Servants of Knowledge
Himachal Pradesh Gazette · Government of Himachal Pradesh

Himachal Pradesh Gazette, No. 225, 16 January 2023

Published 16 January 2023

Gazette no.
225
Gazetteid
225/GAZETTE/2023-16/01/2023
Identifier
in.gazette.himachal.2023-01-16.225_gazette_2023-16_01_2023
Languages
English, Hindi
Published at
Original source ↗

click here for IIIF manifest

राजपत्र, हिमाचल प्रदेश हिमाचल प्रदेश राज्य शासन द्वारा प्रकाशित सोमवार, 16 जनवरी, 2023/26 पौष, 1944

हिमाचल प्रदेश सरकार

HIMACHAL PRADESH ELECTRICITY REGULATORY COMMISSION, SHIMLA

NOTIFICATION

Shimla, the 9th January, 2023

No. HPERC/H(1)-39.—WHEREAS the provision of Section 30 of Electricity Act, 2003 provides that the State Commission shall facilitate and promote transmission, wheeling and inter- 225—राजपत्र/2023-16-01-2023 (9313)9314 राजपत्र, हिमाचल प्रदेश, 16 जनवरी, 2023/26 पौष, 1944 connection arrangements within its territorial jurisdiction for the transmission and supply of electricity by economical and efficient utilization of the electricity;

AND WHEREAS the provision of Section 40 (a) of Electricity Act, 2003 provides that it shall be the duty of a transmission licensee to build, maintain and operate an efficient, co-ordinated and economical intra-State transmission system, as the case may be;

AND WHEREAS the National Electricity Policy has also specified the some performance parameters like frequency & duration of interruptions, voltage parameters, harmonics, transformer failure rate, faulty lines etc. Further policy empowers the Commission to specify the Standard of Performances in order to regulate utilities based on pre-determined indices on quality of power supply ;

AND WHEREAS to operate Intra-State Transmission System for providing an efficient, reliable, co-ordinated and economical system of electricity supply and transmission and to maintain critical grid parameters within the permissible limits, by the Transmission Licensee, the Transmission Performance Standards needs to be fixed;

AND WHEREAS the provisions of Section 57, Section 58 and Section 59 of the Electricity Act, 2003 provides that –

"Section 57. (Consumer Protection: Standards of performance of licensee):

(1) The Appropriate Commission may, after consultation with the licensees and persons

likely to be affected, specify standards of performance of a licensee or a class of

licensees.

(2) If a licensee fails to meet the standards specified under sub-section (1), without

prejudice to any penalty which may be imposed or prosecution be; initiated, he shall

be liable to pay such compensation to the person affected as may be determined by the

Appropriate Commission:

Provided that before determination of compensation, the concerned licensee shall be

given a reasonable opportunity of being heard.

(3) The compensation determined under sub-section (2) shall be paid by the concerned

licensee within ninety days of such determination.

Section 58. (Different standards of performance by licensee): The Appropriate

Commission may specify different standards under Sub-Section (1) of Section 57 for a

class or classes of licensee.

Section 59. (Information with respect to levels of performance):

(1) Every licensee shall, within the period specified by the Appropriate Commission,

furnish to the Commission the following information, namely:—

(a) the level of performance achieved under sub-section (1) of the Section 57;

(b) the number of cases in which compensation was made under sub-section (2) of

section 57 and the aggregate amount of the compensation.

