, Jt . Secy.
The reference is rejected . No costs.
नई दिल्ली, 12 जून , 2007
(Dictated to PA, transcribed by her, corrected and signed by me on 17th May, 2007) . A. R. SIDDIQUI, Presiding Officer नई दिल्ली , 12 जून , 2007
का.आ. 1843.-केन्द्रीय सरकार संतुष्ट हो जाने पर किलोकहित में ऐसा करना अपेक्षित था, औद्योगिक विवाद अधिनियम , 1947 ( 1947 का 14 ) की धारा 2 के खण्ड ( ढ़ ) के उप- खण्ड ( vi ) के उपबंधों के अनुसरण में भारत सरकार के श्रम मंत्रालय की अधिसूचना संख्या का.आ. 4890 दिनांक 28-11-2006 द्वारा लोह अयस्क खनन उद्योग जोकि औद्योगिकविवाद अधिनियम, 1947 ( 1947 का 14 ) की प्रथम अनुसूची की प्रविष्टि 16 में शामिल है , को उक्त अधिनियम के प्रयोजनों के लिए दिनांक 18-12-2006 से छः मास की कालावधि के लिए लोक उपयोगी सोवा घोषित किया था;
और केन्द्रीय सरकार की राय है कि लोकहित में उक्त कालावधि को छः मास की और कालावधि के लिए बढ़ाया जाना अपेक्षित है;
का.आ. 1842.-केन्द्रीय सरकार संतुष्ट हो जाने पर कि लोकहित मेंऐसा करना अपेक्षित था, औद्योगिक विवाद अधिनियम, 1947 ( 1947 का 14 ) की धारा 2 के खण्ड ( ढ़ ) के उप - खण्ड ( vi ) के उपबंधों के अनुसरण में भारत सरकार के श्रम मंत्रालय की अधिसूचना संख्या का. आ. 4891दिनांक 11-12-2006 द्वारा ईंधन गैसों ( कोयला गैस , प्राकृतिक गैस और ऐसी अन्य ) के प्रसंस्करण एवं उत्पादन में लगे उद्योग में सेवाओं कोजोकि औद्योगिक विवाद अधिनियम , 1947 ( 1947 का 14 ) की प्रथम अनुसूची की प्रविष्टि 29 में शामिल है, को उक्त अधिनियम के प्रयोजनों के लिए दिनांक 15-12-2006 से छः मास की कालावधि के लिए लोक उपयोगी सेवा घोषित किया था;
और केन्द्रीय सरकार की राय है कि लोकहित में उक्त कालावधि कोछः मास की और कालावधि के लिए बढ़ाया जाना अपेक्षित है ;
अतः अब, औद्योगिक विवाद अधिनियम , 1947 ( 1947 का 14) की धारा 2 के खण्ड ( ढ़ ) के उप- खण्ड ( vi ) के परन्तुक द्वारा प्रदत्त शक्तियों का प्रयोग करते हुए केन्द्रीय सरकार उक्त उद्योग को उक्त अधिनियम के प्रयोजनों के लिए दिनांक 18-6-2007 से छः मास की कालावधि के लिए लोक उपयोगी सेवा घोषित करती है ।
[ फा. संख्या एस-11017/ 13/ 1997 - आई आर ( पी एल ) ] गुरजोत कौर , संयुक्त सचिव
New Delhi , the 12th June , 2007
अतः अब, औद्योगिक विवाद अधिनियम , 1947 ( 1947 का 14) की धारा 2 के खण्ड ( ढ़ ) के उप - खण्ड ( vi ) के परन्तुक द्वारा प्रदत्त शक्तियों का प्रयोग करते हुए केन्द्रीय सरकार उक्त उद्योग को उक्त अधिनियम के प्रयोजनों के लिए दिनांक 15-6-2007 से छः मास की कालावधिके लिए लोक उपयोगी सेवा घोषित करती है ।
S.O. 1843.--Whereas the Central Government having been satisfied that the public interest so requires that in [फा. संख्या एस-11017/2/2003- आई आर ( पी एल ) ] गुरजोत कौर, संयुक्त सचिव [ भाग II--खंड 3 ( ii ) ]
4037
भारत का राजपत्र : जून 23, 2007/ आषाढ़ 2, 1929
Section 17 of the Employees ' Provident Funds and Miscellaneous Provisions Act, 1952 ( 19 of 1952) (hereinafter referred to as the Act).
