के न्द्र-शासित प्रदेश लद्दाख प्रशासन ADMINISTRATION OF UNION TERRITORY OF LADAKH
GENERAL ADMINISTRATION DEPARTMENT
F. No.: M / 1004 / 2022 - GAD SEC
N O T I F I C A T I O N
Leh, 21st November, 2025
S.O. No. 137, — In exercise of the powers conferred by section 4 read with section 8 of the Jammu and Kashmir Public Services Guarantee Act, 2011 (Act No. IX of 2011) (hereinafter referred to as the 'said Act'), in its application to the Union territory of Ladakh; the Administration of Union territory of Ladakh, hereby notifies the following public services, timelines and the designated officers / appellate authorities for the purposes of the said Act, in respect of the Departments specified in the table below, namely:—
LADAKH GAZETTE : EXTRAORDINARY 2| S. No. | Name of the public service | Timeline | Designated Officer | First Appellate Authority | Second Appellate Authority | NaN | |
| Public Health Engineering (PHE) / Irrigation & Flood Control (I&FC) Department | NaN | ||||||
| 1. | Sanction for Commercial water connection. | 03 working days | Chief Engineer, PHE / I&FC | Deputy Commissioner concerned | Administrative Secretary, PHE / I&FC Department | NaN | |
| 2. | Actual Commercial water connection supply. | 07 working days | Chief Engineer, PHE / I&FC | Deputy Commissioner concerned | Administrative Secretary, PHE / I&FC Department | NaN | |
| Power Development Department (PDD) | NaN | ||||||
| 1. Timeline for Load Sanction / Additional Load | NaN | ||||||
| (a) | Aggregate Loads upto 25 kVA | 03 days of receipt of Application | Assistant Executive Engineer | Executive Engineer | Superintending Engineer | NaN | |
| (b) | Aggregate Loads above 25 kVA & upto 50 kVA | 03 days of receipt of Application | Executive Engineer | Superintending Engineer | Chief Engineer | NaN | |
| (c) | Aggregate Loads above 50 kVA & upto 100 kVA | 03 days of receipt of Application | Superintending Engineer | Chief Engineer | Administrative Secretary, PDD | NaN | |
| (d) | Aggregate Loads above 100 kVA & upto 500kVA | 03 days of receipt of Application | Chief Engineer | Administrative Secretary, PDD | Designated Committee as notified by the PDD | NaN | |
| (e) | Aggregate Loads above 500 kVA & upto 1000 kVA | 03 days of receipt of Application | Administrative Secretary, PDD | Designated Committee as notified by the PDD | NaN | ||
| (f) | Aggregate Loads above 1000 kVA | 03 days of receipt of Application | Designated Committee as notified by the PDD | NaN | |||
| 2. Timeline for Conversion of Services | NaN | ||||||
| (a) Low Tension (LT) Single Phase to LT Three Phase (or vice versa) | NaN | ||||||
| Urban Area | Within 10 working days | Assistant Executive Engineer (Electrical) | Executive Engineer (Electrical) | Superintending Engineer | NaN | ||
| Rural Area | Within 20 working days | Assistant Executive Engineer (Electrical) | Executive Engineer (Electrical) | Superintending Engineer | NaN | ||
| Remote Area | Within 30 working days | Assistant Executive Engineer (Electrical) | Executive Engineer (Electrical) | Superintending Engineer | NaN | ||
| (b) LT to High Tension (HT) (or vice versa) | NaN | ||||||
| Urban Area | Within 10 working days | Assistant Executive Engineer (Electrical) | Executive Engineer (Electrical) | Superintending Engineer | NaN | ||
| Rural Area | Within 20 working days | Assistant Executive Engineer (Electrical) | Executive Engineer (Electrical) | Superintending Engineer | NaN | ||
| Remote Area | Within 30 working days | Assistant Executive Engineer (Electrical) | Executive Engineer (Electrical) | Superintending Engineer | NaN | ||
| (c) HT to Extra High Tension (EHT) (or vice versa) | NaN | ||||||
| Urban Area | Within 10 working days | Executive Engineer (Electrical) | Superintending Engineer | Chief Engineer | NaN | ||
| Rural Area | Within 20 working days | Executive Engineer (Electrical) | Superintending Engineer | Chief Engineer | NaN | ||
| Remote Area | Within 30 working days | Executive Engineer (Electrical) | Superintending Engineer | Chief Engineer | NaN | ||
| 3. Timeline for release of Temporary Connection | NaN | ||||||
| (a) Where supply can be provided from existing network | NaN | ||||||
| Urban Area | Within 03 working days | Assistant Executive Engineer (Electrical) | Executive Engineer (Electrical) | Superintending Engineer | NaN | ||
| Rural Area | Within 05 working days | Assistant Executive Engineer (Electrical) | Executive Engineer (Electrical) | Superintending Engineer | NaN |
| Remote Area | Within 07 working days | Assistant Executive Engineer (Electrical) | Executive Engineer (Electrical) | Superintending Engineer | |
| (b) Where supply can be provided after extension / augmentation of network | |||||
| (i) Low Tension (LT) | |||||
| Urban Area | Within 15 working days | Assistant Executive Engineer (Electrical) | Executive Engineer (Electrical) | Superintending Engineer | |