9315 राजपत्र, हिमाचल प्रदेश, 16 जनवरी, 2023/26 पौष, 1944

(2) The Appropriate Commission shall atleast once in every year arrange for the

publication, in such form and manner as it considers appropriate, of such of the

information furnished to it under sub-section (1)."; and

NOW, THEREFORE, in exercise of the powers conferred by sub-section (1) of Section 181 and Clauses (za) and (zb) of Sub-Section (2) of Section 181, read with Sections 30, 57, 58, 59 and clause (i) of sub-section (1) of section 86 of the Electricity Act, 2003 (36 of 2003), rule 3 of the Electricity (Procedure for Previous Publication) Rules, 2005 and all other powers enabling it in this behalf, and after previous publication, the Himachal Pradesh Electricity Regulatory Commission hereby makes the draft Himachal Pradesh Electricity Regulatory Commission (Transmission Performance Standards) Regulations, 2023 which are hereby published for the information of all the persons likely to be affected thereby and notice is hereby given that the said draft Regulations will be taken into consideration after the expiry of thirty (30) days from the date of publication of this notification in the Rajpatra, Himachal Pradesh, together with any objections or suggestions which may, within the aforesaid period, be received in respect thereto. The text of the aforesaid draft amendment Regulations alongwith explanatory memorandum is available on the website of the Commission i.e. http.//www.hperc.org.

The objections and suggestions in this behalf should be addressed to the Secretary, Himachal Pradesh Electricity Regulatory Commission, Vidyut Aayog Bhawan, Block No. 37, SDA Complex, Kasumpti, Shimla-171 009.

DRAFT REGULATIONS

CHAPTER-I

GENERAL

1. Short title and commencement.—(1) These Regulations may be called the Himachal Pradesh Electricity Regulatory Commission (Transmission Performance Standards) Regulations, 2023.

(2) These Regulations shall be applicable to all licensees engaged in the Transmission of electricity in the State of Himachal Pradesh.

(3) These Regulations shall come into force from the date of their publication in the Rajpatra, Himachal Pradesh.

2. Definitions.—(1) In these Regulations, unless the context otherwise requires—

(a) "Act" means the Electricity Act, 2003 (36 of 2003), including amendments thereto;

(b) "Affected Person" means a user of Intra State Transmission System, who is affected due to non-adherence to the Standards of Performance specified in these Regulations by the transmission licensee;

(c) "Availability" means time in hours, the transmission system is capable to transmit electricity at its rated voltage from the supply point to the delivery point and shall be expressed in percentage (%) of total hours in a given period;

(d) "Delivery Point or Interconnection point" means the physical touch point where the electric power is supplied / received by the user to/from the State transmission system;

9316 राजपत्र, हिमाचल प्रदेश, 16 जनवरी, 2023/26 पौष, 1944

(e) "Extra High Voltage (EHV)" or "Extra High Tension (EHT)" means the voltage, which exceeds 33,000 volts; under normal conditions subject, however, to the percentage variation allowed under electricity rules;

(f) "Force Majeure Event" means, with respect to any party, any event or circumstance, which is not within the reasonable control of, or due to an act or omission of, that party and which, by the exercise of reasonable care and diligence, that party is not able to prevent, including, without limiting the generality of the foregoing:—

(i) acts of God, including but not limited to lightning, storm, earthquakes, flood, drought and natural disaster;

(ii) strikes, lockouts, go-slow, bandh or other industrial disturbances;

(iii) acts of public enemy, wars (declared or undeclared), blockades, insurrections, riots, revolution, sabotage, vandalism and civil disturbance;

(iv) unavoidable accident, including but not limited to fire, explosion, radioactive contamination and toxic chemical contamination;

(v) any shutdown or interruption of the grid, which is required or directed by the State or Central Government or by the Commission or the State Load Despatch Centre;

(g) "Grid Code" means the State Grid Code specified by the Commission under clause (h) of sub-section (1) of Section 86 of the Act;

(h) "Intra-State Transmission System (IaSTS)" means State Transmission System which includes the entire transmission network within the State excluding the Inter-State Transmission System;

(i) "State Transmission Utility (STU)" means the Board or the Government Company specified as such by the State Government under sub-section (1) of Section 39 of the Act;

(j) "System Average Interruption Duration Index (SAIDI)" means the average duration of sustained interruptions at time occurring during the reporting period for a voltage class, determined by dividing the number of EHV sub-stations in service during the reporting period having that class of voltage supply;