pursuance of the provisions ofsub-clause (vi ) of the clause (n) of Section 2 of the Industiral Disputes Act , 1947 (14 of 1947 ) , declared by the Notification of the Government of India in the Ministry of Labour S.O. No. 4890 dated 28-11-2006 the service in the Iron Ore Mining Industry which is covered by item 16 of the First Schedule to the Industrial Disputes Act, 1947 ( 14 of 1947) to be a Public Utility Service for the purpose of the said Act for a period ofsix months from the 18th December, 2006 .
Andwhereas, the Central Government is of opinion that public interest requires the extension of the said period bya further period of six months .
2. And whereas in the opinion of the Central Government, the rules of the provident fund of the said establishment with respect to the rates of contribution are not less favourable to employees therein than those specified in Section 6 of the said Act and the employees are also in enjoyment of other provident fund benefits provided under the said Act or under the Employees ' Provident Funds Scheme , 1952 (hereinafter referred to as the Scheme) in relation to the employees in any other establishment of similar character.
Now, therefore , in exercise of the powers conferred by the proviso to sub -clause ( vi ) of clause (n) of Section 2 ofthe Industrial Disputes Act, 1947 , the Central Government hereby declares the said industry to be a Public Utility Service for the purposes of the said Act , for a period ofsix months from the 18th June , 2007 .
3. Now, therefore, in exercise ofthe powers conferred by clause ( a) of sub -section ( 1 ) of Section 17 of the said Act and subject to the conditions specified in this regard from time to time, the Central Government , hereby, exempts the said establishment from the operation of all the provisions of the said Scheme with effect from 1-3-1989, until further notification.
[File No. S- 11017/ 13/ 1997 - IR (PL) ] GURJOT KAUR, Jt. Secy.
नई दिल्ली , 13 जूम, 2007
[No. S- 35015/8/2007 -SS- II] S. D. XAVIER, Under Secy.
नई दिल्ली, 13 जून , 2007 का.आ. 1844.-जबकि मैसर्स योकोगावा इंडिया लिमिटेड, बेंगलूर ( कर्नाटक क्षेत्र में कोड संख्या के एन/ 13151 के तहत ) ( इसके पश्चात् प्रतिष्ठान के रूप में उल्लिखित ) ने कर्मचारी भविष्य निधि एवं प्रकीर्ण उपबंध अधिनियम, 1952 ( 1952 का 19 ) ( इसके पश्चात् अधिनियम के रूप में उल्लिखित ) की धारा 17 की उप- धारा ( 1 ) के खण्ड ( क ) के अंतर्गत छूट के लिए आवेदन किया है ।
का.आ. 1845.-जबकि मैसर्स कृषक भारती कोआपरेटिव लिमिटेड, दिल्ली ( दिल्ली क्षेत्र में कोड संख्या डी एल/ 5571 के तहत ) (इसके पश्चात् प्रतिष्ठान के रूप में उल्लिखित ) ने कर्मचारी भविष्य निधि एवं प्रकीर्ण उपबंध अधिनियम , 1952 ( 1952 का 19 ) ( इसके पश्चात् अधिनियम के रूप में उल्लिखित ) की धारा 17 की उप- धारा ( 1 ) के खण्ड ( क ) के अंतर्गत छूट के लिए आवेदन किया है । 2. और जबकि केन्द्र सरकार के विचार में अंशदान की दरों के संबंध में उक्त प्रतिष्ठान के भविष्य निधि नियम , उक्त अधिनियम की धारा 6 में विनिर्दिष्ट की तुलना में कर्मचारियों के लिए कम अनुकूल नहीं है और कर्मचारी , उक्त अधिनियम के अंतर्गत अथवा इसी प्रकार के किसी अन्य प्रतिष्ठान में कर्मचारियों के संबंध में कर्मचारी भविष्य निधि स्कीम, 1952 ( इसके पश्चात् स्कीम के रूप में उल्लिखित ) के अंतर्गत प्रदान किए जा रहे अन्य भविष्य निधि लाभों का भी फायदा उठा रहे हैं ।