| Rural Area | Within 20 working days | Assistant Executive Engineer (Electrical) | Executive Engineer (Electrical) | Superintending Engineer | |
| Remote Area | Within 30 working days | Assistant Executive Engineer (Electrical) | Executive Engineer (Electrical) | Superintending Engineer | |
| (ii) High Tension (HT) | |||||
| Urban Area | Within 15 working days | Assistant Executive Engineer (Electrical) | Executive Engineer (Electrical) | Superintending Engineer | |
| Rural Area | Within 25 working days | Assistant Executive Engineer (Electrical) | Executive Engineer (Electrical) | Superintending Engineer | |
| Remote Area | Within 30 working days | Assistant Executive Engineer (Electrical) | Executive Engineer (Electrical) | Superintending Engineer | |
| (iii) Extra High Tension (EHT) | |||||
| Urban Area | Within 15 working days | Executive Engineer (Electrical) | Superintending Engineer | Chief Engineer | |
| Rural Area | Within 25 working days | Executive Engineer (Electrical) | Superintending Engineer | Chief Engineer | |
| Remote Area | Within 30 working days | Executive Engineer (Electrical) | Superintending Engineer | Chief Engineer | |
| 4. Timeline for releasing new electricity connection (energization) | |||||
| New connection / additional load where supply can be provided from existing network (a) | |||||
| Urban Area | Within 03 working days | Assistant Executive Engineer (Electrical) | Executive Engineer (Electrical) | Superintending Engineer | |
| Rural Area | Within 05 working days | Assistant Executive Engineer (Electrical) | Executive Engineer (Electrical) | Superintending Engineer | |
| Remote Area | Within 07 working days | Assistant Executive Engineer (Electrical) | Executive Engineer (Electrical) | Superintending Engineer | |
| Connection requiring enhancement work or transformer capacity enhancement (b) | |||||
| (i) Low Tension (LT) | |||||
| Urban Area | Within 15 working days | Assistant Executive Engineer (Electrical) | Executive Engineer (Electrical) | Superintending Engineer | |
| Rural Area | Within 20 working days | Assistant Executive Engineer (Electrical) | Executive Engineer (Electrical) | Superintending Engineer | |
| Remote Area | Within 30 working days | Assistant Executive Engineer (Electrical) | Executive Engineer (Electrical) | Superintending Engineer | |
| (ii) High Tension (HT) | |||||
| Urban Area | Within 15 working days | Assistant Executive Engineer (Electrical) | Executive Engineer (Electrical) | Superintending Engineer | |
| Rural Area | Within 25 working days | Assistant Executive Engineer (Electrical) | Executive Engineer (Electrical) | Superintending Engineer | |
| Remote Area | Within 30 working days | Assistant Executive Engineer (Electrical) | Executive Engineer (Electrical) | Superintending Engineer | |
| (iii) Extra High Tension (EHT) | |||||
| Urban Area | Within 15 working days | Executive Engineer (Electrical) | Superintending Engineer | Chief Engineer | |
| Rural Area | Within 25 working days | Executive Engineer (Electrical) | Superintending Engineer | Chief Engineer | |
| Remote Area | Within 30 working days | Executive Engineer (Electrical) | Superintending Engineer | Chief Engineer | |
| Connection requiring erection of new substation to extend supply. (c) | |||||
| Urban Area | Case to case basis as per Commission approval | Assistant Executive Engineer (Electrical) | Executive Engineer (Electrical) | Superintending Engineer | |
| Rural Area | Case to case basis as per Commission approval | Assistant Executive Engineer (Electrical) | Executive Engineer (Electrical) | Superintending Engineer | |
| Remote Area | Case to case basis as per Commission approval | Assistant Executive Engineer (Electrical) | Executive Engineer (Electrical) | Superintending Engineer | |
| N ote: The above timelines for conversion of connection, temporary connection, new electricity connection, etc.; requiring the creation of new infrastructure, shall be subject to availability of funds / materials (like distribution transformer, poles, conductors, insulators and allied line materials). |
By order of the Lt. Governor (Administrator), Union territory of Ladakh.
(Jigmet Raftan) JKAS, Deputy Secretary, General Administration Department. Copy to the: 1. All Administrative Secretaries, UT Administration of Ladakh 2. Director General of Police, Ladakh. 3. Deputy Commissioner / CEO, LAHDCs, Leh and Kargil. 4. All Heads of Department / Chief Engineers, UT of Ladakh. 5. Director, NIC, UT of Ladakh for uploading on UT website 6. OSD to Lt. Governor, UT of Ladakh for kind information of Hon'ble Lt. Governor, Ladakh. 7. OSD to the Chief Secretary, UT of Ladakh for kind information of the Chief Secretary, Ladakh. 8. E-Office fileLADAKH GAZETTE : EXTRAORDINARY 7