(k) "System Average Interruption Frequency Index (SAIFI)" means the average frequency of sustained interruptions at time occurring during the reporting period for a voltage class, determined by dividing the number of EHV sub-stations in service during the reporting period having that class of voltage supply;

(l) "State Transmission System" means the system of EHV network and electrical equipments operated and/or maintained by the Transmission Licensee for the purpose of the transmission of electricity among generating stations, external interconnections, distribution systems and any other user connected to it;

9317 राजपत्र, हिमाचल प्रदेश, 16 जनवरी, 2023/26 पौष, 1944

(m) "Transmission Licensee" means a licensee authorized under section 14 of the Act to establish or operate transmission lines. At present "Himachal Pradesh Power Transmission Corporation Limited (HPPTCL)" is transmission licensee in the State;

(n) "User" means any person who uses any segment/ element of the Intra-State Transmission System including Generating Station located in the State, Independent Power Producer(s), Renewable Energy Power Plant, Distribution Licensee, Deemed Licensee, Open Access customer interconnected to State Transmission System and entered into Transmission Service Agreement with Transmission Licensee; and

(o) "Year" means financial year.

(2) The words and expressions used in these Regulations and not defined herein, but defined in the Act or any other Regulations of the Commission, shall have the meaning assigned to them under the Act or any other Regulation of the Commission.

CHAPTER-II

OBJECTIVE, NORMS AND METHODOLOGY

3. Objective.—(1) These standards of performance shall serve as guidelines for transmission licensee to operate its State Transmission System for providing an efficient, reliable, coordinated and economical system of electricity supply and transmission.

(2) These standards set the levels of operational security and quality of supply, which licensee shall be obliged to maintain in making power available for the purposes of supply / receipt to/from user. The objectives of the performance standards are—

(i) to ensure that the Grid Performance meets a minimum standard, which is essential for the User's system demand and the equipment function properly;

(ii) to enable the Users to design their systems and equipment to suit the electrical environment that they operate in;

(iii) to ensure compliance of Standards of Performance by transmission licensees; and (iv) to monitor operational performance of transmission licensee.

4. Performance Standards.—All transmission licensees shall comply with the following Standards of performance specified in these Regulations:—

(I) Transmission System Availability

(II) Reliability Indices

(III) Restoration Time:

Provided that standards of performance as specified in these Regulations shall be minimum standards that transmission licensee shall achieve and maintain:

Provided further that any time limits set out in these Regulations shall refer to maximum time permitted for performing activities to which they relate to:

9318 राजपत्र, हिमाचल प्रदेश, 16 जनवरी, 2023/26 पौष, 1944

Provided further that transmission licensee shall also comply with "Standards for Operation and Maintenance of Transmission Lines" as specified in Central Electricity Authority (Grid Standards) Regulations, 2010 as amended from time to time.

(I) Transmission System Availability.—The Transmission System Availability of a transmission element/ system for a given period is the time during which transmission system is capable of transmitting electricity at its rated overage to the delivery point. The norms of Availability of Transmission System for recovery of Annual Transmission Charges and Incentive shall be as specified in Transmission Service Agreement or HPERC (Terms and Conditions for Determination of Transmission Tariff) Regulations, 2011, as amended from time to time.

(II) Reliability Indices.— (a) System Average Interruption Frequency Index

(SAIFI)—

System Average Interruption Frequency Index (SAIFI) SAIFI = Σ I / N Where, Σ I = Sum number of interruptions exceeding 5 minutes at a time duration in the month for the voltage class.

N = Number of EHV sub-stations in service at the beginning of month having that class of voltage supply.

(b) System Average Interruption Duration Index (SAIDI)—

SAIDI = Σ D/ N Where, Σ D = Sum of duration all interruptions of exceeding 5 minutes at a time in the month for the voltage class.

N = Number of EHV sub stations in service at the beginning of month having that class of voltage supply :

Provided that all interruptions of duration exceeding 5 (five) minute at a time shall be considered for computation of indices:

Provided further that interruptions due to scheduled outage (including three shift operation of agriculture pump sets), load shedding to meet capacity shortage, failure of inter-state transmission system or failure of generating units (leading to grid failure or system islanding) shall be excluded.