2. और जबकि केन्द्र सरकार के विचार में अंशदान की दरों के संबंध में उक्त प्रतिष्ठान के भविष्य निधि नियम, उक्त अधिनियम की धारा 6 में विनिर्दिष्ट की तुलना में कर्मचारियों के लिए कम अनुकूल नहींहै और कर्मचारी, उक्त अधिनियम के अंतर्गत अथवा इसी प्रकार के किसी अन्य प्रतिष्ठान में कर्मचारियों के संबंध में कर्मचारी भविष्य निधि स्कीम, 1952 ( इसके पश्चात् स्कीम के रूप में उल्लिखित ) के अंतर्गत प्रदान किए जा रहे अन्य भविष्य निधि लाभों का भी फायदा उठा रहे हैं । 3. अतः , अब, केन्द्र सरकार उक्त अधिनियम की धारा 17 की उप- धारा ( 1 ) के खण्ड ( क ) द्वारा प्रदत्त शक्तियों का प्रयोग करते हुए, और समय - समय पर इस संबंध में उल्लिखित शर्तों के अध्यधीन केन्द्र सरकार एतद्वारा उक्त प्रतिष्ठान को 1-3-1989 से अगली अधिसूचना तक उक्त स्कीम के सभी उपबंधों के प्रचालन से छूट प्रदान करती है ।
3. अतः , अब, केन्द्र सरकार उक्त अधिनियम की धारा 17 की उप- धारा ( 1 ) के खण्ड ( क) द्वारा प्रदत्त शक्तियों का प्रयोग करते हुए, और समय - समय पर इस संबंध में उल्लिखित शर्तों के अध्यधीन केन्द्र सरकार एतद्द्वारा उक्त प्रतिष्ठान को 1-3-1983 से अगली अधिसूचना तक उक्त स्कीम के सभी उपबंधों के प्रचालन से छूट प्रदान करती है । [संख्या एस-35015/8/2007 - एस.एस.- II ] एस. डी. जेवियर, अवर सचिव
New Delhi , the 13th June , 2007
[संख्या एस-35015/ 14/2007- एस.एस.- II ] एस. डी. जेवियर, अवर सचिव
New Delhi , the 13th June, 2007
S.O. 1845. Whereas M/ s . Krishak Bharati Cooperative Limited, Delhi [ under Code No. DL/5571 in S.O. 1844. Whereas M/ s. Yokogawa India Ltd. , Bangalore (under Code No. KN/ 13151 in Karnataka region) (hereinafter referred to as the establishment ) has applied for exemption under clause (a) of sub - section (1 ) of [PART II- SEC. 3 (ii ) ] THE GAZETTE OF INDIA : JUNE 23 , 2007 /ASADHA 2 , 1929
4038
Provident Funds Scheme, 1952 ( hereinafter referred to as the Scheme) in relation to the employees in any other establishment of similar character.
Delhi ( S) region) ( hereinafter referred to as the establishment) has applied for exemption under clause ( a ) ofsub -section ( 1 ) of section 17 of the Employees ' Provident Funds andMiscellaneous Provisions Act, 1952 (19 of 1952) (hereinafter referred to as the Act) .
3. Now, therefore, in exercise of the powers conferred by clause (a) of sub- section ( 1 ) of section 17 of the said Act and subject to the conditions specified in this regard from time to time, the Central Government, hereby, exempts the said establishment from the operation of all the provisions of the said Scheme with effect from 1-3-1983 , until further notification.
[No. S-35015/14/2007 - SS- II ] S. D. XAVIER, Under Secy.
2. And whereas in the opinion of the Central Government, the rules of the provident fund of the said establishment with respect to the rates of contribution are not less favourable to employees therein than those specified in section 6 of the said Act and the employees are also in enjoyment of other provident fund benefits provided under the said Act or under the Employees '
Printed by the Manager, Govt . of India Press , Ring Road, Maya Puri , New Delhi - 110064 and Published by the Controller of Publications , Delhi - 110054, 2007