(c) SAIFI and SAIDI for the transmission system shall be calculated on monthly basis for each voltage class as per item (a) and (b) above and the same shall not be exceeded to the values as given in the Table-1 below:—

Table-1

SAIFI SAIDI
2 interruptions per month 30 minutes per month

(d) The detail of SAIFI and SAIDI shall be submitted to the Commission as per Regulation 7 of these Regulations.

(III) Restoration Time-9319 राजपत्र, हिमाचल प्रदेश, 16 जनवरी, 2023/26 पौष, 1944 Restoration time for different types of failures of transmission line, power transformers and reactors shall be as per the following Table :—

Table-2

Sl. No. Type of Failures Restoration Time from the date of occurrence of failure (Days)
1. Insulator failure
Plain Terrain 1
Hilly Terrain 2
2. Tower after collapse by Emergency Restoration System (ERS) 12
3. Tower after collapse
Plain Terrain 30
River Bed 50
Hilly Terrain 50
4. Phase conductor broken
Plain Terrain 2
Hilly Terrain 3
5. Failure of earth wire
Plain Terrain 2
Hilly Terrain 3
6. Restoration of Failure of Power Transformer/Inter Connecting Transformer (Single/three Phase). 120
7. Restoration of the failed reactor 120

Note.—Hilly terrain shall be as per notification issued by Central/State government from time to time.

5. Payment of Compensation.—Any failure by the transmission licensee to maintain the standards of performance for restoration time of various elements as specified in Table-2 of clause (III) of Regulation 4 shall render the concerned licensee liable for payment of compensation as per Regulation 6 of these Regulations to an affected person claiming such compensation:

Provided that any failure by the transmission licensee to maintain the standards of performance as provided in Clause (I) and Clause (II) of Regulation 4, the penalties for such failure shall be imposed as provided in the HPERC (Terms and Conditions for Determination of Transmission Tariff) Regulations, 2011 as amended from time to time:

Provided further that the payment of compensation by the transmission licensee shall be without prejudice to any penalty, which may be imposed or any prosecution which may be initiated by the Commission in accordance with the provisions of the Act.

6. Methodology for Compensation.—(1) An affected person, within ninety (90) days from the date of restoration of transmission element for the standards as specified in Table-2 of clause (III) of Regulation 4, may make an appropriate Petition to the Commission for award of compensation alongwith necessary documentary evidences of being affected because of non- adherence of Standards of Performance.

(2) The Commission shall determine the compensation after giving reasonable opportunity to the concerned transmission licensee of being heard:

9320 राजपत्र, हिमाचल प्रदेश, 16 जनवरी, 2023/26 पौष, 1944

Provided that the compensation to be paid by the transmission licensee to the affected party shall be 1.5 times of the applicable transmission charges for the affected person during such period of non-adherence of Standards of Performance or as awarded by the Commission through its order.

CHAPTER-III

INFORMATION TO BE FURNISHED BY TRANSMISSION LICENSEES 7. Information to be furnished by Transmission Licensees.—(1) All transmission licensees, shall furnish the following to the Commission—

(i) the level of performance achieved regarding element wise system availability, total availability of transmission system, SAIFI and SAIDI, provided in Clause (I) and Clause (II) of Regulation 4 of these Regulations, alongwith its business plans to be submitted in accordance with Regulation 37 of HPERC (Terms and Conditions for Determination of Transmission Tariff) Regulations, 2011, as amended from time to time;

(ii) month wise details of element where restoration time has exceeded the standards as specified in Clause (III) of Regulation 4;

(iii) month wise details of compensation paid by the transmission licensee under Regulation 5 of these Regulations; and

(iv) any other information as required by the Commission.

(2) The month wise information provided in sub-regulation (1) of this Regulation, shall be submitted to the Commission in the requisite formats twice during the year, on six monthly basis, i.e. by 31st October and 30th April for the periods April to September and October to March respectively:

Provided that such information also be displayed by the Commission on its website.

(3) All transmission licensees shall display on their websites the actual performance against the specified Standards of Performance on a monthly basis and the aggregate amount of compensation paid, if any, in the formats enclosed in the Schedule.

8. Annual Review of Performance Standards.—The Commission, by an Order, may designate a nodel agency or a Committee to review the performance of each transmission licensee every year and submit its recommendations, if any, to the Commission.

9. Force Majeure.—The Commission may, if it considers necessary or expedient to do so and for the reasons to be recorded in writing, relax adherence to any specific Standard of Performance during Force Majeure event:

Provided that the transmission licensee shall not be discharged from its liability on account of its failure to maintain the Standards of Performance under these Regulations, if such failure can be attributed to the negligence or deficiency or lack of preventive maintenance of the State transmission system or failure to take reasonable precaution which has resulted in loss to the affected person.

9321 राजपत्र, हिमाचल प्रदेश, 16 जनवरी, 2023/26 पौष, 1944 CHAPTER-IV

MISCELLANEOUS

10. Power to remove difficulties.—If any difficulty arises in giving effect to any of the provisions of these Regulations, the Commission may, either suo-motu or on an application made to it, by general or special order, do or undertake or direct the licensee to do or undertake things, which in the opinion of the Commission are necessary or expedient for the purpose of removing the difficulty.

11. Power to amend Schedule.—The Commission, may, at any time, by an order, published in the Official Gazette add, vary, alter, modify or amend any of the provisions of the Schedule to these Regulations.

12. Power to Relax.—The Commission may, by general or special order, for reasons to be recorded in writing, and after giving an opportunity of being heard to the parties likely to be affected by grant of relaxation, may relax any of the provisions of these Regulations on its own motion or on an application made before it by an interested person.

13. Overriding effect.—The provisions of these Regulations shall have overriding effect notwithstanding anything inconsistent therewith contained in any other Regulations of the Commission, for the time being in force or in any instrument/detailed procedure having effect by virtue of any such Regulations.

By Orders of the Commission,

Sd/-

Secretary.

__________

SCHEDULE-A

Information to be furnished by Transmission Licensee to the Commission

(I) Outage Details of AC Transmission Line/Power Transformers/Static VAr Compensator/ Series Compensator/Line Rectors/ Bus Reactors for the month of……………………......

Month-wise Element-wise Transmission System Availability

See Regulation 4(I)

Element Name Outage Restoration Reason of Outage Duration of Outage Attributable to % Availabilit y
Date Time Date Time Transmission Licensee Others Force Majeure Conditions Deemed Available
Hrs: Min Hrs: Min Hrs: Min Hrs: Min
9322 राजपत्र, हिमाचल प्रदेश, 16 जनवरी, 2023/26 पौष, 1944

(II) Yearly Availability of the AC Transmission System

Name of Element Year % Availability

(III) SAIFI and SAIDI of the Transmission System

See Regulation 4(II)

Month SAIFI (in Numbers) SAIDI (in mins)

(IV) The restoration times for different types of failures of a transmission line and failure of power transformer and reactor in the following format:

See Regulation 4(III)

Sl. No. Types of failures Restoration time Actual restoration time (in days)
Table Ref. No. Specified time (in days)
1. Insulator failure
2. Tower after collapse by Emergency Restoration System (ERS)
3. Tower after collapse without emergency Restoration System
4. Snapping of Phase conductor
5. Failure of earth wire
6. Failure of Power Transformer/Inter Connecting Transformer
Restoration of failed Power Transformer/Inter Connecting Transformer (Single/Three Phase Unit)
7. Failure of Reactors (Single/Three Phase Unit)
Restoration of the failed reactor

(V) Details of Elements where restoration time has exceeded the standards specified in Regulation 4(III).

Element Name Restoration time as specified in Regulation 4(III) (in days) Actual restoration time (in days)
Element Name Violation of Regulation 4(I) and 4(II) Violation of Regulation 4(III) Compensation Paid (in Rs.)
% Availability Prescribed Actual % Availability Restoration time as per Regulation (in days) Actual restoration time (in days)
Total. .
9323 राजपत्र, हिमाचल प्रदेश, 16 जनवरी, 2023/26 पौष, 1944 (VI) Details of compensation paid by the transmission licensee under Regulation 5:

___________

TRANSPORT DEPARTMENT

NOTIFICATION

Shimla-02, the 11th January, 2023

No. TPT-C (9)-1/2022.—The Governor, Himachal Pradesh in exercise of the powers conferred by sub-section 14 (3) of the Himachal Pradesh Motor Vehicle Taxation Act, 1972 (Act No 4 of 1973) and all other powers enabling him in this behalf is pleased to exempt the vehicle No. HP 02 K-1221 which is registered in the name of Smt. Prem Lata w/o Gyan Chand Shishamati, P.O. Dhalpur, Teh. & Distt. Kullu, Himachal Pradesh from the payment of Special Road Tax w.e.f. 01-01-2016 to till date in the public interest.

By order,

R.D. NAZEEM,

Principal Secretary (Transport).

__________

TRANSPORT DEPARTMENT

NOTIFICATION

Shimla-02, the 12th January, 2023

No. TPT-C (9)-1/2022.—In supersession to this department notification of even number dated 11-01-2023, the Governor, Himachal Pradesh in exercise of the powers conferred by sub- section 14 (3) of the Himachal Pradesh Motor Vehicle Taxation Act, 1972 (Act No 4 of 1973) and all other powers enabling him in this behalf is pleased to exempt the vehicle No. HP 62-0340 and HP 62-0440 which is registered in the name of Sh. Rattan Chand Birbal Kumar s/o Late Sh.

9324 राजपत्र, हिमाचल प्रदेश, 16 जनवरी, 2023/26 पौष, 1944

Mansukh Dass, r/o V.P.O. Rarang, Tehsil Moorang, Distt. Kinnaur, Himachal Pradesh from the payment of Special Road Tax/Token Tax w.e.f. 01-12-2021 to 06-06-2022 in the public interest.

By order,

R.D. NAZEEM,

Principal Secretary (Transport).

__________

ब अदालत सहायक समाहर्ता प्रथम श्रेणी, पांवटा साहिब, जिला सिरमौर (हि0 प्र0)

श्री सीता राम पुत्र गंगा राम, निवासी गांव गोरखूवाला, तहसील पांवटा साहिब, जिला सिरमौर (हि0 प्र0) . . वादी।

बनाम

आम जनता

.

उनवान मुकद्दमा.--प्रार्थना-पत्र जेर धारा 13(3) जन्म एवं मृत्यु पंजीकरण अधिनियम, 1969.

श्री सीता राम पुत्र गंगा राम, निवासी गांव गोरखूवाला, तहसील पांवटा साहिब, जिला सिरमौर (हि0 प्र0) ने एक प्रार्थना-पत्र प्रस्तुत करके निवेदन किया है कि आवेदक किन्हीं कारणों से अपनी पति की मृत्यु तिथि 24-04-2021 का इन्द्राज निर्धारित अवधि के अन्दर सम्बन्धित ग्राम पंचायत में दर्ज नहीं करवा पाया है। इस बारे आवेदक द्वारा एक ब्यान हल्फी भी पेश किया गया है तथा इस सम्बन्ध में दो गवाहों के शपथ-पत्र भी आवेदक ने अपने प्रार्थना-पत्र के साथ संलग्न किये हैं। आवेदक ने ग्राम पंचायत गोरखूवाला में मृत्यु तिथि 24-04-2021 को दर्ज करने का अनुरोध किया है।

अतः इस इश्तहार द्वारा आम जनता को सूचित किया जाता है कि यदि किसी भी व्यक्ति को श्रीमती सरवती पत्नी सीता राम की मृत्यु तिथि ग्राम पंचायत गोरखूवाला, तहसील पांवटा साहिब में दर्ज करने बारे कोई एतराज हो तो वह मिति 17-01-2023 को या इससे पूर्व हमारे न्यायालय में हाजिर होकर लिखित अथवा मौखिक एतराज पेश कर सकता है। उक्त निश्चित तिथि के बाद कोई भी एतराज मान्य नहीं होगा और समझा जायेगा कि उक्त श्रीमती सरवती की मृत्यु तिथि को सम्बन्धित ग्राम पंचायत गोरखूवाला में दर्ज करने बारे किसी को कोई एतराज नहीं है तथा नियमानुसार मृत्यु तिथि पंजीकरण के आदेश जारी कर दिये जायेंगे। आज दिनांक 17-12-2022 को हमारे हस्ताक्षर व मोहर से जारी हुआ।

मोहर।

हस्ताक्षरित/- कार्यकारी दण्डाधिकारी, पांवटा साहिब, जिला सिरमौर (हि0 प्र0)।

----------

समक्ष श्री राजेन्दर ठाकुर, कार्यकारी दण्डाधिकारी, तहसील ददाहू, जिला सिरमौर, हिमाचल प्रदेश

ब मुकद्दमा परीक्षा देवी पत्नी कपिल देव, निवासी कान्डो हरयास, तहसील ददाहू, जिला सिरमौर (हि0 प्र0)।

बनाम9325 राजपत्र, हिमाचल प्रदेश, 16 जनवरी, 2023/26 पौष, 1944 आम जनता

आवेदन-पत्र जेर धारा 13(3) जन्म एवं मृत्यु रजिस्ट्रीकरण अधिनियम, 1969.

मुकद्दमा जिला सिरमौर, तहसील ददाहू, जिला सिरमौर ने इस अदालत में एक दरख्वास्त गुजारी है कि प्रार्थिया अपने बेटे का नाम आदित्य व जन्म तिथि 14-01-2020 को दर्ज करवाना चाहती है। जिसका रिकार्ड ग्राम पंचायत भाटगड़ में दर्ज नहीं किया है। जिसकी पुष्टि हेतु प्रार्थिया ने आवेदन-पत्र मय हल्फीब्यान, प्रपत्र 10, आधार कार्ड तथा जिला रजिस्ट्रार (जन्म एवम्‌ मृत्यु) एवम्‌ मुख्य चिकित्सा अधिकारी नाहन, जिला सिरमौर की संस्तुति प्रस्तुत की है। प्रार्थिया अपने बेटे का नाम आदित्य व जन्म तिथि 14-01-2020 को ग्राम पंचायत भाटगड़ के मूल रिकॉर्ड में दर्ज करवाना चाहती है।

अतः इस नोटिस द्वारा समस्त जनता ग्राम भाटगड़ व प्रार्थिया के समस्त रिश्तेदारों को सूचित किया जाता है कि यदि किसी को उक्त प्रार्थिया के बेटे का नाम आदित्य व जन्म तिथि 14-01-2020 को ग्राम पंचायत भाटगड़ के रिकॉर्ड में दर्ज करने बारे उजर व एतराज हो तो वह दिनांक 20-01-2023 को असालतन व वकालतन हाजिर होकर अपना एतराज पेश कर सकता/सकती है। उसके उपरांत कोई उजर व एतराज नहीं सुना जाएगा और नियमानुसार प्रार्थना-पत्र का निपटारा कर दिया जाएगा।

आज दिनांक 05-01-2023 को मेरे हस्ताक्षर व कार्यालय की मोहर द्वारा जारी किया गया। मोहर।

हस्ताक्षरित/- (राजेन्दर ठाकुर),

कार्यकारी दण्डाधिकारी,

तहसील ददाहू, जिला सिरमौर (हि0प्र0)।

--------

समक्ष श्री राजेन्दर ठाकुर, कार्यकारी दण्डाधिकारी, तहसील ददाहू, जिला सिरमौर, हिमाचल प्रदेश

ब मुकद्दमा श्री चमन लाल पुत्र श्री लछी राम, निवासी कशेलग माशगा, तहसील ददाहू, जिला सिरमौर (हि0 प्र0)।

बनाम

आम जनता

आवेदन-पत्र जेर धारा 13(3) जन्म एवं मृत्यु रजिस्ट्रीकरण अधिनियम, 1969.

मुकद्दमा जिला सिरमौर, तहसील ददाहू, जिला सिरमौर ने इस अदालत में एक दरख्वास्त गुजारी है, प्रार्थी अपने बेटे का नाम नैतिक व जन्म तिथि 05-12-2015 को दर्ज करवाना चाहता है। जिसका रिकार्ड ग्राम पंचायत कमलाड़ में दर्ज नहीं किया है। जिसकी पुष्टि हेतु प्रार्थी ने आवेदन-पत्र मय हल्फीब्यान, प्रपत्र 10, आधार कार्ड तथा जिला रजिस्ट्रार (जन्म एवम्‌ मृत्यु) एवम्‌ मुख्य चिकित्सा अधिकारी नाहन, जिला सिरमौर की संस्तुति प्रस्तुत की है। प्रार्थी अपने बेटे का नाम नैतिक व जन्म तिथि 05-12-2015 को ग्राम पंचायत कमलाड़ के मूल रिकॉर्ड में दर्ज करवाना चाहता है।

अतः इस नोटिस द्वारा समस्त जनता ग्राम कमलाड़ व प्रार्थी के समस्त रिश्तेदारों को सूचित किया जाता है कि यदि किसी को उक्त प्रार्थी के बेटे का नाम नैतिक व जन्म तिथि 05-12-2015 को ग्राम पंचायत कमलाड़ के रिकॉर्ड में दर्ज करने बारे उजर व एतराज हो तो वह दिनांक 20-01-2023 को असालतन व 9326 राजपत्र, हिमाचल प्रदेश, 16 जनवरी, 2023/26 पौष, 1944 वकालतन हाजिर होकर अपना एतराज पेश कर सकता/सकती है। उसके उपरांत कोई उजर व एतराज नहीं सुना जाएगा और नियमानुसार प्रार्थना-पत्र का निपटारा कर दिया जाएगा।

आज दिनांक 05-01-2023 को मेरे हस्ताक्षर व कार्यालय की मोहर द्वारा जारी किया गया। मोहर।

हस्ताक्षरित/- (राजेन्दर ठाकुर),

कार्यकारी दण्डाधिकारी,

तहसील ददाहू, जिला सिरमौर (हि0प्र0)।

--------

CHANGE OF NAME

I, Priti Thakur w/o Sh. Kshitij Thakur, r/o Lofwer Bhiuli, Tehsil Sadar, District Mandi (H.P.) declares that I have change my name from Priti Devi to Priti Thakur for all purposes in future. Concerned please note.

PRITI THAKUR

w/o Sh. Kshitij Thakur,

r/o Lower Bhiuli, Tehsil Sadar,

District Mandi (H.P.).

नियन्त्रक, मुद्रण तथा लेखन सामग्री, हिमाचल प्रदेश, शिमला-5 द्वारा मुद्रित तथा प्रकाशित इलेक्ट्रॉनिक हस्ताक्षरित राजपत्र, वैबसाइट http://rajpatrahimachal.nic.in पर उपलब्ध है एवम्‌ ऑनलाइन सत्यापित किया जा सकता है।

Cite this issue. Himachal Pradesh Gazette, Government of Himachal Pradesh, 16 January 2023. Indian Gazettes, https://egazette.servantsofknowledge.in/details/in.gazette.himachal.2023-01-16.225_gazette_2023-16_01_2023/. Archive identifier in.gazette.himachal.2023-01-16.225_gazette_2023-16_01_2023.